MONTHYEARIR 05000334/20240042025-02-12012 February 2025 Integrated Inspection Report 05000334/2024004 and 05000412/2024004 IR 05000412/20243012024-12-0202 December 2024 Initial Operator Licensing Examination Report 05000412/2024301 IR 05000334/20244032024-11-13013 November 2024 Cybersecurity Problem Identification and Resolution Inspection Report 05000334/2024403 and 05000412/2024403 (Cover Letter Only) IR 05000334/20240032024-11-13013 November 2024 Integrated Inspection Report 05000334/2024003 & 05000412/2024003 IR 05000334/20240112024-10-17017 October 2024 License Renewal Phase IV Inspection Report 05000334/2024011 IR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) IR 05000334/20244022024-08-22022 August 2024 Security Baseline Inspection Report 05000334/2024402 and 05000412/2024402 (Cover Letter Only) IR 05000334/20240102024-08-20020 August 2024 Comprehensive Engineering Team Inspection - Inspection Report 05000334/2024010 and 05000412/2024010 IR 05000334/20240022024-08-0505 August 2024 Integrated Inspection Report 05000334/2024002 and 05000412/2024002 IR 05000334/20245012024-07-0808 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2024501 and 05000412/2024501 IR 05000334/20244012024-06-26026 June 2024 Material Control and Accounting Program Inspection Report 05000334/2024401 and 05000412/2024401 (Cover Letter Only) ML24135A1702024-05-29029 May 2024 – Steam Generator Tube Inspection - Review of the Spring 2023 Tube Inspection Reports ML24135A2282024-05-29029 May 2024 Review of the Spring 2023 Outage Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F Star Reports IR 05000334/20240012024-05-0808 May 2024 Integrated Inspection Report 05000334/2024001 and 05000412/2024001 IR 05000334/20230062024-02-28028 February 2024 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2023006 and 05000412/2023006) IR 05000334/20230042024-02-12012 February 2024 Integrated Inspection Report 05000334/2023004 and 05000412/2023004 IR 05000334/20230112023-12-0404 December 2023 Age-Related Degradation Inspection Report 05000334/2023011 and 05000412/2023011 IR 05000334/20233012023-11-27027 November 2023 Initial Operator Licensing Examination Report 05000334/2023301 IR 05000334/20230032023-11-0606 November 2023 Integrated Inspection Report 05000334/2023003 and 05000412/2023003 IR 05000334/20234022023-09-29029 September 2023 Security Baseline Inspection Report 05000334/2023402 and 05000412/2023402 (Cover Letter Only) IR 05000334/20234012023-09-21021 September 2023 Cybersecurity Inspection Report 05000334/2023401 and 05000412/2023401 (Cover Letter Only) ML23243A9272023-09-19019 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report IR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) IR 05000334/20230022023-08-0909 August 2023 Integrated Inspection Report 05000334/2023002 and 05000412/2023002 ML23157A1072023-06-0707 June 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000334/2023011 and 05000412/2023011 IR 05000334/20230012023-05-0808 May 2023 Integrated Inspection Report 05000334/2023001 and 05000412/2023001 L-23-058, 180-Day Steam Generator Tube Inspection Report2023-03-27027 March 2023 180-Day Steam Generator Tube Inspection Report IR 05000334/20230102023-03-0808 March 2023 Biennial Problem Identification and Resolution Inspection Report 05000334/2023010 05000412/2023010 IR 05000334/20220062023-03-0101 March 2023 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2022006 and 05000412/2022006) IR 05000334/20220042023-02-0909 February 2023 Integrated Inspection Report 05000334/2022004 and 05000412/2022004 IR 05000334/20224012023-01-0909 January 2023 Security Baseline Inspection Report 05000334/2022401 and 05000412/2022401 (Cover Letter Only) ML22314A2682022-12-16016 December 2022 – Review of the Fall 2021 2R22 Steam Generator Tube Inspection 180 Day Report IR 05000334/20220032022-11-10010 November 2022 Integrated Inspection Report 05000334/2022003 and 05000412/2022003 and Independent Spent Fuel Storage Installation Inspection Report 07201043/2022001 IR 05000334/20220052022-08-31031 August 2022 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2022005 and 05000412/2022005) IR 05000334/20220022022-08-12012 August 2022 Integrated Inspection Report 05000334/2022002 and 05000412/2022002 IR 05000334/20224022022-08-12012 August 2022 Cyber Security Problem Identification and Resolution Inspection Report 05000334/2022402 and 05000412/2022402 (Cover Letter Only) IR 05000334/20225012022-06-29029 June 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2022501 and 05000412/2022501 IR 05000334/20220112022-06-29029 June 2022 Temporary Instruction 2515/194 Inspection Report 05000334/2022011 and 05000412/2022011 IR 05000412/20223012022-06-14014 June 2022 Initial Operator Licensing Examination Report 05000412/2022301 IR 05000334/20220102022-05-12012 May 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000334/2022010 and 05000412/2022010 IR 05000334/20224202022-05-11011 May 2022 Security Baseline Inspection Report 05000334/2022420 and 05000412/2022420 - Cover Letter IR 05000334/20220012022-05-10010 May 2022 Integrated Inspection Report 05000334/2022001 and 05000412/2022001 IR 05000334/20210062022-03-0202 March 2022 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2021006 and 05000412/2021006) IR 05000334/20210042022-02-14014 February 2022 Integrated Inspection Report 05000334/2021004 and 05000412/2021004 L-22-054, Steam Generator Inspection Report- Fall 2021 Refueling Outage2022-02-10010 February 2022 Steam Generator Inspection Report- Fall 2021 Refueling Outage IR 05000334/20210032021-11-0909 November 2021 Integrated Inspection Report 05000334/2021003 and 05000412/2021003 IR 05000334/20210112021-10-19019 October 2021 Temporary Instruction 2515/194 Inspection Report 05000334/2021011 and 05000412/2021011 IR 05000334/20210102021-09-29029 September 2021 Triennial Fire Protection Inspection Report 05000334/2021010 and 05000412/2021010 IR 05000334/20210052021-09-0101 September 2021 Updated Inspection Plan for the Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2021005 and 05000412/2021005) IR 05000334/20214022021-08-18018 August 2021 Security Baseline Inspection Report 05000334/2021402 and 05000412/2021402 2025-02-12
[Table view] Category:Letter
MONTHYEARL-25-049, Submittal of Report of Facility Changes, Tests and Experiments2025-02-24024 February 2025 Submittal of Report of Facility Changes, Tests and Experiments ML25050A0422025-02-14014 February 2025 57484-EN 57484 - Final Report Notification Pursuant to 10 CFR 21.21 Regarding Limitorque SMB-00 Torque Switch Assemblies IR 05000334/20240042025-02-12012 February 2025 Integrated Inspection Report 05000334/2024004 and 05000412/2024004 ML25031A3192025-01-31031 January 2025 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000334/2025010 and 05000412/2025010 ML25029A0872025-01-29029 January 2025 Senior Reactor and Reactor Operator Initial License Examinations L-25-025, Supplement to 10 CFR 50.55a Request BV-ISI-2025-01, Quench Spray Pinhole Leak2025-01-18018 January 2025 Supplement to 10 CFR 50.55a Request BV-ISI-2025-01, Quench Spray Pinhole Leak L-25-024, 10 CFR 50.55a Request BV-ISI-2025-01, Quench Spray Pinhole Leak2025-01-17017 January 2025 10 CFR 50.55a Request BV-ISI-2025-01, Quench Spray Pinhole Leak L-24-275, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-12-19019 December 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24351A1462024-12-16016 December 2024 Notification of Conduct of a Fire Protection Team Inspection IR 05000412/20243012024-12-0202 December 2024 Initial Operator Licensing Examination Report 05000412/2024301 L-24-262, Submittal of October 2024 NPDES Discharge Monitoring Report (NPDES) Permit No. PA00256152024-11-20020 November 2024 Submittal of October 2024 NPDES Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-254, Cycle 25 Core Operating Limits Report2024-11-15015 November 2024 Cycle 25 Core Operating Limits Report IR 05000334/20240032024-11-13013 November 2024 Integrated Inspection Report 05000334/2024003 & 05000412/2024003 IR 05000334/20244032024-11-13013 November 2024 Cybersecurity Problem Identification and Resolution Inspection Report 05000334/2024403 and 05000412/2024403 (Cover Letter Only) L-24-246, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-10-21021 October 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20240112024-10-17017 October 2024 License Renewal Phase IV Inspection Report 05000334/2024011 ML24338A0242024-10-0303 October 2024 MPR Associates, Inc. - Report in Accordance with 10 CFR Part 21 L-24-223, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-09-26026 September 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter L-24-015, Twenty-Ninth Refueling Outage Inservice Inspection Summary Report2024-09-17017 September 2024 Twenty-Ninth Refueling Outage Inservice Inspection Summary Report L-24-038, License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References2024-09-17017 September 2024 License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References ML24260A1912024-09-16016 September 2024 Operator Licensing Examination Approval IR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 IR 05000334/20244022024-08-22022 August 2024 Security Baseline Inspection Report 05000334/2024402 and 05000412/2024402 (Cover Letter Only) L-24-199, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-08-22022 August 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20240102024-08-20020 August 2024 Comprehensive Engineering Team Inspection - Inspection Report 05000334/2024010 and 05000412/2024010 L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000334/20240022024-08-0505 August 2024 Integrated Inspection Report 05000334/2024002 and 05000412/2024002 ML24208A0462024-07-26026 July 2024 NRC Office of Investigations Case No. 1-2023-005 L-24-182, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-23023 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-161, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-19019 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 05000334/LER-2024-004, Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control2024-07-17017 July 2024 Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control L-24-014, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models2024-07-16016 July 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models ML24193A2912024-07-16016 July 2024 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule IR 05000334/20245012024-07-0808 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2024501 and 05000412/2024501 05000334/LER-2024-003, Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping2024-07-0202 July 2024 Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping L-24-164, BV-2, Post Accident Monitor Report2024-06-27027 June 2024 BV-2, Post Accident Monitor Report IR 05000334/20244012024-06-26026 June 2024 Material Control and Accounting Program Inspection Report 05000334/2024401 and 05000412/2024401 (Cover Letter Only) L-24-094, Reactor Vessel Surveillance Capsule Withdrawal Schedule2024-06-24024 June 2024 Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-152, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-06-17017 June 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations 05000334/LER-2024-002, Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation2024-06-11011 June 2024 Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation 05000334/LER-2024-001, Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification2024-06-0606 June 2024 Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification ML24135A1702024-05-29029 May 2024 – Steam Generator Tube Inspection - Review of the Spring 2023 Tube Inspection Reports ML24135A2282024-05-29029 May 2024 Review of the Spring 2023 Outage Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F Star Reports L-24-121, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-05-23023 May 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-021, Cycle 30 Core Operating Limits Report2024-05-23023 May 2024 Cycle 30 Core Operating Limits Report ML24141A1052024-05-20020 May 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24136A0622024-05-15015 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000334/2024010 and 05000412/2024010 L-24-107, CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair2024-05-13013 May 2024 CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair 2025-02-24
[Table view] |
Text
May 17, 2016
SUBJECT:
BEAVER VALLEY POWER STATION, UNITS 1 AND 2 - NRC SECURITY INSPECTION REPORT 05000334/2016201 AND 05000412/2016201
Dear Mr. Larson:
On March, 24, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your Beaver Valley Power Station, Units 1 and 2. On April 7, 2016, the NRC inspectors discussed results of this inspection with Mr. William Willis, Site Security Manager, and other members of your staff. Inspectors documented the results of this inspection in the enclosed inspection report.
NRC inspectors documented three findings of very low security significance (Green) and one unresolved item (URI) in this report. These findings involved violations of NRC requirements.
The NRC is treating these violations as non-cited violations (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.
If you contest these violations or the significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S.
Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator Region I; the Director, Office of Nuclear Security and Incident Response, the Director, Office of Enforcement, and the NRC resident inspector at the Beaver Valley Power Station, Units 1 and 2.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region I, the Director, Office of Nuclear Security and Incident Response and the NRC resident inspector at the Beaver Valley Power Station, Units 1 and 2. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
The material enclosed herewith contains Safeguards Information as defined by 10 CFR 73.21, Protection of Safeguards Information; Performance Requirements, and its disclosure to unauthorized individuals is prohibited by Section 147 of the Atomic Energy Act of 1954, as amended. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, if Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information - Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii),
the NRC is waiving the affidavit requirements for your response.
Sincerely,
/RA/
Robert C. Johnson, Chief Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response
Docket Nos. 50-334, and 50-412 License Nos. DPR-66, and NPF-73
Nonpublic Enclosure: Inspection Report 05000334/2016201 and 05000412/2016201 w/Attachment: Supplemental Information
cc w/ enclosure:
William L. Willis, Senior Manager Site Security
cc w/o enclosure:
Samuel L. Belcher, CNO FirstEnergy Nuclear Operating Company
Jason R. Frame, State Liason Officer Designee, West Virginia Michael Bear, State Liason Officer, Ohio
G. Cannon, State Liason Officer, Pennsylvania
ML16111B147
- via email OFFICE NSIR/DSO/SPEB NSIR/DSO/SPEB NSIR/DSO/SPEB RII NSIR/DSO/SPEB NSIR/DSO/SPEB NAME D. Hostetter J. Clark D. Cardenas B. Desai*
J. Willis R.Johnson DATE 04/ 19 /2016 5 /10 /2016 4/ 25 /2016 5/10/2016 4/ 26 /2016 5/ 17 /16