ML18065B128

From kanterella
Jump to navigation Jump to search
Insp Rept 50-255/97-11 on 970828-1017.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support
ML18065B128
Person / Time
Site: Palisades Entergy icon.png
Issue date: 12/19/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML18065B126 List:
References
50-255-97-11, NUDOCS 9712300164
Download: ML18065B128 (25)


See also: IR 05000255/1997011

Text

U.S. NUCLEAR REGULA TORY COMMISSION

REGION Ill

Docket No.:

License No.:

Report No.:

Licensee:

Facility:

Location:

Dates:

Inspectors:

Approved by:

97i2300164 971219

.

PDR

ADOCK 05000255

Q

PDR

50-255

DPR-20

50-255/97011 (DRP)

Consumers Power Company

212 West Michigan Avenue

Jackson, Ml 49201

Palisades Nuclear Generating Plant

27780 Blue Star Memorial Highway

. Covert, Ml 49043-9530

August 28 - October 17, 1997

M. Parker, Senior Resident Inspector

P. Prescott, Resident Inspector

Bruce L. Burgess, Chief

Reactor Projects Branch 6

EXECUTIVE SUMMARY

Palisades Nuclear Generating Plant

NRC Inspection Report No. 50-255/97011 (DRP)

This inspection reviewed aspects of licensee operations, maintenance, engineering and plant

support. The report covers a 7-week period of resident inspection.

Operations

The inspectors noted that operators were thoroughly prepared for a plant downpower and

main turbine valve testing evolutions. Reactor engineering, system engineering and the

procedure sponsor provided good support for these evolutions (Section 01.2).

Operators failed to ensure that service water system valves were closed, which could

have resulted in the potential draining of the component cooling water system in an

Appendix R design bases fire. This resulted in the plant operating the facility outside the

design bases for 1 O days following discovery of the condition (Section 01.3).

The licensee conservatively decided to shut down the plant due to a relatively minor

increase in containment unidentified leakage. The inspectors noted that control room

operators performed well in bringing the plant to hot shutdown.

The inspectors concluded that the licensee provided good management oversight during

the reactor startup, including the approach to critical with a reactivity manager and reactor

engineering stationed onshift to augment shift coverage. Good conservative decision

making took place on several occasions, specificaljy: to return the plant to a hot

shutdown condition by inserting regulating rods during troubleshooting and repairs to

CROM 39, to insert all regulating rods when the ECP was not achieved with all control

rods out, and to conduct a PRC meeting prior to continuation of a plant startup following

the ECP discrepancy (Section 01.5).

Maintenance

The inspectors noted the operators were challenged by a number of emergent equipment

problems during the plant shutdown. This was indicative that the licensee continues to

struggle with plant material condition issues (Section M1 .1).

The inspectors concluded that the maintenance procedure for repair of the waste gas

surge tank was inadequate for the circumstances. The procedure allowed the waste gas

surge tank to be vented to the auxiliary building atmosphere by allowing the gagging of

relief valve, RV-1114, resulting in the contamination of five individuals during a routine

VCT gas sample. The use of the procedure should have caused operators to question

the potential for a breach of the waste gas surge tank discharge piping. Also, adequate

equipment controls were not provided to prevent personnel contamination. The

inspectors concluded that the use of a fluted tap by maintenance personnel when a

2 inch threaded bolt was specified in the work procedure was inappropriate and

contributed to the contamination of personnel (Section M1 .2).

3

Engineering

The inspectors found the compensatory measures taken for the identified Appendix R

issues to be adequate. The Appendix R enhancement review was found to be

progressing slowly. However, the review appeared to be thorough (Section E1 .1).

Plant Support

The licensee's actions to improve the resin transfer process resulted. in an error-free

evolution for the spent fuel pool job (Section R1 .1).

4

~ .

Report Details

Summary of Plant Status

The plant operated at essentially full power for the inspection period until September 19, 1997. At

9:21 p.m., EST, a power reduction was commenced to 84 percent to perform turbine valve

testing and repacking of a heater drain pump. Operations returned the plant to full power on

September 21, 1997 at 8:00 a.m. On September 29, 1997, at 8:30 p.m., a plant shutdown was

initiated to facilitate repairs on a small leak on a primary coolant pump leakoff line. The turbine

was taken offline at 5: 14 a.m. on September 30, 1997. The reactor was subcritical at 11 :00 a.m.

The forced maintenance outage was completed on October 15, 1997, when the reactor went

critical at 1 :OO p.m. The generator was synchronized and breaker closed at 11 :39 p.m.

I. Operations

01

Conduct of Operations

01.1

General Comments (71707)

Using Inspection Procedure 71707, the inspectors conducted frequent reviews of ongoing

plant operations. The conduct of operations was considered by the inspectors to be

good; specific events and noteworthy observations are detailed below.

01.2

Reactor Downpower and Main Turbine Testing

  • a.

Inspection Scope (71707)

The inspectors observed the conduct of control room operations for the downpower to

repack heater drain pump P-108 and perform main turbine valve testing. Applicable

procedures were reviewed.

b.

Observation and Findings

On September 19, 1997, the inspectors observed control room operators commence a

downpower to 85 percent reactor power. The purpose of the downpower was to allow

operation with only one heater drain pump. Heater drain pump P-108 required repacking

due to excessive leakage and testing of the main turbine governor and stop valves was to

be performed. No operator performance weakness were noted. An extra nuclear control

operator was added to support the shift and the inspectors noted good operator

attentiveness to panels. A reactor engineering supervisor observed the downpower and

issued appropriate guidance to maintain a proper axial shape index curve. The

procedure sponsor was also present to monitor the downpower activity and verify the

adequacy of the downpower procedure. System engineering monitored vibration due to

concerns with the increased main turbine and generator vibrations caused by the missing

piece of shroud on the low pressure tui'bine rotor stage. No problems with vibrations

were noted.

Prior to testing of the main turbine governor and stop valves the operations shift had "just

in time" training on the simulator. A question was asked by operators regarding how to

5

back out of the surveillance should a problem occur requiring a rapid downpower. The

question was resolved prior to commencing the test by assigning an extra nuclear control

operator to enhance control room panel monitoring. System engineering monitored main

turbine and generator vibrations during the testing. No testing problems were identified.

c.

