ES-301 Administrative Topics Outline Form ES-301-1 Facility: _Duane Arnold Energy Center________________

Date of Examination: _June 2017___

Examination Level:

RO X

SRO Operating Test Number: _17-1____

Administrative Topic (see Note)

Type Code*

Describe activity to be performed Conduct of Operations S,D Evaluate License Maintenance and Over Time Requirements Generic K/A 2.1.2 IR: 4.1 Conduct of Operations S,D Perform STP 3.0.0-01, Instrument Checks - SBLC Level, Temperature and Boron Concentration Generic K/A 2.1.18 IR: 3.6 Equipment Control M,S Peer Check STP 3.8.1-01, Offsite Power Sources.

Determine that the STP was done incorrect. Re-performs STP Generic K/A 2.2.12 IR: 3.7 Radiation Control P,D,S Determine Personnel Availablilty to perform Rad Area Tasks Generic K/A 2.3.12 IR: 3.2 NOTE: All items (five total) are required for SROs. RO applicants require only four items unless they are retaking only the administrative topics (which would require all five items).

  • Type Codes & Criteria:

(C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs; 4 for SROs & RO retakes)

(N)ew or (M)odified from bank ( 1)

(P)revious 2 exams ( 1; randomly selected)

ES-301 Administrative Topics Outline Form ES-301-1 Facility: _Duane Arnold Energy Center______________

Date of Examination: __June 2017__

Examination Level:

RO SRO X

Operating Test Number: __17-1____

Administrative Topic (see Note)

Type Code*

Describe activity to be performed Conduct of Operations P,S,D Determine Risk and the Resultant Protected Systems Generic K/A 2.1.2 SRO IR: 4.4 Conduct of Operations S,D DETERMINE REPORTABILITY - UNUSUAL EVENT AND PLANT SHUTDOWN REQUIRED BY T.S.

Generic K/A 2.1.18 SRO IR: 3.8 Equipment Control S,D Review a Work Order for closure IAW ACP 1408.1, Work Orders Generic K/A 2.2.19 SRO IR: 3.4 Radiation Control N, S Vent Primary Containment with Torus Hard Pipe Vent Generic K/A 2.3.11 IR: 4.3 Emergency Plan D,S Evaluate PARS when conditions change Generic K/A 2.4.44 IR: 4.4 NOTE: All items (five total) are required for SROs. RO applicants require only four items unless they are retaking only the administrative topics (which would require all five items).

  • Type Codes & Criteria:

(C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs; 4 for SROs & RO retakes)

(N)ew or (M)odified from bank ( 1)

(P)revious 2 exams ( 1; randomly selected)