Other: ML12079A036, ML12095A224, ML12095A225, ML12095A226, ML12095A227, ML12095A228, ML12095A229, ML12095A230, ML12095A231, ML12095A251, ML12095A252, ML12095A253, ML12095A254, ML12095A255, ML12095A257, ML12095A258, ML12095A259, ML12095A260, ML12095A274, ML12095A275, ML12095A276, ML12095A347, ML12095A348, ML12095A349, ML12095A350, ML12095A353, ML12095A354, ML12095A370, ML12095A371, ML12095A372, ML12095A373, ML12095A374, ML12095A375, ML12095A376, ML12096A059, ML12096A060, ML12096A061, ML12096A062, ML12096A227, ML12101A089, ML12101A090, ML12101A091, ML12101A092, ML12101A093, ML12101A094, ML12101A095, ML12101A096, ML12101A097, ML12101A098, ML12101A099... further results
|
MONTHYEARML12074A0322012-03-0909 March 2012 G20120172/EDATS: OEDO-2012-0147 - Paul Gunter 2.206 Petition & Letter 2.206 - Fitzpatrick Emergency Enforcement Petitions Project stage: Request ML12079A0362012-03-13013 March 2012 G20120172/EDATS: OEDO-2012-0147 - Paul Gunter E-mail Treatment of FitzPatrick Emergency Enforcement Petition, March 9, 2012 Project stage: Other ML1228303422012-03-13013 March 2012 G20120172, EDATS: OEDO-2012-0147, E-mail to Mr. Gunter to Acknowledge the Receipt of the Petition Project stage: Other ML13017A3552012-03-15015 March 2012 from Bhalchandra Vaida to Joseph Pechacek: Fitzpatrick Emergency Enforcement Project stage: Other ML13162A6312012-03-22022 March 2012 from Andrea Russell to Brice Bickett: Action for Your Review/Comment Project stage: Other ML13022A2922012-03-22022 March 2012 from Andrea Russell to Samson Lee: FYI-G20120172 (Fitzpatrick 2.206): Supplements and New Co-Petitioner Project stage: Other ML1228303322012-03-27027 March 2012 G20120172, EDATS: OEDO-2012-0147, E-mail to Petitioner - Communication of Prb'S Decision on the Request for Immediate Action Project stage: Other ML13162A6322012-03-27027 March 2012 from Andrea Russell to Samson Lee: FYI-G20120172 Project stage: Other ML13162A6332012-03-29029 March 2012 from Brice Bickett to Bhalchandra Vaidya: Re PRB Decision on Request for Immediate Action Project stage: Other ML12095A2272012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12101A1442012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3532012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2252012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML13162A7422012-04-0303 April 2012 from Andrea Russell to Samson Lee: Update-G20120172 Project stage: Other ML12095A3472012-04-0303 April 2012 ME8189 - G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3732012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2602012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2542012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3482012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A2282012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2512012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A2262012-04-0303 April 2012 ME8189 - G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2522012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML13022A2932012-04-0303 April 2012 from Bhalchandra Vaidy to Jessica Azulay: Re PRB Decision Project stage: Other ML12095A3702012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A2572012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3502012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3542012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2582012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3712012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2242012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A3492012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3752012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2552012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A3742012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2592012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2532012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A3762012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A2312012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3722012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2302012-04-0404 April 2012 ME8189 - G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2752012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12096A0612012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12096A2272012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12101A1452012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2742012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12096A0622012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2292012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2762012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12096A0592012-04-0404 April 2012 ME8189 - G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other 2012-03-27