Conclusions

The inspectors noted thorough preparedness by operations for the downpower and main

turbine valve testing evolutions. Reactor engineering, system engineering and the

procedures sponsor provided good support for these evolutions.

01.3

Inadequate Appendix R Compensatory Measures

a.

Inspection Scope (71707)

The inspectors reviewed the licensee's corrective actions taken in response to a

reportable 50. 72 involving a condition outside the design basis. This condition is the

result of an Appendix R fire involving the component cooling water (CCW) and service

water (SW) seal cooling valves for the essential safety systems (ESS) pumps. The

  • licensee identified that during a control room fire a hot short may fail open interfacing

CCW/SW systems valves resulting in the loss of all CCW water to the SW system. The

most limiting scenario could lead to draining of the CCW system in approximately

25 seconds.

b.

Observations and Findings

On September 12, 1997, as an interim compensatory measure for the potential Appendix

R component cooling water loss of inventory scenario, an auxiliary operator was directed

to place caution tags on the air supply valves to CV-0951, CV-0880 and CV-0879.

Caution tags were also placed on the respective control switches in the control room.

This compensatory measure was proposed as corrective action for condition

report C-PAL-97-1270, which had detailed the Appendix R scenario. The air supply

valves were required to be in the closed position to ensure the valves would not

inadvertently open.

The onshift shift supervisor and auxiliary operator located the three valves to be caution

tagged in the plant. The auxiliary operator manipulated the air isolation valve to ensure

they were open. This was observed by the shift supervisor. At this point, the shift

supervisor was uncertain how much the auxiliary operator comprehended about the

required task. Also, the auxiliary operator did not realize that to immediately resolve the

issue the desired position for the air isolation valves was closed. The onshift senior

reactor operator guidance to the auxiliary operator was to hang the tags. The auxiliary

operator was not specifically directed by the shift supervisor to place the valves in the

closed position. There is no procedural requirement that when caution tags are used,

plant equipment is verified to ensure it is left in the required position.

A nuclear control operator was tasked to hang the caution tags. The nuclear control

operator directed the auxiliary operator to hang the caution tags on the control valve air

isolation valves. At this point, the nucl.ear control operator was uncertain if he directed

the auxiliary operator to close and tag, or just tag the valves. The nuclear control

6

operator assumed the auxiliary operator understood the issue and knew what actions

were required to proper1y implement the caution tag requirements. The assumption was

based on the fact the auxiliary operator had ear1ier walked down the valves with the shift

supervisor.

The auxiliary operator proceeded to hang the caution tags on the air isolation valves. The

auxiliary operator did not close the air isolation valves because he understood that they

needed to remain open to maintain the control valves closed. This was reinforced by the

fact that during the walk down the auxiliary operator manipulated the valves in front of the

shift supervisor to show the valves were in the open position. The auxiliary operator does

not recall ever being told by either the shift supervisor or nuclear control operator that the

valves needed to be closed.

Guidance under the "Special Instructions "portion of the caution tags read, "Do not open

without SS permission." There was no specific direction to suggest to the operator that

the air supply valves were to be shut at the time the tags were hung.

On September 24, 1997, permanent placards were placed in the control room to indicate

that the air supply valves were permanently closed. The system checklist procedure was

revised with the normal position of the valves indicated as "closed." A different auxiliary

operator removed the temporary caution tags and attached permanent caution tags. The

auxiliary operator found the air supply valves were open and not closed.

The failure to ensure adequate compensatory measures were taken to address the

Appendix R concern is considered a Violation of 10 CFR 50 Appendix B, Criterion XVI,

  • eorrective Action.* However, the inspectors reviewed this licensee's actions for this

self-identified item and determined this was a Non-Cited Violation consistent with

Section Vll.8.1 of the Enforcement Policy {NCV No. 50-255/97011-02).

c.

Conclusions

The onshift operations personnel failed to take adequate measures to ensure the air

supply valves to three SW valves were left in the proper valve configuration. Failure to

ensure the air supply valves were closed could have resulted in the potential draining of

the CCW system in the event of an Appendix R fire. This resulted in the plant operating

the facility outside the design bases for 10 days following discovery of the condition. This

was considered a non-cited Violation.

01.4

Reactor shutdown for Forced Maintenance Outage

a.

Inspection Scope {71707)

The inspectors observed the pre-job brief, simulator "just in time" training and the plant

shutdown for a maintenance forced outage.

b.

Observations and Findings

The control room operators commenced an order1y shutdown of the reactor on

September 29, 1997. The shutdown was initiated due to increased unidentified primary

coolant system leakage. Primary coolant system leakage had risen from an average of

7

0.05 gpm to 0.199 gpm over the last four days. Inspection of the containment identified

the source of the leak as a cracked weld on a seal package controlled bleedoff line for the

P-50A primary coolant pump.

Operators held a pre-job brief and simulator "just in time" training prior to commencing the

shutdown. The pre-job brief was thorough. Roles and responsibilities were discussed

between the members of the operations shift. The operations superintendent provided

management oversight of these activities and subsequent shutdown. The inspectors

noted that the nuclear control operator (NCO) responsible for control rods and reactor

power and the other NCO responsible for turbine load reduction had not previously

performed a reactor shutdown. An extra NCO was assigned to the shift. This NCO was

assigned responsibility for maintaining proper feedwater flow and monitoring other

balance of plant equipment.

The simulator instructor discussed in detail a December 2, 1995, event following a turbine

trip. A high startup rate was observed while withdrawing control rods to maintain primary

coolant system temperature. The instructor stressed that review of the event noted the

NCO attempted to control T _ with control rods. However, at that point in time reactor

power was at approximately 10*1 percent power and the control rods had little or no effect

on T -* The instructor indicated that T _ should be controlled by decay heat removal

through the turbine bypass valve.

During the first simulator practice at taking the turbine and generator offline, simulator

parameters were difficult to control for the operators. Initial simulator conditions caused

feedwater oscillations and a 4 ° F difference in temperature between T rer and T -* The

inspectors noted a weakness in three-way communication with the shift. A subsequent

rerun on the simulator with more normal shutdown conditions noted improved shift

performance.

The off-going shift supervisor conducted a brief with the on-coming crew prior to the

conduct of the normal shift turnover. The oncoming crew assumed the shift with the plant

at approximately 85 percent reactor power. The crew commenced a turbine load

reduction at 24 percent an hour. The downpower proceeded in an orderly manner.

