Category:CONSTRUCTION PERMITS-APPLICATION & AMENDMENTS TO APP
MONTHYEARML17275B2321981-09-0404 September 1981 Application to Amend CPPR-93 Extending Const Completion Date to 840201.Class II Amend Fee Encl ML20098D2741972-09-14014 September 1972 Amend 13 to Application for CP ML20098C8371972-09-14014 September 1972 Amend 13 to Application for Cp,Consisting of Const Cost Summary ML20098D2941972-08-21021 August 1972 Amend 10 to Application for Cp,Consisting of Response to AEC 720728 Questions ML20238D9411972-03-10010 March 1972 Amend 4 to Util Application for Cp,Consisting of Process Data for New Low Temp Recombiner Charcoal Adsorber Sys for Processing Main Condenser Offgas,Per AEC 720120 Questions 9 & 10 ML20098D3441971-08-10010 August 1971 Application for CP 1981-09-04
[Table view] Category:CONSTRUCTION PERMITS-APPLICATION TO AMEND EXISTING CP
MONTHYEARML17275B2321981-09-0404 September 1981 Application to Amend CPPR-93 Extending Const Completion Date to 840201.Class II Amend Fee Encl ML20098C8371972-09-14014 September 1972 Amend 13 to Application for Cp,Consisting of Const Cost Summary 1981-09-04
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML17284A9101999-10-13013 October 1999 Application for Amend to License NPF-21,revising TS 3.3.6.1, Table 3.3.6.1-1, Primary Containment Isolation Instrumentation. Footnote (D) Is Removed Since Both Inboard & Outboard Trip Sys Are Now Functional in All Modes ML17284A8501999-07-29029 July 1999 Application for Amend to License NPF-21,revising TS 3.4.9, RHR Shutdown Cooling Sys - Hot Shutdown. ML17284A8471999-07-29029 July 1999 Application for Amend to License NPF-21,revising Tech Specs SR 3.5.2.2, Condensate Storage Tank Water Level. ML17284A8441999-07-29029 July 1999 Application for Amend to License NPF-21,revising TS Table 3.3.5.1-1, ECCS Instrumentation Items 1.a,2.a,4.a & 5.a. ML17284A8431999-07-29029 July 1999 Application for Amend to License NPF-21,removing License Condition 2.C.(16),Attachment 2,Item 3(b) Re post-accident Neutron Flux Monitoring ML17284A8401999-07-29029 July 1999 Application for Amend to License NPF-21,amending Tech Specs SR 3.8.4.6 of TS 3.8.5, DC Sources - Operating & SR 3.8.5.1 of TS 3.8.5, DC Sources - Shutdown. ML17292B6891999-06-0303 June 1999 Application for Amend to License NPF-21,reflecting Change in Name of Washington Public Power Supply Sys to Energy Northwest.Marked-up Copy of Affected Pages of OL for Plant, Encl ML17292B6441999-04-20020 April 1999 Application for Amend to License NPF-21,revising TS 3.4.11 to Replace Existing Reactor Pressure Temp Limit Curves by 000630 ML17292B6321999-04-0707 April 1999 Application for Amend to License NPF-21,requesting Mod to MCPR Safety Limits by 990930 to Allow Continued Power Operation at Plant Following Restart from R-14 RFO ML17292B4861998-12-17017 December 1998 Application for Amend to License NPF-21,revising TS SR 3.8.1.8 to Allow for Capability to Manually Transfer Between Preferred & Alternate Offsite Power Sources During Modes 1 & 2 by 990125 ML17284A8071998-11-0909 November 1998 Supplemental Application for Amend to License NPF-21, Requesting Minor Wording Changes to Clarify Intent of Proposed New License Section 2.B.(6).Addl Info That Describes Physical Storage of Matls,Encl ML17284A7161998-08-0505 August 1998 Application for Amend to License NPF-21,modifying TS SR 3.8.4.7 to Allow Performance Discharge Test to Be Performed in Lieu of Battery Svc Test for Div 1 & 3,125 Vdc Batteries E-B1-1 & HPCS-B1-DG3 & Div 1,250 Vdc Battery E-B2-1 ML17284A7051998-07-17017 July 1998 Application for Exigent Amend to License NPF-21,modifying TS SR 3.8.4.7 to Allow Performance Discharge Test to Be Performed in Lieu of Battery Svc Test for Div 2,125 Vdc, Battery E-B1-2 ML17292B3401998-04-16016 April 1998 Application for Amend to License NPF-21,modifying Requirement That cold-worked Austenitic Stainless Steel Used in Newly Designed ECCS Pump Suction Strainers Must Have Yield Strength Not Greater than 90,000 Psi ML17292B1301997-12-0404 