ML17290A173
| ML17290A173 | |
| Person / Time | |
|---|---|
| Site: | Columbia |
| Issue date: | 03/17/1993 |
| From: | Imbro E, Jeffrey Jacobson, Norkin D Office of Nuclear Reactor Regulation |
| To: | |
| Shared Package | |
| ML17290A171 | List: |
| References | |
| 50-397-93-201, GL-89-13, NUDOCS 9304090307 | |
| Download: ML17290A173 (66) | |
See also: IR 05000397/1993201
Text
U.S.
NUCLEAR REGULATORY COMMISSION
OFFICE
OF NUCLEAR REACTOR REGULATION
NRC Inspection Report:
50-397/93-201
License No.:
Docket No.:
50-397
Licensee:
Washington Public Power Supply System
Facility Name:
Washington Nuclear Plant, Unit 2
Inspection
Conducted:
From February
1 through February ll, 1993
Inspection
Team:
Jeffrey
B. Jacobson,
Team Leader,
Paul Narbut, Assistant
Team Leader,
Region
V
Christopher Nyers,
Region
V
David Pereira,
Region
V
Steven
Jones,
Ann Dummer,
Prepared
by:
Jeffr
. J
obson,
Team Leader
Date
Team
nspe
ion Section
A
Special
Inspection
Branch
Division of Reactor Inspection
and
Licensee
Performance
Office of Nuclear Reactor Regulation
Reviewed
by:
Don ld
. Norki
,
ec ion Chief
Team Inspection Section
A
Special
Inspection
Branch
Division of Reactor Inspection
and
Licensee
Performance
Office of Nuclear Reactor Regulation
Date
a
Approved by:
Eugene
V. Imbro,
hie
Special
Inspection
Branch
Division of Reactor Inspection
and
Licensee
Performance
Office of Nuclear Reactor Regulation
Date
9304090307
950401
ADOCK 05000397
8
E
EXECUTIVE SUMMARY
The Special
Inspection
Branch of the U.S. Nuclear Regulatory
Commission
performed
a pilot service water system operational
performance
inspection at
Washington Nuclear Plant, Unit 2 from February
1 through
11,
1993.
The
service water system at the station comprises
both the high pressure
core
spray service water
system
and the standby service water system.
The inspec-
tion team focused
on the mechanical
design,
operational
control, maintenance,
and surveillance of the service water system
and evaluated
implementation of
the quality assurance
and corrective action programs.
The team also addressed
the licensee's
implementation of actions in response
"Service Water System
Problems Affecting Safety-Related
Equipment."
The team found the design of the service water system to contain
adequate
margin to account for some calculational
uncertainties
and system degradation.
General
implementation of the licensee's
actions in response
to Generic Letter 89-13 appeared
to be adequate.
However, the team identified four deficiencies
with regard to corrective action program implementation
and procedural
adherence.
The team found that the licensee
did not correct
a "hammering" problem
associated
with service water loop isolation valves
SW-V-12A/B.
Although this
problem had
been
documented,
its extent or its possible ramifications
had not
been adequately
evaluated.
The licensee
had not resolved
a concern that was
identified by an internal review of the service water
system related to the
system.
The operability of this system
had not been
confirmed even though the system status
had
been questioned
by the internal
review team.
Additionally, a problem evaluation request
was not generated
when spray
pond sulfur concentration limits were exceeded
due to biocide
chemical additions.
The team also identified mistakes
made in verifying the
position of spray
pond siphon line vent valves.
Significant observations
included:
~
lack of procedures
to cope with spray
pond icing
a biofouling program that
had not been proceduralized
or adequately
controlled
some degradation
(piping corrosion)
in the physical co'ndition of the
service water system
an improperly stored
crane in the service water pumphouse
potential for the freezing of some spray tree
arms
failure to include instr ument accuracies
in valve position verification
procedures
lack of a procedure for performing inspections of the spray
pond intake
structure
scaffolding in the residual
heat
removal
pump rooms that had
been
installed since plant start-up
The team identified strengths
in the licensee's
programs for performing heat
exchanger
performance testing
and in the internal audit that was performed
on
the service water
system in 1990.
TABLE OF
CONTENTS
1.0
INSPECTION
SCOPE
AND OBJECTIVES
2.0
GENERAL SYSTEM DESCRIPTION
.
3.0
SERVICE
WATER SYSTEM LEVEL REVIEW
~ae
3. 1
System Heat
Removal
Capacity
3.2
Design Function Verification
3.3
Seismic gualification
3.4
Instrumentation
3.5
Freeze
Protection
4.0
HECHANICAL COMPONENTS
REVIEW
.
4.1
SSW and
SW Pumps
4.2
SSW System Piping
4.3
Heat Exchanger
Evaluations
.
~
~
~
~
~
~
~
~
~
~
~
~
~
and Single Failure Analysi s ~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
6
7
8
9
10
11
12
12
4.3. 1
Diesel Cooling Mater Heat Exchanger
4.3.2
RHR Heat Exchanger
.
.
.
.
.
.
.
.
.
4.3.3
Various
Room Coolers
.
5.0
SERVICE WATER SYSTEM MODIFICATION REVIEW .
5.1
Service
Water System
(SWS) Cross-Connect
Hodi
5.2
Replacement
of SW-V-2A/B .
.
6.0
SERVICE MATER SYSTEH SURVEILLANCE AND TESTING
fication
~
~
~
~
~
~
~
~
~
~
12
13
13
14.
14
14
15
6. 1
Technical Specification Surveill
6.2
Preoperational
Test
Review
6.3
Inservice Testing
6.4
System Unavailability Review
.
.
6.5
Heat Exchanger
Performance
Test
7.0
BIOFOULING CONTROL AND TESTING
.
8.0
MAINTENANCE
9.0
OPERATIONS
.
9. 1
Operations
procedures
9.2
Valve line-up program
9.3
Conduct of Operations
9.4
Operator training
ance Testing
~
~
~
Review
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
15
16
16
17
17
18
20
21
21
22
23
24
10.0
SYSTEM WALK-DOWN
11. 0
CORRECTIVE ACTIONS
APPENDIX A SUMMARY OF
INSPECTION FINDINGS
APPENDIX B - LIST OF OBSERVATIONS
APPENDIX
C - EXIT MEETING ATTENDEES
~
~
~
~
~
~
~
~
~
~
25
27
. A-1
. B-1
. C-1
~%
1.0
INSPECTION
SCOPE
AND OBJECTIVES
From February
1 through February
11,
1993, the U.S. Nuclear Regulatory
Commission
(NRC) staff performed
a pilot service water system
(SWS) opera-
tional performance
inspection
(SWSOPI) at Washington Nuclear Plant Unit 2.
The service water system at the station is comprised of both the high pressure
(HPCS
SW)
and the standby service water
(SSW)
systems.
The
SWSOPI focused
on the mechanical
design,
operational
control,
maintenance,
testing
and surveillance of the
and evaluated
implementation
of the quality assurance
and corrective action programs.
The primary objec-
tives of this inspection
were to:
~
assess
the performance of the
SWS through
an in-depth review of mechani-
cal
systems
functional design
and thermal-hydraulic performance;
operating,
maintenance,
and surveillance
procedures
and their implemen-
tation;
and operator training on the
assess
the functional design
and operational
controls of the
SWS based
upon the thermal
and hydraulic performance
requirements,
and determine
whether
SWS components
are operated
in a manner consistent with their
design
bases
assess
the licensee's
planned
and completed actions in response
to
"Service Water System
Problems Affecting
Safety-Related
Equipment," July 18,
1989
assess
the unavailability of the
SWS resulting from planned
maintenance,
surveillance,
and component failures
The team has characterized its findings as deficiencies
and observations.
Deficiencies
are either the apparent failure of the licensee
(1) to comply
with a requirement or (2) to satisfy
a written commitment or to conform to the
provisions of applicable
codes,
standards,
guides,
or other accepted
industry
practices that have not been
made legally binding requirements.
For items
that
may require enforcement
actions,
the
NRC regional office will issue the
Notice of Violation and/or Deviation.
Observations
are items considered
appropriate
to call to licensee
management
attention although they have
no
apparent direct regulatory basis.
2.0
GENERAL SYSTEM DESCRIPTION
During normal operating
and emergency conditions,
the
SSW and
SW systems
transfer heat from various safety-related
systems
and components
to the
ultimate heat sink (See Figure 1).
The
SSW system
and the
SW system,
combined,
are designed
to perform their cooling function following a design
basis
accident
assuming
a loss of offsite power and
a single active failure.
The
SSW system is designed to remove reactor
decay heat from the residual
heat
removal
(RHR) system during
a normal
shutdown,
including periods
when offsite
power is unavailable.
0
0
5
0
&~X~ ?
g
C
RRA SAMPLE ROOM
COO. COILS
0
m
?0
Cl
m
Som
m
PPC KX
RRAISAMPLE RM
COOL COILS
RHR C
RM COOLER
0
RHR 5
PMPIRM COOLER
CIEEEIIRM
SW PH
RM COOL
RN'VAC
0
IIIIIIR PIIMPIRM~
PIIMPIRM COOIEII
OG 1A
OIESELlRM
RM COOL
Et
C
E
I
I
D0
M i~0
0C
0
'00?0
OGIRM
HPCS PUMPIRM
COOLER
i
b'
The ultimate heat sink consists of two square
concrete
ponds,
each with an
associated
pump house
and spray ring.
Loop A of the
SSW system
draws water
from pond A, cools safety-related
equipment
associated
with electrical
Division I, and discharges
to the spray ring over pond
B to dissipate
heat.
Similarly, loop
B draws water from pond B, cools safety-related
equipment
associated
with electrical Division II, and discharges
to the spray ring over
pond A.
The
SW system
draws water from pond A, cools equipment
as-
sociated with the
HPCS system (electrical Division III), and discharges
directly to pond A.
A siphon line between
the two ponds allows for water flow
from one pond to the other.
The ultimate heat sink provides sufficient
cooling capacity to support
a normal
cooldown or an emergency
cooldown
following a loss of coolant accident for a period of thirty days,
coincident
with a loss of offsite power and
a failure of one loop of the
SSW system.
The spray
ponds
are provided with makeup water from the tower makeup
(THU)
system.
The
TNU system supplies river or cooling tower basin water to the
spray
ponds to replace water lost during spray ring operation
due to evapora-
tion and drift.
In addition, the
THU system is designed to replace water lost
from the spay
ponds during
a tornado.
To ensure
system availability for this
mode of operation,
the
THU system is designed to operate following a design
basis tornado coincident with a loss of offsite power.
The
SSW and
SW pumps take suction
on the associated
spray
pond through
the
pump sump.
The bottom of the
pump
sump is depressed
below the bottom of
the spray
pond ensuring that adequate
pump submergence
is maintained at the
lowest design
pond water level.
A sloping pond bottom and
a weir wall around
the
pump
sump form a sand trap to prevent
heavy debris
from entering the
pump
suction.
A fixed screen is also provided to prevent floating debris from
entering the
pump suction
and to collect debris entrained
in the water flowing
toward the
pump suction.
Each
pump is located within a separate
pump bay and
is provided with a separate
sand trap
and intake screen.
