NRR E-mail Capture - Requests for Additional Information - Relief Requests Associated with the Fourth Ten-Year Interval Inservice Testing Program - Columbia Generating Station
ML14183B704
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 07/02/2014
From: Andrea George
Division of Operating Reactor Licensing
To: Linda Williams
Energy Northwest
References
MF3851, MF3854, MF3856, MF3857
Download: ML14183B704 (3)


Text

NRR-PMDAPEm Resource From: George, Andrea Sent: Wednesday, July 02, 2014 1:49 PM To: llwilliams@energy-northwest.com

Subject:

Requests for Additional Information - Relief Requests Associated with the Fourth Ten-Year Interval Inservice Testing Program - Columbia Generating Station (TAC NOS. MF3851, MF3854, MF3856, MF3857)

Attachments: MF3856 MF3857 MF3854 MF3851 - Columbia RAIs RP-01 RP-02 RP-03 RP-06.docx Ms. Williams, By letter dated April 2, 2014 (Agencywide Document Access and Management System (ADAMS) Accession Number ML14101A365), Energy Northwest (the licensee) submitted a series of relief requests for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing Program. The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the submittal and requests additional information (RAI) as detailed in the attachment.

Draft RAIs were issued on July 2, 2014. The NRC project mananger was notified that a clarification call is not needed and it was agreed that Energy Northwest will respond to these RAIs within 30 days, which is August 1, 2014.

If circumstances result in the need to revise the agreed-upon response date, please contact me at (301) 415-1081 or via email at andrea.george@nrc.gov.

Thank you, Andrea George Project Manager Nuclear Regulatory Commission Division of Operating Reactor Licensing andrea.george@nrc.gov 301-415-1081 1

Hearing Identifier: NRR_PMDA Email Number: 1410 Mail Envelope Properties (Andrea.George@nrc.gov20140702134900)

Subject:

Requests for Additional Information - Relief Requests Associated with the Fourth Ten-Year Interval Inservice Testing Program - Columbia Generating Station (TAC NOS. MF3851, MF3854, MF3856, MF3857)

Sent Date: 7/2/2014 1:49:26 PM Received Date: 7/2/2014 1:49:00 PM From: George, Andrea Created By: Andrea.George@nrc.gov Recipients:

"llwilliams@energy-northwest.com" <llwilliams@energy-northwest.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 1117 7/2/2014 1:49:00 PM MF3856 MF3857 MF3854 MF3851 - Columbia RAIs RP-01 RP-02 RP-03 RP-06.docx 23300 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received:

REQUESTS FOR ADDITIONAL INFORMATION (RAI)

ENERGY NORTHWEST COLUMBIA GENERATING STATION RELIEF REQUESTS RP-01, RP-02, RP-03 REQUEST FOR ALTERNATIVE RP-06 DOCKET NUMBER 50-387 By application dated April 2, 2014, to the U.S. Nuclear Regulatory Commission (NRC)

(Agencywide Document Access and Management System (ADAMS) Accession Number ML14101A365), Energy Northwest, the licensee, submitted a series of relief requests for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing Program.

Based on its review, the NRC staff requests the following additional information in order to complete their technical review.

EPNB-RAI-RP-01-1 Please provide the discharge pressures for standby service water pumps SW-P-1A and SW-P-1B, and standby service water, HPCS pump HPCS-P-2 from the inservice tests for the past year.

EPNB-RAI-RP-02-1 It appears that this alternative request is requesting the use of parts of Code Case OMN-16 for the standby service water pumps and the standby service water, HPCS pump. Please confirm if this is correct. If this is correct, please explain how your proposed testing differs from Code Case OMN-16 and provide justification for the differences.

EPNB-RAI-RP-03-1 Relief request RP-03 lists several elements that are used to develop and implement the provided reference pump curves. Relief request RP-03 states that these elements follow the guidance of Code Case OMN-16. Please clarify what portions of ASME OM Code Case OMN-16 are being followed. Also, please explain any deviations from ASME OM Code Case OMN-16 that are being requested in relief request RR-03.

EPNB-RAI-RP-06-1 Alternative request RP-06 provides a table that compares the test flow rate to the design basis accident flow rate. Please provide a table that compares test differential pressure and design basis differential pressure for the pumps for which an alternative is requested.