UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 June 22, 2016 Mr. Anthony Vitale Vice President, Operations Entergy Nuclear Operations, Inc.

Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530

SUBJECT:

INFORMATION REQUEST TO SUPPORT UPCOMING TEMPORARY INSTRUCTION 191 INSPECTION AT PALISADES NUCLEAR PLANT

Dear Mr. Vitale:

This letter is to request information to support our inspection of the Implementation of Mitigating Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communications/Staffing/Multi-Unit Dose Assessment Plans beginning September 26, 2016 at your Palisades Nuclear Plant. This inspection will be performed in accordance with the U.S. Nuclear Regulatory Commission (NRC) Temporary Instruction 2515/191.

In order to minimize the impact that the inspection has on the site and to ensure a productive inspection, we have enclosed a list of documents requested for the inspection. Please provide this information prior to September 9, 2016. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection. Insofar as possible, this information should be provided electronically to the lead inspector.

The lead inspector for this inspection is Dr. Stuart Sheldon. We understand that our primary contact for this inspection is Mr. Jeff Erickson of your organization. If there are any questions about the inspection or the material requested in the enclosure, please contact the lead inspector at 630-829-9727 or via e-mail at Stuart.Sheldon@nrc.gov.

This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.

A. Vitale In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records System (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Team Lead Technical Support Staff Division of Reactor Projects Docket No. 50-255 License No. DPR-20

Enclosure:

Requested for Information to Support Temporary Instruction 2515/191 Inspection Report 05000255/2016008 cc: Distribution via LISTSERV

REQUESTED INFORMATION TO SUPPORT TEMPORARY INSTRUCTION INSPECTION REPORT 05000255/2016008 Please provide the information on a compact disc or another form of electronic media, if possible. For requested lists please provide the information, if possible, in a sortable Excel spreadsheet format. For the purposes of this document request FLEX will mean any item, SSC, procedure, calculation or document that was part of the implementation of Mitigating Strategies, Spent Fuel Pool instrumentation orders and emergency preparedness communications/staffing and multi-unit dose assessment.

In addition, the inspectors will require computer access to the corrective action program (CAP) database while on site.

1. A current copy of administrative procedure(s) for the CAP, modification program, maintenance of FLEX equipment program, operations procedure writing and implementing, and top-level documents for the work control programs, and work scheduling programs. If Flex related procedures such as FSGs or the Final Integrated Plan (FIP) are maintained under a different process please include copies of those procedures.
2. A current copy of the Emergency Operating Procedures, Abnormal Operating Procedures, Off-Normal Procedures and Flex Support Guidelines. Please have available the annunicator response procedures. Also include Station Blackout related procedures if they are separate from the above.
3. A current copy of the FIP and any documentation to or from the NRC related to the FIP.

Please include any changes to the FIP since submittal to the NRC.

4. A listing of any changes to the FIP since issuance of the NRC Safety Evaluation Report.
5. A listing of CAP items related to implementation of FLEX, maintenance of the FLEX program and equipment, modifications related to FLEX, and training related to FLEX.
6. A current copy of the SAFER response plan.
7. A copy of any audits related to your preparation for this inspection as well as any related to the implementation or maintenance of FLEX.
8. A current copy of your outage planning procedures including forced outage planning procedures.
9. FLEX related training documents, aids, and records, including presentations and videos.
10. A listing of plant modifications related to FLEX along with a copy of the spent fuel pool instrumentation modification.
11. A listing of calculations, evaluations, and 50.59 reviews related to FLEX.
12. A copy of the current FLEX strategy basis document.

Enclosure

13. A copy of the FLEX strategies time validation study and the full staffing analysis.
14. Documents and procedures related to your multi-unit dose assessment capability.
15. A copy of the UFSAR, Technical Specifications and TS bases documents.

OTHER:

On the first day of the inspection, please provide the inspection team a briefing of your FIP and overall strategy.

2

A. Vitale In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records System (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Team Lead Technical Support Staff Division of Reactor Projects Docket No. 50-255 License No. DPR-20

Enclosure:

Requested for Information to Support Temporary Instruction 2515/191 Inspection Report 05000255/2016008 cc: Distribution via LISTSERV DISTRIBUTION:

Jeremy Bowen Allan Barker RidsNrrPMPalisades Resource Carole Ariano RidsNrrDorlLpl3-1 Resource Linda Linn RidsNrrDirsIrib Resource DRPIII Cynthia Pederson DRSIII Darrell Roberts ROPassessment.Resource@nrc.gov Richard Skokowski ADAMS Accession Numberd: ML16174A413 Publicly Available Non-Publicly Available Sensitive Non-Sensitive OFFICE RIII RIII RIII RIII NAME SSheldon:rj AStone DATE 06/22/2016 06/22/2016 OFFICIAL RECORD COPY