The piping of the
SSW and
SW systems is constructed of carbon steel to
seismic Category I and American Society of Mechanical
Engineers Boiler and
Pressure
Vessel
Code
(ASME Code),
Section III, Class
3 requirements,
with the
exception of that portion of system piping to and from the plant cooling tower
basin,
which is constructed
to American National
Standards
Institute Standard
(ANSI) B31. 1 and seismic Category II requirements,
and portions of the keep
full subsystem
located in the
pump house,
which is constructed
to ANSI B31.1
and supported to seismic Category I requirements.
The piping was designed for
operating
pressures
of 150 psig or 309 psig,
depending
on location,
and
an
operating temperature
of 150 F.
The piping schedule
selected for the
system includes
a corrosion allowance of 0.080 inches.
For each
SSW loop, the water flows from the
pump discharge
through
a discharge
check valve (SW-V-IA/B) and
a butterfly-type motor operated
discharge
valve
(SW-V-2A/B) to the loads serviced
by the system.
The
RHR heat exchanger
and
the diesel
cooling water
(DCW) heat exchangers
are the dominant loads
on the
SSW system.
The combined flow to these
heat exchangers
is in excess of 80X of
the respective
SSW loop total flow.
Other loads
on the
SSW system include
emergency
core cooling system
(ECCS)
component
and
pump room coolers,
the
reactor core isolation cooling
(RCIC)
pump room cooler,
pump
Jg
house cooler,
containment
atmospheric
control
(CAC) equipment,
diesel
gener-
ator room coolers,
switchgear
room coolers,
and control
room coolers or
chiller condensers.
The
SSW system also serves
as the backup supply of
cooling water to the spent fuel pool
(SFP)
heat exchanger
and
pump room
cooler.
The
B loop of the
SSW system is capable of performing
a beyond design
basis function of core or containment flooding through
a crosstie to the
system.
Flow to each
component is balanced
using
a combination of orifice
plates
and throttle valves.
The return flow from all components
in each loop
combines
in a single return header.
The return header is provided with a
locked open air operated
valve
(SW-PCV-38A/B), formerly used
as
a pressure
control valve,
and
a motor operated
gate-type isolation valve (SW-V-12A/B).
The keep full subsystem
is attached
to the return header
and is intended to
makeup for leakage
from the
SSW system past
SW-V-2A/B and SW-V-12A/B when the
SSW system is idle.
Flow from the return header is manually directed through
the spray ring isolation valve
(SW-V-170A/B) to the associated
spray ring when
cooling of the return water is required,
or directly into the pond through the
spray ring bypass
valve
(SW-V-165A/B) when pond temperature
is sufficiently
low.
Sor the
SW loop, the water flows from the
pump discharge
through
a
discharge
(HPCS-V-28)
and
a butterfly-type motor operated dis-
charge valve
(SW-V-29) to the loads serviced
by the system.
The
HPCS diesel
generator
DCW heat exchanger
receives
in excess of 75K of system flow.
The
other loads serviced
by the
SW system
are the diesel
generator
room
cooler,
switchgear
room cooler,
and the
pump room cooler.
The return
flow combines into a single return header
and is returned directly to spray
pond
A without spray.
The
SSW pumps are
AC motor driven, three stage, vertically mounted,
axial flow
pumps with a rated capacity of 10,500
gpm at
a total developed
head of 500 ft.
The design
minimum submergence
of the
SSW pumps is 4.0 ft.
The
SSW pumps are
provided with electrical
power from their associated
safety-related electrical
division.
Each loop of the
SSW system
may be started
manually, or aligned to
start automatically
when
an
pump associated
with the loop or the diesel
generator
associated
with the loop starts.
On
a start signal with SW-V-2A/B
closed,
SW-V-12A/B begins to open.
When SW-V-12A/B has partially opened,
a
limit switch actuates
to start the
SSW pump.
At a
pump discharge
pressure
of
50 psig,
a pressure
switch actuates
causing
SW-V-2A/B to open partially and
stop, limiting the rate of system fill. Following a time delay of 50 seconds,
SW-V-2A/B continues
opening to its full open position.
The 'SSW pump will trip
on overcurrent,
and closure of SW-V-12A/B.
The
SW pump is an
AC motor driven, vertically mounted,
two stage,
axial
flow pump with a rated capacity of 1200
gpm at
a total developed
head of 123
ft.
Minimum pump submergence
at rated conditions is 2.0 ft.
The
SW pump
is provided with electrical
power from safety-related
electrical Division III.
The
SW system
may be started
manually or aligned to start automatically
on
a
HPCS diesel
generator start.
On
a start signal, the
SW pump starts.
At a
pump discharge
pressure
of 50 psig,
a pressure
switch actuates
causing
SW-V-29 to open fully.
The
SW pump will trip on overcurrent
and under-
voltage.
i
The pumps,
discharge
valves,
and return header isolation valves for each
system loop are located within the
pump house associated
with the respective
loop.
The
SW pump, discharge
and discharge
isolation valve
are located within pump house
A.
The
pump houses
are constructed
to seismic
Category I requirements
and protect
components
in the
SSW and
SW systems
from the effects of postulated
external missiles.
The
pump houses
are heated
by electric blast heaters.
The
pump houses
are cooled
by a fan which draws in
outside air, or,
when the associated
pump is running,
an air handling unit
cooled
by SSW.
To prevent freezing, all
SSW piping and components
are either located in
heated structures,
buried below the frost line, heat traced,
or maintained
by
procedure
in a drained condition during cold weather
when the system is not in
operation.
The structural integrity of the
SSW and
SW piping is also
protected,
in part,
by a cathodic protection
system which applies
an elec-
trical potential to sections of piping in order to reduce the rate of galvanic
corrosion.
3.0
SERVICE WATER SYSTEM LEVEL REVIEW
3. 1
System
Heat
Removal
Capacity
The Service Water System
(SWS)
was designed
to provide sufficient cooling
without additional
makeup water for at least
30 days of operation during
accident or abnormal conditions.
The design
assumed
the worst combination of
controlling parameters
such
as
dew point, wind speed,
and solar radiation,
including appropriate diurnal variations.
This results
in maximum evaporation.
and drift losses
during the worst 30 day average
combination of the control-
ling parameters
pertaining to a recent period of record at least
30 years in
length.
Sufficient conservatism
was provided to ensure that
a 30 day cooling
supply is available
and that the design basis
temperatures
of safety related
equipment
are not exceeded.
The team reviewed the thermal
performance
requirements
of the
SWS during
accident or abnormal conditions,
including the appropriateness
of the design
assumptions,
boundary conditions,
and models.
Calculation HE-02-92-41
provided the room temperatures
during Design Basis Accidents
such
as ashfall
or a loss of coolant accident
(LOCA).
This calculation provides
a maximum
water consumption profile for the spray ponds,
which assumes
that the spray
drift covers
as little of the ponds
as possible,
and maximizes evaporation
losses.
Additionally, the meteorology
was selected
to maximize the evapora-
tion from the spray trees.
Calculation ME-02-92-41 indicated that the
SWS has
adequate
total water
inventory at the end of 30 days of 2,490,000 gallons,
390,000 gallons
more
than the minimum for siphon operation.
The team verified by independent
checking
and by verifying assumptions,
calculations,
and initial boundary
conditions that the results
and conclusions
were accurate
and correct.
The
calculation
had
a starting inventory of 11.92 million gallons which is based '.
on the minimum FSAR pond level of 432'-9".
The Calculation incorporated
several
water consumption
conservatisms.
The most notable
are the following:
I '>
T'l~
%4 (
1
I)
l
I) the meteorology
used for the first three
days of the accident is the worst
single day meteorology of record,
2) zero cloud cover over the entire event,
and 3) wind direction which maximizes spray losses.
The team's
review of Calculation E/I-02-92-14 determined that the heat load
calculation of electrical
equipment
and cables
was appropriate
and presented
the maximum heat load into the various
rooms located in the plant buildings.
The most notable
assumptions
were that
a ground fault occurs in each safety
related division during the operating
modes, all components
(such
as relays,
switches,
and transmitters)
are continuously energized,
and the heat load for
the inverters
and chargers
is calculated
assuming
they are fully loaded to
their rated capacity.
With the maximum heat loads generated
by the electrical
equipment
and cables,
the
SWS thermal capacity performance
requirement
was
still adequate
and the maximum safety equipment
temperatures
were within
design requirements.
The team determined that the
SWS has
adequate
heat
removal capacity
based
on
the worst mass loss analysis for a period of 30 days without outside
makeup.
The
SWS is capable of accomplishing its safety function for a normal
cooldown
or emergency
cooldown following a
LOCA without the availability of off-site
power.
The team had
no concerns
regarding the
SWS thermal capacity performance
requirement.
3.2
Design Function Verification and Single Failure Analysis.
The Service Water System
(SWS) is designed to perform its required cooling
water function following a Loss of Coolant Accident
(LOCA), assuming
a single
.
active failure.
The
SWS has
two main loops:
Loop A (electrical division I)
and
Loop
B (electrical division 2).
They are physically separate
and indepen-
dent of each other.
Each loop has its own cooling pond with spray trees,
but
the ponds
are connected
with a siphon line since only the combined water
volume of the spray
ponds is adequate
to provide the cooling water for 30 days
without makeup.
By design,
Pump
A discharges
into Pond
B,
and
Pump
B dis-
charges
into Pond A.
In addition to Loop A and
Loop B,
a small auxiliary loop
(Loop C, electrical division 3) exists,
which is dedicated exclusively to the
cooling requirements
of the High Pressure
(HPCS)
system.
System
failure mode
and effects analysis of passive
and active components of the
are detailed in the Final Safety Analysis Report
(FSAR).
In addition,
any of
the
assumed
failures of the
SWS can
be detected
in the main control
room by
indication and/or alarms
from the various
system instruments'.
The team reviewed the
SWS for single active failure vulnerabilities
as stated
in the
FSAR and in Calculation NE-02-89-46, "Fault Tree Calculation."
As
described
above,
the three
SWS loops operate
independently,
i.e,
redundancy of
the service water system heat
removal function is achieved
by having multiple
cooling loops available
as
opposed to having redundancy
embedded within each
loop itself.
A single
SWS loop can fail by failure of any single
one of its
essential
components.
The team's
review of Calculation NE-02-89-46
and of the
FSAR addressed
four
principal single failure modes of the
SWS loop.
The first failure mode
was
insufficient coolant flow at the
pump suctions.
This failure can occur if
any debris in the spray
pond gets too close to the
pump house,
so that it gets
drawn onto the
pump intake screen
where it could cause
clogging.
Research
by
the
NRC team of this failure mode determined that with a
pump
sump bottom
elevation of 408'-3"
and
a normal
pond elevation of 433'-6", there is in
excess of 25'f water above the
pump suction,
and the
pump intake screen is
2-3'rom the bottom of the
pump
sump to the wet wall separating
the spray
pond from the
pump sump.
This mode of failure is very unlikely.
The second failure mode
was the failure of the
pump to produce
adequate
head.
This failure mode can
be caused
by failure of the
pump motor to start
due to electrical or mechanical
'causes,
failure of the
pump motor to keep
running for the required mission time,
and mechanical failure of the
pump
itself during the mission time.
The
SWS pumps
have backup electrical
supplies
via the emergency diesel
generators
in case of loss of off-site power.
In
addition, the
pumps consist of two independent
100X capacity
pumps
each
supplying normal
and emergency
shutdown cooling equipment.
A single active
failure of either the
pump or its respective
motor would inactivate that
loop's function.
