MONTHYEARIR 05000309/20240012024-06-26026 June 2024 Company – Independent Spent Fuel Storage Installation NRC Inspection Reports 07200030/2024001 And05000309/2024001 ML24124A1372024-04-30030 April 2024 Independent Spent Fuel Storage Installation - 2023 Individual Monitoring NRC Form 5 Report ML24117A0602024-04-23023 April 2024 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2023 ML24099A0712024-04-0303 April 2024 Independent Spent Fuel Storage Installation - 10 CFR 72.48 Biennial Report ML24094A0602024-03-28028 March 2024 Independent Spent Fuel Storage Installation, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for the Maine Yankee Independent Spent Fuel Storage Installation ML24074A3822024-03-11011 March 2024 Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML24074A3812024-03-11011 March 2024 Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report NG-24-0001, 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update2024-03-0606 March 2024 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update ML23286A3262024-02-29029 February 2024 Issuance of Exemption for Maine Yankee Atomic Power Company Regarding Maine Yankee Independent Spent Fuel Storage Installation ML24025A0392024-01-12012 January 2024 Independent Spent Fuel Storage Installation, Property Insurance Coverage ML23342A1112024-01-0909 January 2024 Company - Independent Spent Fuel Storage Installation Security Inspection Plan ML23117A0452023-04-25025 April 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2022 ML23113A0052023-03-31031 March 2023 Request for Exemption from 10 CFR 50.82 10 CFR 50.75 for the Maine Yankee Independent Spent Fuel Storage Installation NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report ML23068A0112023-03-0606 March 2023 Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML23068A0132023-03-0606 March 2023 Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22340A4622023-02-24024 February 2023 Closeout Letter to Maine Yankee Atomic Power Company Regarding 2018 and 2021 Updated DFPs for Maine Yankee ISFSI IR 07200030/20234012023-01-26026 January 2023 Company - NRC Independent Spent Fuel Storage Security Inspection Report No. 07200030/2023401 (Letter Only) ML23026A0802023-01-17017 January 2023 Company - Property Insurance Coverage IR 07200030/20224012022-10-11011 October 2022 Company - NRC Independent Spent Fuel Storage Security Inspection Report No. 07200030/2022401 ML22216A0682022-07-28028 July 2022 Independent Spent Fuel Storage Installation, Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML22088A0212022-04-0101 April 2022 Independent Spent Fuel Storage Installation, 10 CFR 72.48 Biennial Report ML22088A0182022-04-0101 April 2022 Independent Spent Fuel Storage Installation, 10 CFR 50.59 Biennial Report NG-22-0041, And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report2022-03-31031 March 2022 And Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report ML22088A0122022-03-14014 March 2022 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22088A0162022-03-14014 March 2022 Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML22011A1332022-01-31031 January 2022 Company - Independent Spent Fuel Storage Installation Security Inspection Plan ML22045A0662022-01-20020 January 2022 Independent Spent Fuel Storage Installation - Property Insurance Coverage ML22045A0652022-01-20020 January 2022 Independent Spent Fuel Storage Installation, Nuclear Liability Insurance Coverage ML21362A1592021-12-10010 December 2021 Independent Spent Fuel Storage Installation, Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan IR 05000309/20210012021-10-28028 October 2021 Company - NRC Independent Spent Fuel Storage Installation Inspection Report Nos. 07200030/2021001 and 05000309/2021001 NG-21-0006, 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report2021-03-31031 March 2021 2021 Annual Decommissioning and Spent Fuel Management Funding Status Report ML21105A7392021-03-0202 March 2021 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML21077A1672021-03-0202 March 2021 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML21042B5932021-01-27027 January 2021 Independent Spent Fuel Storage Installation, Property Insurance Coverage ML21042B5942021-01-27027 January 2021 Independent Spent Fuel Storage Installation, Nuclear Liability Insurance Coverage ML21012A3992021-01-13013 January 2021 Company - Independent Spent Fuel Storage Installation Security Inspection Plan ML21042B8962021-01-11011 January 2021 Independent Spent Fuel Storage