ML20055E345
| ML20055E345 | |
| Person / Time | |
|---|---|
| Site: | San Onofre, Rancho Seco |
| Issue date: | 05/04/1989 |
| From: | Yuhas G NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| Shared Package | |
| ML20055C206 | List:
|
| References | |
| NUDOCS 9007110300 | |
| Download: ML20055E345 (22) | |
Text
.
y y i j::a,n.%'
i p
%-)'
%l f
,1 e {s I :;
NUCUF.AR REGULATORY C3hMWSS10N
$+,4
,s memon v N 3;
- p a
un ananu. LANs. som aw L
y' y.
p,,
a
= '...+
- WALNUT creek. CAUFORNIA 9m6mm 4
NAYsi1989 c.i. A qlJ
' Docket No. 50-312 y
.m u
h,
((?t MEMORANDUM FOR:
File S
l FROM:
Gregory P. Yuhas, Chief f"
J f
Emergency Preparedness & Radio?ogical m
Protection Branch
>1 4
('
SUBJECT:
MEETING WITH REPRESENTATIVES OF SACRAMENTO MUNICIPAL L
i UTILITYDISTRIC'i(SMUD)'TODISCUSSTHESTATUSOF:THEIR w
EFFLUENTS & WATER MANAGEMENT PROGRAM (E&WMP) AND THE 1988-ANNUALRADIATIONENVIRONMENTALOPERATINGREPORT(AREOR)
' O
- On Monday, May 1,1989, members of the Region'V st(ff and SMUD met at 10:00 L,m
A'.M..:in the Chief of Emergency Preparedness & Radiological Protection Branch's office. The_ purpose of this. meeting was to discuss the status of the licensee's H
E&WMP and for the licensee to explain administrative changes and some certain L
data in:the ARE0R. The meeting was at the request of the licensee's staff, m
L NRC Attendees:
G.P. Yuhas, Chief J'
Emergency Preparedness & Radiological Protection Branch E.M. Garcia, Acting Chief Lf Facilities Radiological Protection Section p
P C.A. Hooker, Radiation Specialist y
?
SMUD. Attendees:
S. Crunk, Manager, Nuclear Licensing D.G. Yows, Mcaager, Environmental Monitoring & Emergency Preparedness R.F. Orthen. Supervisor, Health Physics & Chemistry.
E Support R.G. Wolfe, Projects Support Engineer, Contractor -
LThe information pertaining to the E&WMP addressed at.the meeting is included
.in the attachment.
'i Mr. Wolfe briefly described the status of the E&WMP as outlined in the'
.. attachment. Regarding Item 2A. of the attachment involving the RHUT Demineralizer Enclosure, Mr. Yuhas stated that the licensee's statement that
.the enclosure, which consists of a plastic curtain around the system, would prevent uncontrolled releases to the environment was an overstatement. The lic.ensee representatives acknowledged this observation.
r
\\-
A i
71ph h b
p_
-P, C
m
o q; i y, p,-
m o
u.1 7,,;
- t- (
' ~ Mr. Orthen informed the Region V staff that two new appendices were added to the ARE0R. These new appendices are Appendix H Radiation and Nuclear Power, f
and Appendix I, Environmental Monitoring Program Design. Mr. Orthen also
' stated that the predicted organ dose based on the 1988 liquid source term L
exceeded the calculated dose based on environmental measurements by j
l approximately 60%. This observed difference is attributed to the conservatism in the licensee's-liquid effluent dose calculations program. The licensee's.
identification of Co-60 and H-3 in well water samples were also discussed.
The licensee stated that the 1988 ARE0R contains details on the subjects.
. discussed at the meeting.
y l
Mr.- Yuhas stated that the NRC's review of the ARE0R would be a. subject of a future inspection.
o a
h.