December 1997 Application for Amend to License NPF-21,modifying Min Critical Power Ratio Safety Limits by 980515 to Allow Continued Power Operation at WNP-2 Following Restart from R-13 Refueling Outage ML17292B0261997-08-14014 August 1997 Application for Amend to License NPF-21,modifying Inservice Testing Requirements Specified in TS 5.5.6 for Inboard Primary Containment Isolation Valve on Transvering in-core Probe (TIP) Sys Nitrogen Purge Line ML17292A9401997-07-16016 July 1997 Application for Amend to License NPF-21,adding New Min Reactor Vessel Pressure Versus Reactor Vessel Metal Temp (P/T) Curves,Applicable Up to 12 Efpys.Changes Support Vessel Leak Testing ML17292A8631997-05-20020 May 1997 Application for Amend to License NPF-21,requesting Mod of Minimum Critical Power Ratio Safety Limits by 970615 ML17292A7561997-03-22022 March 1997 Application for Amend to License NPF-21,modifying Response Time Testing Surveillance Requirements for RPS Instrumentation,Primary Containment Isolation Actuation Instrumentation & ECCS Actuation Instrumentation ML17292A5491996-10-15015 October 1996 Application for Amend to License NPF-21 to Modify TS for Secondary Containment & Standby Gas Treatment Sys to Reflect Revised Secondary Containment Drawdown & post-accident Analyses Results.Affidavit,Encl ML17292A5381996-10-10010 October 1996 Application for Amend to License NPF-21,requesting Addition of Section 2B(6) Re Allowance of Storage of Byproduct, Source & Special Nuclear Materials ML17292A4081996-08-0909 August 1996 Requests Amend to License NPF-21,revising TS Section 6.3 Re Unit Staff Qualifications,By Changing Operations Manager Qualification Requirements Associated W/Operations Knowledge from Meeting Ansi/Ans N18.1-1971 GO2-96-089, Application for Amend to License NPF-21,modifying TS to Support Cycle 12,scheduled to Begin Subsequent to Spring 1996 Outage1996-04-24024 April 1996 Application for Amend to License NPF-21,modifying TS to Support Cycle 12,scheduled to Begin Subsequent to Spring 1996 Outage ML17291B2781996-03-19019 March 1996 Application for Amend to License NPF-21,revising Containment Leakage Testing ML17291B2071996-01-19019 January 1996 Application for Amend to License NPF-21 Re Primary Containment Leakage Testing GO2-95-265, Application for Amend to License NPF-21,revising TS to Be Consistent w/NUREG-1434, STS GE Plants,Bwr 6, Including Improved TS Submittal,Consisting of Application of Selection Criteria,Ts,Comparison Document & NSHC1995-12-0808 December 1995 Application for Amend to License NPF-21,revising TS to Be Consistent w/NUREG-1434, STS GE Plants,Bwr 6, Including Improved TS Submittal,Consisting of Application of Selection Criteria,Ts,Comparison Document & NSHC ML17291B0921995-10-26026 October 1995 Application for Amend to License NPF-21,revising TS to Reflect Replacement of Existing Reactor Recirculation Flow Control Sys W/Adjustable Speed Drive Sys ML17291A8421995-06-0606 June 1995 Application for Amend to License NPF-21,changing TS 6.0, Administrative Controls by Revising Assistant Managing Director,Operations & Plant Manager Position Titles ML17291A8381995-06-0606 June 1995 Application for Amend to License NPF-21,modifying Index of TS by Deleting Ref to Bases Pages.Future Changes to Bases Info Will Be Evaluated Per 10CFR50.59 ML17291A8321995-06-0606 June 1995 Application for Amend to License NPF-21,modifying TS 6.9.3.2 by Adding Re to Three TRs Describing Analytical Methods That May Be Used in Determining Reactor Core Operating Limits for Reload Licensing Applications,Consistent W/Gl 88-16 ML17291A7551995-04-25025 April 1995 Application for Amend to License NPF-21,adding RWCU Sys High Blowdown Containment Isolation Trip Function & Associated LCO & SRs to Tables 3.3.2-1,3.3.2-2 & 4.3.2.1-1 ML17291A4791994-10-31031 October 1994 Application for Amend to License NPF-21,revising TSs to Relocate Safety/Relief Valve Position Indication Instrumentation Requirements ML17291A4741994-10-31031 October 1994 Application for