MONTHYEARML20217F0941999-10-14014 October 1999 Application for Amends to Licenses DPR-39 & DPR-85,to Revise TS Sections 2.2 & 3.0/4.0 to Support Mod P000224 Which Will Install New Power Range Neutron Monitoring Sys & Incorporate long-term thermal-hydraulic Stability Solution Hardware ML20216J3341999-09-27027 September 1999 Supplements Application for Amends to Licenses NPF-39 & NPF-45,to Modify Appearance of TS Page 3/4 4-8 as Typo Was Identified in Section 3.4.3.1 of Ts.Corrected TS Page,Encl ML20212H5521999-09-27027 September 1999 Application for Amends to Licenses NPF-39 & NPF-85,revising TS to Clarify Several Administrative Requirements,Deleting Redundant Requirements & Correcting Typos ML20212F9521999-09-20020 September 1999 Application for Amend to License NFP-39,requesting Issuance of TS Change Request 98-08-0 Re Increase in Allowable as- Found Main Steam SRV Setpoint Tolerance.Util Had Originally Requested That Subject TS Change Be Deferred in ML20196F5471999-06-22022 June 1999 Application for Amends to Licenses NPF-39 & NPF-85,change Request 99-01-0,to Revise TS to Delete Surveillance Requirement 4.4.1.1.2 & Associated TS Administrative Controls Section 6.9.1.9.h ML20195G0421999-06-0707 June 1999 TS Change Request 98-09-0 for Licenses NPF-39 & NPF-85, Revising TS Section 3/4.4.3, RCS Leakage,Leakage Detection Systems, by Clarifying Action Statement Re Inoperative Reactor Coolant Leakage Detection Systems ML20195E7521999-06-0707 June 1999 TS Change Request 91-08-01 to License NPF-39,reflecting Permanently Deactivated Instrument Reference Leg Isolation Valve HV-61-102 in TS Table 3.6.3-1, Primary Containment Isolation Valves & Associated Notations ML20195B8361999-05-26026 May 1999 TS Change Request 99-02-0 for Licenses NPF-39 & NPF-85, Revising TS Section 4.1.3.5.b by Removing & Relocating Control Rod Scram Accumulators Alarm Instrumentation to UFSAR & Revising TS Section 3.1.3.5 ML20207L6561999-03-11011 March 1999 TS Change Request 98-07-2 for License NPF-85,revising MCPR Safety Limit Contained in TS Section 2.1, Safety Limits. Proprietary & non-proprietary Info Re Cycle Specific SLMCPR for Lgs,Unit 2 Cycle 6,encl.Proprietary Info Withheld ML20199G1651999-01-12012 January 1999 TS Change Request 98-08-0 to Licenses NPF-39 & NPF-85, Proposing Rev to TS Section 3/4.4.2 & TS Bases Sections B 3/4.4.2,B 3/4.5.1 & B 3/4.5.2.Supporting TSs & Proprietary & non-proprietary Trs,Encl.Proprietary Info Withheld ML20199A6861999-01-0404 January 1999 TS Change Request 97-01-01 to Licenses NPF-39 & NPF-85, Revising Administrative Section on Controlled Access to High Radiation Areas & Rept Dates for Listed Repts ML20155H6311998-10-30030 October 1998 Application for Amends to Licenses NPF-39 & NPF-85, Respectively,Revising TS Surveillance Requirements 4.8.4.3.b.1,4.8.4.3.b.2 & 4.8.4.3.b.3 in Order to Reflect Relay Setpoint Calculation Methodology ML20154Q8781998-10-15015 October 1998 TS Change Request 97-04-0 to Licenses NPF-39 to NPF-85, Adding New TS Section & TS Bases Section to Incorporate Special Test Exception to Allow Rc Temp Greater than 200 F During IST & Hydrostatic Testing ML20151Z4541998-09-14014 September 1998 TS Change Request 98-04-2 to License NPF-85,revising TS Table 4.4.6.1.3-1 Re Withdrawal Schedule for Reactor Pressure Vessel Matl Surveillance Program Capsules.Ge Rept GE-NE-B1100786,encl ML20151V0731998-09-0404 September 1998 TS Change Request 96-23-0 to Licenses NPF-39 & NPF-85, Revising TS Pages to Ensure Fidelity Between TS Pages & 970324 Submittal ML20236L5151998-07-0202 July 1998 Supplemental Application for Amend to Licenses NPF-39 & NPF-85,consisting of TS Change Request 96-06-0,modifying Appearance of Unit 1,FOL Page 8 ML20202G7591998-02-0909 February 1998 Application for Amend to License NPF-39,revising TS Section 2.1, Safety Limits, to Revise Minimum Critical Power Ratio Safety Limit.Proprietary Supporting Info Withheld (Ref 10CFR2.790) ML20199G7701998-01-27027 January 1998 Application for Amends to Licenses NPF-39 & NPF-89,removing Maximum