. Gregory P as, Chief j
Emergency aredness & Radiological Protection Branch I
fAttachment as sta'ted cc w/ enclosure-L' R.A. Scarano, Director DRSS P
- D.LZinnerman; Acting Director, DRSP
.I a G. Kalman, NRR/ Project Manager LC..Willis, NRR/DREP l
l l'
t-L H
l l'
e a,
p,,
- 7. ;
y :ie:-
.s g,
g.
. :y
.. \\ ^' 4
~ '
.c Q:
o
- [E f 1
l 'l
.i*
EFFL.UENTS '&1 WATER MANAGEMENT PROJECT.
j PROJECT STATUS e
l{
4/25/89 1
.I t.
y
, GENERAL
' tl y
1 TASK'DESCRIFFIONS & STATUS
.e 1
4 ADDITIONAL E & W M TASKS w>^)
- TASK. STATUS,
SUMMARY
7
+.
1 e
?
h
(
i
'il i
a r
e 4
j..
l m
L,a n
L,'* S
., n;j? :.:.
&y
. j
.A *,
y q; r
i* W GENERAL!
- i l,4 1
l 1-
- Shdrt & near term activities outlined in the Effluents & Water Management Action Plan-!
l-
[
dated 9/28/88 were projected for completion by the first quarter of 1989 (figure 3.1);-Most of these tasks (listed in Appendix I) are ec,mplete or essentially complete. The aggressive
- target dates shown in Appendix ! were initially established by project management'and
- i
-later revised as necessary to accomodate:
L, P scope changes within individual tasks '
i
?-
- additional tasks requiring higher priority 1
- strict adherence to District purchasing policies
?
familiarization with the new DCP processes
. forced outages, and.
t pending litigation efforts J
I L
i Present level lof effort on major tasks is satisfactory and overall; progress,. although restrained due to recent outage support, is generally good.
p
- 1. The acquisition of"MO FLOW', a high capacity demineralization system, provides 1
adequate insurance in the event of OTSG tube leaks.
'2. The-implem:ntation of. waste water reduction modifications should significantly reduc'e' the quantity of waste water generated and make existing equipment more i_
effective. These modifications should be effective by mid May 1989.
- 1
- 3. The activity reduction, spill _ mitigation and abnormal release prevention effortsJ have provided more effective control of effluents.
'i
- 4. The long term upgrades (Tank Farm & Waste Water Treatment Facility), are in l
, the engineering phases and targeted for completion in 1990.
)
-,,---.a_-
-,m.-
,r, -..
v-9
r.
1 e4.:
l
' TASK DESCRIPTIONS & STATUS l
1A STORM & EFFLUENT DRAIN VERIFICATION A physical verification of all plant effluent and storm drain piping is being performed to _ update the plant drawings. A volume study will then be made to assess the feasibility of routing consolidation.
STATUS:
Complete. (The volume study is slated for completion by 5/1/89.)
2A.
RHUT DEMINERAL'ZER ENCIASURE The RHUT demineralizers have hoses for interfaces with each other and plant systems. This equipment is set outdoors and an enclosure to prevent' uncontrolled release to the environment is required.
/-
STATUS:
Complete.
3A.
PROCELURE AND SURVEILLANCE PROGRAM Development of procedures and surveillances to periodically sample onsite drains for radioactMty. Additionally, enhanced procedores for normal and abnormal (liquid and gas) releases are also being developed.
tl e-j, y STATUS:
Complete.
4A.
PROCEDURE DEVE1DPMENT Development of a procedure that details specific group responsibility and actions in the event of a potentially uncontrolled offsite rebase.
s STATUS:
Complete 5A.
TRAINING PROGRAM Expand training program for RP Chemistry and Operations personnel in 10 CFR 50 APP I' guidelines and potential release pathways. This will provide keener awareness of environmental impact and general m
concern for effluents.
1 #
STATUS:
Complete. Implementation of the training 4 in progress and has been enhanced as a result oflessons learned from the resin migration event,
(,
t
+
h s
6A.
