RC-17-0033, Annual Operating Report for 2016

From kanterella
(Redirected from ML17082A543)
Jump to navigation Jump to search
Annual Operating Report for 2016
ML17082A543
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 03/23/2017
From: Lippard G
South Carolina Electric & Gas Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RC-17-0033
Download: ML17082A543 (6)


Text

George A. Lippard Vice President, Nuclear Operations 803.345.4810 March 23, 2017 A SCANA COMPANY U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555

Dear Sir/Madam:

Subject:

VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 DOCKET NO. 50-395 OPERATING LICENSE NO. NPF-12 ANNUAL OPERATING REPORT Enclosed is the 2016 Annual Operating Report for the South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Unit No. 1. This report is being submitted in accordance with Technical Specification 6.9.1.4.

If there are any questions, please call at your convenience.

Very truly yours, George A. Lippard SBR/GAL/hk Attachment c: K. B. Marsh K. M. Sutton S. A. Byrne J. C. Mellette J. B. Archie C. Logan (ANI)

N. S. Cams Marsh USA, Inc.

J. H. Hamilton NRC Resident Inspector S. M. Shealy NSRC W. M. Cherry RTS (LTD 292)

C. Haney File (818.02-10, RR 8225)

S. A. Williams PRSF (RC-17-0033)

V. C. Summer Nuclear Station

  • P. 0. Box 88
  • 29065
  • F (803) 941-9776
  • www.sceg.com

VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 2016 ANNUAL OPERATING REPORT

Document Control Desk LTD 292 RC-17-0033 Page 2 of 5 PREFACE The 2016 Annual Operating Report for the Virgil C. Summer Nuclear Station Unit 1 is hereby submitted in accordance with Technical Specification 6.9.1.4 under Docket Number 50-395 and Facility Operating License NPF-12.

Document Control Desk LTD 292 RC-17-0033 Page 3 of 5 TABLE OF CONTENTS SECTION TITLE PAGE 1.0 Introduction 4 2.0 Operational Data 4 3.0 Operating Summary 4 4.0 Failed Fuel 5

Document Control Desk LTD 292 RC-17-0033 Page 4 of 5

1.0 INTRODUCTION

The Virgil C. Summer Nuclear Station (VCSNS) utilizes a pressurized water reactor rated at 2900 MWT. The maximum dependable capacity is 966 MWe.

The station is located approximately 26 miles northwest of Columbia, South Carolina.

2.0 OPERATIONAL DATA For the reporting period of January 1 through December 31, 2016, the station operated at a capacity factor of 102% (using maximum dependable capacity) and a unit availability of 100%.

The reactor was critical for a total of 8784.0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br />, the generator remained on line 8784.0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> and the total gross electrical energy generated for 2016 was 8,999,220 MWH.

3.0 OPERATING

SUMMARY

The Virgil C. Summer Nuclear Station (VCSNS) Unit No.1 operated at 100% power from January 1st through March 4th. On March 4th power was reduced to 91% to support planned main turbine valve testing. Power was restored to 100% on March 5th.

VCSNS operated at 100% power from March 5th to June 3rd. On June 3rd power was reduced to approximately 89.3% to support planned main turbine valve testing. Reactor power was restored to 100% on June 4th.

VCSNS operated at 100% power from June 4th to July 26th. On July 26th power was reduced to approximately 93% due to failure of C Main Feedwater Booster Pump Motor. The failed motor was replaced. Reactor power was restored to 100% on August 3rd.

VCSNS operated at 100% power from August 3rd to September 9th. On September 9th power was reduced to approximately 90.5% to support planned main turbine valve testing. Power was restored to 100% on September 10th.

VCSNS operated at 100% power from September 10th to November 11th. On November 11th power was reduced to 88.5% due to the malfunction of a heater drain valve level controller on the #1B Feedwater Heater. This required isolation of the #1B Feedwater Heater to repair the level controller. Power was restore to 100% on November 11th.

VCSNS operated at 100% power from November 11th to December 2nd. On December 2nd power was reduced to 92% to support planned main turbine valve testing. Power was restored to 100% on December 3rd. The plant operated at 100% power for the remainder of 2016.

Document Control Desk LTD 292 RC-17-0033 Page 5 of 5 Forced Power Reduction >20% Exceeding 4 Hours None 4.0 FAILED FUEL VCSNS did not have any indications of failed fuel in 2016.