Letter Sequence Other |
---|
EPID:L-2018-LLA-0062, License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System (LDCN 16-0013) (Approved, Closed) |
|
MONTHYEARML18068A6852018-03-0909 March 2018 License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System (LDCN 16-0013) Project stage: Request ML18107A7482018-04-17017 April 2018 NRR E-mail Capture - Acceptance Review for EPID L-2018-LLA-0062 Callaway LAR Callaway TS Change for Class 1E AC system-- Status Accepted Project stage: Acceptance Review ML18156A4042018-06-19019 June 2018 Regulatory Audit Plan for September 18-19, 2018, in Support of License Amendment Request to Incorporate New Technical Specification 3.7.20 Project stage: Other ML18353B0162019-01-0404 January 2019 Regulatory Audit Summary License Amendment Request to Incorporate a New Technical Specification 3.7.20 Project stage: Other ML19024A4752019-01-23023 January 2019 Attachment 5 - List of Regulatory Commitments Project stage: Request ULNRC-06477, Supplement to License Amendment Request for Additional of New Technical Specification 3.7.20, Class IE Electrical Equipment Air Conditioning (A/C) System (LDCN 16-0013)2019-01-23023 January 2019 Supplement to License Amendment Request for Additional of New Technical Specification 3.7.20, Class IE Electrical Equipment Air Conditioning (A/C) System (LDCN 16-0013) Project stage: Supplement ML19024A4692019-01-23023 January 2019 Supplement to License Amendment Request for Additional of New Technical Specification 3.7.20, Class IE Electrical Equipment Air Conditioning (A/C) System (LDCN 16-0013) Project stage: Request ML19039A3522019-02-0808 February 2019 Response to Request for Additional Information Pertaining to License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System. Project stage: Request ULNRC-06482, Response to Request for Additional Information Pertaining to License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System.2019-02-0808 February 2019 Response to Request for Additional Information Pertaining to License Amendment Request for Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System. Project stage: Response to RAI ML19044A5052019-02-21021 February 2019 License Conditions Associated with License Amendment Regarding Addition of New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System Project stage: Other ULNRC-06491, Additional Supplement to License Amendment Request for Addition of New Technical Specification 3.7.20, Class IE Electrical Equipment Air Conditioning (A/C) System (LDCN 16-0013)2019-03-0707 March 2019 Additional Supplement to License Amendment Request for Addition of New Technical Specification 3.7.20, Class IE Electrical Equipment Air Conditioning (A/C) System (LDCN 16-0013) Project stage: Supplement ML19073A0012019-04-18018 April 2019 Issuance of Amendment No. 219 to Add New Technical Specification 3.7.20, Class 1E Electrical Equipment Air Conditioning (A/C) System Project stage: Approval 2019-01-04
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000483/20253012024-08-0505 August 2024 Notification of NRC Initial Operator Licensing Examination 05000483/2025301 ML24212A2822024-08-0202 August 2024 Regulatory Audit Summary Concerning Review of Request No. C3R-01 for Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections IR 05000483/20240022024-07-18018 July 2024 and Independent Spent Fuel Storage Installation Integrated Inspection Report 05000483/2024002 and 07201045/2024001 ML24185A1032024-07-16016 July 2024 2024 Biennial Problem Identification and Resolution Inspection Report ULNRC-06891, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00052024-06-26026 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0005 ULNRC-06892, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00062024-06-26026 June 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0006 ULNRC-06884, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00022024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0002 ULNRC-06886, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00042024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0004 ULNRC-06885, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00032024-06-12012 June 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0003 ML24144A0492024-06-11011 June 2024 Requests for Relief from ASME OM Code Pump and Valve Testing Requirements for Fifth 120-Month Inservice Testing Interval ML24178A1132024-06-0606 June 2024 Ameren Missouris Intent to Adopt Revision 1 to Amendment 0 of Certificate of Compliance No. 1040 as Applicable to the ISFSI at the Callaway Plant Site ML24158A5222024-06-0606 June 2024 Application to Revise Technical Specifications to Adopt Tstf-569, Rev. 2, Revise