However, the other
SWS loop is capable of performing the
cooldown function following the
LOCA.
The third failure mode is insufficient coolant flow from the
pump dis-
charge,
which can
be caused
by failure of the check-valve
SW-V-1A/B, the loop
isolation valve SW-V-12A/B, or the discharge
valve SW-V-2A/B.
Appendix A of
Calculation NE-02-89-46 indicated failure unavailabilities of 5.83E-04,
and
6.65E-04, respectively, for the check-valve
and the discharge
valve.
However,
the calculation did not address
failure of the loop isolation valve.
The team
was concerned that uncertainties
with this valve's operation could cause
a
loss of redundant
SW trains.
(See
paragraph
11.0 and Deficiency 93-201-04 in
Appendix A of report).
The fourth failure mode is
a maintenance
error rendering
an essential
component unavailable.
The maintenance
error can interfere with system
operation if a valve,
pump, or pump motor had
been disassembled
and then
incorrectly reassembled.
The licensee
performs
an operating test after
completion of maintenance
work which should reveal
any maintenance
errors.
3.3
Seismic gualification
The Service
Water System
(SWS)
has to accomplish its safety function despite
the occurrence of the most severe site related natural
events
including
ashfall, tornado,
flood, or drought.
The ultimate heat sink spray
ponds
and the pumphouses
were designated
as Seismic Category I.
These
components
provide cooling capability for a period of 30 days without outside
makeup.
The basis for this requirement is General
Design Criterion
2 of
Appendix A,
"Design Bases for Protection Against Natural
Phenomena."
The team conducted
a walkdown of the
SWS to ensure that the safety-related
portions are seismically qualified.
The team noted that the
pump house
"A"
crane
HR-CRA-6A was not stored
against
the southwest wall as required
by Plant
Procedures
Manual
(PPN) 10.2.53,
"Seismic Requirements
for Scaffolding,
Ladders,
Tool
Gang Boxes, Hoists,
and Metal Storage
Cabinets".
In addition,
<<+,c
'II lv
e
attachment
8.4 specifically illustrates the acceptable
locations for storage
of hoists,
but does not indicate the
pump house
"B" crane
HR-CRA-6B (Observa-
tion f93-201-01).
The improperly stored
crane
prompted initiation of Problem
Evaluation Request
(PER) 293-125
on February 3,
1993 by the licensee.
PER
293-125 initiated Procedure
Deviation
Forms
(PDFs) which detailed the storage
requirements for cranes
HR-CRA-6A and
6B upon completion of lifts or mainte-
nance.
The
NRC team determined that both cranes
MR-CRA-6A and
6B were Seismic
Category I as were the dual rails upon which the cranes
are positioned.
No Seismic Category I structures
or components
appeared
to be in danger
by a
Seismic Category II structure.
The team
had
no concerns with the seismic
qualification of the
SWS.
3.4
Instrumentation
The Service
Water System
(SWS) spray
ponds
have two Technical Specification
(TS) requirements
which ensure
a minimum water level at elevation 432'"
Mean
Sea
Level
(HSL), and
a water temperature
of less than or equal to 77 F.
The
requirements for minimum water level
and
maximum water temperature
assure
availability of the ultimate heat sink (spray pond) under all weather condi-
tions,
and allow the operators
to take appropriate
action in case of an alarm
condition in either parameter.
The team verified that the minimum water level requirement of elevation
432'"HSL
provides sufficient water for 30 days of cooling without makeup capabil-
ity.
The team reviewed setpoint Calculation
CHR-90-319 for the high and low
trip points of 434'3"
and 433'0" respectively,
and found adequate
margin to
allow operators
to respond to each
alarm condition.
The low setpoint trip
condition of 433'0"MSL would provide 3" of water level before reaching the
TS
required level of 432'9"HSL which provides
ample time for operator action to
refill the spray
pond or determine
leakage
sources.
The high trip setpoint of
434'3"HSL is sufficiently below the top of the wall (435'HSL) to allow
operator action to stop makeup flow.
The bulk average
temperature
of the
SWS spray
ponds is recorded daily using
surveillance
procedure
PPH 7.0.0 to ensure that the temperature
is below the
77'F
TS requirement of Section 3.7. 1.3.
There is no requirement for a minimum
pond temperature.
The surveillance
procedure
requires four temperature
element readings
which are spaced
at different elevations in each
pond.
The
element readings
are
used in an algorithm developed
in calculation HE-02-84-55
to find the bulk temperature.
In addition, in each of the
pump house pits
are two temperature
elements
which are also
use'd.
The team reviewed the processes
and calculations
in determining the setpoints
of each of the temperature
elements.
A low setpoint of 35
F provides
an alarm
to alert operators
of potential
spray
pond freezing,
and allows operator
action to warm the ponds via system operation in a recirculation
mode.
The
high setpoint of 72'F ensures
that the
TS limit of 77'F is not .attained,
and
allows operator action to commence
spraying to lower pond temperature.
While performing surveillance
PPM 7.0.0 the licensee
discovered that two spray
t
'g
pond temperature
elements,
SW-TE-2A and 2E, were destroyed
by ice falling upon
them in early January
1993.
Problem Evaluation Request
(PER)
293-036 reported
the failed temperature
elements
on January
13,
1993.
The licensee
recommended
actions
were to repair the temperature
elements
when ice is off the pond,
and
continue operation until the temperature
elements
can
be repaired
using the
control
room temperature
indications for SWS
pump suction temperatures,
i.e.,
SW-TI-1A, 1B,
1C,
and
1D.
Those elements
are located in the
pump pits as
mentioned previously
and would not be damaged
by surface ice.
The team
reviewed the corrective actions of PER 293-036
and determined that the
SWS was
still operable
due to operable
pump suction temperature
indications.
The
NRC team reviewed several
concerns
over flow orifices supplied
by the
licensee
and installed in several
flow elements
in the
SWS cooling flow path
to several
components.
The concerns
were whether the flow orifice diameters
had
been determined correctly, whether the orifices were accurately
manufac-
tured in accordance
with standard
practices,
and whether
any measurements
or
testing
had
been
performed to ensure
accurate
flow determination for the
components.
The
NRC team reviewed flow orifice sizing calculations
as
conducted
by the Architect and Engineer
(ARE) Burns
and
Roe, Inc.
and deter-
mined that the calculations
appeared
to be accurate
and correct.
The
NRC
inspector verified the calculation's
design
parameters
to be accurate for the
SWS temperature
and pressure
operating
design basis.
The
NRC inspector reviewed the manufacturing specifications of the orifice
plates
per Project Engineering Directive (PED)W215-I-3727
and
PEDW215-I221
which required the orifice plates to be manufactured
in accordance
with the
Instrument Society of America (ISA) recommended
practice 3.2,
"Recommended
Practice for Orifice Plate Fabrication."
Orifices manufactured
to this
standard
would exhibit an accuracy of within +g-
1 X of the actual rate of
flow.
The
NRC walkdown of the
SWS indicated that the flow orifices were
installed properly and that the orifice plates
have the stamped orifice base
diameter
and instrument
number
on the paddle.
The orifice accuracies
were included in the
SWS loop instrument
accuracy
determinations for temperature
and level instruments.
However, the
NRC
inspector determined that the loop instrument
accuracy calculations for the
SWS flow instrument
had not been
updated to include the flow orifice accuracy
determinations
(see report section 6.1).
The licensee
had planned reviewing
and revising loop instrument calculations for the flow instruments later in
the year.
The team identified that the calculations for the flow instruments
appeared
to contain
adequate
margin to account for the instrument uncertain-
ties.
3.5
Freeze
Protection
The
SWS was designed
to be protected
against freezing
by allowing bypass
operation
and draining of spray header piping, inclusion of heat tracing for
above ground piping,
and by locating equipment within heated
enclosures.
Since the spray
ponds
and the above ground piping are usually exposed to
ambient winter weather conditions,
freeze protection
was designed
into the
system operations.
I,
~ '
1
~jr".
ih-
bf
9'
Paragraph
5.6 of procedure
number 2.4.5,
"Standby Service Water System"
provides for controlling spr ay pond temperature
and ring header
ice formation
by bypassing
the spray rings
and draining the rings
and risers
whenever
spray
pond temperature
decreases
below 60'F or the outside
ambient temperature
can
fall below 32'F.
The
SWS operation in cold weather simply bypasses
the spray
and
dumps the return water into the spray ponds.
This circulating mode
breaks
up any ice formation on the ponds,
and warms
up the ponds
due to excess
heat from the buildings being cooled.
The team identified that the horizontal piping runs for several
of the
spray trees
were sloped slightly down towards the nozzles,
in which case
the
horizontal piping would not be completely drained
back to the vertical risers.
The standing water in the horizontal
runs could freeze
and partially restrict
or completely block the flow of SWS water out the nozzle.
The team found no
more than ten horizontal piping (nozzles)
runs per pond which could freeze
solid, with several
others which would only partially freeze
along the bottom
of the pipe (Observation
93-201-02).The
licensee
issued
PER 293-140 to
evaluate this problem.
The
PER evaluation indicated that
up to four vertical
trees
may be removed
from each
pond
(28 nozzles) without affecting its post-
cccident design function.
4.0
MECHANICAL COMPONENTS
REVIEW
4.1
SSW and
SW Pumps
The team reviewed the operating characteristics
of the
SSW and
SW pumps
with respect
to the capability to perform their design functions.
Specifical-.
ly, the team examined
the adequacy of pump submergence
and the capability both
to provide adequate
flow and to prevent excessive
flow rates
and associated
cavitation
(pump runout)
under all anticipated operating configurations.
The team reviewed vendor supplied test data
and
pump curves,
pump installation
arrangement
drawings,
system pressure
drop and flow rate calculations,
and
preoperational
test results.
Vendor testing
and preoperational
testing
adequately
demonstrated
that the installed configuration of the
SSW and
SW pumps will ensure sufficient submergence
to prevent
pump cavitation or
vortex formation for the design basis
minimum spray
pond inventory.
The
and
SW systems
are flow balanced
such that the associated
pumps typically
operate
near their optimum design conditions.
With the exception of heat
exchangers
and the makeup line associated
with the spent fuel pool,
and, for
SSW loop B, the crosstie to the
RHR system,
the
SSW and
SW systems
normally operate with full flow to each
component.
The team determined that
supplying the heat exchangers
associated
with the spent fuel pool from the
system results in a minimal change
in system flow conditions.
The team did
not identify any system configurations
where
pump runout would be of concern.
The team concluded that the
SSW and
SW pumps
are appropriately sized for
their intended function.
In addition, the team has not identified any
operational
or design features of the
SW systems
which would be
likely to result in premature failure of the associated
pumps.
10
rP~-~
4.2
SSW System Piping
The team reviewed the design of the
SSW and
SW system piping with regard
to the performance capability of the
SSW system
and its conformance with the
design
bases
and engineering
analyses
associated
with the
SSW and
systems.
The team examined
SSW and
SW system flow balance test data,
and
SW system flow velocity and pressure
drop calculations,
and system
design criteria.
Piping size
was adequate
to supply the necessary
flow to each
component.
Flow
restricting orifice plates
and throttle valves were
used to establish
accept-
able
SSW and
SW flow to each
component,
while limiting the pressure
drop
through individual heat exchangers.
The
velocity was most limiting with respect
to pipe wall erosion.