However, at approximately 23 percent reactor power, a problem arose during the transfer

of electrical loads from the station power to startup transformer. The G bus breaker

252-402 would not close. The G bus supplies power to one of the two cooling tower

pumps, P-398. The inspectors noted a momentary loss of command and control

because the shift supervisor and control room supervisor were focused in the effort to

reclose the breaker. The impact of the loss of one of the cooling tower pumps would be

relatively minor on condenser vacuum at this power level. At this time, the operators

were also contending with xenon buildup and its impact on reactor power. Further

attempts to close the breaker were unsuccessful. The shift supervisor and control room

supervisor re-focused on the plant shutdown. At approximately 18 percent power,

operators noted that the condensate pump recirc valve CV-0730 was not opening as

expected. The control room supervisor quickly anticipated plant conditions and the

actions required to address the problem. At approximately 7 percent power the turbine

was taken offline, the main feedwater pump was taken offline and auxiliary feedwater

lined up. The failure of CV-0730 required the condensate pumps to be shut off to prevent

damage to the pump due to low flow conditions. The main steam isolation valves were

closed, which meant loss of the bypass valve to control primary coolant system

8

temperature. The automatic dump valves opened to control primary coolal"!t system

temperature. The inspectors noted one other discrepancy. During the control room

supervisor's discussion of the sequence of events that would occur due to the failure of

CV-0730, the NCO controlling reactivity believed he would control temperature with

control rod movements. In actuality, the NCO's function was to control reactor power.

This had been reviewed during the simulator training.

c.

Conclusions

The licensee conservatively decided to shut down the plant due to a relatively minor

increase in containment sump level. The inspectors noted that control room operators

performed well in bringing the plant to hot shutdown. A momentary weakness in

cpmmand and control was noted when the shift supervisor and control room supervisor

were overly involved in attempts to close breaker 252-402 to maintain cooling tower pump

P-398 online.

01.5

Startup From Forced Outage

a.

Inspection Scope

The inspectors observed the initial and subsequent successful attempts for plant startup

after completing a forced maintenance outage. The main reason for the outage was to

repair a cracked weld of the pump seal package controlled bleedoff line for P-50A primary

coolant pump. "Just in time" simulator training and pre-job brief for the initial startup were

also observed.

b.

Observations and Findings

On October 8, 1997, operators commenced heatup of the primary coolant system. On

October 9, 1997, at 9:05 EST, the plant exited cold shutdown. On October 10, 1997, the

oncoming crew received "just in time" training and conducted a pre-job brief in

preparation for the approach to critical. The inspectors noted both the simulator training

and pre-job brief were well conducted.

However, the off-going shift received the primary coolant pump high/low alarm.

Operations determined the alarm was caused by the purification demineralizer inlet relief

valve RV-2013 lifting. The relief valve lifted when the third letdown orifice stop valve

opened, which caused an excessive differential pressure across the demineralizer.

Radiation protection subsequently notified operations of water leakage in the auxiliary

building. This was traced to the vent hole in the bonnet of RV-2013. A condition report

was initiated to determine why the relief valve lifted. A primary coolant system leak rate

was performed. Leakage had increased from .033 gpm to .3 gpm.

Another problem occurred during performance of procedure R0-21, "Control Rod Drive

System lnter1ocks." Control rod drive mechanism (CROM) 31 acted sluggish compared to

the other control rod drives. Operations discussed the issue with system engineering. A

determination was made to perform R0-22, "Control Rod Drive Drop Timing," for

CROM 31 to ensure there was no mechanical binding which could prevent the control rod

from being inserted into the reactor core. The licensee subsequently decided to place

the plant in cold shutdown and in order to facilitate repairs to RV-2013 and CROM 31.

9

Cold shutdown was reached on October 11, 1997. The rod drive for CROM 31 was

replaced.

On October 13, 1997, with all repairs completed to CROM 31 and RV-2013, the licensee

commenced a reactor heatup to hot shutdown. On October 14, 1997, with the plant on

the approach to critical, CROM 39 was found to exhibit sluggish movement with respect

to the remainder of rods in Group 4. CROM 39 was subsequently declared inoperable. In

order to facilitate troubleshooting and repairs, management directed the plant to be

placed in a hot shutdown condition, requiring all rods to be inserted into the reactor core.

Troubleshooting indicated that the motor's auxiliary contactors did not makeup proper1y.

A decision was made to replace the contactors while holding the plant in a hot shutdown

condition.

On October 15, 1997, with the relay contactor replaced, the plant proceeded on with the

approach to critical with no further difficulties with CROM 39. During the approach to

critical all regulating rods were withdrawn without achieving a critical condition. Initial

review of conditions by the inspectors determined that with all rods out, the estimated

critical position {ECP) was within the bounds of the uncertainty analysis window indicated

in technical specifications, although reactor engineering had predicted a critical rod

position on regulating rod Group 4. The licensee subsequently inserted all regulating

control rods and requested a resample of the primary coolant system boron.

Reanalysis of primary coolant system {PCS) boron concentration determined that the

PCS boron concentration was within the limits of the established ECP critical boron

concentration. The licensee determined that the ECP anomaly was due to

boron-10 depletion. The estimated ECP was recalculated to compensate for depleted

boron-10 concentration. A plant review committee {PRC) meeting was convened to

review the condition report on ECP anomaly and agreed with reactor engineering's

conclusions that the anomaly was due to boron-1 O depletion. The ECP was calculated to

be within the TS limits of 1 percent anomaly.

The new ECP was calculated with a lower boron concentration resulting in criticality with

Group 4 rods partially withdrawn. Criticality was subsequently achieved on October 15,

1997, within limits of the reestablished ECP. The turbine was synchronized to the grid

without incident. During the startup and attempts to achieve criticality, the inspectors

noted good command and control with appropriate conservative decision making. Three

way communication and use of procedures were noted by the inspectors. Good

management oversight was also provided during the startup including the approach to

criticality, with a reactivity manager and reactor engineering stationed on shift to augment

shift coverage.

c.

