Ltr. 08/28/15 Palisades Nuclear Plant - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information Inspection Report 05000255/2015004 (Axd)
ML15240A344
Person / Time
Site: Palisades Entergy icon.png
Issue date: 08/28/2015
From: Christine Lipa
Division of Reactor Safety III
To: Vitale A
Entergy Nuclear Operations
References
IR 2015004
Download: ML15240A344 (8)


See also: IR 05000255/2015004

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, IL 60532-4352

August 28, 2015

Mr. Anthony Vitale

Vice President, Operations

Entergy Nuclear Operations, Inc.

Palisades Nuclear Plant

27780 Blue Star Memorial Highway

Covert, MI 49043-9530

SUBJECT: PALISADES NUCLEAR PLANT - NOTIFICATION OF AN NRC TRIENNIAL

HEAT SINK PERFORMANCE INSPECTION AND REQUEST FOR INFORMATION

INSPECTION REPORT 05000255/2015004

Dear Mr. Vitale:

On November 16, 2015, the U.S. Nuclear Regulatory Commission (NRC) will begin the onsite

portion of the Triennial Heat Sink Performance Inspection at your Palisades Nuclear Plant. This

inspection will be performed in accordance with NRC baseline Inspection procedure 71111.07.

In order to minimize the impact that the inspection has on the site and to ensure a productive

inspection, we have enclosed a request for documents needed for the inspection. The

documents have been divided into three groups.

The first group lists information necessary for our initial inspection scoping activities. This

information should be available to the lead inspector no later than October 1, 2015. By

October 13, 2015, the inspector will communicate the initial selected set of approximately

2-3 risk-significant heat exchangers.

The second group is needed to support our in-office preparation activities. This set of

documents, including the calculations associated with the selected heat exchangers, should

be available at the Regional Office no later than November 5, 2015. This information should

be separated for each selected component, especially if provided electronically (e.g., folder

with component name that includes calculations, condition reports, maintenance history, etc.).

During the in-office preparation activities, the inspector may identify additional information

needed to support the inspection.

The last group includes the additional information above as well as plant specific reference

material. This information should be available onsite to the inspector on November 16, 2015.

It is also requested that corrective action documents and/or questions developed during the

inspection be provided to the inspector as the documents are generated.

All requested documents are to be for the time period from the onsite inspection period back

to the documents that were provided in response to the previous Heat Sink Performance

Inspection. If no activities were accomplished in that time period, then the request applies to

the last applicable document in the previous time period. It is important that these documents

be as complete as possible, in order to minimize the number of documents requested during

the preparation week or during the onsite inspection.

A. Vitale

-2-

The lead inspector for this inspection is Mr. Jorge Corujo-Sandin. We understand that

our regulatory contact for this inspection is Ms. Barbara Dotson of your organization. If

there are questions about the material requested, or the inspection, please call Mr. Jorge

Corujo-Sandin at (630) 829-9741. Please send the information to the following e-mail

address Jorge.Corujo-Sandin@nrc.gov. A hard-copy with the required information is also

an acceptable option.

This letter does not contain new or amended information collection requirements subject to

the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, Control

Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget Control

Number.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public

Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy

of this letter, its enclosure, and your response (if any) will be available electronically for public

inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)

component of the NRC's Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html

(the Public Electronic Reading Room).

Sincerely,

/RA/

Christine A. Lipa, Chief

Engineering Branch 2

Division of Reactor Safety

Docket Nos. 50-255

License No. DPR-20

Enclosure:

Triennial Heat Sink Performance Inspection Document Request

cc w/encl: Distribution via LISTSERV

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

Enclosure

Inspection Report: 05000255/2015004

Inspection Dates:

November 16 - 20, 2015

Inspection Procedure:

IP 71111.07, Heat Sink Performance

Lead Inspector:

Jorge Corujo-Sandin

(630) 829-9741

Jorge.Corujo-Sandin@nrc.gov

I.

Information Requested By October 1, 2015

1. List of the Generic Letter (GL) 89-13, Service Water System Problems Affecting

Safety-Related Equipment, heat exchangers in order of risk significance.

2. Copy of heat exchanger performance trending data tracked for each GL 89-13 heat

exchanger.

3. List of the Corrective Action Program documents (with a short description)

associated with GL 89-13 heat exchangers, heat sinks, silting, corrosion, fouling,

or heat exchanger testing, for the previous 3 years, or since the last Corrective

Action Program document list was sent to the NRC for the previous Heat Sink

Performance Inspection. The list should include all the Corrective Action Program

documents not on the last Corrective Action Program document list.

4. Copy of any self-assessment done on any of GL 89-13 heat exchangers.

5. Last two System Health Report(s) and maintenance rule system notebooks for all

the GL 89-13 heat exchangers.

6. List of engineering-related operator workarounds (with a short description)

associated with GL 89-13 heat exchangers. The requested documents are to be

for the time period from the onsite inspection period back to the documents that

were provided in response to the previous Heat Sink Performance Inspection.