BASIN DISCHARGE VALVE UPORADE Manual discharge valves for release r
or retention basins to the creek are single isolation butterfly valves. A valve leak would result in an uncontrolled release and, therefore, a valve change or the addition of blind flanges will be made..
4 STATUS:
Design engineering is complete. Blind flanges will be added. Field work should be completed by early May 1989.
i 7A.
EFFLUENT FLOW INSTRUMENTATION UPORADE Due to the high
{
maintenance and questionable reliability of existing flow instrumentation an upgrade j
to all effluent flow devices will be made.
)
STATUS:
Design ennineering is complete. Replacement instruments are on site and culvert delivery is slated for May 1989. Physical field work is
.i slated for completion in June 1989.
1j 8A.
AUX STEAM SUMP PUMP UPORADE The aux steam condensate sump pumps need to be redesigned for operation with higher temperature fluids. The current pumps have failed due to the temperature.
STATUS:
Specifications were developed and sent to vendors detailing the.
operating servica conditions and required pump capacities. New l
pumps were procured, installed and tested. Testing indicated that the '
new pumps (the second set) were not suitable for the application.
Nuclear engineering is designing steam trap discharge path back to condenser and adGg sump water cooling. The engineering should be completed in early May with installation presently targeted by. July 1989.
i 9A.
MSR DRAIN REROUTE Rerouting of the MSR and turbine deck drains to a controlled sump will prevent uncontrolled releases due to steam leaks on the turbine deck.
STATUS:
Comolete
---.---------- -.-a-- -..--.------.--a
-a---.---
--.-----x m+-<. - - -
g o
)
+-
s' 10A. SOLIDIFICATION PAD ENCLOSURE BUILDING Radioactive resins and evaporator bottom liquids are currently processed for shipment outdoors.
A building will contain any system leakage.
STATUS:
Buildine desian is complete. Construction effort is in progress with scheduled completion still targeted for June 1989.
TANK FARM UPGRADB The conditions in the tank farm are vulnerable to spills l
11 A.
and contain temporary routing of liquid runoffs. An upgrade to minimize to i
propensity for spills and to ensure that any contaminated system leakage is directed 1
to the RHUTs or radwaste system is being made.
STATUS:
Feasibility study as well as conceptual ennineerinn is complete.
Detailed engineering is in progress and slated for completion in June 1989. Field installation will be treated as non outage work and
{
accomplished so as to not interfere with the refueling outage effort.
i e
Completion is targeted in early 1990.
1 12A. MISC HAZARDOUS MATERIALSITE UPGRADE An evaluation of hazardous material storage locations and outdoor usage and handling particularly in light of potentially uncontrolled offsite leakage through the storm drain system is being conducted. Appropriate follow up action will subsequently take place.
STATUS:
Study and assessment is completed. Tasks slated for implementation will be coordinated as a separate project (not part of Effluents &
Water Management).
13A. CHIDRINATION SYSTEM UPGRADE The Sewage Treatment Effluent Chlorination system needs to be upgraded. Current system does not have desired degree of redundancy, i
STATUS:
A temporary modification utilizing Hypochlorite to provide short term redundancy is being installed and scheduled for completion by 5/5/89.
An engineering evaluation for a permanent system upgrade is also in progress and scheduled for completion in August 1989.
k i
e
h C
y
.yc IB.
REROUTE R 15016 SAMPW FLOW Current drain flow of this Circulating l
Water System (C.WS) radiation monitor is treated as potentially contaminated water.
l Rerouting flow back to the CWS could reduce waste water volume by 1 MGPY.
1
{
STATUS:
Complete 1
1 28.
REROUTE AE CIRC WATER SAMPW FLOW CWS sampling flows should be rerouted to CWS (Volume reduction
.5 MGPY)
STATUS:
Comolete l
i i
3B.