Isolation Time for HPCI Turbine Exhaust Containment Isolation Valve HV-055-1(2)F072 from Ts.Change Request 98-01-0 & marked-up TS Encl ML20198M7551998-01-12012 January 1998 TS Change Request 97-02-1 to License NPF-39,revising TS Table 4.4.6.1.3-1 to Change Withdrawal Schedule for First Capsule to Be Withdrawn from 10 Effective Full Power Yrs to 15 Efpy.Ge Rept GE-NE-B1100786-01,Rev 1 Encl ML20212D1761997-10-24024 October 1997 Application for Amend to License NPF-39,revising TS Section 3/4.1.3.6,to Exempt Control Rod 50-27 from Coupling Test for Remainder of Cycle 7,provided Certain Conditions Are Met ML20216H0931997-09-0808 September 1997 Application for Amends to Licenses NPF-39 & NPF-85, Supplementing Changes Request 96-06-0 by Adding Three Addl TS Pages Containing Typo Errors Discovered Since 970225 Submittal ML20210T9141997-09-0202 September 1997 TS Change Request 96-20-0 to Licenses NPF-39 & NPF-85, Revising TS Section 4.0.5 & Bases Sections B 4.0.5 & B 3/4.4.8,re SRs Associated W/Isi & Inservice Testing of ASME Code Class 1,2 & 3 Components ML20137X7931997-04-0909 April 1997 TS Change Request 96-24-0 to Licenses NPF-39 & NPF-85, Deleting Requirement to Correct Specific Gravity Values Based on Electrolyte Battery State of Charge ML20137G6611997-03-24024 March 1997 Application for Amends to Licenses NPF-39 & NPF-85,deleting Drywell & Suppression Chamber Purge Sys Operational Time Limit & Adding SR to Ensure Purge Sys Large Supply & Exhaust Valves Are Closed as Required ML20135D0861997-02-25025 February 1997 Application for Amends to Licenses NPF-39 & NPF-85, Reflecting Name Change from PA Electric Co to PECO Energy Co ML20135F0911996-12-0606 December 1996 Application for Amend to License NPF-85,revising TS 2.1 to Change Minimum Critical Power Ratio Safety Limit ML20135A3841996-11-25025 November 1996 Application for Amends to Licenses NPF-39 & NPF-85,revising TS SR 4.8.1.1.2.e.2 & Supporting TS Bases Section 3/4.8,to Clarify Requirements Associated W/Single Load Rejection Testing of EDGs ML20128N7551996-09-27027 September 1996 Application for Amends to Licenses NPF-39 & NPF-85, Requesting Rev to Increase Reactor Enclosure Secondary Containment Maximum Inleakage Rate ML20116L2551996-08-0808 August 1996 Application for Amends to Licenses NPF-39 & NPF-85,revising TS Sections 3/4.3.1,3/4.3.2,3/4.3.3 & Associated TS Bases Sections 3/4.3.1 & 3/4.3.2 to Eliminate Selected Response Time Testing Requirements ML20116H6161996-08-0505 August 1996 Application for Amend to License NPF-85,revising TS Section 2.1, Safety Limits, to Revise Min Critical Power Ratio Safety Limit ML20116E5981996-08-0101 August 1996 Application for Amend to License NPF-85,revising TS Section 3/4.4.4.6 to Reflect Addition of Two Hydroset Curves Effective for 6.5 & 8.5 Effective Full Power Years,To Existing Pressure-Temp Operating Limit for LGS Unit 2 ML20115A9071996-06-28028 June 1996 Application for Amend to Licenses NPF-39 & NPF-85 to Perform Containment leakage-rate Testing Per 10CFR50,App J, Primary Reactor Containment Leakage Testing for Water-Cooled Power Reactors, Option B ML20117H2441996-05-20020 May 1996 TS Change Request 96-12-0 to Licenses NPF-39 & NPF-85, Revising TS Sections 3/4.4.9.2,3/4.9.11.1,3/4.9.11.2 & Associated TS Bases 3/4.4.9 & 3/4.9.11 to More Clearly Describe,Rhr Sys Shutdown Cooling Mode of Operation ML20117D7451996-05-0303 May 1996 Application for Amends to Licenses NPF-39 & NPF-85,revising TS SRs to Change Surveillance Test Frequency for Performing Flow Testing of SGTS & RERS from Monthly to Quarterly ML20107M5061996-04-25025 April 1996 TS Change Request 95-08-0 to Licenses NPF-39 & NPF-85, Relocating TS 3/4.7.7 Re Traversing in-core Probe LCO ML20101L9111996-03-29029 March 1996 Application for Amends to Licenses NPF-39 & NPF-85, Respectively,Revising TS SR 4.5.1.d.2.b to Delete Requirement to Perform Functional Testing of ADS Valves as Part of start-up Testing Activities ML20095K4801995-12-22022 December 1995 Application for Amend to Licenses NPF-39 & NPF-85,increasing