Conclusions

The inspectors concluded that the licensee provided good management oversight during

the reactor startup including the approach to criticality with a reactivity manager and

reactor engineering stationed onshift to augment shift coverage. Good conservative

decision making took place on several occasions, specifically: to return the plant to a hot

shutdown condition by inserting regulating rods during troubleshooting and repairs to

10

08

08.1

CROM 39, to insert all regulating rods when ECP was not achieved on an all rods out

condition, and to conduct a PRC meeting prior to continuation of a plant startup following

the ECP discrepancy.

Miscellaneous Operations Issues (92701 and 92901)

(Closed) Violation 50-255/94014-1A: Operations failed to ensure that the control rod

drive mechanisms (CROMs) were mechanically locked prior to inserting a reactor trip

signal, resulting in the CROM racks dropping into the reactor vessel upper guide

structure. On November 7, 1996, preparations were being made to remove the reactor

vessel head. Operations discussed the status of the uncoupling of the CROMs, in

support of reactor vessel head removal, with Refueling Services. It was understood that

the Refueling Services procedure was the controlling document. Operations then

number 33 was stuck. Maintenance personal began troubleshooting CRD 33.

Operations, in a subsequent shift turnover, failed to specify the Refueling Services

procedure as the document controlling the CRDMs. Maintenance, upon completing

repairs to CRD 33, withdrew it and mechanically locked CRO 33 in place. The shift

supervisor was notified of CRO 33 being repaired, withdrawn and locked into place. The

shift supervisor assumed the next step was to place the reactor protection system in the

reactor trip mode. The shift supervisor did not verify the status nor the controlling

procedure of the control rod drive racks. When the shift supervisor directed that the

reactor protection system be placed in the reactor trip mode, all control rod drive racks

except CRO 33 reinserted into the reactor. The Refuel Services procedure allowed the

control rod drive racks to be locked after all the racks were withdrawn .

On November 18, 1996, the licensee suspended all refueling work and conducted a

standdown meeting to reinforce nuclear, radiation and industrial safety concerns with all

work groups. Several events over the first two weeks of the outage were reviewed. A

common theme between events was the lack of communications between work groups

and alignment among workers.

Three specific responsibilities reinforced at the operations standdown meetings were:

Shift supervisors will identify operations activities from the outage schedule with

an understanding of the relationship between these activities and others. The

purpose of this action is to contribute to informed decision making within the

operations organization.

Work control senior reactor operators are to route work activities having

operations involvement to control room personnel for authorization. This action

will provide a direct exchange of information between work control and control

room personnel.

Control room personnel are to ensure they have a complete understanding of

activities.requested of them and that proper adjustments to work activities or plant

configuration have been made.

Also, the control rod drive blades and racks were inspected for damage due to the trip.

No damage was identified. This item is closed .

11

08.2

CClosedl Violation 50-255/9601+o1B: Operations shift did not return the isolation handle

Y-50 to the nonnal position prior to returning the bypass handle to the automatic position,

resulting in a loss of power to instrument AC bus Y-01. Circumstances that caused this

event were similar to those detailed in 50-255/96014-0lA. The event occurred on

November 17, 1996. Reasons for this event included inadequate understanding of the

work scope, inadequate communications, inadequate work control documents and

improper equipment operation.

The same specific responsibilities reinforced at the November 18, 1996 operations

department standdown meetings detailed in 50-255/96014-0lA above, were also part of

the corrective actions for this event. Additional corrective actions taken were:

All operations personnel involved discussed this event and the barriers that could

. have prevented it. The discussion included responsibilities for proper

communication, pre-job briefings, self checking and other aspects of operator

conduct.

The shift operations supervisor briefed all senior reactor operators on the need to

identify and conduct pre-job briefs. The expectation was reinforced to conduct a

pre-job brief whenever coordination between two or more work groups is required.

The maintenance and construction manager reinforced pre-job brief expectations

with maintenance and construction supervisors, using this event as an example.

This item is closed.

II. Maintenance

M1

Conduct of Maintenance

M1 .1 * General Comments

a.

Inspection Scope (62707 and 61726)

The inspectors observed all or portions of the following work activities:

Work Order No:

24713553:

27412530:

24514171:

.

24712252220:

081397HN01:

CV-0733 Slowdown isolation valve: Troubleshoot increased

stroke time

P-558 charging pump: Repack and reassemble pump

P-558 Seal lubrication pump: Retenninate seal lube motor

leads

Dry fuel storage cask: Loading, dry runs

Sluice T-50 Spent fuel pool demineralizer

12

24711013:

24711141:

Surveillance Activities

M0-38:

Heater drain pump P-108: Repack

Heater drain pump P-108: Fitting upstream of MV-HED114

leaking. Repair

Auxiliary Feedwater System Monthly Test Procedure

(P-8C)

SOP-8 Attachment 2: Testing of Main Turbine Valves/Protective Trips

GOP-12:

Heat Balance Calculation

b.

Observations and Findings .

The inspectors found the work performed to be professional and thorough. All work

observed was done with the work pack.age present and in active use. Work pack.ages

were comprehensive for the task and post maintenance testing requirements were

adequate. The inspectors frequently observed supervisors and system engineers

monitoring work. When applicable, work was done with the appropriate radiation control

measures in place.

c.

Conclusions

Overall, the inspectors observed good procedure adherence, maintenance and radiation

worker practices. Specific observations are detailed below.

M1.2

Volume Control Tank Gas Sample Leak into the Auxiliary Building

a.

Inspection Scope

On August 12, 1997, during a routine volume control tank (VCT) gas sample by a

chemistry technician, radioactive gas was released into the auxiliary building via the

waste gas system contaminating several individuals. The inspectors observed the

licensee's actions to identify the source of the system leakage and the impact on the

contaminated individuals.

b.

Observations and Findings

On August 12, 1997, waste gas compressor, C-50A, was tagged out of service (OOS)

due to ongoing maintenance. During the time the waste gas compressor was OSS, a

chemistry technician received permission from the operating shift to sample the VCT.

During the sampling process, the purged gasses from the VCT were discharged to the

waste gas surge tank room, subsequently contaminating the maintenance crew.