REROUTE AE-77609 DISCHARGE Sample pmt discharge should be returned
{
L to the source process instead of discharged to the RHUTs. (.5 MGPY)
I L
STATUS:
Reroute conceptual design being evaluated in light of new t":' me
)
o sampling system (TSS) design.
I 4B.
REROUTE POLISHER SAMPLE DISCHARGES Same as 3B. (3 MGPY)
STATUS:
Since the new TSS will completely change existing sample routes, a temporary modification to route polisher sample discharges back to the condensate return tank is being evaluated.
5B.
RECYCW COID LAB SAMPWS Same as 3B. (2 MGPY)
I STATUS:
The new TSS will require essentially the same sample discharge I
routing as the existing cold lab. Conceptual engineering design has been initiated.
6B.
DOO BONE SEALS & COND SEAIS REROUTE - The turbine vacuum seals and condensate pump seal leakoffs are now being discharged to the RHUTs.
Returning leakoffs to the hotwell could reduce the waste water volume by 5 MGPY.
STATUS:
Field work is essentially complete. Minor changes to installed field.
work have been made :o accomodate testing, tie in and turnover during plant operation. Targeted co.mpletion is May 1989.
f i
l
-- - - ~
R b
c l
78.
REROUTE AFW MINI FLOW TO GT The Condensate Storage Tank (CST)
I supplies the AFW mini Dow with the discharge directed to the hotwell. Current operation administratively restricts rejecting high hotwell level back to the CST and requires dumping the excess water to waste. Rerouting discharge back to the CST could ieduce volume of waste water by 7 MPGY.
STATUS:
Field construction of the mini flow reroutes is complete. Testing and l
turnover to operations is slated for completion in May 1989. (AFW test line tie in will require a plant outage at cold conditions.)
8B. - GT OVERFLOW REROUTE If CST were to become contaminated an overflow would result in an uncontrolled release. Routing this overflow to a monitored drain path is included in the Tank Farm Upgrade.
STATUS:
Although permanent rerouting is included in the Tank Farm Upgrade, a near aerm modification to reroute this overflow to a monitored drain
- s being evaluated.
98.
POLISHER SLUICE WATER DEMINS - Addition of a filter and/or demineralization system to condensate polisher resin transfer sluice water return will clean up contamination prior to entering the RHUTs. (90% activity reduction)
STATUS:
Complete (Further evaluation to return sluice water to the hotwell is presently being evaluated)
L 10B. WASTE WATER TREATMENT SYSTEM UPGRADE-An upgrade to the waste water treatment system to provide increased capability for waste water clean up during normal operation as well as SGTL conditions will be made, i
L STATUS:
A waste water treatment facility (long term fix) as mentioned in item p
2C is preferred over " upgrades" to existing equipment.
Current operation is within the guidelines of Appendix ! and modifications to
[
reduce waste water volume should only enhance existing equipment-capabilities.
11B. REIMS DEVEIDPMENT - Development of an automated release calculations program that contains many other useful features.
STATUS:
Comolete.
4 i
2
.-.a.-
r n,-
e s
g
}
4 4
12B.
OIL SKDdMER INSTAUATION Installation of oil skimming equipment in turbine building sumps and RHUTs will ensure that State of California water q requirements are met and that any Rad material clean up system will operate at
. peak efficiency.
STATUS:
Installation is comolete.
System testing and turnover should be completed by 5/7/89.
IC.
SHORT TERM PLAN OF ACTION Formulate a plan that describes actions,
)
, responsibilities and equipment that will be required during operation under OTSO tube leak conditions. The plan includes leasing a mobile high flow filtration &'
demineralization system, organization of a water coordination team and outli appropriate actions.
STATUS:
Plan is formulated and hiah flow demineralization system is on site.
Plant modifications for hook up and use of"MO FLOW" are currently g@
0 in progress and should be completed in May 1989.
o Nf
\\
2C.