Drywell & Suppression Chamber Purge Sys Operating Time Limit from 90 H Each 365 Days to 180 H Each 365 Days ML20092J3941995-09-18018 September 1995 TS Change Request 95-01-0 to Licenses NPF-39 & NPF-85, Revising TS Table 4.3.1.1-1, RPS Instrumentation SRs to Reflect Change in Calibr Frequency for LPRM Signal from Every 1,000 EFPH to Every 2,000 Megawatt Days Per Std Ton ML20092J3181995-09-14014 September 1995 Application for Amends to Licenses NPF-39 & NPF-85,revising TS to Remove Secondary Containment Isolation Valve Tables ML20087C9451995-08-0101 August 1995 TS Change Request 95-12-0 Revising TS Section 3/4.9.1, to Provide Alternate Actions to Allow Continuation of Core Alterations in Event Certain RMCS & Refueling Interlocks Are Inoperable ML20086S5981995-07-28028 July 1995 Application for Amends to Licenses NPF-39 & NPF-85,revising TS Table 4.3.1.1-1,to Reflect Changes to Surveillance Test Frequency Requirements for Various RPS Instrumentation ML20086U4821995-07-28028 July 1995 TS Change Request 94-28-0 to Licenses NPF-39 & NPF-85, Revising TS SR & Deleting Specific Requirements to Perform Surveillances Prior to Beginning or Resuming Core Alterations or CR Withdrawal Assoc W/Refueling Activities ML20086U4361995-07-28028 July 1995 TS Change Request 95-09-0 to Licenses NPF-39 & NPF-8, Revising Ts,By Deleting Operability & SR Involving Secondary Containment Diffrential Pressure Instrumentation ML20086T6061995-07-28028 July 1995 TS Change Request 95-13-0 of License NPF-39 & NPF-85, Requesting Change to Ts,To Eliminate TS Requirement to Perform 10CFR50,App J,Type C,Hydrostatic Testing on Certain Valves ML20086A1631995-06-23023 June 1995 Application for Amend to License NPF-85,consisting of Change Request 95-07-2,extending AOT to Allow Adequate Time to Install Isolation Valves & cross-ties on ESW & RHRSW Sys to Facilitate Future Insps or Maint ML20085M8811995-06-20020 June 1995 Application for Amend to Licenses NPF-39 & NPF-85,consisting of Change Request 95-06,requesting one-time Schedular Exemption from 10CFR50,App J, Primary Containment Leakage Testing for Water-Cooled Power Reactors ML20085M9171995-06-19019 June 1995 Application for Amend to License NPF-39,consisting of Change Request 95-03,revising TS Section 2.1, Safety Limits, to Change MCPR Safety Limit,Due to Use of GE13 Fuel Product Line ML20084Q9241995-06-0505 June 1995 Application for Amends to Licenses NPF-39 & NPF-85, Consisting of TS Change Request 94-49-0,revising TS Section 3/4.1.5, SLCS to Remove Min Flow Rate Requirement for SLCS Pumps ML20083R0031995-05-19019 May 1995 Application for Amends to Licenses NPF-39 & NPF-85, Consisting of Change Request 95-02,revising TS Table 3.3.3-3, ECCS Response Times to Reflect Value of 60 Seconds for HPCI Sys Response Time Instead of 30 Seconds ML20082J4001995-04-0606 April 1995 Application for Amends to Licenses NPF-39 & NPF-85, Consisting of TS Change Requests 94-51 Delete Independent Tech Review Section from TS, 94-52 Delete Nrb Review Section from TS, 94-53 Delete Nrb Audit Section from Ts 1999-09-27
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML20217F0941999-10-14014 October 1999 Application for Amends to Licenses DPR-39 & DPR-85,to Revise TS Sections 2.2 & 3.0/4.0 to Support Mod P000224 Which Will Install New Power Range Neutron Monitoring Sys & Incorporate long-term thermal-hydraulic Stability Solution Hardware ML20216J3341999-09-27027 September 1999 Supplements Application for Amends to Licenses NPF-39 & NPF-45,to Modify Appearance of TS Page 3/4 4-8 as Typo Was Identified in Section 3.4.3.1 of Ts.Corrected TS Page,Encl ML20212H5521999-09-27027 September 1999 Application for Amends to Licenses NPF-39 & NPF-85,revising TS to Clarify Several Administrative Requirements,Deleting Redundant Requirements & Correcting Typos ML20212F9521999-09-20020 September 1999 Application for Amend to License NFP-39,requesting Issuance of TS Change Request 98-08-0 Re Increase in Allowable as- Found Main Steam SRV Setpoint Tolerance.Util Had Originally Requested