05000321/LER-1979-053-03, Ler 79-053/03L-0 on 790801:during Surveillance Procedure HNP-1-3001,high Reactor Pressure Trip Switch B21-N023B Actuated at 1075 Psig.Caused by Setpoint Drift.Switch Recalibr & Functional Test Successfully Completed

From kanterella
(Redirected from ML19249A794)
Jump to navigation Jump to search
Ler 79-053/03L-0 on 790801:during Surveillance Procedure HNP-1-3001,high Reactor Pressure Trip Switch B21-N023B Actuated at 1075 Psig.Caused by Setpoint Drift.Switch Recalibr & Functional Test Successfully Completed
ML19249A794
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 08/17/1979
From:
GEORGIA POWER CO.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19249A786 List:
References
LER-79-053-03L-01, LER-79-53-3L-1, NUDOCS 7908240339
Download: ML19249A794 (1)


LER-1979-053, Ler 79-053/03L-0 on 790801:during Surveillance Procedure HNP-1-3001,high Reactor Pressure Trip Switch B21-N023B Actuated at 1075 Psig.Caused by Setpoint Drift.Switch Recalibr & Functional Test Successfully Completed
Event date:
Report date:
3211979053R03 - NRC Website

text