IDNG TERM WASTE WATER 1REATMENTSYSTEM Upgrade Waste Water i
Treatment System to allow continued operation under OT3G tube leak conditions.
This permanent plant upgrade will provide high capacity water treatment cap and contain those functions now currently being handled on a temporary basis i
Outside contractors.
l STATUS:
The enaineerina study is comolete. The installation of a permanent i
facility (with high capacity demineralization, filtration, etc.) for the treatment of waste water was determined to be feasible and prudent.
Design engineering effort will commence after data from current plant modifications are available. Target completion is 1990, i
i l
l L
1
[
l' I
Lw
)
C g
.f ADDITIONAL E&WM TASKS 1
1.
CPS & PDS PUMP SEAL WATER REROUTE. Condensate pit sump & polisher demin sump pumps have seal water presently being discharged to waste. These discharges should be rerouted to the hotwell.
1 I
STATUS:
Design is comolete. Field installation & turnover to operations is scheduled for 5/30/89.
j 2.
RETENTION BASIN CURBS. Physical location of the retention basins allows runoff from' surrounding dirt mounds to enter the basins.
The task requires construction of curbs around the basins to minimize the volume of solid waste build j
i up in the retention basins.
STATUS:
Comolete.
l l
3.
RHUT TEli TAIE DRAIN a tell tale drain would provide a method for establishing the existence of a RHUT liner leak.
(
l STATUS:
Engineering Complete. Construction scheduled for completion in early L
June 1939.
L
(.
4.
RHUT IEAKAGE COLLECTION the potential for leaks in the immediate vicinity of the RHUTs exists. Additionally, the RHUT overflow sump is currently L
directed to the normal effluent path. The building of berms to contain potential leaks.and the rerouting of the, overflow sump is suggested.
STATUS:
Berm installation is scheduled for completion in mid May 1989.
i Rerouting of overflow sump discharge is slated for completion in 1989.
5.
RESIN ISSUE CORRECTIVE ACrlONS - Implementation of the Resin Management Action Plan tasks was asigned to the Effluents and Water Management Project.
L L
STATUS:
Resin Issue Corrective Actions should be completed with Action Plan closed buy 5/7/89.
y 6.
BIO ACCUMUIATION FACIDR REDUCrlON Review of environmental data
]
suggests the possibility of reducing the Bio Accumulation Factor currently being used u
at Rancho Seco.
STATUS:
Data review and modeling are currently in progress by Jene Vance and Associates. After completion of the modeling (scheduled for early May 1989), a l
validation by SMUD and LLNL will take place prior to submittal to the commission.
c 3 G
Q t'
EFFLUENT 3 & WATER MANAGEMENT F
TASK STATUS L
4/15/89 l
A.
TASKS COMPLETED (or essentially complete) 1.-
Retention Basin Curbs 2.
MSR Drain Reroute i
i 3.
Storm Drain Drawing Update 4.
RHUT Demineralizer Enclosure 5.
Procedure and Surveillance Program Development Operations Procedure Development l
l 6.
7.
Training Program Development 8.
R15016 Sample Flow Discharge Reroute 9.
Reroute AE CIRC Water Sample Flow 10.
Polisher Sluice Water Demin Installation 11.
Reims Development t
12.
Dog Bone Seal & Condensate Pump Seal Water Reroute l
13.
AFW Mini Flow Reroute 14.
Oil Skimmer Installation 15.
Tube I.eak Short Term Plan (Mo Flow)
- 16. -
Chlorination System Upgrade 17.
Resin issue Closure t
B.
TASKS SCHEDULED FOR NEAR TERM COMPLETION 1.
Basin Discharge Valve Upgrade (May 1989) 2.
Effluent Flow Instrumentation Upgrade (June 1989) 3.
Solidification _and Enclosure Bldg. (June 1989) 4.
RHUT Leakage Collection (May 1989) 5.
CPS & PDS Pump Seal Water Reroute (May 1989) 6.