Installation, Biennial Update of the Defueled Safety Analysis Report ML21050A2302021-01-11011 January 2021 Independent Spent Fuel Storage Installation - Formal Announcement of New ISFSI Manager IR 07200030/20204012020-10-21021 October 2020 Company - NRC Independent Spent Fuel Storage Security Inspection Report No. 07200030/2020401 ML20136A3372020-04-22022 April 2020 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2019 ML20101H9312020-04-0101 April 2020 Independent Spent Fuel Storage Installation - 10 CFR 50.59 Biennial Report ML20097B6692020-03-19019 March 2020 Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML20087J6772020-03-11011 March 2020 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML20015A5492020-01-15015 January 2020 Company - Independent Spent Fuel Storage Installation Security Inspection Plan ML19352E1412019-12-11011 December 2019 Independent Spent Fuel Storage Installation - Adoption of NAC-UMS System, Amendment No. 6 Certificate of Compliance and Canister Registration ML19241A4582019-08-29029 August 2019 Letter to T. Matthews Maine Yankee Atomic Power Company - Threshold Determination That NRC Consent Is Not Required in Connection with Acquisition of Emera Maine by Enmaz Corporation ML19182A0402019-07-0505 July 2019 Letter to P. Dostie Maine Yankee Atomic Power Company Exemption Request from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for the ISFSI ML19182A0322019-07-0505 July 2019 Letter to J. Brown Maine Yankee Atomic Power Company Exemption Request from Certain Requirements of 10 CFR 72.214 for the ISFSI ML19113A1032019-04-23023 April 2019 Request for NRC Threshold Determination That NRC Consent Is Not Required in Connection with Acquisition of Emera Maine by Enmax Corporation 2024-06-26
[Table view] Category:Status Report
MONTHYEARML24074A3822024-03-11011 March 2024 Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML24074A3812024-03-11011 March 2024 Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report NG-24-0001, 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update2024-03-0606 March 2024 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report ML23068A0112023-03-0606 March 2023 Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML23068A0132023-03-0606 March 2023 Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22088A0122022-03-14014 March 2022 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML21077A1672021-03-0202 March 2021 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML20097B6692020-03-19019 March 2020 Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML20087J6772020-03-11011 March 2020 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML18082A0972018-03-0505 March 2018 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML17087A2822017-03-0909 March 2017 Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML16102A0772016-03-23023 March 2016 Independent Spent Fuel Storage Installation Re Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML16076A3152016-03-0909 March 2016 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML15065A1372015-02-10010 February 2015 ISFSI - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML14085A0162014-03-12012 March 2014 Company - Decommissioning Funding Assurance Status Report ML14085A0152014-03-12012 March 2014 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML13128A2902013-03-26026 March 2013 Company, Maine Yankee Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML13092A1422013-03-19019 March 2013 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML1211501982012-03-27027 March 2012 Redacted - Maine Yankee, Decommissioning Funding Assurance Status Report - 10 CFR 50.75 ML1108105672011-03-15015 March 2011 Decommissioning Funding Assurance Status Report - 10 CFR 50.75 ML0517507002005-06-20020 June 2005 to Maine Yankee Final Status Survey Release Record FD-3500 Storm Drains Survey Unit 2. ML0517507072005-06-20020 June 2005 to Maine Yankee Final Status Survey Release Record FR-0200 Yard East Survey Unit 7. ML0517507052005-06-20020 June 2005 to Maine Yankee Final Status Survey Release Record FR-0200 Yard East Survey Unit 6. ML0517507082005-06-16016 June 2005 to Maine Yankee Final Status Survey Release Record FR-0200 Yard East Survey Unit 8. ML0517507132005-06-15015 June 2005 to Maine Yankee Final Status Survey Release Record FR-2900 Roads/Railroad Survey Unit 3. ML0517507022005-06-13013 June 2005 to Maine Yankee Final Status Survey Release Record FR-0200 Yard East Survey Unit 5. ML0517507122005-06-0808 June 2005 to