In reviewing the switching and tagging orders for the maintenance activity, the inspectors

determined that the VCT sampling should not have had any effect on the maintenance

activity. However, in reviewing the work instructions, Permanent Maintenance Procedure

WGS-M-2, "Inspection and Repair of Waste Gas Compressors, C-50A and C50B," the

13

inspectors noted that the procedure requires the use of a relief valve gagging device to

be installed on the discharge of C-50A. The procedure requires the use of a two inch

long bolt to be installed as a gagging device on relief valve, RV-1114. This gagging

device was installed to prevent an inadvertent relief valve lift during hydrostatic pressure

testing following repairs. However, a proper size bolt was not available and a fluted tap

was installed in its place. The installation of a gagging device resulted in breaching the

system boundary. The fluted tap verses a threaded bolt further compounded the situation

in that it resulted in a larger opening in the discharge piping. The installation of the

gagging device resulted in inadvertently venting the waste gas surge tank to atmosphere,

as the relief valve discharges to the waste gas surge tank. Thus once the VCT gasses

were purged to the waste gas surge tank, they were vented back through the relief

valve's discharge line to the auxiliary building atmosphere. The VCT sampling resulted in

a release of radioactive gases to the waste gas surge tank room where the maintenance

crew was working on the waste gas compressor. *All five individuals working on the

compressor at the time of the radioactive release were found contaminated. The failure

to adequately control the breaching of the relief valve discharge piping is considered a

violation of 10 CFR 50 Appendix B, Criterion V, in that Permanent Maintenance

Procedure WGS-M-2, was inadequate for the circumstances and resulted in the

contamination of the maintenance crew.

The operating crew was alerted to the high airborne conditions when radwaste area

monitor, RE-1809, alarmed and tripped the auxiliary building supply fan, V-10. Radiation

protection personnel were immediately notified and restricted access to the auxiliary

building and obtained air samples of the area. The released gases were subsequently

discharged to the stack and had an activity level of approximately 1300 counts per

minute. The radioactive release alert alarm setpoint was 1,300,000 counts per minute.

The maintenance personnel working in the area of the waste gas surge tank room were

informed of the problem and proceeded to access control. The repairmen were all

monitored for contamination and all five alanned the PCM-1 B monitors at access control.

All cleared the PM-7 monitors on egress to the protected area for whole body counting,

after being detained at access control to allow the activity to decay. The maintenance

workers were subsequently whole body counted with no positive results prior to leaving

the site.

c.

Conclusions

The inspectors conciuded that the maintenance procedure was inadequate for the

circumstances. The procedure allowed the waste gas surge tank to be vented to the

auxiliary building atmosphere by allowing the gagging of relief valve, RV-1114, resulting in

the contamination of five individuals during a routine VCT gas sample. The procedure did

not appropriately alert operations personnel to the potential for a breach of the discharge

piping. Therefore, adequate equipment controls were not provided to prevent personnel

contamination. The inspectors also concluded that the use of a fluted tap by

maintenance personnel when a two inch threaded bolt was specified in the work

procedure, was inappropriate and contributed to the contamination of personnel.

14

M1 .3

Complicating Factors on Plant Shutdown

a.

Inspection Scope (62707)

The inspectors observed the plant shutdown for the forced maintenance outage. Several

emergent equipment problems were noted.

b.

Observations and Findings

The main purpose of the outage was to perform a weld repair to a cracked section of

piping on the pump seal package controlled bleedoff line for P-50A primary coolant pump.

The P-50A pump had small seal flow oscillations and occasional seal pressure spikes~

The root cause for the line developing cracks had not yet been determined.

The original scope of the outage was significantly increased however due to several other

equipment problems encountered during the shutdown. Condensate recirc valve

CV-0730 failed to open at lower turbine loads. This forced operators to stop the

condensate pumps and complicated the shutdown. An air leak was found in the air

controller pneumatic relay assembly. The licensee determined to bring the plant to cold

shutdown instead of hot shutdown due to the emergent equipment problems. With the

plant in cold shutdown, the licensee also chose to replace the primary coolant

pump P-508 seal package. The upper stage of the seal package had destaged and the

other three stages compensate for the failed stage. The P-50A and P-50C also have seal

flow oscillations of .01 gpm and .05 gpm, respectively. Also, instrumentation cables for

the P-50A motor temperature indication had to be replaced due to damaged conduit

which allowed water inleakage from the cracked controlled bleedoff line. Failure of the

instrumentation was the means by which the licensee determined the suspected source

of the primary coolant system leak.

The shutdown was also complicated by the failure of the 1-G bus breaker 252-402 to

transfer from the station power to startup transformer. This forced the operators to shut

down cooling tower pump P-398. Subsequently, the breaker fast transferred when the

main turbine generator was tripped.

There were other less significant operator distractions. Control rod drive number 39 was

noted to be sluggish moving a few inches out of synchronization with the other control*

rods in its group during withdrawal. Also, the temperature margin monitor low

temperature over-pressure pre-trip alarm had drifted slightly out of calibration low,

causing the annunciator to frequently alarm.

c.

Conclusions

The inspectors noted the operators were challenged by a number of emergent equipment

problems during the plant shutdown. This was indicative that the licensee continues to

struggle with significant plant material condition issues .

15

MS

Miscellaneous Maintenance Issues (92902 and 92700)

M8.1

(Closed) LER 95005-00: Inadvertent actuation of the safety injection system. On July 21,

1995, which the plant shut down for refueling, two inadvertent safety injection signals

were received while performing surveillance R0-12, "Containment High Pressure and

Spray System Test." In both instances, the left channel of safety injection was

inadvertently actuated. The cause of the first safety injection signal actuation was two

wires being taped together after removal from a terminal in an attempt to isolate the

safety injection system signal. The cause of the second safety injection signal aetuation

was a screwdriver inadvertently touching a terminal on the safety injection signal relay.

All equipment which had not been isolated prior to the event responded as required.

The licensee determined the root cause of the first inadvertent safety injection system

was inadequate communication between the system engineer procedure sponsor and

electrical maintenance personnel. This was the first time the revised procedure was used

and the first time electrical maintenance personnel performed the test. The licensee

determined that the second inadvertent actuation was due to insufficient work space.

The terminals were in a tight configuration where the wire was to be landed.

Procedure R0-12 was revised to specify that the wires removed from the terminal were to

be isolated and insulated from each other. caution statements were added to the

procedure regarding the tight work space, and suggested temporary insulation may be

necessary. Also, the training department collected test related problems that occurred in

the 1995 refueling outage for a case study lesson plan. This lesson plan was presented

to the engineering, operations and maintenance departments. This item is closed.

