NRC Region I Twitter posts from Oct. 1 to Dec. 31, 2018 Oct. 3, 2018 The NRC staff has issued a Draft Safety Evaluation for NextEras license amendment request that seeks to address alkalai silica reaction (ASR), or concrete degradation, issues at the Seabrook nuclear power plant in Seabrook, N.H.:

https://www.nrc.gov/docs/ML1822/ML18226A205.pdf Oct. 4, 2018

The #NRC has a new Senior Resident Inspector at the #Pilgrim #nuclear power plant in Plymouth, Mass.: nrc.gov/reading-rm/doc https://www. -collections/news/2018/18-022.i.pdf .

Oct. 4, 2018 The #NRC has formally accepted for review the application to transfer the license for the

  1. OysterCreek #nuclear power plant, in #Lacey Township (Ocean County), N.J., from Exelon to Holtec: https://www.nrc.gov/docs/ML1827/ML18270A021.pdf

Oct. 10, 2018 The #NRC has issued a report on its third Confirmatory Action Letter follow-up inspection at the

  1. Pilgrim #nuclear power plant in #Plymouth, Mass.: nrc.gov/docs/ML1828/ML .

https://www. 18282A039.pdf Oct. 12, 2018 The #NRC has approved the transfer of the license for the permanently shutdown #VermontYankee

  1. nuclear power plant following a thorough review: nrc.gov/reading-rm/doc .

https://www. -collections/news/2018/18-047.pdf

Oct. 16, 2018 The #NRC is participating in a biennial graded emergency preparedness exercise for the

  1. Susquehanna #nuclear power plant, in Salem Township (Luzerne County), Pa., this evening.

Preliminary results will be presented during a public meeting at 10 a.m. on 10/19 in Wilkes-Barre, Pa.

Oct. 18, 2019

The #NRC has approved requests for exemptions and a license amendment involving changes to the #OysterCreek #nuclear power plants post-shutdown emergency plan:

https://www.nrc.gov/reading-rm/doc-collections/news/2018/18-048.pdf . The changes cannot be implemented at the Lacey, N.J., plant until on or after 9/17/19.

Oct. 23, 2018 The #NRC has published a Federal Register notice on our review of the license transfer proposal for the #OysterCreek #nuclear power plant in New Jersey:

https://www.gpo.gov/fdsys/pkg/FR-2018-10-19/pdf/2018-22844.pdf . The notice advises the public that the windows to request a hearing or submit comments have opened.

Oct. 31, 2018 A panel of experts that advises the #NRC on nuclear safety matters will hear about efforts to address concrete degradation at the #Seabrook #nuclear power plant during a meeting that begins this morning: https://www.govinfo.gov/content/pkg/FR-2018-10-24/pdf/2018-23170.pdf Nov. 7, 2018 The #NRC recently issued a report on our fourth Confirmatory Action Letter follow-up inspection at the #Pilgrim #nuclear power plant. The NRC has now closed out about 74 percent of the areas in need of improvement, as spelled out in the letter:

https://www.nrc.gov/docs/ML1830/ML18305A834.pdf .

Nov. 20, 2018 The #NRC has received a license transfer application for the #Pilgrim #nuclear power plant. The agency will conduct an initial review before determining if the proposal meets the requirements for more detailed technical and financial reviews.

Dec. 10, 2018 The #NRC's fifth and final quarterly inspection to assess safety performance improvements at the #Pilgrim #nuclear plant, in Plymouth, Mass., got under way today. The team will be checking on the company's progress in addressing items listed in a Confirmatory Action Letter.

Dec. 10. 2018 The #NRC has proposed a $3,500 fine for a #Delaware medical firm for failing to properly secure licensed nuclear material, specifically radioactive seeds used to treat different types of cancer: https://www.nrc.gov/reading-rm/doc-collections/news/2018/18-023.i.pdf .

Dec. 11, 2018 The #NRC has extended the public comment period for a license transfer application for the Oyster Creek #nuclear power plant, in #Lacey Township., #NJ. The new deadline is Jan. 9, 2019:

https://www. gpo.gov/fdsys/pkg/FR-2 018-12-10/pdf/2018-26615.pdf Dec. 17, 2018 An independent body of experts that advises the #NRC on nuclear safety matters, has published its conclusions on concrete degradation issues @Seabrook #nuclear power plant, in New Hampshire: https://www.nrc.gov/docs/ML1834/ML18348A951.pdf

Dec. 21, 2018 The #NRC staff has completed its review of Exelons Post-Shutdown Decommissioning Activities Report (PSDAR) for the #OysterCreek #nuclear power plant, in #Lacey Township, N.J., and determined that it meets our regulatory requirements: nrc.gov/docs/ML1824/ML .

https://www. 18241A068.pdf Dec. 21, 2018 The #NRC has accepted for formal review Entergy's decommissioning roadmap report for the

  1. Pilgrim #nuclear power plant in #Plymouth, Mass.: https://www.govinfo.gov/content/pkg/FR-2018-12-21/pdf/2018-27724.pdf . Public comments will be accepted on the Post-Shutdown Decommissioning Activities Report (PSDAR) until March 21.