However,
calculated flow velocities were within acceptable
ranges to limit system
erosion for all sections of piping.
The calculated
flow velocity values
were
based
on flow rates
measured
during flow balance testing,
ensuring consistency
between
assumed
system
parameters
and actual
system flow characteristics.
The
functional capability of the siphon line demonstrated
during preoperational
-testing is consistent
with the performance
assumed
in the determination of
available spray
pond inventory.
The
SSW and
SW system piping was constructed
to acceptable
standards
in
accordance
with Section III of the
ASHE Code.
An appropriate
corrosion
allowance
was specified,
recognizing the susceptibility of carbon steel
piping
to general
corrosion.
Calculated piping stresses
are such that postulation of
through-wall cracks in
SSW system
ASME Code Class
3 piping is beyond the
design basis for flooding.
However, separation
of the two
SSW loops provides
a'dded
assurance
that flooding will 'not result in
a common
mode failure of
both
SSW system loops.
The keep full subsystem
is not constructed
to ASHE
Code Class
3 requirements,
but
a check valve in the
keep full subsystem,
which
is regularly tested
under the
WNP-2 inservice test plan, is constructed
to
ASNE Code Class
3 requirements
and blocks this potential flooding path.
The team concluded that the
SSW and
SW system piping design is adequate
for the
SSW and
SW systems to satisfy their performance
requirements,
and
is constructed
to standards
which are in accordance
with the design
bases
of
the systems.
4.3
Heat Exchanger Evaluations
4.3. 1
Diesel
Cooling Water Heat Exchanger
The diesel
generators
were supplied with
OCW heat exchangers
mounted
on the
diesel skid.
The vendor specified the required cooling water flow rate
based
on 95'F service water.
SSW and
SW flow rates
provided to the
DCW heat
exchangers
during flow balancing
are consistent with the vendor
recommended
values.
The Division I and Division II diesel
generators
are
tandem mounted diesels
driving a single generator,
and the flow balancing
procedure
establishes
the
combined outlet throttle valve position based
on total flow to the two
DCW
heat exchangers
associated
with each diesel
generator.
The piping configura-
tion results
in one
DCW heat exchanger receiving greater flow than the other.
Calculation
number HE-02-92-14,
evaluated
the capability of the heat exchanger
receiving the lower
SSW flow to cool the diesel
engine
under the greater
load.
The calculation
assumed
the second
DCW heat exchanger,
which is receiving the
greater flow, cools the diesel
engine operating at the lower load.
Adequate
cooling is provided to the Division I and Division II diesel
generators
under
these
non-uniform
SSW flow conditions.
There is little margin between the calculated
DCW temperature
under the
assumed
non-uniform flow and load conditions,
and the high
DCW temperature
alarm setpoint.
The licensee
indicated that
a modification to equalize the
SSW flow to the two
DCW heat
exchangers
of each
tandem diesel
generator is
under evaluation.
4.3.2
RHR Heat Exchanger
The
RHR heat exchangers
were designed for a
SSW flow rate of 7400
gpm at
an
inlet temperature
of 95 F.
The acceptable
flow range for SSW to the
RHR heat
axchangers,
established
during
SSW system flow balancing in accordance
with
procedures
PPH 7.4.7. l.l. 1 and
PPH 7.4.7. 1. 1.2, is 6900
gpm to 7600 gpm.
Calculation
number HE-02-92-245,
determined that
a
SSW flow of 6900
gpm at an
inlet temperature
of 90'F is capable of removing heat from the
RHR heat
exchanger
at the limiting design rate of 121.7 million BTU/hr.
The calcula-
tion adequately justified the capability of the
RHR heat exchanger
to perform
its design
heat
removal function at the established
SSW system
minimum flow
rate of 6900 gpm.
4.3.3
Various
Room Coolers
Calculations
HE-02-92-40
and HE-02-92-43,
determined
the maximum expected
temperatures
under design basis accident conditions for rooms cooled
by
and
SW.
Internal
heat loads resulting from operation of various elec-
trical equipment
were correctly evaluated
and accounted for in the calcula-
tions.
The heat loads resulting from infiltration, conduction
and convection
were generally correctly evaluated.
For the diesel
generator building and the
SSW pump houses,
the heat load resulting from solar radiation
was omitted, but
the effect of this omission is negligible.
The calculations correctly used
vendor data to determine cooling coil performance
under other than design
conditions.
Overall, the calculational
methodology is accep'table for deter-
mining maximum expected
room temperatures
under design basis accident condi-
tions.
5.0
SERVICE WATER SYSTEH MODIFICATION REVIEW
5. 1
Service Water System
(SWS) Cross-Connect
Hodification
The licensee
determined that in order to allow for periodic maintenance
of
submerged
steel structural
supports
and piping in the ultimate heat sink
(UHS)
spray ponds, it was necessary
to drain the ponds
one at
a time during
a
refueling outage.
The present
system design results
in the service water
(SW)
pumps taking suction
on one pond, providing cooling water to plant room
12
5
coolers
and essential
equipment,
returning cooling water to the other pond for
spray cooling,
and returning water to the
pump suction in the first pond via a
30 inch siphon.
This mode of operation precludes
draining of a pond for
maintenance.
A cross-connect
design
change will allow the return of water to
the pond from which it was drawn.
The change
involves the cross connection of
the return piping via
a removable
spool piece,
which will be installed
between
two permanently
located butterfly valves,
and the blockage of the siphon with
a plug.
By this change,
one
pond can
be drained with this cross connection
capability in place.
The
SWS cross-connect
modification was accomplished
via two Basic Design
Changes
(BDCs).
The first BDC;
No 84-1724-0D,
provides
a design for the first
stage
which installs flanges
on
SW return piping.
The second
BDC;
No 89-0103-
OA, provides the design of the connecting valves
(SW-V-933A and 933B)
and the
piping between
the flanges
and the siphon plug design.
Both
BDCs use ASHf
Section III, Code Class
3 fittings and piping to connect to the Class
3
piping.
The
BDC packages
were of excellent quality; the
SWS piping and instrumentation
xliagrams
(P&IDs) were updated to include the two valves
SW-V-933A and 933B.
The final safety analysis report
(FSAR) was modified to discuss this modifica-
tion and the added ability to drain one spray
pond during certain
modes of
shutdown operation.
The licensee
conducted
a Design Safety Analysis on the
SWS cross-connect
modification with focus in four areas:
1) redundancy
requirements,
(UHS) water inventory, 3)
UHS cooling
water temperature limitations,
and 4) severe natural
phenomena.
The Design
Safety Analysis assumptions,
analysis,
and conclusions
were determined to be
complete
and thorough.
The team concluded that the
SW cross-connection
modification appeared
to be installed in accordance
with the modification's
design
packages.
5.2
Replacement
of SW-V-2A/B
In 1986, the
SSW system experienced
a water hammer while placing the supply
line to the spent fuel pool cooling water heat exchanger
in service.
This
event
damaged
piping and pipe supports.
Valve SW-V-2A/B had also required
substantial
maintenance
due to the severe throttling duty of the valve during
system startup since the valve was not designed for this function.
Hodifications were performed
under Plant Hodification Record 02-86-0324-1 to
reduce the potential for hydraulic transients
during system startup
and
decrease
required maintenance
of valve SW-V-2A/B.
The modifications included
replacement of pump discharge
valve SW-V-2A/B, deactivation of SW-PCV-38A/B,
activation of SW-V-12A/B for system discharge isolation,
and installation of
the
"keep full" subsystem.
Following the modification,
no further damage
due to hydraulic transients
has
been observed.
The more robust valve design
used for SW-V-2A/B has decreased
required maintenance.
Therefore,
the team concludes that the modification has.
improved the reliability of the
SSW system.
13
4"
1
I
The team reviewed relevant design
change
packages
and determined that the
modifications to the system were performed in accordance
with the requirements
of 10 CFR 50.59.
Each package
included
a safety evaluation of the proposed
modification, revised drawings, test requirements,
and field work procedures
necessary
to implement the change.
Procedure
numbers
TP 8.3.65
and
TP 8.3.73
addressed
testing following imple-
mentation of PHR 02-86-0324-1 for SSW loop
A and
B, respectively.
Testing of
the
SSW system controls
and interlocks
was performed satisfactorily.
However,
post-modification testing of the system
was performed in a partially, rather
than completely drained condition.
Since valves
SW-V-2A/B and SW-V-12A/B are
not required to be leak tight to perform their function,
and since the keep
full system is not safety grade,
the team concluded that testing from a
completely drained condition would be necessary
to ascertain
that damaging
hydraulic transients
would not occur under the most limiting conditions.
Operational
experience
and
a system startup
observed
by the team from a nearly
completely drained condition (without water hammer) indicate that the proba-
bility of hydraulic transients
has
been substantially
reduced
by the modifica-
tion.
Therefore,
the team concluded that the modification has likely elimi-
nated the potential for water
hammer
and
made the intended
improvement in
system reliability.
6.0
SERVICE
WATER SYSTEN SURVEILLANCE AND TESTING
6.1
Technical Specification Surveillance Testing
The
WNP-2 Technical Specifications
(TS) require that the Standby Service Water.
System
be demonstrated
at least
once every 31 days
by verifying
proper valve position
and at least
once every
18 months
by verifying that each
automatic valve actuates
to its correct position
on
a service water actuation
test signal.
In response
WNP-2 committed to continue
performing periodic flow balancing of each of the service water loops for TS
operability verifications.
TS-related
procedures
PPH 7.4.7. 1.1. 1 "Standby Service Water Loop A Valve
Position Verification," PPH 7.4.7.1.1.2
"Standby Service Mater Loop
B Valve
Position Verification," and
PPH 7.4.7.1.1.3
"HPCS Service
Water Valve Position
Verification" demonstrate
the operability of the
SSW system.
Valve lineups
are performed monthly to verify flow path valve positions.
Automatic valve
function is verified annually during the train operability demonstration.
Flow balancing is performed annually to adjust flows to the heat exchangers
and
room coolers.
The required flow values specified in the
SSW system valve position verifica-
tion procedures
did not include
an allowance for instrument error (Observation
93-201-03).
Based
on
a review of the documents
forming the bases for the
required flow values,
the team determined that sufficient margin exists to
compensate
for the effect on heat
exchanger
performance of a small reduction
in
SSW flow rate resulting from instrument inaccuracy.
However,
a formal
evaluation of the acceptability of the potentially reduced
SSW flow rate to
each
component
had not been performed.
14
6.2
Preoperational
Test Review
In 1983,
WNP-2 performed
a series of tests
on the Standby Service Water System
to verify its readiness
to perform its required functions.
Preoperational
Test Procedure
PT-58.0-A "Standby Service Water," tested
the system's inter-
locks and the operation of pumps
and valves.
Preoperational
Test SLT-S58.0-3
"SW Flow Balance,
" the original flow balance
procedure for the system,
measured
flow for each load
on the permanent
flow meter for each
component.
All flows matched
the required flows listed in the
FSAR except for the
pump seal
cooler.
The original design specification for the seal
cooler was
12 gallons per minute
(gpm) of service water flow at 105'F.
However, in the
test procedure,
the flow to the seal
cooler was reduced
from 12
gpm to 9 gpm.
The licensee
does not have documentation
to support the adequacy of the
reduced flow, but stated that the basis for the
9 gpm would be determined.