Maine Yankee Final Status Survey Release Record FR-0900 Balance of Plant Land Survey Unit 4. ML0517507112005-06-0707 June 2005 to Maine Yankee Final Status Survey Release Record FR-0200 Yard East Survey Unit 9. ML0515204002005-05-25025 May 2005 Final Status Survey Release Record FR-2900 Roads/Railroad Survey Unit 2 RA-05-031, Release of Non-ISFSI Site Land - FSS Final Report No. 102005-05-25025 May 2005 Release of Non-ISFSI Site Land - FSS Final Report No. 10 ML0515203962005-05-24024 May 2005 Final Status Survey Release Record FR-0111 Yard West Excavations Survey Unit 20 ML0515203892005-05-24024 May 2005 Final Status Survey Release Record FD-0600 Service Water Survey Unit 2 ML0515203942005-05-23023 May 2005 Final Status Survey Release Record FR-0111 Yard West Excavations Survey Unit 19 ML0515203982005-05-17017 May 2005 Final Status Survey Release Record FR-0200 Yard East Survey Unit 4 RA-05-023, Release of Non-ISFSI Site Land - Final Status Survey Final Report No. 9A, Revision 02005-05-0505 May 2005 Release of Non-ISFSI Site Land - Final Status Survey Final Report No. 9A, Revision 0 ML0515203912005-05-0404 May 2005 Final Status Survey Release Record FR-0111 Yard West Excavations Survey Unit 18 RA-05-019, Response to NRC RAI on FSS Final Report Nos 1 and 22005-04-13013 April 2005 Response to NRC RAI on FSS Final Report Nos 1 and 2 ML0510501102005-04-0707 April 2005 Final Status Survey Release Record FR-0800 Admin & Parking Area Survey Unit 1 ML0510500772005-04-0707 April 2005 Final Status Survey Release Record FR-0111 Yard West Excavations Survey Unit 12 RA-05-017, Release of Non-ISFSI Site Land - Final Status Survey (FSS) Final Report No. 92005-04-0707 April 2005 Release of Non-ISFSI Site Land - Final Status Survey (FSS) Final Report No. 9 ML0510500672005-04-0707 April 2005 Final Status Survey Release Record FD-3500 Storm Drains Survey Unit 1 ML0510500802005-04-0505 April 2005 Final Status Survey Release Record FR-0111 Yard West Excavations Survey Unit 17 ML0510500722005-04-0505 April 2005 Final Status Survey Release Record FD-3500 Storm Drains Survey Unit 2 ML0510500752005-04-0404 April 2005 Final Status Survey Release Record FD-3500 Storm Drains Survey Unit 4 ML0510500992005-04-0404 April 2005 Final Status Survey Release Record FR-0200 Yard East Survey Unit 3 ML0510500832005-03-31031 March 2005 Final Status Survey Release Record FR-0200 Yard East Survey Unit 2 ML0510501062005-03-31031 March 2005 Final Status Survey Release Record FR-0220 Spare Transformer Pad Footprint Survey Unit 1 RA-05-015, Decommissioning Funding Status Report - 10 CFR 50.75(f) - 20042005-03-30030 March 2005 Decommissioning Funding Status Report - 10 CFR 50.75(f) - 2004 ML0510500762005-03-0808 March 2005 Final Status Survey Release Record FR-0111 Yard West Excavations Survey Unit 11 2024-03-06
[Table view] |
Text
MAINE YANKEE 321 Old Ferry Road, Wiscasset, Maine 04578 February 10, 2015 OMY-15-010 10 CFR 50.4 10 CFR 50.82(a)(8)(vii)
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555 - 0001 Maine Yankee Atomic Power Company Maine Yankee Independent Spent Fuel Storage Installation NRC License Nos. DPR-36 and SFGL-14 (NRC Docket Nos. 50-309 and 72-30)
Subject:
Funding Status Report for Managing Irradiated Fuel and GTCC Waste On August 7, 1997, Maine Yankee Atomic Power Company (Maine Yankee) informed the USNRC that the Board of Directors of Maine Yankee had decided to permanently cease operations at the Maine Yankee plant and that fuel had been permanently removed from the reactor (Reference 1). In accordance with 10 CFR 50.82(a)(2), the certifications in the letter modified the Maine Yankee license to permanently withdraw Maine Yankee's authority to operate the reactor. In 1998, Maine Yankee commenced decommissioning the power plant. On September 30, 2005, the NRC amended the Maine Yankee license, releasing most of the formerly licensed land for unrestricted use, shrinking the licensed land to that utilized to support the Independent Spent Fuel Storage Installation (ISFSI) (Reference 2). Presently, Maine Yankee is storing irradiated fuel and Greater than Class C (GTCC) waste on site until the Department of Energy (DOE) satisfies its contractual obligations to take title and possession of the spent fuel and GTCC waste and remove them from the site.
In Attachment 1, Maine Yankee provides the attached Funding Status Report for Managing Irradiated Fuel and GTCC Waste at the Maine Yankee ISFSI to comply with 10 CFR 50.82(a)(8)(vii).
This letter contains no regulatory commitments.
