Letter Sequence Response to RAI |
---|
|
Results
Other: ML23136B278, ML23136B279, ML23136B280, ML23136B281, ML23136B284, ML23136B286, ML23136B287, ML23136B288, ML23136B289, ML23136B290, ML23220A398, ML23220A399, ML23220A401, ML23220A404, ML23313A064
|
MONTHYEARML20065H1612020-02-28028 February 2020 U.S. Dept. of Commerce, National Institute of Standards & Technology (NIST) - Reply to Request for Additional Information - 2019 Decommissioning Funding Plan Submittal Project stage: Response to RAI ML22293A2692022-09-27027 September 2022 Us Dept of Commerce, National Institute of Standards & Technology (Nist), Transmittal of Decommissioning Funding Plan Project stage: Request ML23060A2622023-01-24024 January 2023 National Institute of Standards and Technology (Nist), Reply to Request for Supplemental Information - 2022 Triennial Update to Decommissioning Funding Plan Project stage: Supplement ML23136B2782023-04-25025 April 2023 Decontamination and Decommissioning Cost Estimate (Dce) for the National Institute of Standards and Technology Project stage: Other ML23136B2812023-04-25025 April 2023 Historical Site Assessment for the National Institute of Standards and Technology Project stage: Other ML23136B2862023-04-25025 April 2023 Radiological Scoping Study Report for the National Institute of Standards and Technology Project stage: Other ML23136B2792023-04-30030 April 2023 NIST-TR-23-003, Appendix a - Facility Laboratory Cost Estimating Worksheets Project stage: Other ML23136B2802023-04-30030 April 2023 NIST-TR-23-003, Appendix B - Accelerator Component and Area Cost Estimating Worksheets Project stage: Other ML23136B2872023-05-16016 May 2023 Scoping Report 144265-RPT-001, Appendix a - Scoping Survey Calibration Sheets, Rev. a Project stage: Other ML23136B2842023-05-16016 May 2023 NIST Historical Site Assessment NIST-TR-23-001, Rev. a, Appendix B - Hsa Investigation List for All Rooms Project stage: Other ML23136B2852023-05-16016 May 2023 Department of Commerce, National Institute of Standards and Technology Reply to Request for Supplemental Information - 2022 Triennial Update to Decommissioning Funding Plan Project stage: Supplement ML23136B2892023-05-16016 May 2023 Scoping Report: 144265-RPT-001, Appendix C - Liquid Scintillation Results, Rev. a Project stage: Other ML23136B2902023-05-16016 May 2023 Scoping Report: 144265-RPT-001, Appendix D - Tennelec Results, Rev. a Project stage: Other ML23136B2882023-05-16016 May 2023 Scoping Report: 144265-RPT-001, Appendix B - Scoping Surveys Project stage: Other ML23220A4042023-08-0808 August 2023 Enclosure 5 RSO Delegation of Authority Project stage: Other ML23220A4012023-08-0808 August 2023 Enclosure 2: Requested Exemptions Under 10CFR36.17 and 70.17 Project stage: Other ML23220A3982023-08-0808 August 2023 Us Dept. of Commerce, National Institute of Standards & Technology (NIST) - Submittal of License Renewal Application Project stage: Other ML23220A4002023-08-0808 August 2023 Enclosure 1: NRC Form 313 Application for Materials License Renewal Project stage: Request ML23220A3992023-08-0808 August 2023 Us Dept. of Commerce, National Institute of Standards & Technology (NIST) - License Renewal Application Project stage: Other ML23313A0642023-10-20020 October 2023 Us Dept. of Commerce, National Institute of Standards and Technology - Designation of Trustworthiness and Reliability Official Project stage: Other ML24022A2952024-01-12012 January 2024 NIST 2022 DFP Update: Response to Request for Additional Information Project stage: Response to RAI 2023-04-25
[Table View] |
|
---|
Category:Letter
MONTHYEARML24248A1702024-09-18018 September 2024 U.S. Department of Commerce, National Institute of Standards and Technology - 2022 Decommissioning Cost Estimate and Decommissioning Funding Plan Triennial Update Submittal ML24205A0572024-07-11011 July 2024 GL Report from Us Dept. of Commerce, National Institute of Standards & Technology (Nist), Regarding Transfer Off Devices ML24198A1452024-07-0909 July 2024 Reply to Request for Final 2022 Decommissioning Cost Estimate and Decommissioning Funding Plan - Enterprise Project Identification Number L-2023-RNW-0017 ML24113A2932024-05-16016 May 2024 Letter - Approval of NISTs 2022 DFP Update ML24071A1782024-03-11011 March 2024 Reply to Request for Additional Information: U.S. Department of Commerce, National Institute of Standards and Technology (NIST) Application for Renewal of Special Nuclear Materials License Number 362 - EPID L-2023-RNW-0017 ML23320A1352024-02-0909 February 2024 NIST LRA - RAI Transmittal Letter ML24022A2952024-01-12012 January 2024 NIST 2022 DFP Update: Response to Request for Additional Information ML23355A2542023-12-29029 December 2023 Request for Due Date Extension to Provide Responses to Request for Additional Information Regarding U.S. Department of Commerce, National Institute of Standards and Technology 2022 Triennial Update to Decommissioning Funding Plan ML23355A2552023-12-0808 December 2023 National Institute of Standards and Technology Second Request to Extend Due Date for Providing Request for Additional Information Responses (NIST 2022 DFP Update) ML23313A0642023-10-20020 October 2023 Us Dept. of Commerce, National Institute of Standards and Technology - Designation of Trustworthiness and Reliability