RHUT Tell Tale Drain (June 1989)
_ ~,,
\\
g O
L.I C.
TASKS IN PROGRESS i
s 1.
Aux Steam Sump Pump Upgrade (July 1989) 2.
Bio Accumulation Factor Reduction (Fall 1989) 3.
Reroute AE 77609 Discharge (Previously on Hold) i 4
Reroute Polisher Sample Discharges s
5.
Cold Sample Reroute (Previously on Hold)-
j 6.
Tank Farm Upgrade (1990) 7.
Waste Water Treatment Facility (1990)
D.
TASKS DELETED FROM EFFLUENTS AND WATER MANAGEMENT.
1.
Hazardous Material S & H Upgrade (Project Status) 2.
CST Overflow Reroute (Implemented by C 6).
3.
Waste Water Treatment System Upgrade (Covered by C 7) l h
l 5
9 e
.1,..,
l.
(..
Es I
[
_ il n
E yll EB
==
I EM' I
EW g
llW
- i:i:i:!:!
3 l
u :::
l i
g
'=
C l
=
if!f!f!,!:
3 d]
' g' ' ' '
I =gj 5
7
-ll
/
51 c
g.'
l g
4 v,
8 l1l8 EBll N
1 E
s l
lljlll!
1 l
s c
g g
a g
i i
Y a
)
]
\\
J
Q
-k
</
)
EFFLUENTS & WATER MANAGEMENT PROJECT STATUS 4/25/89 GENERAL' t
TASK DESCRIPTIONS & STATUS ADDITIONAL E & W M TASKS TASK STATUS
SUMMARY
l l
l I
i i
(
j f.
f I
}4*
- J..'
i 6A.
BASIN DISCHARGE VALVE UPGRADE. Manual discharge valves for relea or retention basins to the creek are single isolation butterfly valves. A valve leak I
would result in an uncontrolled release and, therefore, a valve change or the addition of blind flanges will be made.
STATUS:
Design engineering is complete. Blind Danges will be added. Field work should be completed by early May 1989.
i 7A.
EFFLUENT FLOW INSTRUMENTATION UPGRADE Due to the high i
I maintenance and questionable reliability of existing flow instrumentation to all effluent now devices will be made.
STATUS:
Design engineering is comolete. Replacement instruments are on site and culvert delivery is slated for May 1989. Physical field work is i
stated for completion in June 1989.
8A.
AUX STEAM SUMP PUMP UPGRADE The aux steam condensate su need to be redesigned for operation with higher temperature Dulds. The current
{
pumps have failed due to the temperature.
STATUS:
Specifications were developed and sent to vendors detailing the operating service conditions and required pump capacities. New i
pumps were procured, installed and tested. Testing indicated that the new pumps (the second set) were'not suitable for the application.
L Nuclear engineering is designing steam trap discharge path back to l
condenser and adding sump water cooling. The engineering should be completed in early May with installation presently targeted by Ju c
1989.
jL f
&y y
9A.
l MSR DRAIN REROUTE Rerouting of the MSR and turbine deck drains to a controlled sump will prevent uncontrolled releases due to steam leaks on the turbine deck.
STATUS:
Complete
,e
--.-g,
10A.
SOLIDIFICATION PAD ENCLOSURE BUILDING building will contain any system leakage. evapo c
ent outdoors.
A STATUS:
Buildine design is comolete.
scheduled completion still targeted for June 1989.
I1A.
ard contain temporary routing of liquid runo u nerable to spills to the RHUTs or radwaste system is being mad es rected STATUS:
Eeasibility study Detailed engineering is in progress and s 1989.
accomplished so as to not interfere une Completion is targeted in early 1990.
1 -
12A.
MISC. HAZARDOUS MATERIALSITE UPGR material storage locations and outdoor usage and ha on of hazardous potentially uncontrolled offsite leakage through the s y n g t of conducted. Appropriate follow up action will subsequently ta s e ng place.