Response Time Testing Definition (LDCN 24-0008) ML24143A1632024-05-23023 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Storage Canister HGMPC0001 ML24137A2342024-05-16016 May 2024 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Canister HGMPC0011 ULNRC-06882, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC00122024-05-16016 May 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0012 ML24122A1502024-05-0707 May 2024 Audit Plan to Support Review of Steam Generator License Renewal Response to Commitment Nos 34 and 35 IR 05000483/20244022024-05-0606 May 2024 Security Baseline Inspection Report 05000483/2024402 (Full Report) ULNRC-06877, Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 252024-05-0606 May 2024 Final Safety Analysis Report Revision OL-27 and Technical Specification Bases Revision 25 ULNRC-06856, CFR 50.59 and 10 CFR 72.48 Summary Report2024-05-0101 May 2024 CFR 50.59 and 10 CFR 72.48 Summary Report IR 05000483/20240112024-05-0101 May 2024 NRC Post-Approval Site Inspection for License Renewal (Phase 2) Report 05000483/2024011 ML24122A1132024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radioactive Effluent Release Report ULNRC-06869, Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report2024-04-30030 April 2024 Submittal of Callaway, Unit 1, 2023 Annual Radiological Environmental Operating Report ULNRC-06876, Registration of Dry Spent Fuel Storage Canister HGMPC00102024-04-25025 April 2024 Registration of Dry Spent Fuel Storage Canister HGMPC0010 ULNRC-06866, Submittal of Cycle 26 Commitment Change Summary Report2024-04-17017 April 2024 Submittal of Cycle 26 Commitment Change Summary Report ULNRC-06871, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00072024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0007 ULNRC-06872, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC00082024-04-17017 April 2024 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Canister HGMPC0008 ML24108A1082024-04-17017 April 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Canister HGMPC0009 IR 05000483/20240012024-04-16016 April 2024 Integrated Inspection Report 05000483/2024001 IR 05000483/20244042024-04-0909 April 2024 Cyber Security Inspection Report 05000483/2024404 05000483/LER-2024-001, Submittal of LER 2024-001-00 for Callaway Plant, Unit 1, Reactor Trip Due to Turbine Trip2024-04-0404 April 2024 Submittal of LER 2024-001-00 for Callaway Plant, Unit 1, Reactor Trip Due to Turbine Trip ML24088A3212024-04-0101 April 2024 Notification of Commercial Grade Dedication Inspection (05000483/2024013) and Request for Information ML24086A5132024-03-26026 March 2024 CFR 50.46 Annual Report Regarding ECCS Evaluation Model Revisions ULNRC-06863, Submittal of Annual Exposure Report for 20232024-03-20020 March 2024 Submittal of Annual Exposure Report for 2023 ML24079A1622024-03-19019 March 2024 Re Nuclear Property Insurance Reporting ML24066A1932024-03-0707 March 2024 2024 Callaway Plant Notification of Biennial Problem Identification and Resolution Inspection and Request for Information ULNRC-06852, Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 262024-03-0505 March 2024 Owners Activity Reports (OAR-1 Forms) for Cycle/Refuel 26 IR 05000483/20230062024-02-28028 February 2024 Annual Assessment Letter for Callaway Plant Report 05000483/2023006 ML24052A3662024-02-26026 February 2024 Regulatory Audit Plan in Support of Proposed Alternative to ASME Code, Section XI Requirements for Containment Building Inspections ULNRC-06858, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-02-21021 February 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation IR 05000483/20230022024-02-21021 February 2024 Amended Integrated Inspection Report 05000483/2023002 ML24036A1712024-02-20020 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0079 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ULNRC-06853, Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.7172024-01-29029 January 2024 Submittal of 2023 Fitness for Duty Performance Data Per Per 10 CFR 26.717 IR 05000483/20230042024-01-19019 January 2024 Integrated Inspection Report 05000483/2023004 ML24008A0552024-01-19019 January 2024 Acceptance of Requested Licensing Action - Proposed Alternative to the Requirements of the ASME Code (EPID L-2023-LLR- 0061) ML23353A1712024-01-18018 January 2024 Issuance of Amendment No. 237 to Clarify Support System Requirements for the Residual Heat Removal System and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23317A0012024-01-12012 January 2024 Audit Summary Regarding LAR to Clarify Support System Requirements for the Residual Heat Removal and Control Room Air Conditioning System Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 