Official ML23271A2202023-10-0606 October 2023 Acceptance of National Institute of Standards and Technology License Renewal Application Dated August 8, 2023 ML23221A3572023-09-12012 September 2023 Request for Additional Information - Letter ML23220A3982023-08-0808 August 2023 Us Dept. of Commerce, National Institute of Standards & Technology (NIST) - Submittal of License Renewal Application ML23157A2672023-06-14014 June 2023 NRC Staff Assessment of NISTs Supplemental Information and Continuation of Review of 2022 Triennial of DFP Update ML23136B2852023-05-16016 May 2023 Department of Commerce, National Institute of Standards and Technology Reply to Request for Supplemental Information - 2022 Triennial Update to Decommissioning Funding Plan ML23067A2202023-03-15015 March 2023 NRC Staff Assessment and Temporary Suspension of NISTs 2022 DFP Update ML23060A2622023-01-24024 January 2023 National Institute of Standards and Technology (Nist), Reply to Request for Supplemental Information - 2022 Triennial Update to Decommissioning Funding Plan ML22348A1722022-12-17017 December 2022 Request for Supplemental Information Re NIST 2022 DFP Update- Transmittal Letter ML22230B4832022-10-0505 October 2022 EA-22-009: Notice of Violation - U.S. Department of Commerce, National Institute of Standards and Technology - NRC Investigation Report I-2022-001; NRC Inspection Report No. 07000398/2021003 ML22293A2692022-09-27027 September 2022 Us Dept of Commerce, National Institute of Standards & Technology (Nist), Transmittal of Decommissioning Funding Plan ML21126A1152021-05-20020 May 2021 Enclosure 1 - SEP G150 Relocation ML21126A1142021-05-20020 May 2021 Transmittal, Response to License Amendment Request ML21126A1162021-05-20020 May 2021 Enclosure 2 - SNM-362 License (Publicly Available) ML21078A0452021-03-12012 March 2021 Us Dept. of Commerce, National Institute of Standards & Technology, License Amendment Request Letter ML20168A6262020-06-24024 June 2020 U.S. Department of Commerce - Amendment 10, Change to Possession Limit for Americium-241 (Enterprise Project Identification Number L-2019-PMP-0024 ML20085G2152020-04-0303 April 2020 Transmittal, Approval of NIST 2019 Triennial Update to Decommissioning Funding Plan ML20065J8042020-03-0505 March 2020 Request for Additional Information - License Amendment Request, Special Nuclear Material License, SNM 362, Docket 07000398 (Cac/Epid 000222/07000398/L-2019-PMP-0024) ML20065J8062020-03-0505 March 2020 Enclosure - RAI Increased Possession Limits ML20065H1612020-02-28028 February 2020 U.S. Dept. of Commerce, National Institute of Standards & Technology (NIST) - Reply to Request for Additional Information - 2019 Decommissioning Funding Plan Submittal ML20038A3712020-02-14014 February 2020 Acceptance Review - License Amendment Request, Possession Limits Request Submittal SNM 362, Docket 07000398 ML20030A6792020-02-0404 February 2020 Request for Additional Information - 2019 Decommissioning Funding Plan Submittal, Special Nuclear Material License, SNM-362, Docket 07000398 (Cac/Epid 000224/07000398/L-2019-DFA-0008) ML19317E5702019-11-20020 November 2019 Acceptance Review-2019 Decommissioning Funding Plan Submittal, SNM 362, Docket 07000398 ML19241A9172019-08-28028 August 2019 Us Department of Commerce, National Institute of Standards and Technology - NRC Inspection No. 07000298/2019001 Public ML18241A2632018-08-24024 August 2018 NRC Inspection Report No. 07000398/2017001, U.S. Department of Commerce (Acknowledgement Letter) ML18183A4772018-07-13013 July 2018 Transmittal LAR Amendment 9 Corrected Copy 2024-09-18
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARML24071A1792024-03-11011 March 2024 U.S. Department of Commerce, National Institute of Standards and Technology (Nist), Response to NRC RAI (ML23320A133) ML24022A2952024-01-12012 January 2024 NIST 2022 DFP Update: Response to Request for Additional Information ML23060A2622023-01-24024 January 2023 National Institute of Standards and Technology (Nist), Reply to Request for Supplemental Information - 2022 Triennial Update to Decommissioning Funding Plan ML20065H1612020-02-28028 February 2020 U.S. Dept. of Commerce, National Institute of Standards & Technology (NIST) - Reply to Request for Additional Information - 2019 Decommissioning Funding Plan Submittal 2024-03-11
[Table view] |
Text
UNITED STATES DEPARTMENT OF COMMERCE National Institute cf Standards and Technology Gaithersburg, Maryland 20888 FEB 2 8 2020 OFFICE OF THE DIRECTOR U.S. Nuclear Regulatory Commission License No. SNM-362 ATTN: Document Control Desk Docket# 70-398 Washington, DC 20555-0001 TAC No. L32643 Mr. Tyrone Naquin Project Manager, Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Subject:
REPLY TO REQUEST FOR ADDITIONAL INFORMATION - 2019 DECOMMISSIONING FUNDING PLAN SUBMITTAL
Dear Mr. Naquin,
The National Institute of Standards and Technology (NIST) intends to manage its radioactive sources inventory in a manner that will ensure adequate disposition in the event licensed activities need to be suspended for the SNM-362 license. The attached response to the Request for Additional Information (ML20030A679) further clarifies the key assumptions and basis for the cost estimate associated with the disposition ofNIST-owned sources and customer-owned sources.