The design temperature
of the standby service water system is 85'F, which
would provide more cooling at
9 gpm than
12 gpm at 105'F service water.
In
addition, the licensee
stated that the installed cooler is
a different model
than
shown in the original design drawing and requires less flow.
Therefore,
the team concluded that the reduced flow to the
RHR pump seal
cooler was not
significant.
6.3
Inservice Testing
The inservice test
(IST) program implementation
and surveillance
procedures
were reviewed to verify conformance with Section
XI of ASME Boiler and
Pressure
Vessel
Code
and Generic Letter 89-04.
The team reviewed the follow-
ing inservice test program procedures:
PPM 7.4.0.5. 16 "Standby Service
Water
.
Loop A Operability Demonstration,"
PPM 7.4.0.5. 17 "Standby Service Water Loop
B Operability Demonstration,"
and
PPM 7.4.0.5. 18
"HPCS Service
Water Operabil-
ity Demonstration."
These
procedures
describe quarterly measurements
of valve
pump vibration velocity,
pump discharge
pressure
and flow, and
pond water temperature
and level.
and valves is consistent with Section XI, of the
ASME Boiler and Pressure
Vessel
Code.
IST results indicated that no pumps or
valves in the
SSW system
have
been in the Action Range in the last two years.
There is
a relief request
pending
on WNP-2's
pump test method.
The
SSW system
does not have
a means of setting constant
pressure
or flow for the purpose of
IST pump performance testing.
WNP-2 has developed
a reference
curve based
on
varying pressure
and flow.
Trending of pump performance is based
on normal-
ized data obtained
by dividing the measured
discharge
pressure
by the refer-
ence discharge
pressure
for,a given flow.
The instruments
used in IST
pressure
and flow measurements,
PI-32A/B and FI-8A/B, are accurate
to within
2X, as specified
by ASME Section XI.
6.4
System Unavailability Review
The licensee
developed
a system notebook for use in the Individual Plant
Evaluation
( IPE) that includes the system's
safety functions
and dependencies
on support
systems.
The unavailability used in the
IPE for the
SSW system
was
based
on assumptions
made in the development of the system notebook.
15
Actual system unavailability for the last two years
was determined
based
on
LCO logs
and Problem Evaluation Reports.
Unavailability of the
SSW from
planned
maintenance
and testing for the last two years
was less than
assumed
for the IPE.
HPCS Service Mater was
assumed
to have
no unavailability for
test
and maintenance
in the
IPE because all planned
maintenance
is performed
during outages.
Based
on the review of actual
system unavailability, the team
determined that the assumptions
made
by the licensee for the
IPE are valid.
6.5
Heat Exchanger
Performance
Test Review
WNP-2 committed to heat exchanger
performance testing in its response
to
WNP-2 also committed to inspect,
clean,
and eddy-current test the
service water side of the heat exchangers
on
a 5-year interval
as preventive
maintenance.
The licensee
also indicated they would perform annual
preventive
maintenance
inspections
on the air side of all air-to-water cooling coils in
the
SSW system.
The licensee
has developed
procedures
for data collection.
The results
are
trended to indicate
changes
in heat exchanger
performance.
The heat exchanger
performance testing includes
measurement
of cooling water flow and inlet and
outlet temperatures.
Flow measurements
are taken at the local flow meter for
each load
and
by ultrasonic test equipment.
Temperature
measurements
are
made
using six thermocouples
installed
around the outside of the pipe.
The
differential pressure
across
each
heat
exchanger is trended to detect tube
fouling.
Differential pressure
testing is performed
on the fan coolers
and
on
the
RHR pump seal
coolers.
Fan differential pressures
are trended
as
an
indicator of air flow.
WNP-2 is planning to install permanent
instrumentation.
(RTD thermowell
and permanent
flow element)
in the diesel
generator jacket
water cooler line in an upcoming outage.
WNP-2 began collecting data
on
heat exchanger
performance
in 1988.
In 1992,
a decreasing
trend
was noted in
the overall heat transfer coefficient for the
RHR heat exchanger.
The
licensee
concluded that the heat exchanger fouling had not reduced
the heat
removal capability of the heat
exchanger to an unacceptable
level.
However,
all
SSW heat exchangers
were cleaned
during the
1992 refueling outage.
After
cleaning,
baseline
heat exchanger
performance
data
was collected
and trended
during 1992.
Performance tests
conducted
under procedures
8.4.42, 8.4.54, 8.4.62,
and
8.4.63
measure
the overall heat transfer coefficient of the
RHR and
DCW heat
exchangers.
The licensee
evaluated
the acceptability of heat exchanger
performance
based
on
an assumption
that any degradation
in performance
from
design conditions calculated
from test results
was due to fouling of the heat
exchanger.
The licensee
explained that much of the observed
reduction in the
overall heat transfer coefficient indicated
by the test data resulted
from
decreased
shell side flow when low temperature
SSW is provided to the compo-
nent.
The licensee
has not identified
a correlation to determine the expected
shell
side film coefficient under reduced flow conditions,
such
as experienced
during heat
exchanger
performance testing.
Such
a correlation would permit
a
determination of the deviation from expected
performance
at reduced flow
conditions.
The present
method of evaluating
heat exchanger
performance test
16
Ci~-
I
data is conservative
in predicting the ability of the heat
exchanger to
perform its design function, but does not provide
an indication of the degree
of heat
exchanger fouling.
Test data is being collected
under various flow conditions,
and that by
comparing the results of tests
performed
under similar flow and temperature
conditions, it may be possible to determine
the degree of fouling which
occurred in the period
between tests.
This approach is acceptable
due to the
absence
of other more direct methods of determining the degree of heat
exchanger fouling.
The team determined that the licensee's
heat exchanger
performance testing and-
preventive maintenance
programs
meet the commitments
made in the Generic
Letter response.
The program is adequate
to determine
acceptable
performance
of the
SWS and trending of system performance will result in a more accurate
estimate of heat exchanger fouling.
7.0
BIOFOULING CONTROL AND TESTING
4RC Generic Letter 89-13, Action I, requested
that licensees
implement
and
maintain
an ongoing program of surveillance
and control techniques
to signifi=
cantly reduce the incidence of flow blockage
problems
as
a result of biofoul-
ing.
The actions
requested
included intake structure
inspections,
chemical
treatment of service water systems,
and periodic service water system flush-
ing/flow testing.
Prior to the issuance
of the generic letter, the
SWS spray
pond contained
significant concentrations
of algae
and water insects.
The choice of treat-
ment chemicals for use in the
SSW system
was limited by two factors.
First,
the
RHR heat exchangers
contain stainless
steel
components
which are subject
to intergranular stress
corrosion cracking
(IGSCC)
when the metal
comes in
contact with halogen
based
treatment
chemicals.
Second,
the water inventory
of the
SSW system
remains relatively static.
Continually treating the system
with a chemical that does not breakdown
may result in pond water of increasing
toxicity as well as anion concentrations
high enough to induce
Buckman Laboratories
proposed
a program using Bulab 6003, that could meet the
above
two constraints
and eliminate fouling caused
by microorganisms,
elimi-
nate microbiologically induced corrosion potential, eliminate potential
fouling caused
by clams
and improve the
SSW system reliabili'ty.
Bulab 6003 is
a 35K-active solution of two different active ingredients.
It does not
contain
PCBs or priority pollutants which would violate the
WNP-2 National
Pollutant Discharge Elimination System
(NPDES) permit and it has the capabil-
ity of breaking
down quickly without building up toxins in the system.
The licensee
requested
and received the Energy Facility Site Evaluation
Council
(EFSEC)
approval of Bulab 6003 for a one year period.
EFSEC is the
Washington state
agency that oversees
environmental
regulation.
The licensee
needed
approval for the
SSW spray
ponds since the treated water would
subsequently
be released
to the Columbia river.
The Council set
a condition
that discharge
into the plant blowdown line can not occur before
30 days
have
elapsed after application
and chemical
analyses
shows
no detectable
active
ingredients.
17
In September
1991, the licensee
commenced
treatment of the
SSW spray
ponds
with Bulab 6003, at
a concentration of 15-30
ppm on
a monthly basis.
The
Bulab was fed from a tank adjacent to "B" Pumphouse
via flexible tubing and
discharged
immediately
above the
pump suction.
Plate counting
and the
turbidity of the bulk water were measured
from samples to monitor the effect
of the treatment relative to these
parameters.
Algae was
a predominant
problem prior to the Bulab addition.
After the Bulab addition, the algae
content
was noticeably diminished.
However, the aerobic bacteria
counts
showed
a sharp
increase
due to the dead algae.
This disturbance
in the
ecological
balance of the spray
ponds
had not been foreseen
by the licensee.
During plant shutdown
on April 19,
1992,
degraded
heat transfer performance
was observed for the
RHR "A" heat exchanger while in the shutdown cooling
mode.
The heat exchanger
was found to be coated with a layer of silt trapped
within a slime matrix.
The slime was believed to have originated
from a slime
forming bacteria within the
SSW spray
pond water.
The licensee
determined
the
root cause of the event
was insufficient monitoring of the
SSW system in
predicting fouling magnitude
and rates.
The inside surfaces of all of the
tubes in the
RHR "A" heat exchanger
were mechanically cleaned of the biologi-
cal fouling.
Due to the biofouling problems which existed in the
summer of 1992,
an
extensive
amount of Bulab 6003,
which contains sulfur,
was
added to the spray
ponds.
Consequently,
the sulfur concentration
went above the licensee's
control limit of 150
ppm in the
SSW system which was set to prevent
IGSCC on
the
RHR heat
exchanger tubing.
The licensee
did not issue
a Problem Evalua-
tion Request
(PER) to evaluate
exceeding
the sulfur limit.
This is identified.
as Deficiency 93-201-01 in Appendix A.
After the growth in the
summer of 1992, the licensee
developed
techniques
to
more effectively monitor biological growth in the spray ponds.
The biocide
additions
were based
on pond visual indications.
For example,
a brilliant
Kelly green
was indicative of a thriving, growing algae population.
A drab
olive or beige tinted green
was indicative of a biostatically suppressed
pond.
Two slime box units are
now operating in a side stream flow to monitor algae
(transparent
box)
and bacterial
(dark box) growth.
The growths observed
in
these
boxes closely parallel the pond growth and are useful
when
SSW pumps
are
not available to keep the pond agitated.
Also, the slime boxes
are easily
interpreted
backups to the subjective
methods of reading
pond health
by visual
observation of color and clarity.
The licensee
purchased
a Deposit Accumula-
tion Testing System
(DATS) biofouling monitor and is planning to install it in
the near future in the
SSW "A" pump house.
This unit will measure
changes
in
heat flux across
a stainless
steel
heat exchanger
tube
and changes
in flow
through the tube
as the tube
becomes
fouled with biological growth.
The tube
is easily removed for periodic inspection,
cleaning or replacement,
thus
allowing close correlation
between
changes
in operating
parameters
and
physical evaluation of the rate
and magnitude of biological growth.
The licensee
indicated they had inspected
the spray
ponds
once per refueling
outage,
and
no fouling accumulation
had
been
found in the safety-related
18
system.
However, this inspection
had not been proceduralized
(Observation
93-
201-04).
The licensee
agreed to implement
an
SMS card which is
a tracking
system to verify that the inspections
are completed.