ML23347A1212024-01-11011 January 2024 Issuance of Amendment No. 236 to Adopt TSTF-501, Revision 1, Relocate Stored Fuel Oil and Lube Volume Values to Licensee Control EPID L-2023-LLA-0046) ML24011A1492024-01-11011 January 2024 Notification of Post-Approval Site Inspection for License Renewal and Request for Information (05000483/2024011) ULNRC-06847, Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01)2023-12-21021 December 2023 Supplement to Relief Request from Requirements of ASME BPV Code, Section XI, Subsection Iwl Regarding Examination and Testing of the Unbonded Post-Tensioning System (Relief Request C3R-01) ULNRC-06849, License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds2023-12-20020 December 2023 License Renewal Resolution for Commitments 34 and 35 Perform Evaluation of Crack Initiation and Propagation in Steam Generator Divider Plate and Tube-To-Tubesheet Welds 2024-08-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, O.C. 20555-0001 February 21, 2019 Mr. Fadi Diya Senior Vice President and Chief Nuclear Officer Ameren Missouri Callaway Energy Center 8315 County Road 459 Steedman, MO 65077
SUBJECT:
CALLAWAY PLANT, UNIT NO. 1 -LICENSE CONDITION ASSOCIATED WITH LICENSE AMENDMENT REGARDING ADDITION OF NEW TECHNICAL SPECIFICATION 3.7.20, "CLASS 1E ELECTRICAL EQUIPMENT AIR CONDITIONING (A/C) SYSTEM" (EPID L-2018-LLA-0062)
Dear Mr. Diya:
By application dated March 9, 2018 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML18068A685), as supplemented by letters dated January 23, 2019, and February 8, 2019 (ADAMS Package Accession Nos. ML19024A469 and ML19039A352, respectively), Union Electric Company (dba Ameren Missouri, the licensee),
requested the addition of a new Technical Specification (TS} to the Callaway Plant, Unit No. 1 (Callaway) operating license.
The license amendment request proposes a new TS to address the operation of the room cooling for essential electrical equipment. Specifically, the proposed amendment would add new TS 3.7.20, "Class 1E Electrical Equipment Air Conditioning (A/C) System," including (1) a Limiting Condition for Operation (LCO) statement, (2) an Applicability statement, during which the LCO must be met, (3) Actions to be applied when the LCO is not met, including Conditions, Required Actions, and Completion Times, and (4) Surveillance Requirements with a specified Frequency to demonstrate that the LCO is met. In addition, the proposed amendment also revises TS 5.5.11, "Ventilation Filter Testing Program (VFTP)," Item "e" in the Administrative Controls section of the Callaway TSs, wherein the value specified for the wattage required to be dissipated by the heater in each control room pressurization train is proposed to be changed from 15 +/- 2 kilowatts (kW) to 5 +/- 1 kW. of the supplemental letter dated January 23, 2019 (ADAMS Accession No. ML19024A475), provided a list of regulatory commitments, which superseded the regulatory commitments provided as Attachment 6 of the application dated March 9, 2016 (ADAMS Accession No. ML18068A692). The U.S. Nuclear Regulatory Commission (NRC) staff has determined that completion of the commitments and the implementation of the amendment's modifications are essential to the operability and performance of the new system and its related TS change. Therefore, if the amendment is approved, the NRC staff intends to elevate all of the commitments in Attachment 5 of the letter dated January 23, 2019, as a condition of the license by referring to it in a future Section 2.C.18. Please provide revised TS markup pages, and TS clean pages to supplement the amendment, accordingly, by March 8, 2019.
F. Diya The proposed license condition was discussed with Mr. Tom Elwood of your staff on February 13, 2019. To support the issuance of the safety evaluation in a timely manner, Union Electric Company should review the regulatory commitments in Attachment 5 of the supplemental letter dated January 23, 2019, to prevent any unintended consequences of their use as license conditions. The review should be reflected and confirmed in a letter submitted by March 8, 2019. It should be noted, however, that the licensee's confirmation of the license condition format does not constitute completion of the NRC staff's review or approval of the proposed license amendment.
If you have any questions, please contact me at 301-415-5136 or via e-mail at John.Klos@nrc.gov.
Sincerely, L. John Klos, Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-483 cc: Listserv
ML19044A505 OFFICE NRR/D0RL/LPL4/PM NRR/D0RL/LPL4/LA NRR/D0RL/LPL4/BC NRR/D0RL/LPL4/PM NAME JKlos PBlechman RPascarelli JKlos (MO'Banion for)
DATE 2/14/2019 2/15/2019 2/19/19 2/21/19