Amend to License NPF-21,revising TS 3/4.1.3.1, Reactivity Control Sys. ML17291A4201994-09-26026 September 1994 Suppl to 930709 Application for Amend to License NPF-21 Re Increase in Power Operation,Changing Power/Flow Maps in TS 3/4.2.6,3/4.2.7,3/4.2.8 & 3/4.4.1 & Bases to Reflect Use of Siemens Power Corp Staif Code for Stability Analysis ML17291A3941994-09-18018 September 1994 Application for Amend to License NPF-21,changing TS Table 3.6.3-1 Re Primary Containment Isolation Valve Requirements ML17291A3171994-08-0808 August 1994 Application for Amend to License NPF-21,amending TS 4.0.5, Surveillance Requirements for Inservice Insp & Testing Program. ML17291A2151994-07-12012 July 1994 Application for Amend to License NPF-21,requesting Amend to Ts,Relocating TS Table for Instrument Response Time Limits ML17291A2201994-07-0808 July 1994 Application for Amend to License NPF-21,revising TS W/Regard to Control Rod Scram Insertion Testing Under Emergency Circumstances ML17290B1711994-05-0606 May 1994 Application for Amend to License NPF-21,revising TSs 3/4.3.7.5,3/4.4.2 & 3/4.5.1 for Main Steam Relief Valve Position Indication ML17290B1551994-05-0505 May 1994 Application for Amend to License NPF-21,requesting Mod of Three Equipment Piece Numbers Included in Table 3.6.3-1, Primary Containment Isolation Valves. ML17290A9631994-02-17017 February 1994 Application for Amend to License NPF-21,revising TS to Support Hydrostatic Testing ML17290A9601994-02-17017 February 1994 Application for Amend to License NPF-21,revising TS Section 6.0, Administrative Controls, Including Changing Reporting Relationship for QA Functions in Section 6.2.1.e of TS from Managing Director to Assistant Managing Director,Operations ML17290A9551994-02-0808 February 1994 Application for Amend to License NPF-21,consisting of Changes to TS Table 3.6.3-1,for RCIC-V-8,increasing Stroke Time from 13 Seconds to 26 Seconds & Deleting Note (J) Reference from RCIC-V-8 & RCIC-V-63 ML17290A9031994-01-13013 January 1994 Application for Amend to License NPF-21,requesting Continued Plant Operation W/Eccs Functional,But Not in Strict Compliance W/Requirements for Demonstrating That Response Time within Limits of TS 3/4.3.3, ECCS Instrumentation. ML17290A8961994-01-0606 January 1994 Application for Amend to License NPF-21,requesting Changes to TS to Clarify Instrumentation Testing Requirements ML17290A8781994-01-0606 January 1994 Application for Amend to License NPF-21,requesting Rev to TS to Relocate Requirements for Seismic Monitoring Instrumentation to FSAR & Plant Procedures ML17290A8921994-01-0606 January 1994 Suppl to 930709 Application for Amend to License NPF-21, Increasing Licensed Power Level from 3,323 Mwt to 3,486 Mwt W/Extended Load Line Limit & Changing SRV Setpoint Tolerance to Include Changes to TS Paragraph 6.9.3.2 ML17290A8391993-12-20020 December 1993 Application for Amend to License NPF-21,revising TS 3/4.6.1.8, Drywell & Suppression Chamber Purge Sys. ML17290A8181993-12-0606 December 1993 Application for Amend to License NPF-21,requesting TS Surveillance Requirement 4.6.6.1.b.3 Be Revised to Provide Appropriate Acceptance Criteria for Demonstrating Operability of Primary Containment Hydrogen Recombiner Sys ML17290A8221993-12-0606 December 1993 Application for Amend to License NPF-21,adding Footnote to TS Table 4.3.7.5-1, Accident Monitoring Instrumentation Srs, Exempting Channel Calibr of Safety/Relief Valve Position Indicators from Spec 4.0.4 for 24 H 1999-07-29
[Table view] |
Text
REGULATOR NFORMATION DISTRIBUTION TEM (RIDS)
ACCESSIOIN- NBR; 8109150158 DOC 0 DATE: 81/09/00 NOTARIZED; NO DOCKKtT FACIL<:50 397 NPPSS Nuclear Projects Unit 2r Nashington Public Powe" 050.00397 AUTH'AME AUTHOR AFFILIATION BOUCHEIY<G,D. washington Public Power Supply System REC IP ~ NAMEI RECIPIENT AF F IL>>I ATION DENTONFH',RB Office. of Nuclear Reactor Regulationr Director>>
SUBJECT:
- Application to amend CPPR-93 extending const completion datet to 800201 ~ Class il amend feel encl.