The licensee
believes that Bulab 6003 has
been successful
in controlling algae
to reduce the incidence of flow blockage
problems
as
a result of biofouling,
although they are still in a trial period.
The team found there is
a need to
better proceduralize
the biofouling program
as is evidenced
by several
of the
teams
concerns
as well as
by WNP's
own gA audit of this program.
(See section
11.0 of the report).
The licensee
agreed to implement
a document to clearly
outline the program,
which will include the necessary
steps for each of the
departments
involved for the monitoring of biofouling at WNP-2.
8.0
MAINTENANCE
Action III of Generic Letter 89-13
recommended
that
a routine inspection
and
maintenance
program
be established
to ensure that corrosion,
erosion,
protec-
tive coating failure, silting and biofouling cannot
degrade
the performance of
the safety related
systems
supplied
by the service water system.
Action V
.further recommended
that maintenance
practices
be adequate
to reduce
human
errors in the repair
and maintenance
of the service water system.
In their February
5,
1990 response
to
GL 89-13, the licensee
committed to
perform
a) regularly scheduled
inspection,
cleaning,
and eddy current testing of
all service water heat exchangers
with accessible
tubing,
b) annual
inspection of the air side of air-to-water cooling coils,
and
c) monitoring of corrosion
coupons.
The licensee identified that in-service inspection
under
ASME Section XI and
periodic flow balancing for technical specification surveillance of the
service water system would also detect
system degradation
due to fouling.
The
licensee's
response
stated that the technical
accuracy
and completeness
of all
maintenance
procedures
was assured
through routine biennial
procedure
reviews.
The team reviewed maintenance
procedures
and completed
maintenance activities
performed during the past year
and found them adequate.
The results of eddy
current inspections of the residual
heat
removal
heat
exchan'gers
were reviewed
and found to be adequate.
8.1
Erosion Monitoring
The service water system
was not routinely monitored for pipe wall thinning
due to the low pressure
and temperature
operating conditions for the system.
The licensee
had observed cavitation erosion of a piping elbow downstream of
the service water
pump discharge
valve SW-V-2B.
The discharge
valve throttles
flow initially during system startup.
The degradation
had
been
obser'ved
visually during replacement
of the discharge
valve when the piping system
was
open.
The elbow was weld repaired to restore
the pipe wall thickness
in the
affected areas.
Following repair,
the area
was ultrasonically tested
(UT) to
19
establish
baseline
data for trending of future wall thinning.
No further
erosion
had
been detected
in subsequent
UT monitoring.
The licensee's
actions
were appropriate.
9. 0
OPERATIONS
9. 1
Operations
procedures
The team reviewed operations
procedures for normal,
abnormal,
and emergency
conditions,
procedures
for operating logs,
and examined
completed log records.
The
SSW procedures
are in the plant procedures
manual
(PPM).
Volume
1
contains administrative
procedures
including the operating
data
and logs
procedure;
volume
2 contains
normal operating
procedures
such
as procedures
to
make the
SSW system available;
volume
3 contains general
operating
procedures
such
as startup
and shutdown procedures;
volume
4 contains
response
procedures
and abnormal
operations
procedures
such
as the loss of
SSW;
and volume
5 contains
the emergency
response
procedures.
Volume 7
contains surveillance
procedures
including shift and daily instrument checks.
.The licensee's
procedures
generally described
system operation
adequately,
except
as described
below:
None of the licensee's
operating
procedures
provided guidance to the operators
on pond icing (Observation
93-201-05).
During January
1993, the spray
ponds
iced over heavily.
Approximately SOX of the pond surfaces
were frozen with
thicknesses
estimated to be
up to
5 inches thick.
The inspectors
requested
the licensee
to consider the need for clear operator guidance
on what degree
of icing was acceptable,
and what actions
should
be taken if that icing limit
was approached.
As a result of the team's
questions,
the licensee
issued
Problem Evaluation
Request
(PER)
293-140
on February
5,
1993.
The licensee
concluded that pond
icing up to 5 inches in thickness
was acceptable
based
on the successful
operation of the system
on January ll, 1993 when the pond had
a solid covering
of ice up to 5 inches.
The return flow broke through the ice within 20
seconds.
The licensee corrective actions described
in the
PER include
revising the plant procedures
to provide operator guidance for icing and to
evaluate the effects of ice on operability, including the effect of the ice on
the seismic qualification of the steel
support structures for the spray nozzle
rings.
The evaluations
are scheduled
to be completed
by November
1,
1993,
preceding
the next expected
cold weather period.
The licensee
issued
a procedure
change,
Procedure
Deviation Form
(PDF)93-167
to
PPM 2.4.5,
on February
10,
1993 for the
operating procedure,
instruct-
ing the operator to monitor ice build up and contact the system engineer if
the pond freezes
over.
9.2
Valve line-up program
The team examined
the licensee's
valve lineup program including independent
verification, the locked valve program,
and the throttled valve program.
The
examination consisted of a review of the licensee's
valve line up procedures;
20
4'i
f*
~ f
I f
1
a review of records;
discussions
with operations
managers,
licensed
operators
and non-licensed
operators;
and
a walk down of portions of the system with an
operator verifying valve positions.
The licensee's
programs
were generally
sound
and met technical specification requirements.
The team observed
two areas
which were of concern.
There were insufficient instructions for setting the throttle valves for the
control
room ventilation cooling coils.
For a January
7,
1993
SSW valve line-
up specified
by
PPH 7.4.7. 1. l. 1,
"Standby Service Mater Loop A Valve Position
Verification", Section 7.2 of the procedure
requires
the flow to the control
room ventilation cooling coils be set to 120-125
gpm.
However, this flow is
established
by setting
two parallel throttle valves,
SW-V-104D and SW-V-106D,
which throttle flow to two parallel cooling coils.
The flow is read
by a
single flow meter,
SW-FI-35A, which is in a common return line from two branch
lines from the two throttle valves.
A similar condition exists for the
Loop
B
procedure
and valves.
The procedures
did not describe
how the flow split
should
be established.
Discussions
with operations
managers
and shift
personnel
showed that several different opinions existed
as to how the two
.valves should
be positioned to provide equal flow to the two coils.
The team
concluded the instructions
were insufficient.
The licensee
subsequently
issued
procedure
changes,
Procedure
Deviation Forms93-175
and 93-176,
on February 8,
1993, to revise the instructions to open
both valves
an equal
number of turns.
Additionally, the licensee
issued
an
interoffice memorandum
dated
February
11,
1993, to the Plant Technical
Services
Nanager which evaluated
the as-found condition of the control
room
cooling coils.
The estimated
flow imbalance
involved 80 gpm in one coil and
40 gpm in the other coil.
The licensee's
analysis
found the effects of this
imbalance
on control
room cooling to be small
and well within design limits.
The effect of the imbalance resulted in a 0.3'F increase
in the temperature
of
the air leaving the coils.
The team noted errors
made in the valve line up completed
on June
17, 1992 for
the
SSW system.
The errors all involved valves
SW-V-168B and
SW-V-169B which
are small vent valves
on the
B pond side of the large
A pond to
B pond siphon
line.
The errors consisted of:
The valve positioner initialed the valve line up sheet verifying that
the valves were shut.
However,
the valves were inaccessible
under water
at the time of the valve line up.
The valve position verifier annotated
the valve line up sheet with a
note that stated
"Valves removed
and line is capped".
The valves were,
in fact, not removed at the time of the valve lineup.
The shift manager
accepted
the valve line up and,
on June
17,
1992,
signed the system line up deviation sheet
which stated
"Valve removed,
line capped,
need
H524/1 print correction".
The shift manager did not
initiate
a drawing change
request for the
assumed error indicated
by his
21
note nor did he initiate a procedure revision request for the checklist
discrepancies
as required
by the plant startup
procedure
PPH 3. 1. 1
"Haster Startup Checklist".
The failure to perform the valve lineup verification of valves
SW-V-168B and
SW-V-169B is identified as Deficiency 93-201-02 in Appendix A to the report.
The team did not consider this
an immediate operability concern
as the
licensee
was able to provide evidence that the valves were closed
as required.
(See Deficiency 93-201-02 for details).
PPH 2.4.5,
"Standby Service Water System",
Attachment 6. 1 provided the normal
valve line up for the system
and required valves
SW-V-171A and SW-V-171B,the
spray header drain valves to be open.
The cold weather procedure,
Section 5.6
of PPH 2.4.5,
ends with the valves in a closed position.
This potential
confusion
was identified to the licensee.
The licensee
subsequently
issued
a procedure
change,
Procedure
Deviation
Form
93-167,
dated
February 8,
1993,
which changed
the normal position of the drain
valves to closed in normal weather
and open in cold weather.
The team
.identified the change to require additional operator actions not required
by
the original procedure.
Previously the header
was maintained
in a drained
condition in normal weather.
With the change,
the header will be maintained
full.
The full header will require operators
to be more alert to cold weather
conditions,
and to drain the header
when the temperature
drops.
The previous
normally drained condition was, therefore,
less susceptible
to operator error.
In addition, the full header
may introduce
new corrosion or nozzle plugging
problems.
The licensee
stated
they were considering
a change to remove the
valves or provide
a drainage
hole in the spray header.
9.3
Conduct of Operations
The team walked through selected
portions of procedures,
observed
a
SSW system
start,
and examined
pond level control
and makeup.
The team found that the
conduct of operations
was generally
sound.
The walk through
was conducted with an equipment operator,
a non-licensed
position.
The equipment operator
performs rounds,
performs valve
and breaker
lineups,
and operates
equipment.
The inspector
examined portions of PPH
7.4.7. 1. 1. 1,
"Standby Service
Water Loop A Valve Position Verification", and
PPH 2.4.5,
"Standby Service Mater System",
Section 5.2,
"Haimtaining Spray
Pond Level."
The equipment operator
demonstrated
familiarity with the
component locations,
was able to go directly to the applicable
components
selected
by the inspector
and was familiar with the procedures
and drawings
involved.
The team observed
a
SSW system start.
The control
room staff conducted
the
start at the request of the team to demonstrate
that the problem of system
water
hammer
had
been eliminated.
The team members
were stationed
at several
locations for the test.
The locations included the control
room, the higher
elevations of the reactor building near the residual
heat
removal
heat
exchangers,
and in the
pump house.
The operators
started
the system in
accordance
with their procedures.
Command,
control
and communications
22
I
'lg,j~ ~
,$4
appeared
to be good.
The system start resulted in a large
number of distract-
ing alarms.
The alarms
were expected
by the operators
and were considered
nuisance
alarms.
Operators
properly assessed
each
alarm both
on the front and
back panels
and acknowledged
them.
The results of the test were that water
hammer
was not observed.
The operators
properly secured
the system in
accordance their procedures.
Discussions
with several
operators
and equipment
operators
indicated that water
hammer
had not been
a problem for several
years
since the valve opening
sequence
had
been modified.
The team examined the cause
and status of the system startup nuisance
alarms;
The alarms
were due to the long time required for the
SSW system to achieve
operating pressure
due to the valve opening
sequence
and the large size of the
system.
The alarms
show up at components
served
by the
SSW system,
such
as
the diesel generators.
The alarms are, for instance,
"Loss of SSW flow".
The
problem of the nuisance
alarms
had
been identified by the licensee
in 1989 in
PER 289-0785.