M8.2

(Closed) VIO 50-255/96008-03: Unauthorized operation of plant equipment. During

performance of emergency diesel generator preventive maintenance, an electrical

technician started the supply ventilation fan to the emergency diesel generator room

without authorization of operations personnel. The manipulation of the fan was contrary

to guidance in administrative procedure AP 4.02, "Control of Equipment." The electrical

technician's supervisor discussed the inappropriate action taken with the individual. The

various department managers, In standdown or continuous training meetings, discussed

with personnel the expectation that equipment control requirements in procedure AP 4.02

be followed. This item is closed.

M8.3

(Closed) LER 97004-00: Trip of high pressure safety injection pump while filling the

safety injection tank. On February 21, 1997, during boron concentration sampling of

safety injection tank T-82C, the tank was declared inoperable due to low level and

pressure. The licensee entered a one hour allowed outage time per TS 3.3.2.a to obtain

the sample. Concurrently, the high pressure safety injection pump P-66A tripped during

initial filling of tank T-82C. The trip of pump P-66A concurrent with tank T-82C being

inoperable was a condition prohibited by TSs, which required immediate entry into 3.0.3. *

Inspection of pump P-66A breaker by electricians found the Y-phase time over-current

relay target dropped. Root cause of the time over-current relay trip was a small metal

particle which lodged between the top surface of the induction disk and the relay's

magnet. This prevented the induction disk from rotating back to the reset position. The

particle was sent out for electron microscope examination. The laboratory analysis

determined the particle was a fragment to a terminal screw.

16

The time overcurrent relay was a sealed unit. This would lead to the conclusion that the

particle was introduced during manufacture. A new time over-current relay was installed

and tested satisfactorily. This item is closed.

M8.4

(Closed) LER 50-255/97005-00: Operation outside design basis due to unacceptable

Code repairs. Subsequent inspection after repairs to main steam isolation valves

CV-0501 and CV-0510, determined that unacceptable repairs had been made to the

valves' stuffing box pipe plugs which created steam leaks. These inadequate

  • ASME Code violations were considered to have resulted in operation of the plant outside

the design basis. This event was in detail in Inspection Report No. 50-255/96017 and

50-255/97005. This issue resulted in violations (50-255/97005-01, 02, 03). The

corrective actions for this LER will be tracked under the violations; therefore this LER is

closed.

Ill. Engineering

E1

Conduct of Engineering

E1.1

Licensee Appendix R Review (37551)

a.

Inspection Scope

The inspectors reviewed the licensee's progress and recent findings that pertained to the

Appendix R enhancement effort. Two recent significant findings are detailed below. The

compensatory measures taken were reviewed for* adequacy. Discussions were held with

the system engineering supervisor and personnel supporting this effort. Applicable

documentation and procedures were reviewed.

b.

Observations and Findings

The licensee is presently working to complete the Appendix R enhancement effort and

complete incorporation of the 1996 refueling outage modifications into the Appendix R

data base. The applicable Appendix R analyses are being reviewed to be certain that all

conclusions of the supporting calculations have been incorporated into the base-Appendix

R engineering analyses. Affected off normal procedures are being revised. The licensee

identified the following Appendix R issues.

Design Issue One

On September 12, 1997, the licensee identified an error in a calculation assumption

during an Appendix R design bases review. Specifically, the error involved an improper

evaluation for effects that resulted in the spurious operation of valves due to the

introduction of a hot smart short in the electrical interface between the component cooling

water (CCW) and service water (SW) systems. A single spurious operation of a valve

between the interface of the CCW/SW systems could result in the loss of CCW inventory

to the lower pressure SW system. The time period in which the CCW inventory is lost

would not allow for manual action to prevent an unanalyzed condition.

17

The licensee made a 1-hour nonemergency 10 CFR 50.72 notification for being in a

condition outside of design bases. The part of the SW system involved was the seal

cooling water for the essential safety system pumps. The most limiting of the three

potential scenarios calculated that only 25 seconds would be available to close

engineering safeguards pump cooling service water retum valve, CV-0951. This valve is

normally closed. An open item of this calculation acknowledged the 25 second

requirement, but concluded since the essential safety system (ESS) pumps are not

running during normal operation and the CCW supply and retum valves (CV-0913 and

  • CV-0950, respectively) to the ESS pumps' sealing cooling piping are normally closed,

then the spurious opening of any one CCW/SW interface valve could not result in the loss

of CCW inventory. Based on this information, another calculation did not consider

actions for the required time period. This reasoning is in error because CV-0913 and

CV-0950 are normally open and fail open on loss of air or loss of electric power. A single

spurious operation of CV-0951 would require a 25 second operator response to mitigate

the consequences, which is not possible. The licensee's compensatory measures are

detailed in Section 01.3 of this inspection report.

Design Issue Two

The second event was reported to NRC via a 10 CFR 50.72. It involved the Appendix R

analysis assuming all four primary coolant pumps being tripped if the fire causes an

evacuation of the control room. *The Off Normal Procedure for Alternate Shutdown did

not reflect the analysis and only directed the operators to trip two of the four primary.

coolant pumps.

The procedure ONP-25.2, "Alternate Safe Shutdown Procedure," does not specifically

address securing all the primary coolant pumps when the operators lose the ability to

monitor the pumps, such as during a control room evacuation or a damage to the

instruments. ONP 25.2 does not only cover fires where a control room evacuation is to

take place, but also provides guidance for fires where the control room is still manned.

The procedure assumes that monitoring of the primary coolant pumps is a condition of

their continued operation.

Several fire scenarios would result in a loss of component cooling water to the primary

coolant pump seals and bearing coolers. Upon leaving the control room, operators do not

have primary coolant pump monitoring capability or instrumentation to monitor the CCW

system. The licensee's design basis for the primary coolant pumps indicated they are

designed to operate without seal cooling for periods of up to ten minutes. Immediate

corrective action was to initiate a procedure revision to direct operators to trip all four

primary coolant pumps prior to control room evacuation.

This scenario assumes a fire is severe enough to cause a loss of CCW to the primary

coolant pumps via loss of CCW pumps or closure of the CCW valves to/from containment

but not severe enough to cause a loss of offsite power. Securing all primary coolant

pumps for a fire of lesser severity may not be prudent. For this type of scenario the

operators have additional guidance from ONP 6.2 "Loss of Component Cooling Water."