That Subject TS Change Be Deferred in ML20196F5471999-06-22022 June 1999 Application for Amends to Licenses NPF-39 & NPF-85,change Request 99-01-0,to Revise TS to Delete Surveillance Requirement 4.4.1.1.2 & Associated TS Administrative Controls Section 6.9.1.9.h ML20195E7521999-06-0707 June 1999 TS Change Request 91-08-01 to License NPF-39,reflecting Permanently Deactivated Instrument Reference Leg Isolation Valve HV-61-102 in TS Table 3.6.3-1, Primary Containment Isolation Valves & Associated Notations ML20195G0421999-06-0707 June 1999 TS Change Request 98-09-0 for Licenses NPF-39 & NPF-85, Revising TS Section 3/4.4.3, RCS Leakage,Leakage Detection Systems, by Clarifying Action Statement Re Inoperative Reactor Coolant Leakage Detection Systems ML20195B8361999-05-26026 May 1999 TS Change Request 99-02-0 for Licenses NPF-39 & NPF-85, Revising TS Section 4.1.3.5.b by Removing & Relocating Control Rod Scram Accumulators Alarm Instrumentation to UFSAR & Revising TS Section 3.1.3.5 ML20207L6561999-03-11011 March 1999 TS Change Request 98-07-2 for License NPF-85,revising MCPR Safety Limit Contained in TS Section 2.1, Safety Limits. Proprietary & non-proprietary Info Re Cycle Specific SLMCPR for Lgs,Unit 2 Cycle 6,encl.Proprietary Info Withheld ML20199G1651999-01-12012 January 1999 TS Change Request 98-08-0 to Licenses NPF-39 & NPF-85, Proposing Rev to TS Section 3/4.4.2 & TS Bases Sections B 3/4.4.2,B 3/4.5.1 & B 3/4.5.2.Supporting TSs & Proprietary & non-proprietary Trs,Encl.Proprietary Info Withheld ML20199A6861999-01-0404 January 1999 TS Change Request 97-01-01 to Licenses NPF-39 & NPF-85, Revising Administrative Section on Controlled Access to High Radiation Areas & Rept Dates for Listed Repts ML20155H6311998-10-30030 October 1998 Application for Amends to Licenses NPF-39 & NPF-85, Respectively,Revising TS Surveillance Requirements 4.8.4.3.b.1,4.8.4.3.b.2 & 4.8.4.3.b.3 in Order to Reflect Relay Setpoint Calculation Methodology ML20154Q8781998-10-15015 October 1998 TS Change Request 97-04-0 to Licenses NPF-39 to NPF-85, Adding New TS Section & TS Bases Section to Incorporate Special Test Exception to Allow Rc Temp Greater than 200 F During IST & Hydrostatic Testing ML20151Z4541998-09-14014 September 1998 TS Change Request 98-04-2 to License NPF-85,revising TS Table 4.4.6.1.3-1 Re Withdrawal Schedule for Reactor Pressure Vessel Matl Surveillance Program Capsules.Ge Rept GE-NE-B1100786,encl ML20151V0731998-09-0404 September 1998 TS Change Request 96-23-0 to Licenses NPF-39 & NPF-85, Revising TS Pages to Ensure Fidelity Between TS Pages & 970324 Submittal ML20236L5151998-07-0202 July 1998 Supplemental Application for Amend to Licenses NPF-39 & NPF-85,consisting of TS Change Request 96-06-0,modifying Appearance of Unit 1,FOL Page 8 ML20247M6891998-05-14014 May 1998 Amend 128 to License NPF-39,documenting NRC Staff Approval of Implementation of Plant Mod to Support Installation of Replacement Suction Strainers for ECCS at Plant,Unit 1 ML20217Q5001998-05-0404 May 1998 Amend 127 to License NPF-39,revising Minimal Critical Power Ratio Safety Limits for Operation Cycle 8 ML20217M0731998-03-31031 March 1998 Amends 125 & 89 to Licenses NPF-39 & NPF-85,respectively, Revising LGS Units 1 & 2 TS Section 4.0.5 & Bases Sections B 3/4.4.8 Re Surveillance Requirements Associated W/Isi & IST ML20202G7591998-02-0909 February 1998 Application for Amend to License NPF-39,revising TS Section 2.1, Safety Limits, to Revise Minimum Critical Power Ratio Safety Limit.Proprietary Supporting Info Withheld (Ref 10CFR2.790) ML20199G7701998-01-27027 January 1998 Application for Amends to Licenses NPF-39 & NPF-89,removing Maximum Isolation Time for HPCI Turbine Exhaust Containment Isolation Valve HV-055-1(2)F072 from Ts.Change Request 98-01-0 & marked-up TS Encl ML20198M7551998-01-12012 January 1998 TS Change Request 97-02-1 to License NPF-39,revising TS Table 4.4.6.1.3-1 to Change Withdrawal Schedule for First Capsule to Be Withdrawn from 10 Effective Full Power Yrs to 15 Efpy.Ge Rept GE-NE-B1100786-01,Rev 