DISTRIBUTION CODES B0060 COPIES RECEEVED:LTR f ENCL SIZE'::
NOTES:2 copies-- all matl:PM'5000397 TITLEt: Requests for Ekemptions (Al Types) 1 RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME( LTTR ENCL ID CODE/NAME LTTR" ACTION: A/D LICENSNG 07 L>>IC BR P2 BC 06 LIC BR 02" LA OQ AULUCKPR, 05 INTERNALS: A/D TECHNOLOG10., 1 ABKLLPT' "
16" D/DIR, HUM S 11>> 1 DIRF DIV OF LIC DIR'r HU9, FAC S12', 1 DIR ENS ING13. ENCL'XTERNALI:
IH,EI 09 2 G F IL 01-ACRS 15 16 INPOPJ ~ STARNKS LPDR 03>> 1 NRC PDR 02'TIS NSIC 08 1
~p] g 931 0
TOTAL NUMBER OF COPIES REQUIRED: LTTR Q ENCL'f
ft I'
Washington Public Power Supply System P.O. Box 968 3000 George Washington Way Richland, Washington 99352 (509) 372-5000 eiO iSOiS8 September 4, 1981 PDR
<>OCg 8iO9Oy G02-81-276 OSOOO39y NS-L-GCS-81-239 POR Docket No. 50-39/-
Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555
Dear Mr. Denton:
Subject:
WASHING ON PUBLIC OWER SU PLY SYSl%E NUCLEAR PROJECT NO. 2 (WNP-2) EXTENSION OF CONSTRUCTION COMPLETION DATE The Supply System requests an amendment to Construction Permit No. CPPR-93 for WNP-2 to extend the "latest completion date" pursuant to 10CFR50.55(b) to February 1, 1984. The earliest completion date for purposes of this extension is December 1, 1982. Construction Permit No. CPPR-93 currently specifies December 1, 1981, as the latest date for completion of construction for WNP-2. In estimating new completion dates for WNP-2, the Supply System has carefully developed revised construction schedules. The revised official completion date is September 1983, and a manaqement objective of improvinq this date to December 1982 has been established. The February 1, 1984, latest construction completion date we are requesting for the purpose of construction permit duration reflects a reasonable allowance for uncertainty.
We consider this appropriate given the potential for continued regulatory changes, labor difficulties, delays in delivery of equipment and materials or other unforeseen events.
The primary factors causing these delays in WNP-2 construction completion were as follows:
~ Changes in the scope of the project including increases in the amount of material and engineering required as a result of regulatory actions, in particular those subsequent to the TMI-2 accident.
~ Construction delays and lower than estimated productivity, which resulted in delays in installation of material and equipment and delays in completion of systems necessitating rescheduling of pre-operational testing.
Strikes by portions of the construction work force.
~ Changes in plant design.
e" Delays in delivery of equipment and materials.
g g,oo.oo
0 I
IP U'
(l,
~
IJV
~f I
V
'Mr. Harold R. Denton, Director Page Two Since this amendment involves no significant hazards.consideration, the Supply System requests that the Commission dispense with advance'otice of the amendment, pursuant to Section. 189(a) of the Atomic Energy Act of-1954, as amended. 42 USC 2239(a)
Accordingly, the Supply System requests; pursuant to 10CFR50.55(b) that'he Nuclear Regulatory Commission amend Construction Permit No. CPPR-93 to specify February 1, 1984, as the latest date for completion of WNP-2 with December, 1, 1982, as the earliest date for completion.
The request regarding an amendment of Construction Permit No. CPPR-93 is a Class II amendment, as it has no safety or environmental significance.and is a matter of fo'rmali ty and administrative in nature. (See 10CFR170.22.)
Enclosed is our check i n the amount of $ 1,200 for a Class II Amendment.
The Supply System. recently filed a.,request with the Commission .for a full refund of all fees paid to the NRC by the Supply System. This request for a refund of fees was denied by a letter from Daniel J. Donoghue to R. L. Ferguson, dated August 12, 1981. The Supply System is currently evaluating the NRC position on this matter and accordingly we remit the fee for this construction permit, amendment under protest and subject to refund pending a decision on whether to pursue our request for refund further.
Very -truly yours, G. D. BOUCHEY Director, Nuclear Safety GDB:GCS:lc Attachment cc: RE Auluck, NRC C. R. Bryant, BPA R. Ferdon N. S. Reynolds, D&L E. Beckett, NPI