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24277A2972024-10-10010 October 2024 October 2, 2024, Summary of Pre Submittal Public Meeting with Constellation Fitzpatrick, LLC to Discuss Future Amendment on Main Steam Line Radiation Monitor High Radiation System Isolations ML24155A1992024-06-0303 June 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Meeting Summary ML24128A2512024-05-14014 May 2024 Summary of April 11, 2024, Public Meeting with Constellation Energy Generation, LLC Regarding Proposed Alternative to Implement American Society of Mechanical Engineers Operation and Maintenance Code Case OMN-32 ML24113A2872024-04-25025 April 2024 Summary of Public Meeting with Constellation Energy Generation, LLC Regarding Hooded Masks ML23320A2472023-11-17017 November 2023 Constellation - Summary of November 14, 2023, Public Pre-Application Meeting with Constellation Energy Generation, LLC on Adoption of TSTF-591 ML23271A2682023-10-0505 October 2023 September 25, 2023, Summary of with Constellation Energy Generation, LLC on Proposed Changes to Emergency Plans ML23263B1062023-09-22022 September 2023 R. E. Ginna Nuclear Power Plant - Constellation - Pre-Application Amse 9/18/2023 Meeting Summary ML23179A0012023-06-28028 June 2023 6/7/2023 - Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - Meeting Summary ML23055A0352023-03-24024 March 2023 Summary of February 23, 2023, with Constellation Energy Generation, LLC on Proposed Changes to Emergency Plans to Revise Emergency Action Levels ML22187A1462022-07-0606 July 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Meeting Summary ML21333A1532021-11-30030 November 2021 Summary of November 16, 2021, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Extend the Inservice Inspection Interval ML21237A0412021-08-30030 August 2021 Summary of the July 27, 2021, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Use Case OMN-28, ML21176A0822021-07-0606 July 2021 June 15, 2021, Summary of Meeting with Exelon Generation Company, LLC Vessel Nozzle Repair Related to a Planned Request for an Alternative Related to Reactor Pressure ML21139A1852021-06-22022 June 2021 Summary of Meeting with Exelon Generation Company, LLC Regarding Its Requested Alternative to Eliminate Certain Documentation Requirements for the Replacement of Pressure Retaining Bolting ML21011A2822021-01-21021 January 2021 Summary of January 6, 2021, Presubmittal Meeting Between the NRC and Exelon Generation Company, LLC Regarding Licensing Activities to Support the Planned Early Closures of Byron, Unit Nos. 1 and 2 and Dresden, Units 2 and 3 ML20351A2832020-12-18018 December 2020 Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Exemption to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs ML20342A3522020-12-10010 December 2020 Summary of November 13, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alterantive to Certain Documentation Requirements for the Replacement of Pressure Retaining Bolting (EPID-L-2020-LRM-0102) ML20323A0332020-12-0101 December 2020 Summary of November 4, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs ML20205L3712020-07-23023 July 2020 and R.E. Ginna Nuclear Power Plant Summary of Meeting ML20163A1722020-06-12012 June 2020 Summary of June 9, 2020, Pre-Submittal Meeting with Exelon Generation Company, LLC, Regarding Planned License Amendment Request to Modify Surveillance Requirement 3.6.1.3 ML19326C3582019-12-0303 December 2019 Summary of November 20, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Revise the Quality Assurance Program ML19326A3152019-12-0303 December 2019 Summary of November 18, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Supplemental Valve Position Indication Testing Requirements ML19302F8772019-11-0404 November 2019 Summary of the October 28, 2019, Meeting with Exelon Generation Company, LLC, Regarding a Planned Supplement to a License Amendment Request Regarding Revising the Allowable Value for Reactor Water Cleanup System Isolation ML19291A0022019-11-0101 November 2019 10/03-10/08/2019 Summary of Meetings with Exelon Generation Company, LLC, on Emergency Amendment Request Regarding One-Time Extension to Technical Specifications 3.8.1 Action A.3 Completion Time for Inoperable Offsite Source (EPID L-2019-LL ML19302D3152019-10-28028 October 2019 Annual Assessment Meeting for James A. Fitzpatrick