Summary of 870826 & 27 Meetings W/Util in Bethesda,Md Re Proposed Revs to Tech Specs.List of Attendees Encl
ML17342A959
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 09/28/1987
From: Macdonald D
Office of Nuclear Reactor Regulation
To:
Office of Nuclear Reactor Regulation
References
TAC-63038, TAC-63039, NUDOCS 8710150550
Download: ML17342A959 (7)


Text

eptember 28, 1987 Docket Nos.

50-250 and 50-251 LICENSEE:

Florida Power and Light Company FACILITY:

Turkey Point Units 3 and 4 DISTRIBUTION NRC PDR Local PDR PD22 Rdg HBerkow DMcDonald OGC-Bethesda EJordan JPartlow ACRS (10}

BTroskowski DLangford CMoon AToalston

SUBJECT:

SUMMARY

OF MEETING HELD WITH FLORIDA POWER AND LIGHT COMPANY (FPSL)

ON AUGUST 26 AND 27,

1987, REGARDING TECHNICAL SPECIFICATION CONVERSION

REFERENCE:

TAC Numbers 63038 and 63039 Back round Members of the NRC staff met with the 'licensee's representatives at Bethesda, Maryland, to discuss proposed revisions to specific sections of the Turkey Point Plant Units 3 and 4 Technical Specifications.

The 'licensee is converting the existing custom plant Technical Specifications, which were issued in the early 1970's, to the format and content of the Standard Technical Specifications for Westinghouse Pressurized Water Reactors (NUREG-0452).

A list of attendees is enclosed.

Sunmary The meeting was initially scheduled for the purpose of performing a detailed review of the proposed Technical Specifications relating to safety limits and instrumentation (Sections 2.0 and 3/4.3).

Neither the licensee nor the NRC had adequate time to prepare for the review of these sections.

It was deter-mined that the meeting should still be held and the time utilized to resolve the open items identified in previous meetings.

The open items relating to Sections 3/4.9, 3/4.10, 3/4.11 and 3/4.12, as well as the associated

bases, were resolved.

The NRC staff will issue a

second draft of these sections which will reflect the agreed-upon resolutions.

The licensee will ensure that the no significant hazards consideration evaluation addresses all the changes.

Subsequent to the meeting, the licensee and NRC staff determined that the next meeting to address safety limits and instrumentation willPe held in

Bethesda, Maryland during the first part of October.

The staff will also pro-vide, comments on Section 3/4.8 for the licensee's consideration in preparing

, /or a future meeting on this section.

87i0150550 870928 PDR ADOCK 0500025p P

PDR

I A

4 W

'E

%F II E

r

~,

The followup meetings will take place at the site, the Region II office and at Bethesda to assure interaction with all the participants.

Physical systems and components can be verified during the site meetings.

The licensee identified some sections of the proposed Technical Specifications to be deleted or added which differ from the Standard Technical Specifications due to plant-specific design features.

Daniel G. NcDonald, Senior Project Hanager Project Directorate II-2 Division of Reactor Projects-I/II

Enclosure:

As stated cc w/enclosure:

See next page A:

r 9/

/87 22 DMcDona1 d 9/y5/87 D:PD2 HBerko 9/ g/87

MI M

~

4 4

4 +

I I

/PI pl

~ t 4 'I I llpl 4

~ 4 I,

IM 4~

IN NN I

4

',I 4 ~ 'IN'(

N N

"N M

~ M'NM

Mr. C. 0. Woody Florida Power and Light Company Turkey Point Plant CC:

Harold F. Refs, Esquire Newman and Holtzinger, P.C.

1615 L Street, N.W.

Washfngton, DC 20036 Mr. Jack Shreve Office of the Public Counsel Room 4, Holland Building Tallahassee, Florida 32304 Norman A. Coll, Esquire

Steel, Hector and Davis 4000 Southeast Financial Center Miami, Flor"fda 33131-2398 Nr. C. N. Wethy, Yfce President Turkey Point Nuclear Plant Florida Power and Light Company P.O.

Box 029ggL

'Nfamf, Florf~a 33102 Nr. M. R. Stierheim County Manager of Metropolitan Dade County Niamf, Florida 33130 Resident Inspector U.S. Nuclear Regulatory Coamfssfon Turkey Point Nuclear Generating Station Post Office Box 57-1185 Miami, Florida 33257-1185 Jacob Daniel Nash Offfce of Radiation Control Department of Health and Rehabilitative Services 1317 Wfnewood Blvd.

Tallahassee, Florida 32399-0700 Intergovernmental Coordfnatfon and Review Office of Planning 5 Budget Executive Offfce of the Governor The Capitol Building Tallahassee, Florida 32301 Administrator Department of Envfronmen'tal Regulation Power Plant Siting Section'tate of Florida 2600 Blair Stone Road Tallahassee, Florida 32301 Regfonal Administrator, Region II U.S. Nuclear Regulatory Coamission Suite 2900 101 Marietta Street Atlanta, Georgia 30323 Martin H. Hodder, Esquire 1131 kE, 86th Street Miami, Florida 33138 Joette Lorion 7269 SW, 54 Avenue Miami, Florida 33143 Nr. Chris J. Baker, Plant Manager Turkey Point Nuclear Plant Florida Power and Light Company P.O.

Box 029100 Nfamf, Florida 33102 Attorney General Department of Legal Affafrs The Capitol Tallahassee, Florida 32304

ENCLOSURE ATTENDANCE LIST AUGUST 26 AND 27, 1987

  • D. McDonald B. Burdick

<<T. Grozan C. Moon C. Morton

  • D. Langford

<<J. 'Trotter

<<A. Toalston ORGANIZATION NRR/PM FP&L - Licensing FP&L - Licensing NRR/DOEA/OTSR EG&G-EM (LLNL3 NRR/DOEA/OTSB NUS NRR/SELB

<<Denotes part-time attendance