STATUS:
Study and assessment is comoleted. Tasks slate l'
will be coordinated as a separate project (not part Water Management).
-l t on l
13A.
CHLORINATION SYSTEM UPGRADE - The Sewage Tr Chlorination system needs to be upgraded. Current syst eatment Effluent degree of redundancy.
o ave desired
'1 STATUS:
A temporary modification utilizing Hypochlorite to pr
\\
An engineering evaluation for a per m
progress and scheduled for completion in August 1989.
n
~
l l I i
4 l
j 78.
REROUTE AFW MINI FLOW TO CST The Condensate Storage T t
supplies the AFW mini flow with the discharge directed to the hotwell. Cu operation administratively restricts rejecting high hotwelllevel back to the requires dumping the excess water to waste. Rerouting discharge back to th could reduce volume of waste water by 7 MPGY.
STATUS:
Field construction of the mini flow reroutes is comnlete. Testing a turnover to operations is slated for completion in May 1989. (AFW test line tie in will require a plant outage at cold conditions.)
)
88.
CST OVERFLOW REROUTE If CST were to become contam would result in an uncontrolled release. Routing this overflow to a monitored d path is included in the Tank Farm Upgrade.
STATUS:
Although permanent rerouting is included in the Tank Farm Upgrad a near term modification to reroute this overflow to a monitored d is being evaluated.
9B.
POL 1 SHER SLUICE WATER DEMINS - Addition of a filter demineralization system to condensate polisher resin transfer sluice water re clean up contamination prior to entering the RHUTs. (90% activity reduc t
STATUS:
Complete (Further evaluation to return sluice water to the hotwell I
is presently being evaluated) 10B.
WASTE WATER TREATMENTSYSTEM UPGRADE An upgrade to the waste i
water treatment system to provide increased capability for waste water clean u during normal operation as well as SGTL conditions will be made.
STATUS:
A waste water treatment facility (long term th) as mentioned in item l
2C is preferred over " upgrades" to existing equipment. Current operation is within the guidelines of Appendix I and modifications to reduce waste water volume should only enhance existing equipment capabilities.
11B.
REIMS DEVELOPMENT Development of an automated release calculations p;ogram that contains many other useful features.
/,,
STATUS:
Complete.
h
128. OIL SKIMMER INSTALLATION Installation of oil skimming equipment in turbine building sumps and RHUTs will ensure that State of California w requirements are met and that any Rad material clean up system will operate peak efficiency.
STATUS:
Installation is complete.
System testing and turnover should be completed by 5/7/89.
I C.
SHORT TERM PIAN OF ACrlON Formulate a plan that describes actions,
. responsibilities and equipment that will be required during operation under OTSG tube leak conditions. The plan includes leasing a mobile high now filtration &
demineralization system, organization of a water coordination team and ou i
appropriate actions.
STATUS-Plan is formulated and hinh Dow demineralization system is on site,
[/,8'@ in progress and should be com Plant modifications for hook up and use of"MO. FLOW"are currently b
i 2C.
LONG TERM WASTE WATER TREATMENTSYSTEM Upgrade Waste Water Treatment System to allow continued operation under OTSG tube leak conditions.
This permanent plant upgrade will provide high capacity water treatment ca and contain those functions now currently being handled on a temporary bas outside contractors.
STATUS:
The engineerina study is complete. The installation of a permanent facility (with high capacity demineralization, filtration, etc.) for the i
treatment of waste water was determined to be feasible and prudent.
Design engineering effort will commence after data from current plant modifications are available. Taroet completion is 1990, l
.m
v.
i ADDIT lONAL E&WM TASKS i
l.
CPS & PDS PUMP SEAL WATER REROUTE. Condensate pit sump & polisher demin sump pumps have seal water presently being discharged to waste. These discharges should be rerouted to the hotwell.