Nuclear Power Plant and Nine Mile Point Nuclear Generating Station - Meeting Summary ML19176A0042019-07-15015 July 2019 Summary of Meeting with Exelon Generation Company, LLC, on a Planned License Amendment Request Regarding the Relaxation of Containment Differential Pressure Requirements ML19183A1282019-07-15015 July 2019 Summary of June 20, 2019, Meeting with Exelon Generation Company, LLC, on a Planned License Amendment Request Regarding Main Steam Isolation Valve Leak Rate Increase Utilizing ML19162A0272019-06-21021 June 2019 Summary of June 4, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Extend the Test Interval for Safety Relief Valves ML19036A8832019-02-0707 February 2019 Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Use ASME Code Case N-879 ML18354B1712019-01-0202 January 2019 Summary of December 19, 2018, Meeting with Exelon Generation Company, LLC Regarding the Use of Boiling Water Reactor Vessel and Internals Project Guidelines ML18347B4932019-01-0202 January 2019 Summary of Pre-Application Meeting with Exelon Generation Co., LLC (Exelon) Forthcoming License Amendment Requests to Revise Technical Specification Requirements for Main Steam Isolation Valve Leak Rate Tests ML18325A1712018-11-28028 November 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Planned Fleet License Amendment Request to Revise Technical Specifications for High Radiation Areas ML18304A1662018-11-0606 November 2018 Summary of October 23, 2018, Teleconference with Exelon Generation Co., LLC to Discuss Potential License Amendment Request Ultimate Heat Sink Bar Rack Bar Heaters ML18297A1722018-10-26026 October 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Planned License Amendment Request to Adopt TSTF-427 ML18262A3662018-09-18018 September 2018 August 21, 2018, James A. Fitzpatrick Nuclear Power Plant (Fitzpatrick) and Nine Mile Point Nuclear Generating Station (Nine Mile Point) Summary of Public Meeting ML18163A2682018-06-19019 June 2018 Summary of June 5, 2018, Teleconference with Exelon Generation Company, LLC to Discuss Emergency Plan Changes at James A. Fitzpatrick Nuclear Power Plant and Nine Mile Point Nuclear Station ML18120A1772018-05-0101 May 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Draft Guidance for Emergency Response Organization Staffing ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML17256A7482017-09-28028 September 2017 Summary of September 5, 2017, Meeting with Exelon Generation Co., LLC to Discuss Potential License Amendment Request Technical Specifications Task Force Traveler TSTF-542, Revision 2, for James A. Fitzpatrick Nuclear Power Plant ML17216A1732017-09-0707 September 2017 Notice of Meeting with Florida Power & Light Company and NextEra Energy to Discuss Closing Out Generic Safety Issue-191 and Generic Letter 2004-02 ML17144A2852017-06-0202 June 2017 Summary Teleconference with Exelon Generation Company, LLC, on Planned Submittals of License Amendment Requests to Change Emergency Action Levels Associated with Lake Ontario Water Level ML17143A3582017-05-23023 May 2017 Summary of Public Meeting for James A. Fitzpatrick and Nine Mile Point ML17143A1902017-05-23023 May 2017 Public Meeting Handouts and Sign in Sheet ML17031A2802017-02-0808 February 2017 Summary of Teleconference with Entergy Nuclear Operations, Inc. Regarding Verbal Authorization for Relief Request RR-21 for the James A. Fitzpatrick Nuclear Power Plant ML16229A4542016-08-16016 August 2016 Summary of Annual Assessment Meeting for James A. Fitzpatrick Nuclear Power Plant ML15197A3332015-07-24024 July 2015 June 29, 2015 Summary of Meeting with Beyond Nuclear, Et. Al., Regarding Its 10 CFR 2.206 Petition Requesting Enforcement Action Against the James A. FitzPatrick Nuclear Power Plant ML15120A0212015-04-28028 April 2015 April 23, 2015, Summary of Annual Assessment Meeting for James A. FitzPatrick Nuclear Power Plant on 4/23/2015 ML14197A5832014-09-18018 September 2014 Summary of the June 19, 2014, Category 1 Public Meeting with Entergy to Discuss Seismic Hazard Reevaluations Associated with Implementation of Japan Lessons-Learned Near-Tear Task Force Recommendation 2.1 ML14086A1532014-03-26026 March 2014 Summary of Annual Assessment Meeting for Nine Mile Point Nuclear Station and James A. FitzPatrick Nuclear Power Plant on 3/18/2014 ML13100A1172013-04-10010 April 2013 Summary of Public Meeting Regarding Nine Mile Point Nuclear Station and James A. Fitzpatrick Nuclear Power Plant 2024-06-03
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 24, 2015 LICENSEE: Entergy Nuclear Operations, Inc.
