ML110620625

From kanterella
Jump to navigation Jump to search
EOC Annual Assessment Letter and Inspection/Security Plan
ML110620625
Person / Time
Site: Palisades  Entergy icon.png
Issue date: 03/04/2011
From: Khadijah West
Division Reactor Projects III
To: Kirwin T
Entergy Nuclear Operations
References
IR-11-001
Download: ML110620625 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 March 4, 2011 Mr. Tom Kirwin Vice-President, Operations (Acting)

Entergy Nuclear Operations, Inc.

Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR PALISADES NUCLEAR PLANT (REPORT 05000255/2011001)

Dear Mr. Kirwin:

On February 17, 2011, the NRC completed its end-of-cycle performance review of Palisades Nuclear Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2010, through December 31, 2010. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRCs assessment of your performance in the Security Cornerstone and its security-related inspection plan.

The NRC determined that overall, Palisades Nuclear Plant operated in a manner that preserved public health and safety and met all cornerstone objectives. Performance during the most recent quarter was within the Licensee Response Column of the NRC=s Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Plant performance for the first, second, and third quarters of 2010 was within the Regulatory Response column of the NRCs Action Matrix based on one inspection finding in the Initiating Events Cornerstone, from the fourth quarter of 2009, which involved degradation of the neutron absorption capability of the Spent Fuel Pool plates. On September 17, 2010, the NRC completed a supplemental inspection (Inspection Report No. 05000255/2010009) which closed the finding and concluded that Palisades transitioned to the Licensee Response column at the end of the third quarter. Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2012. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 9 months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

T. Kirwin In addition to the ROP baseline, inspections are planned for Temporary Instruction 2515/179, Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in National Source Tracking System, Inspection Procedure 71003, Post-Approval Site Inspection for License Renewal, and also Independent Spent Fuel Storage Installation (ISFSI) Inspection Procedure 60855.1, Operation of an ISFSI at Operating Plants.

In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 630/829-9619 with any questions you have regarding this letter.

Sincerely,

/RA/

Steven West, Director Division of Reactor Projects Docket No. 50-255;72-007 License No. DPR-20

Enclosure:

Palisades Inspection/Activity Plan cc w/encl: Distribution via ListServ

Palisades Inspection / Activity Plan 03/01/2011 - 06/30/2012 Planned Dates No. of Staff Start End Inspection Activity Title on Site BI EP - EP ROUTINE INSPECTION / PI VERIFICATION 1 04/11/2011 04/15/2011 IP 7111402 Alert and Notification System Testing 04/11/2011 04/15/2011 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 04/11/2011 04/15/2011 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 04/11/2011 04/15/2011 IP 71151 Performance Indicator Verification BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 04/25/2011 04/29/2011 IP 71124.04 Occupational Dose Assessment 04/25/2011 04/29/2011 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 04/25/2011 04/29/2011 IP 71151-BI01 Reactor Coolant System Activity 04/25/2011 04/29/2011 IP 71151-PR01 RETS/ODCM Radiological Effluent BI ENG - COMPONENT DESIGN BASES INSPECTION 7 06/13/2011 07/15/2011 IP 2515/177 Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 06/13/2011 07/15/2011 IP 7111121 Component Design Bases Inspection BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 06/13/2011 06/16/2011 IP 71124.02 Occupational ALARA Planning and Controls BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 07/25/2011 07/29/2011 IP 71124.02 Occupational ALARA Planning and Controls 07/25/2011 07/29/2011 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 07/25/2011 07/29/2011 IP 71151-OR01 Occupational Exposure Control Effectiveness ISFSI - ISFSI INSPECTION - SCHEDULE DEPENEDENT 2 09/01/2011 10/31/2011 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 10/31/2011 11/04/2011 IP 71124.01 Radiological Hazard Assessment and Exposure Controls BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 01/23/2012 01/27/2012 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 01/23/2012 01/27/2012 IP 71124.04 Occupational Dose Assessment BI OL - BIENNIAL REQUAL PROGRAM INSPECTION 2 02/20/2012 02/24/2012 IP 7111111B Licensed Operator Requalification Program BI ENG - INSERVICE INSPECTION 1 04/08/2012 05/13/2012 IP 7111108P Inservice Inspection Activities - PWR BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 04/16/2012 04/20/2012 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 04/16/2012 04/20/2012 IP 71124.02 Occupational ALARA Planning and Controls OL PREP - PALISADES INIT PREP - JUNE 2012 3 06/04/2012 06/08/2012 W90246 OL - INITIAL EXAM - JUNE 2012 - PALI

Palisades Inspection / Activity Plan 03/01/2011 - 06/30/2012 Planned Dates No. of Staff Start End Inspection Activity Title on Site OL EXAM - PALISADES INIT EXAM - JUNE 2012 3 06/25/2012 07/06/2012 W90246 OL - INITIAL EXAM - JUNE 2012 - PALI

T. Kirwin In addition to the ROP baseline, inspections are planned for Temporary Instruction 2515/179, Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in National Source Tracking System, Inspection Procedure 71003, Post-Approval Site Inspection for License Renewal, and also Independent Spent Fuel Storage Installation (ISFSI) Inspection Procedure 60855.1, Operation of an ISFSI at Operating Plants.

In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 630/829-9619 with any questions you have regarding this letter.

Sincerely,

/RA/

Steven West, Director Division of Reactor Projects Docket No. 50-255;72-007 License No. DPR-20

Enclosure:

Palisades Inspection/Activity Plan cc w/encl: Distribution via ListServ DOCUMENT NAME: G:\DRPIII\1-Secy\1-Work In Progress\2010 EOC Letters\Palisades 2010 Annual Assessment Letter.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII NAME RLerch:dtp JGiessner*RL for SWest DATE 03/03/11 03/03/11 03/03/11 OFFICIAL RECORD COPY

Letter to T. Kirwin from S. West dated March 4, 2011.

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR PALISADES NUCLEAR PLANT (REPORT 05000255/2011001)

DISTRIBUTION:

Daniel Merzke RidsNrrPMPalisades Resource RidsNrrDorlLpl3-1 Resource RidsNrrDirsIrib Resource Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPassessment Resource