SUBJECT:
ANNUAL ASSESSMENT LETTER FOR RIVER BEND STATION (REPORT 05000458/2016006)
Dear Mr. Maguire:
On February 15, 2017, the U.S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance assessment of River Bend Station, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2016, through December 31, 2016. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.
The NRC determined the performance at River Bend Station during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2018. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence.
Additionally, as reflected in the enclosure, during this period the NRC staff will complete Temporary Instruction 2515/191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/
Staffing/Multi-Unit Dose Assessment Plans. This inspection will be conducted at River Bend Station to confirm the stations full implementation of Commission Orders EA-12-049 and EA-12-051.
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION IV
1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511 March 1, 2017 In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Greg Warnick at 817-200-1144 with any questions you have regarding this letter.
Sincerely,
/RA/
Troy Pruett, Director Division of Reactor Projects Docket No.
50-458 License No.
NPF-47 Enclosure:
River Bend Station Inspection Plan
SUNSI Review By: GWarnick/dll ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive Keyword:
NRC-002 OFFICE RIV/C RIV/DRS:D RIV/DRP:D
NAME GWarnick AVegel TPruett SIGNATURE
/RA/
/RA JClark for/
/RA/
DATE 2/27/16 2/25/17 2/27/17
River Bend Inspection / Activity Plan 01/01/2017 - 12/31/2018 Unit Number Report 22 No. of Staff on Site Planned Dates Start End Inspection Activity Title Page 1 of 2 02/23/2017 11:47:35
- INSERVICE INSPECTION
02/06/2017 02/10/2017 IP 7111108G Inservice Inspection Activities - BWR
- RADIATION SAFETY
02/06/2017 02/10/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls
02/06/2017 02/10/2017 IP 71124.02 Occupational ALARA Planning and Controls
02/06/2017 02/10/2017 IP 71151-OR01 Occupational Exposure Control Effectiveness
02/06/2017 02/10/2017 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences
TSB 52B
- BIENNIAL PI&R
04/10/2017 04/14/2017 IP 71152B Problem Identification and Resolution
04/24/2017 04/28/2017 IP 71152B Problem Identification and Resolution
TI-191
- MITIGATING STRATEGIES/SFP INST FOR BDBEE
05/22/2017 05/26/2017 IP 2515/191 Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012
- BIENNIAL EP PROGRAM INSPECTION
05/22/2017 05/26/2017 IP 7111402 Alert and Notification System Testing
05/22/2017 05/26/2017 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System
05/22/2017 05/26/2017 IP 7111404 Emergency Action Level and Emergency Plan Changes
05/22/2017 05/26/2017 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies
- EP PERFORMANCE INDICATOR VERIFICATION
05/22/2017 05/26/2017 IP 71151-EP01 Drill/Exercise Performance
05/22/2017 05/26/2017 IP 71151-EP02 ERO Readiness
05/22/2017 05/26/2017 IP 71151-EP03 Alert & Notification System Reliability
EB1-21M
- RBS COMPONENT DESIGN BASIS INSPECTION
06/12/2017 06/30/2017 IP 7111121M Component Design Bases Inspection (Teams)
- RS TEAM
08/21/2017 08/25/2017 IP 71124.05 Radiation Monitoring Instrumentation
08/21/2017 08/25/2017 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment
08/21/2017 08/25/2017 IP 71124.07 Radiological Environmental Monitoring Program
08/21/2017 08/25/2017 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation
EB1-07T
- RBS HEAT SINK PERFORMANCE
09/18/2017 09/22/2017 IP 7111107T Heat Sink Performance
EXAM
- INITIAL EXAM
05/21/2018 05/25/2018 X02622 INITIAL EXAM RB(6/18)
06/25/2018 07/03/2018 X02622 INITIAL EXAM RB(6/18)
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
River Bend Inspection / Activity Plan 01/01/2017 - 12/31/2018 Unit Number Report 22 No. of Staff on Site Planned Dates Start End Inspection Activity Title Page 2 of 2 02/23/2017 11:47:35
- RAD SAFETY
01/22/2018 01/26/2018 IP 71124.02 Occupational ALARA Planning and Controls
01/22/2018 01/26/2018 IP 71124.04 Occupational Dose Assessment
EB2-02
- LICENSE RENEWAL INSPECTION
03/26/2018 03/30/2018 IP 71002 License Renewal Inspection
04/09/2018 04/13/2018 IP 71002 License Renewal Inspection
- EP EXERCISE INSPECTION
06/25/2018 06/29/2018 IP 7111401 Exercise Evaluation
06/25/2018 06/29/2018 IP 7111404 Emergency Action Level and Emergency Plan Changes
06/25/2018 06/29/2018 IP 71151-EP01 Drill/Exercise Performance
06/25/2018 06/29/2018 IP 71151-EP02 ERO Readiness
06/25/2018 06/29/2018 IP 71151-EP03 Alert & Notification System Reliability
BRQ
- BRQ
08/27/2018 08/31/2018 IP 7111111B Licensed Operator Requalification Program
EB1-17T
- RBS 50.59 CHANGES, TESTS, EXPERIMENTS
09/10/2018 09/14/2018 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications
RS 13PI
- RAD SAFETY
11/05/2018 11/09/2018 IP 71124.01 Radiological Hazard Assessment and Exposure Controls
11/05/2018 11/09/2018 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation
11/05/2018 11/09/2018 IP 71151-OR01 Occupational Exposure Control Effectiveness
11/05/2018 11/09/2018 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences Comments:
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.