Schedule Revision for the Review of the Sequoyah Nuclear Plant License, Renewal Application
ML14337A769
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 12/17/2014
From: Chris Miller, Sayoc E
License Renewal Projects Branch 1
To: James Shea
Tennessee Valley Authority
Sayoc E, NRR/DLR/RPB1, 301-415-4084
References
TAC MF0481, TAC MF0482
Download: ML14337A769 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 17, 2014 Mr. Joe W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority P.O. Box 2000 Soddy-Daisy, TN 37384

SUBJECT:

SCHEDULE REVISION FOR THE REVIEW OF THE SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS.

MF0481 AND MF0482)

Dear Mr. Shea:

By letter dated January 7, 2013, Tennessee Valley Authority (TVA) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew operating licenses DPR-77 and DPR-79, for the Sequoyah Nuclear Plant (SQN) for review by the U.S. Nuclear Regulatory Commission (NRC) staff. This letter is to inform you of a change in the schedule for the SQN license renewal review.

The safety review milestone due date for Issue final SER is revised from January 2015, to February 5, 2015. In addition the Advisory Committee on Reactor Safeguards (ACRS) full committee meeting date is revised from February 5, 2014, to March 5, 2015. The issuance of a revised schedule is based on your updated request for additional information (RAI) response to the staffs RAI B.1.34-9d, dated December 4, 2014, concerning reactor vessel internals program action item 1. Enclosed is the NRC staff's revised review schedule for the SQN license renewal application.

If you have any questions related to this revised schedule, for the safety review please contact Emmanuel Sayoc, at 301-415-4084 or by e-mail at emmanuel.sayoc@nrc.gov, and for the environmental review, please contact David Drucker, at 301-415-6223 or by e-mail at david.drucker@nrc.gov.

Sincerely,

/RA Jane Marshall for/

Christopher G. Miller, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-327 and 50-328

Enclosure:

Revised Schedule cc w/encl: Listserv

ML14337A769

  • Concurred via e-mail OFFICE LA:DLR:RPB1* PM:RPB1:DLR PM:RPB2:DLR BC:RPB1:DLR BC:RPB2:DLR D:DLR NAME YEdmonds ESayoc DDrucker YDiaz-Sanabria BWittick CMiller (JMarshall for)

DATE 12/12/14 12/15/14 12/16/14 12/16/14 12/16/14 12/17/14

ENCLOSURE SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION SCHEDULE REVISION UPDATED REVIEW SCHEDULE Milestone Schedule Actual Receive license renewal application (LRA) 1/2013 1/15/13 Publish Federal Register Notice (FRN) - LRA availability 2/2013 2/22/13 Publish FRN - acceptance/rejection and opportunity for hearing 3/2013 3/05/13 Publish FRN - environmental scoping meeting 3/2013 3/08/13 Audit - Scoping & Screening Methodology 3/11/13 3/11/13 Audit - Aging Management Programs 3/18/13 3/18/13 Public Meeting - License Renewal Overview and Environmental Scoping meeting 4/03/13 4/03/13 Audit - Environmental 4/08/13 4/08/13 Environmental scoping period ends 5/2013 5/03/13 Deadline for filing hearing requests and petitions for intervention 5/2013 5/06/13 Inspection - Regional 11/18/13 &

12/08/13 11/18/13 &

12/08/13 Issue draft supplemental environmental impact statement (SEIS) 7/2014 7/31/14 U.S. Environmental Protection Agency FRN Published - draft SEIS available for comment 8/2014 8/15/14 Public Meeting - draft SEIS meeting 9/17/14 9/17/14 End of draft SEIS comment period 9/29/14 9/29/14 Issue safety evaluation report (SER) with open items 10/05/14 9/29/14 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 11/05/14 11/05/14 Issue final SER 2/05/15 Issue final SEIS 3/2015 ACRS full committee meeting 3/05/15 U.S. Environmental Protection Agency FRN Published - availability of final SEIS 4/2015 Decision - Director, NRR 6/2015 Commission decision (if hearing is granted)

NA

Letter to J. Shea from C. Miller dated December 17, 2014

SUBJECT:

SCHEDULE REVISION FOR THE REVIEW OF THE SEQUOYAH NUCLEAR PLANT LICENSE, RENEWAL APPLICATION (TAC NOS. MF0481 AND MF0482)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource ESayoc RPlasse DDrucker BWittick DWrona BMizuno, OGC BHarris, OGC DMcIntyre, OPA john.pelchat@nrc.gov gena.woodruff@nrc.gov siva.lingam@nrc.gov wesley.deschaine@nrc.gov galen.smith@nrc.gov scott.shaeffer@nrc.gov jeffrey.hamman@nrc.gov craig.kontz@nrc.gov caudle.julian@nrc.gov