NRR E-mail Capture - (External_Sender) Hope Creek and Salem: Draft SE Regarding Revision to CSP Milestone 8 Implementation Schedule (MF8071, MF8072. & MF8073)
ML17102A909
Person / Time
Site: Salem, Hope Creek  PSEG icon.png
Issue date: 04/11/2017
From: Bernard Thomas
Public Service Enterprise Group
To: Carleen Parker
Plant Licensing Branch 1
References
MF8071, MF8072, MF8073
Download: ML17102A909 (3)


Text

NRR-PMDAPEm Resource From: Thomas, Brian J. <Brian.Thomas@pseg.com>

Sent: Tuesday, April 11, 2017 2:31 PM To: Parker, Carleen Cc: Duke, Paul R.

Subject:

[External_Sender] RE: Hope Creek and Salem: DRAFT SE Regarding Revision to CSP Milestone 8 Implementation Schedule (MF8071, MF8072. & MF8073)

Carleen:

The draft SE was reviewed for security related information by our security staff and determined that the document does not contain any security related information.

Any questions let me know.

Brian Brian J. Thomas PSEG Licensing Salem & Hope Creek 856-339-2022 brian.thomas@pseg.com PSEGSC From: Parker, Carleen [1]

Sent: Monday, April 10, 2017 10:28 AM To: Thomas, Brian J.; Duke, Paul R.

Subject:

Hope Creek and Salem: DRAFT SE Regarding Revision to CSP Milestone 8 Implementation Schedule (MF8071, MF8072. & MF8073)

Email sent from outside of PSEG. Use caution before using links/attachments.

Good Morning, By letter dated June 30, 2016 (ADAMS Accession No. ML16190A248), PSEG Nuclear LLC (PSEG or the licensee) submitted a request for changes to the Hope Creek Generating Station (Hope Creek) and Salem Nuclear Generating Station (Salem), Unit Nos. 1 and 2, Renewed Facility Operating Licenses (FOLs). The requested changes would revise the Cyber Security Plan (CSP) Milestone 8 implementation schedule for Hope Creek and Salem, Unit Nos. 1 and 2. Specifically, this change extends the PSEG CSP Milestone 8 full implementation date as set forth in the PSEG CSP implementation schedule and revises the FOLs.

Attached is the draft Safety Evaluation (SE) that the Nuclear Regulatory Commission (NRC) staff has prepared to support the proposed license amendment. Pursuant to Section 2.390 of Title 10 of the Code of Federal Regulations (10 CFR), we have made a preliminary determination that the enclosed draft SE does not contain security-related information. However, since the NRC's review was based largely on review of security-related information, the NRC staff requests that the licensee confirm that the draft SE does not contain any information that is considered security-related. If you believe that any information is security-related, please identify such information line-by-line.

1

Since the NRC review is not yet complete, this letter and the enclosure do not convey or represent an NRC staff position regarding the licensee's request.

If you have any questions, please contact me.

Carleen Parker Project Manager -

Hope Creek and Salem Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission (301)415-1603 carleen.parker@nrc.gov The information contained in this e-mail, including any attachment(s), is intended solely for use by the named addressee(s). If you are not the intended recipient, or a person designated as responsible for delivering such messages to the intended recipient, you are not authorized to disclose, copy, distribute or retain this message, in whole or in part, without written authorization from PSEG. This e-mail may contain proprietary, confidential or privileged information. If you have received this message in error, please notify the sender immediately. This notice is included in all e-mail messages leaving PSEG. Thank you for your cooperation.

2

Hearing Identifier: NRR_PMDA Email Number: 3435 Mail Envelope Properties (eb7b2cdf766847c98b7b398e74f59f56)

Subject:

[External_Sender] RE: Hope Creek and Salem: DRAFT SE Regarding Revision to CSP Milestone 8 Implementation Schedule (MF8071, MF8072. & MF8073)

Sent Date: 4/11/2017 2:30:40 PM Received Date: 4/11/2017 2:31:04 PM From: Thomas, Brian J.

Created By: Brian.Thomas@pseg.com Recipients:

"Duke, Paul R." <Paul.Duke@pseg.com>

Tracking Status: None "Parker, Carleen" <Carleen.Parker@nrc.gov>

Tracking Status: None Post Office: pseg.com Files Size Date & Time MESSAGE 3266 4/11/2017 2:31:04 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: