Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection; Inspection Report 05000255/2022010
ML21327A296
Person / Time
Site: Palisades Entergy icon.png
Issue date: 11/23/2021
From: Mel Holmberg
NRC/RGN-III/DRS/EB1
To: Corbin D
Entergy Nuclear Operations
References
IR 2022010
Download: ML21327A296 (7)


See also: IR 05000255/2022010

Text

Mr. Darrell Corbin

Vice President, Operations

Entergy Nuclear Operations, Inc.

Palisades Nuclear Plant

27780 Blue Star Memorial Highway

Covert, MI 49043-9530

SUBJECT: PALISADES NUCLEAR PLANT INFORMATION REQUEST FOR NRC TRIENNIAL

EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS (50.59) BASELINE

INSPECTION; INSPECTION REPORT 05000255/2022010

Dear Mr. Corbin:

On February 28, 2022, the U.S. Nuclear Regulatory Commission (NRC) will begin a

10 CFR 50.59 Baseline Inspection at the Palisades Nuclear Plant. This inspection will be

performed in accordance with the NRC Baseline Inspection Procedure 71111.17T. The onsite

portion of the inspection will take place on February 28, 2022 - March 4, 2022.

Experience has shown that these baseline inspections are extremely resource intensive, both

for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on the

site and to ensure a productive inspection for both parties, we have enclosed a request for

documents needed for the inspection. These documents have been divided into three groups.

The first group of information is necessary to ensure that the inspection team is adequately

prepared for the inspection. This information should be made available via compact disc

and delivered to the regional office no later than February 8, 2022. The inspection team will

review this information and, by February 16, 2022, will request specific items that should be

provided for review in the regional office by February 22, 2022.

The second group of requested documents contains additional items that the team will

review, or need access to, during the inspection. Certain documents contained within

Group II (i.e., Item (1)), will be requested for review in the regional office prior to the

inspection by February 8, 2022, as identified above. The remaining documents should be

available by the first day of the onsite inspection, February 28, 2022.

The third group lists information necessary to aid the inspection team in tracking issues

identified as a result of the inspection. It is requested that this information be provided to the

lead inspector as the information is generated during the inspection. It is important that all

of these documents are up to date and complete in order to minimize the number of

additional documents requested during the preparation and/or the onsite portions of the

inspection.

November 23, 2021

D. Corbin

-2-

The lead inspector for this inspection is Mr. M. Holmberg. We understand that our regulatory

contact for this inspection is Ms. M. Peak of your organization. If there are any questions about

the inspection or the material requested, please contact the lead inspector at 630-829-9748 or

via e-mail at msh@nrc.gov.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget,

Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not

required to respond to, a request for information or an information collection requirement

unless the requesting document displays a currently valid Office of Management and Budget

Control Number.

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

Mel Holmberg, Reactor Inspector

Engineering Branch 1

Division of Reactor Safety

Docket No. 50-255

License No. DPR-20

Enclosure:

Modification and 50.59 Inspection

Document Request

cc: Distribution via LISTSERV

Signed by Holmberg, Melvin

on 11/23/21

D. Corbin

-3-

Letter to Darrell Corbin from Mel Holmberg dated November 23, 2021.

SUBJECT: PALISADES NUCLEAR PLANT INFORMATION REQUEST FOR NRC TRIENNIAL

EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS (50.59) BASELINE

INSPECTION; INSPECTION REPORT 05000255/2022010

DISTRIBUTION:

Jessie Quichocho

Robert Williams

RidsNrrPMPalisades Resource

RidsNrrDorlLpl3

RidsNrrDroIrib Resource

John Giessner

Mohammed Shuaibi

Jamnes Cameron

Shelbie Lewman

Allan Barker

DRPIII

DRSIII

ADAMS Accession Number: ML21327A296

Publicly Available

Non-Publicly Available

Sensitive

Non-Sensitive

OFFICE

RIII

NAME

MHolmberg:mb

DATE

11/23/2021

OFFICIAL RECORD COPY

Enclosure

MODIFICATION AND 50.59 INSPECTION DOCUMENT REQUEST

Inspection Report: 05000255/2022010

Inspection Dates:

February 28, 2022 - March 4, 2022

Inspection Procedure:

IP 71111.17T, Evaluations of Changes, Tests, and Experiments

Lead Inspector:

Mel Holmberg

630-829-9748

msh@nrc.gov

I.

Information Requested for In-Office Preparation Week

The following information is requested by February 8, 2022, or sooner, to facilitate the

selection of specific items that will be reviewed during the onsite inspection week. The

inspection team will select specific items from the information requested below and

submit a list to your staff by February 16, 2022. We will request that certain items be

made available to the regional office prior to the inspection by February 22, 2022. We

request that the remaining items selected from the lists be available and ready for review

on the first day of inspection. All requested information should identify the associated

system and cover the time frame from the receipt of information for the last MOD/50.59

inspection to the present.