1 Encl ML20212D1761997-10-24024 October 1997 Application for Amend to License NPF-39,revising TS Section 3/4.1.3.6,to Exempt Control Rod 50-27 from Coupling Test for Remainder of Cycle 7,provided Certain Conditions Are Met ML20216H0931997-09-0808 September 1997 Application for Amends to Licenses NPF-39 & NPF-85, Supplementing Changes Request 96-06-0 by Adding Three Addl TS Pages Containing Typo Errors Discovered Since 970225 Submittal ML20210T9141997-09-0202 September 1997 TS Change Request 96-20-0 to Licenses NPF-39 & NPF-85, Revising TS Section 4.0.5 & Bases Sections B 4.0.5 & B 3/4.4.8,re SRs Associated W/Isi & Inservice Testing of ASME Code Class 1,2 & 3 Components ML20137X7931997-04-0909 April 1997 TS Change Request 96-24-0 to Licenses NPF-39 & NPF-85, Deleting Requirement to Correct Specific Gravity Values Based on Electrolyte Battery State of Charge ML20137G6611997-03-24024 March 1997 Application for Amends to Licenses NPF-39 & NPF-85,deleting Drywell & Suppression Chamber Purge Sys Operational Time Limit & Adding SR to Ensure Purge Sys Large Supply & Exhaust Valves Are Closed as Required ML20135D0861997-02-25025 February 1997 Application for Amends to Licenses NPF-39 & NPF-85, Reflecting Name Change from PA Electric Co to PECO Energy Co ML20135F0911996-12-0606 December 1996 Application for Amend to License NPF-85,revising TS 2.1 to Change Minimum Critical Power Ratio Safety Limit ML20135A3841996-11-25025 November 1996 Application for Amends to Licenses NPF-39 & NPF-85,revising TS SR 4.8.1.1.2.e.2 & Supporting TS Bases Section 3/4.8,to Clarify Requirements Associated W/Single Load Rejection Testing of EDGs ML20128N7551996-09-27027 September 1996 Application for Amends to Licenses NPF-39 & NPF-85, Requesting Rev to Increase Reactor Enclosure Secondary Containment Maximum Inleakage Rate ML20116L2551996-08-0808 August 1996 Application for Amends to Licenses NPF-39 & NPF-85,revising TS Sections 3/4.3.1,3/4.3.2,3/4.3.3 & Associated TS Bases Sections 3/4.3.1 & 3/4.3.2 to Eliminate Selected Response Time Testing Requirements ML20116H6161996-08-0505 August 1996 Application for Amend to License NPF-85,revising TS Section 2.1, Safety Limits, to Revise Min Critical Power Ratio Safety Limit ML20116E5981996-08-0101 August 1996 Application for Amend to License NPF-85,revising TS Section 3/4.4.4.6 to Reflect Addition of Two Hydroset Curves Effective for 6.5 & 8.5 Effective Full Power Years,To Existing Pressure-Temp Operating Limit for LGS Unit 2 ML20115A9071996-06-28028 June 1996 Application for Amend to Licenses NPF-39 & NPF-85 to Perform Containment leakage-rate Testing Per 10CFR50,App J, Primary Reactor Containment Leakage Testing for Water-Cooled Power Reactors, Option B ML20117H2441996-05-20020 May 1996 TS Change Request 96-12-0 to Licenses NPF-39 & NPF-85, Revising TS Sections 3/4.4.9.2,3/4.9.11.1,3/4.9.11.2 & Associated TS Bases 3/4.4.9 & 3/4.9.11 to More Clearly Describe,Rhr Sys Shutdown Cooling Mode of Operation ML20117D7451996-05-0303 May 1996 Application for Amends to Licenses NPF-39 & NPF-85,revising TS SRs to Change Surveillance Test Frequency for Performing Flow Testing of SGTS & RERS from Monthly to Quarterly ML20107M5061996-04-25025 April 1996 TS Change Request 95-08-0 to Licenses NPF-39 & NPF-85, Relocating TS 3/4.7.7 Re Traversing in-core Probe LCO ML20101L9111996-03-29029 March 1996 Application for Amends to Licenses NPF-39 & NPF-85, Respectively,Revising TS SR 4.5.1.d.2.b to Delete Requirement to Perform Functional Testing of ADS Valves as Part of start-up Testing Activities ML20095K4801995-12-22022 December 1995 Application for Amend to Licenses NPF-39 & NPF-85,increasing Drywell & Suppression Chamber Purge Sys Operating Time Limit from 90 H Each 365 Days to 180 H Each 365 Days ML20092J3941995-09-18018 September 1995 TS Change Request 95-01-0 to Licenses NPF-39 & NPF-85, Revising TS Table 4.3.1.1-1, RPS Instrumentation SRs to Reflect Change in Calibr Frequency for LPRM Signal from Every 1,000 EFPH to Every 2,000 Megawatt Days Per Std Ton