ML19088A211
| ML19088A211 | |
| Person / Time | |
|---|---|
| Site: | Summer |
| Issue date: | 03/28/2019 |
| From: | Lippard G South Carolina Electric & Gas Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 19-136 | |
| Download: ML19088A211 (6) | |
Text
< scE&G A SCANA COMPANY ATTN : Document Control Desk U. S. Regulatory Commission Washington, D. C. 20555-001 March 28, 2019 VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 DOCKET NO. 50-395 OPERATING LICENSE NO. NPF-12 ANNUAL OPERATING REPORT Serial No.19-136 LIC/SR RO Docket Nos.
50-395 License No.
NPF-12 Enclosed is the 2018 Annual Operating Report for the South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Unit No. 1. This report is being submitted in accordance with Technical Specification 6.9.1.4.
If there are any questions, please call Ms. Susan B. Reese at (803) 345-4591.
Sincerely,
~
ppa;d Vice President, Nuclear Operations V. C. Summer Nuclear Station cc:
G. J. Lindamood C. Haney S. A. Williams NRC Resident Inspector Marsh USA C. Logan (ANI)
V. C. Summer Nuclear Station* P. 0. Box 88
- Jenkinsville, South Carolina* 29065
- F (803) 941-9776
- www.sceg.com
VIRGIL C. SUMMER NUCLEAR STATION UNIT 1 2018 ANNUAL OPERATING REPORT
PREFACE Serial No.19-136 Docket No. 50-395 VCSNS Annual Operating Report Page 1 of 4 The 2018 Annual Operating Report for the Virgil C. Summer Nuclear Station Unit 1 is hereby submitted in accordance with Technical Specification 6.9.1.4 under Docket Number 50-395 and Facility Operating License NPF-12.
SECTION 1.0 2.0 3.0 4.0 TABLE OF CONTENTS TITLE Introduction Operational Data Operating Summary Failed Fuel Serial No.19-136 Docket No. 50-395 VCSNS Annual Operating Report Page 2 of 4 PAGE 3
3 3
4
1.0 INTRODUCTION
Serial No.19-136 Docket No. 50-395 VCSNS Annual Operating Report Page 3 of 4 The Virgil C. Summer Nuclear Station (VCSNS) utilizes a pressurized water reactor rated at 2900 MWT. The maximum dependable capacity is 966 MWe.
The station is located approximately 26 miles northwest of Columbia, South Carolina.
2.0 OPERATIONAL DAT A For the reporting period of January 1 through December 31, 2018, the station operated at a capacity factor of 87.1 % (using maximum dependable capacity) and a unit availability of 86.1 %. The reactor was critical for a total of 7567.6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, the generator remained on line 7539.4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> and the total gross electrical energy generated for 2018 was 7,665,652 MWH.
3.0 OPERATING
SUMMARY
VCSNS Unit No.1 operated at 100% power from January 1st through April 5th_
On April 5th power was reduced to 91 % to support main turbine valve testing.
Reactor power was restored to 100% on April 7th_
VCSNS operated at 100% power from April 7th to May 1st. On May 1st power was reduced to 87% following the trip of 'B' Main Feedwater Pump. Reactor power was restored to 100% on May 5th.
VCSNS operated at 100% power from May 5th to June 15th_ On June 15th power was reduced to 91 % to support main turbine valve testing. Reactor power was restored to 100% on June 15th_
VCSNS operated at 100% power from June 15th to October 5th. On October 5th the plant was shutdown to begin Refueling Outage Twenty-Four (RF-24). The main generator breaker was opened on October 5th at 2352 hours0.0272 days <br />0.653 hours <br />0.00389 weeks <br />8.94936e-4 months <br />. The outage was completed on November 25th at 1843 hours0.0213 days <br />0.512 hours <br />0.00305 weeks <br />7.012615e-4 months <br /> when the main generator breaker was closed. Power was restored to 100% on November 29th at 0230 hours0.00266 days <br />0.0639 hours <br />3.80291e-4 weeks <br />8.7515e-5 months <br />.
The unit remained at 100% power for the remainder of 2018.
Refueling Outage 24 Summary Serial No.19-136 Docket No. 50-395 VCSNS Annual Operating Report Page 4 of 4 The main generator breaker was opened on October 5th at 2352 hours0.0272 days <br />0.653 hours <br />0.00389 weeks <br />8.94936e-4 months <br />. The outage duration was scheduled for 52 days. The main generator breaker was closed on November 25th at 1843 hours0.0213 days <br />0.512 hours <br />0.00305 weeks <br />7.012615e-4 months <br />.
Major work included:
Open Phase Condition (OPC) Strategy for Off-site Power Sources Reactor Coolant Oil Collection Enclosure Modification "A" Train Inverter Replacements (XIT 5901/5902)
Feed Reg Valve Positioner Upgrade CROM System Demolition - Phase 1 Simplex Upgrade "B" Loop Auxiliary Crane XIT 5905 CROM Duct Permanent Flange Refueling Outage 24 duration was 50.8 days. Personnel exposure in 2018 due to the outage was approximately 47.311 Rem.
Forced Power Reduction >20% Exceeding 4 Hours None 4.0 FAILED FUEL VCSNS did not have any indications of failed fuel in 2018.