Revision 24 to Updated Final Safety Analysis Report, Chapter 13, Table of Contents
ML18117A425
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 04/06/2018
From:
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML18117A343 List: ... further results
References
TMI-18-047
Download: ML18117A425 (4)


Text

TMI-1 UFSAR CHAPTER 13 13-i REV. 18, APRIL 2006 FSAR Chapter 13 "Initial Tests and Operations" is a reprint of the original FSAR Chapter 13.

Initial startup and test results were submitted in a report to the NRC dated November 27, 1974.

FSAR Chapter 13 is provided for historical information purposes only

CHAPTER 13 - INITIAL TEST AND OPERATION TABLE OF CONTENTS

SECTION TITLE 13.0 INITIAL TESTS AND OPERATION

13.1 TEST PROGRAM DESCRIPTION 13.1.1 ADMINISTRATIVE PROCEDURES (TESTING) 13.1.1.1 TEST PROCEDURES 13.1.1.2 TEST INDEX 13.1.1.3 PREREQUISITE LISTS 13.1.1.4 TEST SCHEDULES 13.1.1.5 TEST MANNING ASSIGNMENTS 13.1.1.6 TEST PLAN 13.1.1.7 TEST INSTRUCTIONS 13.1.2 ADMINISTRATIVE PROCEDURES (MODIFICATIONS) 13.1.3 TEST OBJECTIVES AND PROCEDURES 13.1.3.1 CONSTRUCTION TEST PHASE 13.1.3.2 PREOPERATIONAL TEST PHASE 13.1.4 FUEL LOADING AND INITIAL OPERATION 13.1.5 ADMINISTRATIVE PROCEDURES (SYSTEM OPERATION)

13.2 AUGMENTATION OF APPLICANT'S STAFF FOR INITIAL TESTS AND OPERATIONS 13.2.1 ORGANIZATIONAL FUNCTIONS, RESPONSIBILITIES, AND AUTHORITIES 13.2.1.1 GPU SERVICE CORPORATION (GPUSC) 13.2.1.2 UNITED ENGINEERS AND CONSTRUCTORS (UE&C) 13.2.1.3 METROPOLITAN EDISON COMPANY (MET-ED) 13.2.1.4 GILBERT ASSOCIATES, INC. (GAI) 13.2.1.5 BABCOCK & WILCOX, INC. (B&W) 13.2.1.6 GENERAL ELECTRIC CO. (GE) 13.2.2 INTERRELATIONSHIPS AND INTERFACES 13.2.2.1 PLANT OPERATIONS REVIEW COMMITTEE (PORC) 13.2.2.2 TEST WORKING GROUP (TWG) 13.2.2.3 DESIGNER, OWNER, TESTER (DOT) 13.2.3 PERSONNEL FUNCTIONS, RESPONSIBILITIES, AND AUTHORITIES 13.2.3.1 GPU TEST SUPERINTENDENT 13.2.3.2 GPU ASSISTANT TEST SUPERINTENDENT 13.2.3.3 GPU SHIFT TEST ENGINEER (STE) 13.2.3.4 GPU TECHNICAL ENGINEER 13.2.3.5 GPU COGNIZANT TEST ENGINEER 13.2.3.6 MET-ED ASSISTANT STATION SUPERINTENDENT

TMI-1 UFSAR TABLE OF CONTENTS (cont'd)

SECTION TITLE CHAPTER 13 13-ii REV. 18, APRIL 2006 13.2.3.7 MET-ED SUPERVISOR OF OPERATIONS 13.2.3.8 MET-ED SHIFT FOREMAN 13.2.3.9 UE&C LEAD STARTUP ENGINEER 13.2.3.10 NSSS SITE OPERATIONS MANAGER 13.2.3.11 TURBINE GENERATOR SUPPLIER SITE REPRESENTATIVE 13.2.3.12 ARCHITECT ENGINEER - STARTUP TEST ENGINEER 13.2.3.13 MET-ED TEST AUDITOR

TMI-1 UFSAR CHAPTER 13 13-iii REV. 18, APRIL 2006 LIST OF TABLES

TABLE TITLE 13.1-1 LIST OF TEST INSTRUCTIONS

13.1-2 SAFETY RELATED TESTS TO BE PERFORMED DURING PREOPERATIONAL AND INITIAL STARTUP TEST PHASES

13.1-3 HOT FUNCTIONAL TESTS

13.1-4 POWER ESCALATION TESTING PROGRAM

TMI-1 UFSAR CHAPTER 13 13-iv REV. 18, APRIL 2006 LIST OF FIGURES FIGURE TITLE 13.2-1 TEST PROGRAM ORGANIZATION