ML20092J3181995-09-14014 September 1995 Application for Amends to Licenses NPF-39 & NPF-85,revising TS to Remove Secondary Containment Isolation Valve Tables ML20087C9451995-08-0101 August 1995 TS Change Request 95-12-0 Revising TS Section 3/4.9.1, to Provide Alternate Actions to Allow Continuation of Core Alterations in Event Certain RMCS & Refueling Interlocks Are Inoperable ML20086S5981995-07-28028 July 1995 Application for Amends to Licenses NPF-39 & NPF-85,revising TS Table 4.3.1.1-1,to Reflect Changes to Surveillance Test Frequency Requirements for Various RPS Instrumentation ML20086U4821995-07-28028 July 1995 TS Change Request 94-28-0 to Licenses NPF-39 & NPF-85, Revising TS SR & Deleting Specific Requirements to Perform Surveillances Prior to Beginning or Resuming Core Alterations or CR Withdrawal Assoc W/Refueling Activities ML20086U4361995-07-28028 July 1995 TS Change Request 95-09-0 to Licenses NPF-39 & NPF-8, Revising Ts,By Deleting Operability & SR Involving Secondary Containment Diffrential Pressure Instrumentation ML20086T6061995-07-28028 July 1995 TS Change Request 95-13-0 of License NPF-39 & NPF-85, Requesting Change to Ts,To Eliminate TS Requirement to Perform 10CFR50,App J,Type C,Hydrostatic Testing on Certain Valves ML20086A1631995-06-23023 June 1995 Application for Amend to License NPF-85,consisting of Change Request 95-07-2,extending AOT to Allow Adequate Time to Install Isolation Valves & cross-ties on ESW & RHRSW Sys to Facilitate Future Insps or Maint ML20085M8811995-06-20020 June 1995 Application for Amend to Licenses NPF-39 & NPF-85,consisting of Change Request 95-06,requesting one-time Schedular Exemption from 10CFR50,App J, Primary Containment Leakage Testing for Water-Cooled Power Reactors ML20085M9171995-06-19019 June 1995 Application for Amend to License NPF-39,consisting of Change Request 95-03,revising TS Section 2.1, Safety Limits, to Change MCPR Safety Limit,Due to Use of GE13 Fuel Product Line 1999-09-27
[Table view] |
Text
._- -- - - . - .- . . - . __
7
Ye *e 10 CFR 50.90 0; i PHILADELPHIA ELECTRIC COMPANY j NUCLEAR GROUP HEADQUARTERS f 955 65 CHESTERBROOK BLVD. !
WAYNE, PA 19087 5691 f' m .i........ .
i t
March 20, 1990 !
Docket No. 50-352 i License No. NPF-39 l 1
U.S. Nuclear Regulatory Commission l ATTN: Document Control Desk Washington, DC 20555
SUBJECT:
Limerick Generating Station, Unit 1 i Technical Specifications Change Request !
t Dear Sir-PhiladelphiaElectricCompany(PECo)herebysubmitsUnit1 Technical l Specifications Change Request No. 89-06, in 6ccordance with 10 CFR 50.90, !
requesting an amendment to the Technical Specifications (Appendix A) of j' Operating License No. NPF-39. . Information supporting this Change Request, which i; L. makes administrative changes to eliminate differences between Unit 1 and Unit 2 ;
l Technical Specifications, is contained in Attachment 1 to this letter. The l > proposed replacement pages are contained in Attachment 2. All proposed changes !
are indicated in the text by revision bars in the u rgin. .j If you have any questions regarding this matter, please contact us. !
l t Very truly yours, i
- 4. a.
G. A. Hur.ger, Jr, Mep), . !
Director i Licensing Section :
Nuclear Services Department
-cc: 'W. T. Russell, Administrator, Region I. USNRC T. J. Kenny, USNRC Senior Resident Inspector, LGS T. M. Gerusky, Director, PA Bureau of Radiological Protection i l f@[0ggggk$$ {2 e
1
a i, ,- TECHNICAL SPECIFICATIONS CHANGE REQUEST
(. .
NO. 89-06 L
I f
COMMONWEALTH OF PENNSYLVANIA
[ ss.
. COUNTY OP CHESTER :
F.
D. R. Helwig, being first duly sworn, deposes and sayst That he is Vice President of Philadelphia Electric Company; the Applicant'herein; that he has read the foregoing Application for Amendment of Facility Operating Licenses to make administrative changes to eliminate differences between Unit 1 and Unit 2 Technical Specifications, and knows the contents thereof; and that the statements and matters set forth therein are true and correct to the best of his knowledge, information and belief.