FACILITY: James A. Fitzpatrick Nuclear Power Plant
SUBJECT:
SUMMARY
OF JUNE 29, 2015, MEETING WITH BEYOND NUCLEAR, ET. AL.,
REGARDING ITS 10 CFR 2.206 PETITION REQUESTING ENFORCEMENT ACTION AGAINST THE JAMES A. FITZPATRICK NUCLEAR POWER PLANT (TAC NOS. ME8189)
On June 29, 2015, a Category 3 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Beyond Nuclear, et. al. (the petitioners), at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to provide the petitioners an opportunity to address the NRC Petition Review Board (PRB) in accordance with Management Directive (MD) 8.11, "Review Process for 10 CFR 2.206 Petitions." The meeting notice and agenda dated June 11, 2015, is available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML15177A075. A list of attendees is provided as Enclosure 1.
On March 9, 2012 (ADAMS Accession No. ML12074A032), as supplemented on March 13, (ADAMS Accession No. ML12079A036), and March 20, 2012 (ADAMS Accession No. ML12081A284), the petitioners submitted a joint petition to the NRC, under Title 10 of the Code of Federal Regulations, Part 2.206, regarding the James A. FitzPatrick Nuclear Power Plant.
The petitioners also submitted a Freedom of Information Act (FOIA) request dated October 11, 2012, requesting various communications between the NRC Office of Nuclear Reactor Regulation (NRR), the Office of General Counsel, Region I, and the resident inspectors. The staff satisfied this request from the petitioners with a response on August 7, 2013 (ADAMS Accession No. ML13154A313). The petitioners stated that this information was necessary in order to address the PRB for a second time.
As described in MD 8.11, the petitioners are provided the opportunity to address the PRB in order to provide any relevant additional explanation and support for their petition after the PRB has communicated its initial recommendation. The purpose of this meeting was to provide the petitioners another opportunity to address the PRB provide additional relevant explanation and support for the petition request in light of the PRB's initial recommendation, and the information contained in the FOIA request and response. The petitioners' scripts and supplemental information are available at ADAMS Accession Nos. 15198A047, ML15198A051, and ML15198A054. This meeting was recorded by the NRC's Operations Center and transcribed by a court reporter. The transcript is available in ADAMS at Accession No. ML15197A307. The audio recording is available through the public document room with instructions for finding it at ADAMS Accession No. ML15197A327.
Members of the public were in attendance. Public Meeting Feedback forms were not received prior to issuance of this summary.
Please direct any inquiries to me at 301-415-2549, or Alexander.Chereskin@nrc.gov.
~
Alexa er N. Chereskin, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-317 and 50-318
Enclosure:
- 1. List of Attendees cc w/encl: Distribution via Listserv Jessica Azulay (jessica@allianceforagreeneconomy.org)
Paul Gunter (paul@beyondnuclear.org)
Tim Judson (timj@nirs.org)
LIST OF ATTENDEES JUNE 29, 2015, PRB MEETING WITH BEYOND NUCLEAR, ET. AL., REGARDING ITS 10 CFR 2.206 PETITION REQUESTING ENFORCEMENT ACTION AGAINST THE JAMES A. FITZPATRICK NUCLEAR POWER PLANT U.S. Nuclear Regulatory Commission Alex Chereskin Samson Lee Patricia Jehle Merrilee Banic Robert Fretz Mandy Halter Brett Titus Tom Setzer*
Doug Pickett Booma Venkataraman Neil Sheehan*
Entergy Nuclear Operations, Inc. (Licensee)
Chris Adner*
Jerry Nappi*
Petitioners and Members of the Public Jessica Azulay*
Paul Gunter Tim Judson Ruth Thomas*
Marvin Lewis*
- via teleconference Enclosure 1
Meetin Notice ML15177A075 ML15197A333 *via dated e-mail OFFICE NRR/DORL/LPLl-1/PM NRR/DPR/PGCB/PM NRR/DORL/LPLl-1/LA NAME AChereskin MBanic* KGoldstein*
DATE 7/24/2015 07/24/2015 07/23/2015 OFFICE NRR/DORL/LPLl-1 /BC NRR/DORL/LPLl-1 /PM NAME MDudek AChereskin DATE 7/24/2015 7/24/2015