If you have any questions regarding this letter, please do not hesitate to contact me at (860) 267-6426 x304.
t lly, Carla M. Pizzella Vice President, Chief Financial Officer, and Treasurer
Maine Yankee Atomic Power Company OMY- 15-010\February 10, 2015\Page 2
Attachment:
- 1. Funding Status Report for Managing Irradiated Fuel and GTCC Waste at the Maine Yankee Independent Spent Fuel Storage Installation (Status as of 12/31/2014)
References:
- 1. M. B. Sellman (Maine Yankee) letter to USNRC, "Certifications of Permanent Cessation of Power Operation and Permanent Removal of Fuel from the Reactor," dated August 7, 1997
- 2. USNRC letter to Maine Yankee, License Amendment No. 172 to Facility Operating License No. DPR-36, dated September 30, 2005 cc: D. H. Dorman, NRC Region I Administrator M. S. Ferdas, Chief, Decommissioning Branch, NRC, Region 1 J. Goshen, NRC Project Manager P. Dostie, State of Maine, Nuclear Safety Inspector J. Hyland, State of Maine, Manager Radiation Control Program
ATTACHMENT 1 TO OMY-15-010 FUNDING STATUS REPORT FOR THE MANAGING OF IRRADIATED FUEL AND GTCC WASTE AT THE MAINE YANKEE INDEPENDENT SPENT FUEL STORAGE INSTALLATION (STATUS AS OF 12/31/2014)
Attachment 1 to OMY-15-010 Funding Status Report for the Managing of Irradiated Fuel and GTCC Waste at the Maine Yankee Independent Spent Fuel Storage Installation (Status as of 12/31/2014) 10 CFR Requirement J Response Comment 10 CFR 50.82(a)(8)(vii) Requirements
- 1. The amount of funds accumulated ~$104.2 Maine Yankee Atomic Power Company (Maine Yankee) has established an account to cover the cost of managing the million (as of within its Nuclear Decommissioning Trust (NDT) entitled, "ISFSI Radiological irradiated fuel. 12/31/14) Decom," that segregates the funds for decommissioning of the Maine Yankee Independent Spent Fuel Storage Installation (ISFSI) from the larger balance of funds for ongoing management of irradiated fuel and Greater than Class C (GTCC) waste held in the NDT. This accrued market value balance established here excludes the funds set-aside for decommissioning the ISFSI.
- 2. The projected cost of managing -181.2 million In 2013, Maine Yankee submitted a revised cost estimate for management of the irradiated fuel until title to the (2015 through irradiated fuel and GTCC waste at the Maine Yankee ISFSI to the Federal Energy fuel and possession of the fuel is 2033) (In Regulatory Commission (FERC). It extended the duration of storage of irradiated fuel transferred to the Secretary of 2014 dollars) and GTCC waste based on recent information published by the DOE as a result of Blue Energy. Ribbon Commission recommendations. This cost estimate was approved by FERC in June, 2013.
- 3. If the funds accumulated do not See Comment The Company has several methods of obtaining additional funds to cover projected cover the projected cost, a plan to costs.
obtain additional funds to cover the cost. First, Maine Yankee may collect funds through its power contracts and amendatory agreements under FERC regulation. The power contracts and the amendatory agreements specify the obligations of the purchasers for the costs of Maine Yankee, including the ongoing costs of managing irradiated fuel and GTCC waste.
Pursuant to these power contracts, Maine Yankee has the ongoing ability to seek collections from its purchasers for additional funds that may be required to cover these costs.
Second, Maine Yankee has received proceeds from the successful litigation of the first and second phases of its breach of contract damages claims against the DOE for failure to begin the removal of spent nuclear fuel (SNF) and GTCC waste from the site in 1998.
Maine Yankee will continue to file claims against the DOE as long as the DOE continues to breach its contract obligations related to SNF and GTCC waste. To that end, in August, 2013 the Company filed a third round of claims against the DOE Page 1 of 2
Attachment 1 to OMY-15-010 Funding Status Report for the Managing of Irradiated Fuel and GTCC Waste at the Maine Yankee Independent Spent Fuel Storage Installation (Status as of 12/31/2014) 10 CFR Requirement Response Comment seeking damages for the years 2009 - 2012. The trial is scheduled to commence in June 2015. Each of these prospective claims will likely result in the receipt of proceeds that can be used to offset future costs, if required.
Accordingly, Maine Yankee's most recent FERC filing which was approved in June, 2013, implemented a fifteen year funding mechanism. Until the 2013 FERC filing, the Company had employed a "full funding" assumption in developing funding requirements. The fifteen year funding mechanism was put in place to incorporate the potential for the receipt of future DOE breach of contract damages as a source of funding as discussed below. If future damage recovery does not occur, the Company has the ability to apply to FERC for more funding, if necessary. The approved FERC filing also requires Maine Yankee to provide an information filing regarding the adequacy of funding if five years pass without receipt of damage awards from litigation with the DOE.
Third, Maine Yankee expects to utilize the investment return on Decommissioning Trust assets to offset future costs. The current assumed rate of investment return, after fees and taxes is 4.5%.
Page 2 of 2