Thank you for your attention to this letter and attached.response. If you have further questions about this response, please contact the NIST Gaithersburg Radiation Safety Officer, Mr. Manuel Mejias at 301-975-5800 or manny.mejias@nist.gov.
Sincerely, vfl~;f-Walter G. Copan, Ph.D.
Under Secretary of Commerce for Standards and Technology &
Director, National Institute of Standards and Technology Enclosure DFP RAI Response cc:
E. A. Mackey, NIST Chief Safety Officer A. K. Thompson, NIST IRSC Chair M. Mejias, NIST Radiation Safety Officer H. Wixon, NIST Chief Counsel NISI
NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY SPECIAL NUCLEAR MATERIAL LICENSE SNM-362, (DOCKET NO. 70-0398)
RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION DECOMMISSIONING FUNDING PLAN UPDATE
Background
On February 4, 2020, NIST was asked to justify key assumptions in the Decommissioning Cost Estimate (DCE) related to the disposition of inventory (Title 10 Code of Federal Regulations [10 CFR] Part 70.25(e)(2)(v); 10 CFR 70.25(e)(l)(i)(A); 10 CFR 70.25(e)(l)(ii)). NIST was also informed that the Draft Interim Staff Guidance on Decommissioning Funding Plans for Materials Licensees, developed by NRC (ML18163A087), offers guidance supplemental to NUREG 1757 Vol. 3, describing ways in which the disposition of inventory can be covered in the Decommissioning Cost Estimate (DCE). NIST was specifically asked to provide further explanation for the basis of the costs included in the 2016 Decommissioning Funding Plan (DFP), which were incorporated in the 2019 DFP, for the packing, shipping, and disposal of sealed sources.
NIST-Owned Inventory In the Request for Additional Information (RAI), NIST was asked to provide further explanation for the basis of costs included in the 2016 DFP. The basis had been presented in table form in table 3.14, "PACKAGING, SHIPPING, AND DISPOSAL OF RADIOACTIVE WASTES" (page 354 of 359, ML16279A280) and table 3.18, "TOTAL DECOMMISSIONING COSTS" (page 358 of 359, ML16279A280). The tables break down each category of material for packaging, shipping, and disposal costs. The RAI mentioned a special waste dispositioning project undertaken by NIST in 2015 in which Ecology Services, Inc., brokered and facilitated dispositioning and asked whether this contract was relied upon for adjustments to the DCE. In response, NIST advises that the contract served to confirm the basis presented in the previous DCE, and did not result in cost adjustments. The assumptions and methodology used by NIST for its DFP are intended to ensure that the full cost of dispositioning the NIST inventory is accurately incorporated into the DCE.
Customer-Owned Inventory The RAI indicated that the Draft Interim Staff Guidance on DFPs for Materials Licensees allows an alternative to including the costs for packaging, loading, and transporting of radioactive sources if the licensee has existing contracts under which the customer is responsible for the costs. NIST enters into Cooperative Research and Development Agreements (CRADAs) and Inter-Agency Agreements (IAAs) in which ownership is clearly established as a responsibility for the customer for a small number of sources. NIST does not in these agreements seek to obtain credit and thereby to reduce the financial liability. In preparing its response to the RAI, NIST carefully reviewed the number of sources used in previous calculations and has confirmed that NIST's worst-case scenario assumption was, in fact, applied in NIST's previous submittals. NIST acknowledges that previous submittals 1
indicated that customer-owned sources would be returned to the customer. However, NIST's practice has been to prepare the DCE assuming a worst-case scenario, under which NIST is responsible for the entire inventory, whether it is customer-owned or not. Furthermore, NIST has an active waste disposal contract to permit the disposition of unsealed sources (i.e. Dry Active Waste - DAW) that is already funded and available. In summary, NIST ensures that the disposition of customer-owned inventory is covered in the DCE and is not dependent on agreements or contracts, and that the DCE reflects NIST's assumption of the obligation to pay for dispositioning of the sources.
2