The licensee
had prepared
a plant modification to install time
delays in the alarm circuits to eliminate the nuisance
alarms.
The modifica-
tion was
on the licensee's
schedule for accomplishment
in fiscal year
1994.
The team
had
no further questions
regarding the alarms.
The pond level control procedures
and methods
were discussed
with plant
personnel.
The makeup
system to the ponds is tapped off the Tower Hake
Up
(THU) system
which is the makeup
system for the non-safety circulating water
system for the main condensers.
This feature provides certain operating
strengths
in that the
THU is run constantly
and is not
a standby
system.
Therefore,
problems
such
as intake blockage would be noted
as they occurred
and would not be
a dormant problem revealed
only on system
demand.
9.4
Operator training
The team examined the licensee's
training program
as it applied to the
system.
The training for licensed
and non-licensed
operators
was examined
through discussion with a licensee training specialist,
review of training
manuals,
lesson
plans,
and training schedules.
The inspector also examined
the licensee's
training for plant modifications.
The team generally found the
training program adequately
addressed
the
SSW system.
Documentation
examined
included:
I
the
SSW chapter of the general training manual,
82-RSY-1404-T3,
October
1989
the "License Training System Descriptions,"
82-RSY-1405-T3,
January
1992
the lesson
guide for licensed operator
and Shift Technical Advisor (STA)
training, 82-RSY-1404-L3,
February
27
1992
the lesson
plan for non-licensed
operators,
82-EOS-0402-LP,
July 28,
1992
other lesson
plans applicable to equipment operators
from earlier years
23
I)
\\
II
In general,
the licensee's
program for SSW training met regulatory require-
ments.
The licensee
had regular simulator training,
about six times per year
per crew,
and regular post-outage
training on modifications, including service
water modifications.
10.0
SYSTEH WALK-DOWN
The team conducted
an in-depth walkdown of large portions of the
SSW system
and the spray ponds.
The walkdown was conducted with non-licensed
operators,
with a shift support supervisor,
and by unaccompanied
NRC inspectors.
The
inspectors
observed
valve positions, electrical
breaker positions,
the
presence
of locks
on locked valves,
the presence
of lead seals
on sealed
throttle valves, material condition of the system
and machinery spaces,
heat
trace operation,
valve labeling, flow rates to components,
control
room switch
positions,
alarms
and annunciators,
and
system
components
in operation.
The
inspectors
made the following observations:
A room cooler was located in the overhead
and
was difficult (required
a
ladder
and climbing) to access.
Nonetheless,
the cooling coils were
clean.
~
Temporary thermocouples
were installed at several
heat exchanger
locations to improve the performance
assessment
capability of the heat
exchangers.
~
Each of the many large
and small
SSW heat exchangers
was provided with a
flow indication device,
a valuable
system feature
from an operations
standpoint.
The majority of piping runs in the reactor building were unpainted
and
had experienced light corrosion.
The corrosion at flange fasteners
was
more severe
but had not yet produced significant stud wastage.
Without
attention,
the condition could eventually
become significant (Observa-
tion 93-201-06).
On the other hand the piping in the diesel
generator
rooms
had
been painted
and appeared
to be in much better condition.
During
SSW system operation,
the spray
pond return flow header valve
SW-
V-165B was properly shut with the spray nozzles
in operation,
but was
leaking at about 50-100
gpm.
This is
a large butterfly valve that is
used to bypass
the spray nozzles in cold weather.
Excess
bypass flow,
in warm weather could be
a problem.
The inspector inquired whether
a
maintenance
work request
(HWR) had
been submitted.
The licensee
determined that
an
HWR had not been submitted,
and consequently
generat-
ed HWR-AP-2337 describing the leak.
The leakage
was assessed
by
engineering
as described
in an interoffice memorandum
dated
February
11,
1993, to the manager of plant technical
services.
The assessment
concluded
the leakage
was not significant from an operability standpoint
I
yJ
and would result in an increase of maximum pond temperature of only
0.2'F.
The team considered this action to be adequate.
The team's
examination of the
HWR database
showed that the plant staff had not been
reluctant to write HWR's on the valve in the past.
~
Scaffolding was installed in both
RHR heat exchanger
rooms
on an
apparently
permanent
basis
(Observation
93-201-07).
Scaffolding is
ordinarily a temporary installation for a short duration job.
Per
discussion with the operator,
the scaffolding had
been installed since
startup
and
was used in a monthly surveillance
procedure.
The proce-
dure,
PPH 7.4.5. 1. 1,
"LPCS,
HPCS,
and
LPCI Fill Verification," requires
monthly venting from the top of the
RHR heat exchangers
to verify that
the system is full.
The scaffolding is necessary
to reach the high
point vent valves.
The team noted that the need for continuing operator
access
usually is met by providing permanent
ladders
and platforms
through
a design
change.
~
The spray
pond return header piping in spray
pond
B was heavily corroded
at the location where it exits the
B pumphouse
and transits
the spray
pond.
The piping at this location is horizontal
and is partially
submerged
in the pond water.
The heavy corrosion occurred at the
waterline which is subjected
to wetting and drying cycles.
The corro-
sion scale
was visually estimated
to be I/O inch.
The team
was con-
cerned that minimum wall thickness
might be affected
and discussed
the
observation with plant management.
The licensee
wrote
PER 293-150 to
address
the concern.
The
PER resolution stated that the corrosion
was
acceptable
based
on the observations
of the engineer in the opposite
pond when it was drained in 1992.
The observations
of heavy scale
on
structural
members at the waterline
showed very little thickness
reduction
when cleaned.
In addition, the
PER stated that the piping
design
allowed for a generous
corrosion allowance.
The
PER also stated
that the piping would be inspected
when the pond was drained during the
upcoming outage
in the spring of 1993.
The team considered
the
PER
evaluation to be adequate.
The
18 inch diameter
handwheel for Limitorque actuator
SW-MO-70B
appeared
to be oversized.
Since this valve could only be manually
operated,
the team
was concerned that excessive
torque could be applied
with the larger
handwheel
which could damage
the actuator.
Vendor
information from the actuator manufacturer
(Limitorque') specifically
prohibits the use of cheaters
to increase
handwheel
The
licensee initiated
PER 293-145 which determined that the oversized
handwheel
was acceptable
and
had apparently existed since construction.
The licensee initiated
a drawing change to identify the as-built
configuration.
The team found the licensee
actions
adequate.
11.0
CORRECTIVE ACTIONS
In their February
5,
1990 response
to Action III of GL 89-13, the licensee
identified that corrective actions
would be taken for indications of fouling
25
't
k)
t5
in the heat exchangers
of the service water system.
Routine corrective
maintenance
would be accomplished
through the use of maintenance
work requests
(MWRs).
The inspector
reviewed the licensee's
corrective actions for
deficiencies
identified in MWRs for the service water system for the past
two years,
and
the findings from the licensee's
Safety
Systems
Functional
Inspection
(SSFI)
of the service water system conducted
in December,
1990.
Recent audits
conducted
by the guality Assurance
department
and minutes of the onsite
and
offsite safety review groups
were also reviewed.
The purpose of this review
was to assess
the timeliness
and technical
adequacy of the licensee's
resolu-
tion of the deficiencies.
The licensee
s self-assessments
were corn'prehensive.
Substantive
findings were identified during their SSFI
and
gA audits.
Identified deficiencies
were generally adequately
resolved except for three
specific instances
of inadequate
corrective action which were noted
by the
inspection
team.
The licensee
had not resolved deficiencies previously identified in the
cathodic protection for the service water system.
The operational
status of
.the active cathodic protection
system
had
been identified as indeterminate
during the SSFI.
In the licensee's
disposition of the SSFI finding, the
existing system
was considered
unnecessary,
and
no corrective action was taken
pending engineering
evaluation.
During the
NRC inspection,
as
a result of the
team's questioning,
the licensee
determined that the installed cathodic
protection
system
was necessary
for the protection of buried piping from
corrosive attack.
The licensee initiated Problem Evaluation Request
PER-293-
152 to establish
corrective actions to restore
and maintain the system's
functional capability.
The non-conservative initial disposition
and untimely
engineering
evaluation of the SSFI finding was considered
a deficiency
and is
identified as Deficiency Number 93-201-03 in Appendix A to the report.
gA Audit 91-555,
dated
October
24,
1991,
was
an annual
audit of the licensee's
environmental
and effluent monitoring
performed
by the licensee's
Corporate
Licensing
and Assurance
group.
The audit identified that procedures
had not
been established
for the biofouling monitoring program.
The licensee
had
initiated
a guality Finding Report to address
the lack of procedures
for the
program.
At the time of the
NRC inspection,
procedures still had not been
established
for the licensee's
biofouling program.
The inspector
found the
lack of formal documentation
to be
a weakness
(Observation
93-201-08).
The licensee
had also not adequately
resolved
an apparent
common
mode defi-
ciency identified in the operation of motor operated
valves
(MOVs) in both
trains of the service water system.
The licensee
had identified that the loop
isolation valves
SW-V-12A/B repeatedly
hammered
when closing.
The control
logic for these
valves includes
a continuous
close
demand signal
which is
present
even after the valve has closed.
Due to apparent
relaxation of the
spring pack in the Limitorque actuator after closing, the torque switch (which
normally opens to stop motor operation at valve closure)
can again close.
Because of the ever-present
close
demand signal,
the actuator restarts
26
unexpectedly
and attempts to further close the already closed valve.
This
results in a short stroke
hammering of the valve disk into the seat.
The
licensee
had not determined
the cause of the repeated
relaxation of the spring
pack.
The licensee's
lack of corrective actions to preclude recurrence
of hammering
of SW-V-12A/B is identified as Deficiency Number 93-201-04 in Appendix A to
the report.
27
~
A
C
t
APPENDIX A
SUMMARY OF
INSPECTION FINDINGS
DEFICIENCY NUMBER 93-201-01
FINDING TITLE:
Inadequate
Evaluation of Spray
Pond Chemistry
(Section 7.0)
ESCRIPTION
OF CONDITION:
The
150
ppm sulfur limit in
PPM 1. 13. 1 was established
by Inter-Office Memo
SS2-PE-92-524
from materials
and welding dated
June
23,
1992 in order to
minimize the potential of stress
corrosion cracking in the stainless
steel
tubing of RHR heat exchangers
in the
SSW system.
The limit of 150
ppm of
sulfur was set at
a conservative
level
based
upon various research efforts.
Bulab 6003,
which is used to control the biofouling in the
SSW system,
contains sulfur.
Due to the biofouling problems
experienced this past
summer,
an extensive
amount of Bulab 6003
was
added to the spray ponds.
Water samples
were taken from the spray
ponds
by the Plant Support Chemistry Laboratory
after the addition of Bulab 6003 starting in September
1991.
The team found
that the sulfur concentration
in the Standby Service
Water
(SSW)
system
had
been at or above the
150
ppm control limit of sulfur since
September
1992
and
had reached
levels
as high as
183
ppm.
Although the sulfur limit was exceed-
ed, the licensee
could not discharge
into the plant blowdown line before
30
days elapsed
from the last Bulab application
due to the Energy Facility Site
Evaluation Council regulation.
The licensee failed to issue
a
PER when the
sulfur limit was exceeded
and only did so when this matter
was highlighted by
the team.
The
PER stated that even though the sulfur excursion
exceeds
the
current limit, there should
be
no detrimental effects to the heat exchanger
tubing based
upon
a review of the technical
basis for the limits.