7. List of permanent and temporary modifications (with a short description) associated

with GL 89-13 heat exchangers. The requested documents are to be for the time

period from the onsite inspection period back to the documents that were provided

in response to the previous Heat Sink Performance Inspection.

II.

Information Requested By November 5, 2015

1. Copies of the GL 89-13 responses.

2. Copy of the Updated Final Safety Analysis Report (UFSAR) section applicable to the

GL 89-13 Heat Exchanger Program.

3. Copies of procedures developed to implement the recommendations of GL 89-13

(e.g., the GL 89-13 Heat Exchanger Program description).

4. Copies of the selected Corrective Action Program documents.

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

2

5. For the specific heat exchangers selected:

a. Copies of the UFSAR sections applicable for each heat exchanger.

b. Copy of system description and design basis document for the heat exchangers

(as applicable).

c. Provide a list of calculations (with a short description) which currently apply to

each heat exchanger.

i.

establish the limiting design basis heat load required to be removed by each

of these heat exchangers;

ii.

demonstrate the heat exchangers capacity to remove the limiting heat load;

iii.

correlate surveillance testing and/or inspection results from these heat

exchangers with design basis heat removal capability (e.g., basis for

surveillance test and/or inspection acceptance criteria);

iv.

evaluate the potential for water hammer in each heat exchanger or

associated piping; and

v.

evaluate excessive tube vibration in each heat exchanger.

d. Copy of any operability determinations or other documentation of degradation

associated with the heat exchangers or the systems that support the operation

for the selected heat exchangers.

e. Copy of the construction code, Design Specification, heat exchanger data

sheets, and vendor documents including component drawings applicable for the

heat exchangers.

f. Copies of normal, abnormal, and emergency operating procedures associated

with the selected heat exchangers.

6. For the ultimate heat sink (UHS) and the safety-related service water system (or

equivalent):

a. Copies of the applicable UFSAR sections.

b. Copy of system description and design basis document (as applicable).

c. Copy of any operability determinations or other documentation of degradation

associated with the UHS and the safety-related service water system.

d. Copy of the document (e.g., UFSAR or Technical Requirements Manual) that

states the maximum cooling water system inlet temperature limit that still allows

full licensed power operation of the nuclear reactor.

e. Copy of system description and design basis document (as applicable).

f. Copy of the construction code and Design Specification.

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

3

g. Copies of normal, abnormal, and emergency operating procedures associated

with the UHS and safety-related service water systems including procedures for

loss of these systems.

h. Copy of any operability determinations or other documentation of degradation

associated with the UHS, and the safety-related service water system.

i.

Copies of corrective action documents associated with waterhammer or hydraulic

transients in the service water system since the last Heat Sink Inspection.

j.

If available, provide an electronic copy of piping and instrumentation diagrams for

the service water system, including the intake structure.

k. Provide a list of calculations (with a short description), which currently apply to

UHS and service water system.

l.

Provide a list of instruments (with a short description) associated with automatic

or alarm functions for the safety-related service water system and/or UHS.

m. Provide a list of any design change (with a short description) performed on the

UHS or safety-related service water system since the last Heat Sink Performance

Inspection.

7. A schedule of all inspections, cleanings, maintenance, or testing of any

safety-related plant heat exchanger to be performed during the on-site portion of the

inspection.

III.

Information Requested to be Available on First Day of Inspection,

November 16, 2015

1. For the specific heat exchangers selected. :

a. Copy of the calculation which correlates surveillance testing results from these

heat exchangers with design basis heat removal capability (e.g., basis for

surveillance test acceptance criteria).

b. Copies of the two most recent completed tests and evaluation data confirming

thermal performance for those heat exchangers which are performance tested.

c. Documentation and procedures that identify the types, accuracy, and location of

any special instrumentation used for the two most recently completed thermal

performance tests for the heat exchangers (e.g., high accuracy ultrasonic flow

instruments or temperature instruments). Include calibration records for the

instruments used during these tests.

d. Information regarding any alarms which monitor on-line performance.

e. Copy of the document describing the inspection results of each heat exchanger.

The requested documents are to be for the time period from the onsite inspection

period back to the documents that were provided in response to the previous

Heat Sink Performance Inspection.

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

4

f.

The cleaning and inspection maintenance schedule for each heat exchanger for

the next 5 years.

g. Copy of the design specification and heat exchanger data sheets for each heat

exchanger.

h. Copy of the vendor manuals including component drawings for each heat

exchanger.

i.

Copy of the calculation which establishes the limiting (maximum) design basis

heat load which is required to be removed by each of these heat exchangers.

j.

Copy of the operating procedure that ensures that the maximum cooling water

system inlet temperature limit is not exceeded.

k.

Copy of the calculations or documents which evaluate the potential for water

hammer in each heat exchanger or associated piping.

l.

Copy of the calculations that evaluate excessive tube vibration in each heat

exchanger and the documents that describe the controls that prevent heat

exchanger degradation due to excessive flow induced vibration during operation.

m. Copy of the periodic flow testing at or near maximum design flow. The requested

documents are to be for the time period from the onsite inspection period back to

the documents that were provided in response to the previous Heat Sink

Performance Inspection.

n. Copy of the document which identifies the current number of tubes in service for

each heat exchanger and the supporting calculation which establishes the

maximum number of tubes which can be plugged in each heat exchanger.

o. Copy of the document establishing the repair criteria (plugging limit) for degraded

tubes which are identified in each heat exchanger.

p. Copies of the documents that verify the structural integrity of the heat exchanger

(e.g., eddy current summary sheets, ultrasonic testing results, and visual

inspection results).

q. Copies of those documents that describe the methods taken to control water

chemistry in the heat exchangers.

2. For the review of the operation of the safety-related service water system (or

equivalent) and the UHS :

a. Copies of any design change performed on the UHS. The requested

documents are to be for the time period from the onsite inspection period back

to the documents that were provided in response to the previous Heat Sink

Performance Inspection.

b. Copies of any design change performed on the safety-related service water

system. The requested documents are to be for the time period from the onsite

inspection period back to the documents that were provided in response to the

previous Heat Sink Performance Inspection.

TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST

5

c.

Copies of procedures for a loss of UHS.

d. Copies of procedures for a loss of service water system.

e. Inspections and/or maintenance related to preventing macrofouling (e.g., silt,

dead mussel shells, or debris) and biotic fouling (e.g., fish, algae, grass, or kelp).

The requested documents are to be for the time period from the onsite inspection

period back to the documents that were provided in response to the previous

Heat Sink Performance Inspection.

f.

Copies of chemistry procedures that monitor for pH, calcium hardness, etc. Also,

provide copies of the associated results. The requested documents are to be for

the time period from the onsite inspection period back to the documents that

were provided in response to the previous Heat Sink Performance Inspection.

g. Copies of documents associated with the monitoring of pump performance for

potential strong-pump vs. weak-pump interaction.

3. For the review associated with the system walkdown of the service water intake

structure :

a. Copies of corrective maintenance for the last 6 years associated with

service water strainers, traveling screens and trash racks. Copies of the last

2 inspections and/or surveillances associated with service water strainers,

traveling screens and trash racks. List of preventive maintenance, including

frequency, associated with service water strainers, traveling screens and trash

racks.

b. Copies of abnormal procedures for the traveling screens and service water

strainers.

c.

Copies of the last two inspections and/or surveillances documenting that

component mounts have not excessively degraded (i.e., due to corrosion).

For example, inspections for the mounts for the service water pumps, service

water strainers, traveling screens and trash racks. Copies of the documents

associated with the monitoring, trending, and remediation of silt accumulation

at the service water pump bay.

d. Copies of surveillance procedures and testing results performed on the service

water pump bay water level instruments. The requested documents are to be for

the time period from the onsite inspection period back to the documents that

were provided in response to the previous Heat Sink Performance Inspection.

e. Copies of procedures associated with operating during adverse weather

conditions (e.g., icing, high temperatures, or low level).

f.

Copy of the evaluation for the potential effects of low flow/level on underwater

weir walls intended to limit silt or sand intake, if applicable.

If the information requested above will not be available, please contact Mr. Jorge Corujo-Sandin

as soon as possible at (630) 829-9741, or email Jorge.Corujo-Sandin@nrc.gov.

A. Vitale

-2-

The lead inspector for this inspection is Mr. Jorge Corujo-Sandin. We understand that our regulatory

contact for this inspection is Ms. Barbara Dotson of your organization. If there are questions about the

material requested, or the inspection, please call Mr. Jorge Corujo-Sandin at (630) 829-9741. Please

send the information to the following e-mail address Jorge.Corujo-Sandin@nrc.gov. A hard-copy with the

required information is also an acceptable option.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements

were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not

conduct or sponsor, and a person is not required to respond to, a request for information or an

information collection requirement unless the requesting document displays a currently valid Office of

Management and Budget Control Number.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections,

Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the NRCs

Public Document Room or from the Publicly Available Records (PARS) component of the NRC's

Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the

NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Christine A. Lipa, Chief

Engineering Branch 2

Division of Reactor Safety

Docket Nos. 50-255

License No. DPR-20

Enclosure:

Triennial Heat Sink Performance Inspection Document Request

cc w/encl: Distribution via LISTSERV

DISTRIBUTION:

Kimyata MorganButler

RidsNrrPMPalisades Resource

RidsNrrDorlLpl3-1 Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Darrell Roberts

Richard Skokowski

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

Jim Clay

Carmen Olteanu

ADAMS Accession Number ML15240A344

Publicly Available

Non-Publicly Available

Sensitive

Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE

RIII

RIII

RIII

RIII

NAME

GODwyer for JCorujo-Sandin:cl

CLipa

DATE

08/28/15

08/28/15

OFFICIAL RECORD COPY