] V ,
Vice P estdent Subscribed and sworn to before me thisdOIay ofIX'Mefl990.
bCCArh< r/$ NI M Notary Public NOTAFUAL SEAL CATHERINE A. MENDEZ. Notary Public Trecyffrin Two.. Chester County My Commies!ci Encires Sect. 4.1903 I
J
5, a;c c
i ATTACHMENT 1 LIMERICK GENERATING STATION UNIT 1 Docket No. 50-352 License No. NPF-39 i
TECHNICAL SPECIFICATIONS CHANGE REQUEST Proposed Changes to the Technical Specifications to Eliminate Differences Between Unit 1 and Unit 2 l
Technical Specifications i
i Supporting Infomation for Changes - 8 pages i
1 L
L
~
y i /. ' . +
I ;
5 7
,- Docket No. 50-352 .i I'
j Philadelphia Electric Company (PECo). Licensee under Facility. i Operating License NPF-39 for Limerick Generating Station (LGS), Unit 1 hereby requests that the Technical Specifications (TS) contained in AppeMix A of the i Operating License be amended as proposed herein to make various administrative !
changes to eliminate differences between the Unit 1 and Unit 2 TS. The proposed ;
changes are listed and the proposed change pages are provided in Attachment 2.
The proposed changes are indicated by vertical bars in the margin of the pages. (
PECo requests the changes proposed herein to be effective upon issuance of the L Amendment. I l
This change request provides a discussion and description of the :
proposed TS changes, a safety assessment of the proposed TS changes, infomation
- supporting a finding of No Significant Hazards Consideration, and information i supporting an Environmental Assessment.
l . Discussion and Description of Changes ,
I s
The proposed changes to the LGS Unit 1 TS are identified on the the
" List of Changes" contained in the front of Attachment 2. These changes have l- been divided into seven (7) groups as shown by the numbers in the left hand j column of the List. A discussion of each group is provided 'velow by the c rresponding numbers. The proposed changes that are editorial changes are l l- identified as such on the " List of Changes" and no further discussion is l
l provided below.
i l 1. Revise Note
- in Table 3.3.2-1. Table 4.3.2.1-1 and Section 3.6.5.2.2 of the TS in accordance with the changes previously made to Note
, *} - Docket No. 50-352 ;
m -
i Lic;nse No. NPf-39 I i
TS Sections 3.6.5.1.2 and 3.6.5.3 by Unit 1 TS Amendment 29. These changes clarified the definition of OPERATIONAL CONDITION
- but the changes were not implemented in every TS which references OPERATIONAL l
CONDITION *. This is an administrative change to achieve consistency-throughout the Unit 1 TS and to eliminate differences between Unit 1 i
and Unit 2 TS.
- 2. Revise TS Section 4.3.7.2.2 by incorporating the changes incorporated by NRC in the original Unit 2 TS. This change is an administrative change to clarify the fact that some seismic instruments are not accessible during power operation and to clarify when these '
instruments are required to be restored to OPERABLE status following an actuation. ,
l Revise TS Table 3.3.7.2-1 to replace the triaxal seismic trigger and switches range information with notes which provide setpoint information. This is an administrative change to correct an error, i Providing range information for the trigger and switches is not t
l meaningful because their function is to activate recording equipment at a given setpoint. Therefore, the appropriate information to be ;
! included is the setpoint.
l l Add for clarification, the location of the seismic trigger and the response spectrum analyzer since these locations were originally I omitted from the Table. All of the above proposed changes will eliminate differences between Unit 1 and Unit 2 TS.
- 3. Delete the statements / note from TS Sections 4.6.5.3.g and 4.7.2e.3 ana TS Bases 3/4.6.5 which refer to " initial criticality of Unit 2" l
l
. ',; ,f Docket No. 50-352 l
License No. NPF-39 i e :
and "the issuance of the Unit 2 full power operating license." These i events have already occurred and therefore the statements / note no longer apply and can be administratively removed.
i
- 4. Add "- COW ON SYSTEM" to the TS Section 3/4.6.5.3 title for Standby Gas Treatment System (SGTS) and to the TS Section 3/4.7.2 title for Control Room Emergency fresh Air Supply System (CREFAS). The NRC l proposed and implemented the same editorial change to the Residual ;
Heat Removal Service Water System (RHRSW) and the Emergency Service Water System (ESW) in Unit 1 TS Amendment 27 to clearly alert the operators that there is an interdependency between units. This same interdependency exists for SGTS and CREFAS and the proposed change will achieve consistency throughout the Unit 1 TS. The appropriate changes to the corresponding TS Index pages and Bases pages will also be made. This change was incorporated by the NRC throughout the original Unit 2 TS for the SGTS, CREFAS, RHRSW and ESW.
- 5. Revise the ACTION statements for the diesel generators in TS Section '
3.9.1.1 to incorporate the more restrictive ACTION requirements which were administrative 1y required by PORC Position 45 as committed to in our June 14, 1989 letter to the NRC and incorporated in the original -
Unit 2 TS.
During the developmeni, of the Unit 2 TS, the NRC determined that the l
proposed TS ACTION requirements for an inoperable diesel generator were not restrictive enough. Specifically, the NRC concluded that a 92 day allowable out-of-service time (A0T) for one diesel generator was too long, therefore the probability of failure of a second diesel generator, if required, was too high. This became critical if l _ _ .
i
_, Docket No, 50-352 l
i Lic:nse No. NPF-39 l R certain combinations of diesel generators became unavailable, resulting in two-train safety systems without the capability of being p powered by an OPERABLE on-site power source. Thus, the 92 day A0T I was reduced to 30 days.