C
DEFICIENCY NUMBER 93-201-02
~FEPIE
TITLE:
FIT
t
p
I
I
lt
pf
I
Ittp
dure (Section 9.2)
ESCRI PTION 0
CONDITION:
The following errors
made in the valve line up completed
on June
17, 1992 for
the
SSW system involved valves
SW-V-168B and SW-V-169B, which are small vent
valves
on the
B pond side of the large
A pond to
B pond siphon line.
~
The valve positioner initialed the valve line up sheet verifying that
the valves were shut.
However, the valves were inaccessible
under water
at the time of the valve line up.
The valve position verifier annotated
the valve line up sheet with a
note that stated
"Valves removed
and line is capped".
He did not
initial the sheet.
The valves were, in fact, not removed at the time of
the valve line up.
The shift manager
accepted
the valve line up and,
on June
17,
1992,
signed the system line up deviation sheet
which stated
"Valve removed,
line capped,
need
M524/1 print correction"
M524/1 is the piping and
instrumentation
diagram for the
SSW system.
The shift manager did not
initiate a drawing change
request for the
assumed
error indicate4
by his
note nor did he initiate
a procedure revision request for the checklist
discrepancies
as required
by the plant startup
procedure
PPM 3. 1.1
"Master Startup Checklist".
During the system walk down the team noted that the two vent valves were under
water and were very heavily rusted to the point of being probably inoperable.
The errors identified above represented
the last valve line up record.
The
team could not obtain
any valve line up verification that the valves were
properly positioned.
Licensee
management
indicated that the valves
had last
been positioned during startup,
around
1983, but that valve lineup records
were not kept for more than three years.
The team asked the licensee
to
verify that the safety function of the siphon line was not impaired.
The position of the vent valves is important in an accident
scenario
assuming
SSW design basis criteria.
The vent valves are
used to vent the air out of
the pond cross
connect
siphon line during pond filling. After pond filling,
the vent valve should
be shut to keep air out of the siphon line should
pond
level drop below the siphon line horizontal run.
The siphon line will not
work if it becomes air bound.
The accident
scenario
assumes
no makeup water
is available to the
pond for 30 days.
The inventory of both ponds is suffi-
cient to meet this criteria;
however,
the siphon must work to transfer
inventory from one
pond to the other.
Problem Evaluation
Request
(PER)
293-129
was written on February 4,
1993 to
address
the inspectors
concerns.
The licensee
concluded that the siphon line
was operable
based
on observations
made in the
summer of 1992 when the
A pond
was drained
and cleaned.
During that time, the siphon line was plugged
on the
A-2
~
A
l
r
water filled 8 pond side.
The
A pond was dry.
The system engineer stated
that
he observed that
no water was flowing from the siphon line on the
A pond
side.
If the vent line (underwater
on the
8 pond side)
was open, water would
be expected
to continuously flow into the dry A pond side.
The team consid-
ered this evaluation for siphon line operability to be adequate.
A-3
~
4
'V
DEFICIENCY NUMBER 93-201-03
KIIICICCTITLT:
I dd
PIT -dd
Ctddt
P t tt
ddt
C
(Section
11.0)
DESCRIPTION
OF CONDITION:
The operational
status of the active cathodic protection
system
had
been
identified as indeterminate
during the SSFI.
In the licensee's
disposition of
the SSFI finding, the existing system
was considered
unnecessary,
and
no
corrective action
was taken
pending engineering
evaluation.
During the
NRC
inspection,
the licensee
determined that the installed cathodic protection
system
was necessary
for the protection of buried piping from corrosive
attack.
The licensee initiated Problem Evaluation
Request
PER-293-152 to
establish
corrective actions to restore
and maintain the system's
functional
capability.
The inspector
found the licensee's
corrective actions to be technically
adequate.
The non-conservative initial disposition
and untimely engineering
>valuation of the
SSFI finding was considered
a deficiency.
k
C
~ 0
J
V
v
j
0
DEFICIENCY NUMBER 93-201-04
~IMOIN
T iLE:
F ii
t
t
h
i
9 f
1
EII-V-12A/B
(Section
11.0)
ESCRIPTION
OF CONDIT 0:
The inspector
found that the licensee
had not adequately
resolved
an apparent
common
mode deficiency identified in the operation of motor operated
valves
(MOVs) in both trains of the service water system.
In May of 1991, the
licensee
had identified in PER 291-359 that the loop isolation valves
SW-V-
12A/8 repeatedly
hammered
when closing.
The control logic for thes'e
valves
includes
a continuous
close
demand signal
which is present
even after the
valve has closed.
Due to apparent relaxation of the spring pack in the
Limitorque actuator after closing, the torque switch (which normally opens to
stop motor operation at valve closure)
can again close.
Because of the ever-
present
close
demand signal,
the actuator restarts
unexpectedly
and attempts
to further close the already closed valve.
This results in a short stroke
hammering of the valve disk into the seat.
The licensee
had not determined
-the cause of the repeated
relaxation of the spring pack.
However, the
licensee
considered
the hammering to be acceptable if not occurring more than-
six times per hour.
The licensee
based this limit on the duty cycle of the
motor.
The licensee's
disposition stated that no valve damage
would result
from continued
hammering
because
the torque switch limited the closing forces.
The inspector
found that the licensee
had not adequately
evaluated
the
potential overthrust condition resulting from the repeated
hammering.
Instances
of excessive
operational
loads
and valve damage
had
been identified
as the result of hammering in NRC Information Notice 85-20.
Vendor informa-
tion from the actuator manufacturer
(Limitorque) had also identified the
deficiency
and corrective actions.
In response
to the inspector's
concern,
the licensee initiated
a Problem Evaluation
Request to evaluate
the potential
damage to the valve.
During the inspection,
the licensee
reviewed data from
tests
conducted
in April, 1991,
which displayed
up to seven
hammering events.
The licensee
determined that
a
IOX increase
in closing thrust could be
attributed to the hammering.
The licensee
concluded the effects of hammering
could
be tolerated within the capability of the valve and actuator.
In
addition, at the request of the inspector,
the licensee
monitored motor
current for SW-V-12A/B to determine if hammering
were continuing undetected
after operation of the valve.
No hammering of either valve SW-V-12A/B was
observed
during the hour following closure.
Despite the fact that the valves did not exhibit hammering
when monitored,
the
inspector
was concerned that the potential for hammering
had not been elimi-
nated
and that the effects of continued
hammering
were not well known.
The
inspector noted that the
1991 diagnostic signature for the valves
showed that
the spring pack continued to relax after the valve stopped
hammering,
indicat-
ing
a potential
for spurious
hammering to occur.
In response
to the inspect-
or's concerns,
the licensee
indicated that both valves
SW-V-12A/B would be
disassembled
and inspected
during the next outage to determine the root cause
of the problem.
A-5
'\\
WO f
,J
The inspector
reviewed licensee
procedure
10.25. 132, Revision 3, "Thrust
Adjustment
and Diagnostic Analysis of Hotor Operated
Valves."
Paragraph
4.22
identified that hammering
may damage
the valve.
It further stated,
in part,
"Ensure that switches
and relays
are operated
and control logic has sufficient
contacts to open the circuit to prevent valve hammer... Inform Engineering if a
valve hammers."
In addition, the inspector
reviewed licensee
procedure
10.25.74,
Revision 8, "Testing Hotor Operated
Valve Hoto} s and Controls."
Paragraph
4.5 identified that hammering would eventually overthrust
and
damage
the valve.
It further stated,
in part,
"Contact the System Engineer to
address this condition if it exists."
Despite these
procedural
warnings,
the
licensee
had not taken corrective actions to preclude
recurrence of hammering
of SW-V-12A/B.
The inspector reviewed the design basis calculation NE-02-90-17 for the sizing
of the actuator
and found that the actuator did not appear to have adequate
capability under worst case
design basis conditions to perform its safety
function to open.
Under degraded
voltage conditions
and worst case
stem
lubrication conditions,
the rated pullout capability of the actuator
was
calculated to be 27232 lbs.
The force to unseat
valves
SW-V-12 A/B had
been
measured
under static test conditions to be 28701
and 31370 lbs.
The licensee
identified that the
maximum actuator torque
had not been
exceeded
during
pullout at the higher unseating
loads
because
of good stem lubrication.
The
licensee
concluded that the sizing of the actuator
was adequate
to assure
capability under design basis conditions
assuming
good stem lubrication.
However, since the pullout force also increases
due to hammering,
the inspec-
tor was concerned that the actuators
may not be able to unseat
the valve disk
to open the valve.
A-6
APPENDIX 8
LIST OF OBSERVATIONS
Observation
Number
93-201-01
93-201-02
93-201-03
93-201-04
93-201-05
e ort Para ra
h
3.3
3.5
6.1
7.0
9.1
~it~1
Improperly Stored
Crane in
Pumphouse.
Potential
Freezing of Spray
Tree Arms
Failure to Include Instrument
Accuracies
In Position
Verification Procedures.
Lack of Procedure for
Performing Intake Inspection
Inadequate
Spray
Pond Icing
Guidance
93-201-06
93-201-07
93-201-08
10.0
10.0
11.0
SWS Piping Corrosion
Permanently Installed
Scaffolding in
RHR Pump
Room
Inadequate
Procedures
for
Biofouling Program
APPENDIX
C
EXIT MEETING ATTENDEES
uclear
Re ulator
Commission
Paul Narbut
David Pereira
Eugene
V. Imbro
Jeffrey B. Jacobson
Christopher
Hyers
Lew Miller
R.
C. Barr
J.
W. Clifford
Ann. Dummer
Steven
Jones
WNP-2
.J.
D. Arbuckle
R. L. Koenigs
J.
V. Parrish
A. L. Oxsen
Phil Harness
Rod Webring
Jack Baker
James
C. Gearhart
Larry Harrold
Gregory 0 Smith
Alan Hosier
Ron Barbee
Stan Davison
Tom Hoyle
Carl Fies
J.
E.
Rhoads
LL Grumme
John
Dabney
William H. Sawyer
Clyde R. Noyes
Dennis
H. Hyers
Dan Becker
Curtis Moore
J.
S.
Flood
Paul
Inserra
Douglas
L. Williams
Inspector,
RV
Inspector,
RV
Reactor Engineer Intern,
Chief, Special
Inspection
Branch,
Team Leader,
Inspector,
Region
V
Chief, Reactor Safety,
Region
V
Senior Resident
Inspector,
RV
Senior Project Manager,
Mechanical
Engineer,
Mechanical
Engineer,
Senior Licensing Engineer
Acting Engineering Director
Assistant
Managing Director
Acting Managing Director
Design Engineering
Manager
Plant Technical
Manager
Plant Manager
Director
gA
Assistant
Plant Manager
Operations Division Manager
Licensing Manager
Systems
Engineering
Manager
WNP-2
Plant
gA Manager
Lead,
Valve Programs
Licensing Engineer
Operating
Event Analysis
8 Resolution
Manager Nuclear Safety Assurance
Work Control
Manager
Shift Manager
Manager Engineer
Programs
Supervisor Mechanical
Engineering
Supervisor,
Electric/
IEC
Plant Technical
Engineer
Principal Operations
Engineer
Plant Technical
Supervisor
Nuclear Engineer
~ W
+'
~
ff.
F~,