STATUS:
Design is comple.t.s. Field installation & turnover to operations is scheduled for 5/30/89, 2.
RETENTION BASIN CURBS Physical location of the retention basins allows runoff from surrounding dirt rnounds to enter the basins.
The task requires
)
construction of curbs around the basins to minimize the volume of solid waste b i
up in the retention basins.
STATUS:
Complem 3.
RHUT TELL TAIE DRAIN a tell tale drain would provide a method for establishing the existence of a RHUT liner leak.
STATUS:
Engineering Comnlete. Construction scheduled for completion in early June 1989.
I 4.
RHUT LEAKAGE COLIECrlON the potential for leaks in the immediate vicinity of the RHUTs exists. Additionally, the RHUT overnow sump is currently directed to the normal ef0uent path. The building of berms to contain potential leaks and the rerouting of the overflow sump is suggested.
i STATUS:
Berm installation is scheduled for completion in mid.May 1989.
Rerouting of overflow sump discharge is slated for completion in 1989.
5.
RESIN ISSUE CORRECTIVE ACrlONS _- Implementation of the Resin ManageMont Action Plan tasks was assigned to the Efauents and Water l
l Management Project.
i STATUS:
Resin Issue Correc:ive Actions should be completed with Action Plan closed buy 5/7/89.
9 g
6.
BIO ACCUMULATION FACTOR REDUCrlON Review of environmental data suggests the possibility of reducing the Bio Accumulation Factor currently being used -
at Rancho Seco.
L STNFUS:
Data review and modeling are currently in progress by Jene Vance and Associates. After completion of the modeling (scheduled for early May 1989), a
- validation by SMUD and LLNL will take place prior to submittal to the commission.
I a
i
EFFLUENTS & WATER MANAGEMENT l
TASK STATUS 4/15/89 i
A.
TASKS COMPLETED (or essentially complete) 1.
Retention Basin Curbs 2.
MSR Drain Reroute 3.
Storm Drain Drawing Update 4.
RHUT Demineralizer Enclosure 5.
Procedure and Surveillance Program Development M
4 i
6.
Operations Procedure Development 7.
Training Program Development 8.
R15016 Sample Flow Discharge Reroute 9.
Retoute AE CIRC Water Sample Flow 10.
Polisher Sluice Water Demin Installation 11.
Reims Development 12.
Dog Bone Seal & Condensate Pump Seal Water Reroute 13.
AFW Mini Flow Reroute 14 Oil Skimmer Installation 15.
Tube Leak Short Term Plan (Mo Flow) 16.
Chlorinadon System Upgrade i
17.
Resin issue Closure B.
TASKS SCHEDULED FOR NEAR TERM COMPL 1.
Basin Discharge Valve Upgrade (May 1989) 2.
Effluent Flow Instrumentation Upgrade (June 1989) 3.
Solidification and Enclosure Bldg. (June 1989) 4.
RHUT Leakage Collection (May 1989) 5.
CPS & PDS Pump Seal Water Reroute (May 1989) 6.
RHUT Tell Tale Drain (June 1989) i i
4 u
y 1..
t C.
TASKS IN PROGRESS 1.
i Aux Steam Sump Pump Upgrade (July 1989) 2,.
Bio Accumulation Factor Reduction (Fall 1989) 3.
Reroute AE 77609 Discharge (Previously on Hold) 4 Reroute Polisher Sample Discharges" 5.
Cold Sample Reroute (Previously on Hold) 6.
Tank Farm Upgrade (1990) 7.
Waste Water Treatment Facility (1990) k i
)
i D.
TASKS DELETED FROM EFFLUENTS AND WAT MANAGEMENT i
1.
Hazardous Material S & H Upgrade (Project Status) 2.
CST Overflow Reroute (Implemented by C 6).
3.
Waste Water Treatment System Upgrade(Covered by C 7) i 6..
. m m.
.