Also, due to the system loading of the diesel generators. ACTION 'e' '
wasrevisedtoreflectthatifone(nolongertwo)dieselgenerator l becomes inoperable, the redundant systems fed from the remaining OPERABLE diesel generator (s) must be OPERABLE. ;
l The 30 day allowable out-of-service time (A0T) and the revised ACTION r
'e' are more restrictive than the requirements presently contained in the Unit 1 TS, which were originally determined to be acceptable by the NRC for operation of Unit 1 as a single unit station. A note j i
will also be added to TS ACTIONS 'a', 'b', 'c', 'd', and 'h' to serve as a reminder to the operators to consider the special requirements of ACTION 'e.' The Unit 1 TS Bases 3/4.8 will also be revised to incorporate, as appropriate, the changes made by the NRC to the Unit 2 TS Bases which were required by the revision of the ACTION statements. These are administrative changes which incorporate more ;
restrictive requirements and which will eliminate differences between Unit I and Unit 2 TS.
- 6. Add a statement to TS Bases 3/4.4.3.2 concerning the ACTION requirements for pressure isolation valves. This is an administrative change to the TS Bases which was requested by the NRC during the development of the Unit 2 TS in order to clarify the existing bases. This change will eliminate differences between the Unit 1 and Unit 2 TS.
{ y i p '; , _ ',* Docket No. 50-352 !
L License No. NPF-39 .[ !
- 7. Add an asterisk to the title of TS Section 6.9.1.6. " Monthly f Operating Reports." to indicate that a single submittal of the report f is made for both units. This is an administrative change to achieve !
I consistency between Unit 1 and Unit 2 TS. :
l Safety Assessment The proposed changes to the TS will achieve consistency throughout I the TS. provide clarification, correct errors, eliminate statements thet no '
longer apply, and make editorial changes. These are purely administrative changes. The proposed diesel generator TS ACTION changes administratively i incorporate into the TS previously implemented requirements that are more ,
restrictive than the requirements presently included in the TS. The proposed '
changes to the TS do not affect plant design, hardware, system operation, or procedures. Therefore, the changes do not impact any accidents previously cvaluated in the SAR nor any equipment important to safety.
l Information Supporting a Finding of No Significant Hazards Consideration .
We have concluded that the proposed changes to the LGS Unit 1 TS, '
l-l .which make administrative changes to eliminate differences between Unit 1 and .
1 Unit 2 TS do not constitute a significant hazards consideration. In support of this determination, an evaluation of each of the three standards set forth in 10 CFR 50.92 is provided below.
- 1. The proposed changes do not involve a significant increase in the ,
r probability or consequences of an accident previously evaluated.
- p. ,.
, 'c- Docket ~No. 50-352 g License No. NPF-39 The proposed changes to the TS will achieve consistency throughout the TS, provide clarification, correct errors, eliminate statements that no longer apply, and make editorial changes. These are purely administrative changes. The proposed diesel gerarator TS ACTION
' changes administrative 1y incorporate into the TS previously f
implemented requirements that are more restrictive than the I requirements presently included in the TS. The proposed changes to the TS do not affect plant design, hardware, system operation, or i procedures. Therefore, the proposed changes will not result in a ;
significant increase in the probability or consequences of an accident previously evaluated.
- 2. The proposed changes do not create the possibility of a new or ,
difference kind of accident from any accident previously evaluated.
P As discussed in item 1. above, the proposed TS changes are purely administrative changes and do not affect plant design, hardware. ;
system operation, or procedures. Therefore, the proposed changes do not create the possibility of a new or different kind of accident from any accident previously evaluated.
l 1
- 3. The proposed changes do not involve a significant reduction in a margin of safety.
I '
As discussed in Item 1. above, the proposed TS changes are purely administrative changes and do not affect plant design, hardware system operation, on procedures. Therefore, the proposed changes do not involve a significant reduction in a margin of safety.
L l
, , Docket No. 50-352 Licens? No. NPf-39 l Jnformation Supporting an Environmental Assessment l
l An environmental assessment is not required for the changes proposed I by this Change Request because the requested changes conform to the criteria for i
- actionseligibleforcategoricalexclusion"asspecifiedin10CFR51.22(c)(9). ,
l The requested changes will have no impact on the environment. This Change ,
Request does not involve a significant hazards consideration as discussed in the l preceding section. This Change Request does not involve a significant change in the types or significant increase in the amounts of any effluents that may be ;
released offsite. In addition, this Change Request does not involve a ,
significant increase in individual or cumulative occupational radiation '
exposure..
4 Conclusion The Plant Operations Review Committee and the Nuclear Review Board <
have reviewed these proposed changes to the TS and have concluded that they do not involve an unreviewed safety question or a significant hazards consideration, and will not endanger the health and safety of the public.