This procedure directs further securing of the primary coolant pumps for degraded CCW

18

cooling. This guidance is feH to be adequate in the short tenn until ONP 25.2 can be

clarified. Operator training includes the necessity of CCW cooling for primary coolant

pump for operation, lherefore the operators are encouraged to secure primary coolant

pumps when CCW is no longer capable of being monitored.

c.

Conclusions

The inspectors found the compensatory measures taken for the identified Appendix R

issues to be adequate. The Appendix R enhancement review was found to be

progressing slowly. However, the review appeared to be thorough.

EB

Miscellaneous Engineering Issues (92700 and 92903)

EB.1

{Closed) Licensee Event Report 95008-00: Bypassed containment high pressure trips on

reactor protection system. The licensee discovered that all four channels of containment

high pressure trip in the reactor protective system were inadvertently bypassed since a

modification in 1992. The event was the focus of Inspection Report No. 50-255/95010),

which resulted in violations 50-255/95010-01, 02 and 03. The corrective actions

documented in the LER will be tra~ed by the violations; therefore, this LER is closed.

EB.2

(Closed) LER 95012-00: Unqualified electrical connection in containment service water

outlet valve solenoid valve (SV-0824). The unqualified connection (wire nuts) was

located in a pull box in the component cooling water room outside eontainment. This

area is not affected by the loss of coolant accident pressure/temperature, but would be

exposed to radiation effects due to the radioactive "shine" through the containment wall.

The wire nut connections were replaced with environmentally qualified connections. A

walkdown of junction boxes to check for environmentally qualified connections done in

1992 missed this pull box because the electrical drawings used did not identify pull boxes.

Since the basis for the 1992 review were the electrical drawings the problem was not

discovered, and a 1995 review done after the identification of SV-0824 used the cable

and raceway schedule (E-33 series), which indicated the existence of a connection

regardless of the box type designation. The remaining pull boxes were inspected. All

remaining pull boxes identified on the E-33 series drawings were inspected, except four

which required the erection of scaffolding or were prohibitive due to high radiation

exposure. No other wire nut connections were found during this walkdown. Inspection of

the remaining four boxes is not considered necessary. This item is closed.

EB.3

(Closed) Violation 50-255/96-003-02: Failure to maintain design basis document (DBDs)

  • current. The inspectors identified that the required biennial review and revision on 14 of

36 DBDs had not been perfonned with a 2-year period. During review of this issue,

engineering personnel identified several programmatic weaknesses and corrective

actions were initiated.

Engineering personnel developed a DBD change request log. Outstanding change

requests are now posted in front of controlled DBDs. All non-qualified DBD owners

  • completed the necessary training. All DBDs were then subsequently reviewed to ensure

the DBDs were updated in a timely matter. The inspectors perfonned a random review of

DBDs. No over due change requests were identified.

19

E8.4

E8.5

E8.6.

The existing plant modification procedures specifically require the change initiator to

prepare a DBD change request. However, operating procedures do not cover this area.

This was addressed through a change to administrative procedure 3.07, "Safety

Evaluations," by the addition of the following question on the safety review form: "Should

this be included in a 080 update?" This item is closed.

(Closed) VIO 50-255/96008-04: Failure to follow surveillance procedure. On August 4,

1996, the licensee performed surveillance M0-7A-1, "Emergency Diesel Generators 1-1

and 1-2" for the emergency diesel generator 1-1. After the emergency diesel generator

was started, but prior to loading the generator, the system engineer noticed the arm of

the fuel rack was oscillating. The system engineer touched the fuel rack to stop the

motion. The surveillance continued and the diesel declared operable. This manipulation

of the fuel rack was contrary to the surveillance. The licensee re-performed the

surveillance on August 14, 1996, without any intervention with the functionality of the fuel

rack. The surveillance was completed satisfactorily. The system engineers supervisor

discussed the inappropriate action taken with the individual. The various department

managers, in standdown or continuous training meetings, discussed with personnel the

expectation that equipment control requirements in administrative procedure AP 4.02,

"Control of Equipment" be followed. This item is closed.

(Closed) LER 96010-00: On July 17, 1996, the safety injection tanks (SITs) were being

sampled for boron concentration. While filling SIT T-82C, high pressure safety injection

pump P-66A tripped. T-82C was inoperable due to low pressure during the sampling

evolution. With these two conditions, TS 3.0.3 was immediately entered. Two minutes

later, TS 3.0.3 was exited when T-82C nitrogen pressure was restored. A 24-hour

limiting condition for operation was then entered as required by TS 3.3.2.c.

Troubleshooting revealed that P-66A tripped due to the Y-phase time overcurrent (TOC)

relay on the pump breaker not resetting .after each successive start. The P-66A motor

was checked and cleaned. The TOC relay was* checked and calibrated. Then, P-66A

was test started three times. Proper resetting of the relay was verified after each start.

P-66A was declared operable, but degraded. On July 18, 1996, the LCO was exited.

The relay was replaced on July 1996.

Dust or grease buildup was determined to have caused an interference, preventing the

TOC relay from resetting. All similar relays were inspected for potentially degraded

conditions. No problems were found. This appeared to be a random failure. This item is

closed.

(Closed) Violation 50-255/96014-04: Inadequate design control of a temporary

modification to a polar crane solenoid. On November 6, 1996, temporary

modification 96-050 to the containment polar crane did not contain adequate installation

instructions for replacement of a single solenoid with two solenoids. The original solenoid

was hard mounted and was provided with sufficient ventilation t<>. prevent premature

failure. As a result of inadequate preparation and review, temporary modification 96-050

did not provide instructions for mounting the second of two replacement solenoids. The

second solenoid was installed using duct tape and tie-wraps in a manner which resulted

in overheating and failure of the solenoid coil, which resulted in a minor electrical fire .

20

The licensee subsequently replaced the two 250 volt coils with a new 460 volt coil. This

event was reviewed by the design engineering group and lessons learned were

developed. Discussions covered conditions leading to the event and the need to

consider all operating design characteristics. A review of all temporary modifications was

conducted to verify that acceptable standards were used for installation. Administrative

procedure 9.31, "Temporary Modification Control," section 7.2.3 was revised to add the

requirement to verify physical installation when critical to a design. This item is closed.