The required information identified below should be provided on compact disc (CD) or

online data base accessible for inspectors (e.g., Sharefile, Certrec). Please provide

three copies of each CD submitted (i.e., one for each inspector). The preferred file

format is a searchable pdf file. The CDs should be indexed and hyper-linked to

facilitate ease of use, if possible. If you have any questions regarding this information,

please call the inspection team leader as soon as possible.

1.

List of all Title 10 of the Code of Federal Regulations (CFR), Part 50.59 completed

evaluations involving (a) calculations, (b) procedure revisions, (c) changes to the

facility (modifications), (d) non-routine operating configurations, or (e) departures in

methods of analyses. This list should include 50.59 evaluations for the following:

a.

Changes that have been made under the provisions of 10 CFR 50.59 that have

been updated in accordance with 10 CFR 50.71(e)(4) since the last MOD/50.59

inspection;

b.

Modifications that are field work complete; and

c.

Changes to calculations (or initiation of new calculations) that have been issued.

The list should contain the number and title of each document, a brief description

of the change, and the corresponding number and type of the affected document

2

(i.e., the modification or procedure to which the evaluation applies). The list

should NOT include any evaluations in which prior U. S. Nuclear Regulatory

Commission approval was sought and obtained.

2.

A list of all 10 CFR 50.59 changes that have been screened out as not requiring a full

evaluation involving: (a) calculations; (b) procedure revisions; (c) changes to the

facility (modifications); (d) non-routine operating configurations; or (e) departures in

methods of analyses.

The list should contain the number and title of each document, and the

corresponding number and type of the affected document (i.e., the modification or

procedure to which the evaluation applies).

3.

A list of any modifications, procedure revisions, or Updated Final Safety Analysis

Report (UFSAR) changes where it was determined that 10 CFR 50.59 did not apply.

4.

A list of calculation changes that have been issued for use.

5.

A list of corrective action documents (open and closed) that address 10 CFR 50.59

issues, concerns, or processes. These documents should also include the corrective

action documents associated with the modification and the 50.59 change

implementation.

The list should contain the number, title and revision (or date) of each document, the

affected system and corresponding documentation (if applicable) and should be

sorted in order of significance.

6.

Copies of procedures addressing the following: modifications, design changes, set

point changes, equivalency evaluations or suitability analyses, commercial grade

dedications, post-modification testing, 10 CFR 50.59 evaluations and screenings,

and UFSAR updates.

7.

UFSAR updates submitted in accordance with 10 CFR 50.71(e)(4). Provide copies

of the complete submittal.

8.

Copy of the UFSAR change log or a synopsis of the changes. This should include all

of the changes made to the UFSAR that were incorporated in the last

10 CFR 50.71(e)(4) submittal.

9.

Electronic copy of the UFSAR and technical specifications, if available.

10. Name(s) and phone numbers for the regulatory and technical contacts.

11. Current management and engineering organizational chart.

II.

Information Requested to Be Available Prior to Inspection. Requests Will Be Made

for Specific Item (1) Documents by February 16, 2022, for Availability of Requested

Item (1) Documents in Regional Office by February 22, 2022, and Items (2), (3) and

(4) Documents on First Day of Inspection (February 28, 2022).

1.

Copies of all selected items from Section I. This includes copies of associated

3

documents such as calculations, modification packages (including description),

10 CFR 50.59 evaluations or screenings, and any corrective action documents.

2.

Copies of these documents do not need to be solely available to the inspection team

as long as the inspectors have easy and unrestrained access to them.

a.

UFSAR, if not previously provided;

b.

Original Final Safety Analysis Report Volumes;

c.

Original Safety Evaluation Report and Supplements;

d.

Final Safety Analysis Report Question and Answers;

e.

Quality Assurance Plan;

f.

Technical Specifications, if not previously provided;

g.

Latest Individual Plant Examination/Probabilistic Risk Assessment Report;

h.

Vendor Manuals; and

i.

The latest 10 CFR 50.59 UFSAR Update Submittal.

3.

Please ensure that other supporting documents for the selected items have been

located and are readily retrievable as the inspection team will likely be requesting

these documents during the inspection. Examples of supporting documents are:

a.

Drawings supporting the modifications;

b.

Procedures affected by the modifications; and

c.

UFSAR change papers generated due to a 10 CFR 50.59 evaluation.

4.

Assessment and Corrective Actions:

a.

The most recent 50.59 Quality Assurance audit and/or self-assessment; and

b.

Corrective action documents (e.g., condition reports, including status of

corrective actions) generated as a result of the most recent 50.59

Quality Assurance audit and/or self-assessment.

III.

Information Requested to Be Provided Throughout the Inspection

1.

Copies of any corrective action documents generated as a result of the

inspection teams questions or queries during this inspection.

2.

Copies of the list of questions submitted by the inspection team members and the

status/resolution of the information requested (provide daily during the inspection

to each inspection team member).

4

If you have any questions regarding the information requested, please contact the inspection

team leader.