IV. Plant Support

R1

Radiological Protection

R1 .1

Spent Fuel Pool Resin Transfer

a.

Inspection Scope (71750 and 83750)

The inspectors observed the spent fuel pool resin transfer activity. Discussions were held

with the radwaste system engineer and supervisor on corrective actions instituted to

prevent resin inventory monitoring problems which occurred during the previous resin

sluice. The licensee received a violation for inadequate procedural controls for a

December 23, 1996 standard resin sluice from the purification and deborating ion

exchanger T-518 to spent resin storage tank T-100. Although there were several

contributing factors that led to the violation, the inspector's main concerns in observing

this resin transfer were the inadequate controls for monitoring tank resin levels and low

sensitivity to radwaste systems deficiencies by operations, system engineering and

radiation safety personnel.

b.

. Observations and Findings

The inspectors noted greater personnel resources were applied to the spent fuel pool

resin transfer than in similar previous activities. A senior reactor operator managed the

overall activities for the transfer of resin. A senior reactor operator was in constant direct

communication with the several auxiliary operators responsible for valve manipulations

and monitoring the radwaste system during the resin transfer. All the operators were

knowledgeable of their tasks. Health physics performed initial radiation surveys of the

tanks involved it the resin transfer, which were more detailed than previous surveys. The

flush of the resin transfer was also performed longer than in the past to ensure all resin

had been moved. Post radiation surveys of the tanks and in-line filters were also more

extensive than in past resin transfers.

The inspectors noted the procedure covering resin transfer had been revised to include

more thorough documentation of resin inventory. Precautions were added to the

procedure to heighten personnel awareness regarding the interconnecting system

flowpaths and the potential for abnormal radiological conditions such as plugging of

radwaste filters.

21

c.

Conclusions

The licensee's actions to improve the resin transfer process resulted in an error-free

evolution for the spent fuel pool job. The inspectors noted good attention to detail and

awareness of changing radiological conditions. Procedure revisions for tending resin

inventory and heightening personnel awareness of the radiological significance of

performing a resin transfer were successful.

V. Manaaement Meetings

X1

Exit Meeting Summary

The inspectors presented the inspection results to members of licensee management at

the conclusion of the inspection on October 17, 1997. No proprietary information was

identified.

22

. .

PARTIAL UST OF PERSONS CONTACTED

Licensee

R. A. Fenech, Senior Vice President,

Nuclear, Fossil, and Hydro Operations

T. J. Palmisano, Site Vice President - Palisades

G. B. Szczotka, Manager, Nuclear Performance Assessment Department

D. W. Rogers, General Manager, Plant Operations

D. P. Fadel, Director, Engineering

S. Y. Wawro, Director, Maintenance and Planning

R. J. Ger1ing, Manager, Design Engineering

P. D. Fitton, Manager, System Engineering

T. C. Bordine, Manager, Licensing

J. P. Pomeranski, Manager, Maintenance

D. G. Malone, Shift Operations Supervisor

M. P. Banks, Manager, Chemical & Radiation Services

K M. Haas, Manager, Training

M. E. Parker, Senior Resident Inspector, Palisades

P. F. Prescott, Resident Inspector, Palisades

23

u

INSPECTION PROCEDURES USED

IP 37551:

IP 61726:

IP 62707:

IP 71707:

Onsite Engineering

Surveillance Observations

Maintenance Observation

Plant Operations

IP 71750:

IP 83750:

IP 92700:

IP 92701:

Plant Support Activities

Occupational Radiation Exposure

Licensee Event Reports

Followup

IP 92901:

IP 92902:

IP 92903:

Followup - Operations

Followup - Maintenance

Followup - Engineering

ITEMS OPEN

"SO-~J97&!.1 01 -

VIO

-fcailyre to ~

50-255/97011-02

50-255/95005-00

50-255/95008-00

50-255/95012-00

50-255/96003-02

50-255/96008-03

50-255/96008-04

50-255/96010-00

50-255/96014-01a

50-255/96014-01b

50-255/96014-04

NCV

Failure to take adequate corrective actions for an Appendix R

concern

ITEMS CLOSED

LER

Inadvertent actuation of the safety injection

LER

Bypassed containment high pressure trips on reactor protection

system

LER

VIO

VIO

VIO

LER

VIO

VIO

VIO

Unqualified electrical connection in containment service water

Failure to maintain design basis document (OBOs) current

Unauthorized operation of plant equipment

Failure to follow surveillance procedure

Trip of high pressure safety injection pump

Failure to ensure control rod drive mechanisms locked prior to

inserting a reactor trip signal

Failure to position instrument AC bus Y-01 control handle to the

correct position resulting in loss of power to bus _ _

__

Inadequate design control of temporary modification for polar crane

solenoid

24

. ,

50-255/97004-00

50-255/97005-00

LER

Trip of high pressure safety injection pump while following the

safety injection tank

LER

Operation outside the design basis due to unacceptable Codes

repairs

25

A LARA

AC

AP

ASME

ccw

CFR

CRD

CROM

CV

DBD

DRP

ECP

ESS

GOP

gpm

IP

LCO

LER

MO

NRC

NCO

NCV

ONP

oos

PCM

PCS

PDR

QO

RO

RPS

RV

SIT

SOP

SW

sv

T

TOC

TS

VCT

VIO

WGS

UST OF ACRONYMS USED

As Low As Reasonably Achievable

Alternating Current

Administrative Procedure

American Society of Mechanical Engineers

Component Cooling Water

Code of Federal Regulations

Control Rod Drive

Control Rod Drive Mechanism

Control Valve

Design Basis Document

Division of Reactor Projects

Estimated Critical Position

Essential Safety System

General Operating Procedure

Gallons Per Minute

Inspection Procedure

Limiting Condition for Operation

Licensee Event Report

Monthly Operating (procedure)

Nuclear Regulatory Commission

Nuclear Control Operator

Non-Cited Violation

Off Normal Procedure

Out Of Service

Personnel Contamination Monitor

Primary Coolant System

Public Document Room

Quarterly Operations (procedure)

Refueling Operations (procedure)

.Reactor Protection System

Relief Valve

Safety Injection Tank

System Operating procedure

Service Water .

Solenoid Valve

Tank

Time Over-Current

Technical Specification

Volume Control Tank

Violation

Waste Gas System

26