Letter Sequence Other |
---|
|
Results
Other: CNL-14-029, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant, CNL-14-033, Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, CNL-14-130, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant, CNL-15-038, Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), ML12307A104, ML13063A011, ML13063A183, ML13247A286, ML13247A291, ML15033A430
|
MONTHYEARML12307A1042012-10-29029 October 2012 Tennessee Valley Authority - Initial Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13063A1832013-02-28028 February 2013 Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other ML13063A0112013-02-28028 February 2013 Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (EA-12-051) Project stage: Other ML13198A3542013-07-17017 July 2013 Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) Project stage: RAI ML13235A0072013-08-16016 August 2013 Response to NRC Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation Project stage: Response to RAI ML13247A2862013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other ML13247A2912013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant Project stage: Other ML13312A4152013-11-21021 November 2013 Interim Staff Evaluation and Request for RAI Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: RAI CNL-14-029, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant2014-02-28028 February 2014 Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant Project stage: Other CNL-14-033, Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-03-0505 March 2014 Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other CNL-14-130, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant2014-08-28028 August 2014 Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant Project stage: Other ML14302A1972014-11-0606 November 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Acceptance Review CNL-15-038, Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML15033A4302015-03-0303 March 2015 Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other 2013-08-28
[Table View] |
|
---|
Category:Letter type:CNL
MONTHYEARCNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-006, Application to Modify Technical Specifications 3.8.1, AC Sources – Operating, and 3.8.2, AC Sources – Shutdown, for Sequoyah Nuclear Plant (SQN-TSC-22-03)2024-04-15015 April 2024 Application to Modify Technical Specifications 3.8.1, AC Sources – Operating, and 3.8.2, AC Sources – Shutdown, for Sequoyah Nuclear Plant (SQN-TSC-22-03) CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements CNL-24-007, Annual Insurance Status Report2024-03-27027 March 2024 Annual Insurance Status Report CNL-24-008, Guarantee of Payment of Deferred Premiums - 2023 Annual Report2024-03-27027 March 2024 Guarantee of Payment of Deferred Premiums - 2023 Annual Report CNL-24-027, Response to Request for Additional Information Regarding Sequoyah Nuclear Plant, Units 1 and 2, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-03-14014 March 2024 Response to Request for Additional Information Regarding Sequoyah Nuclear Plant, Units 1 and 2, Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-24-029, Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 372024-03-14014 March 2024 Response to Request for Additional Information Regarding Tennessee Valley Authority - Request for Exemption from Specific Requirements of 10 CFR Part 37 CNL-24-023, Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-17, Revision 252024-02-20020 February 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-17, Revision 25 CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions CNL-23-068, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions CNL-23-049, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan .2023-06-26026 June 2023 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan . CNL-23-042, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-05-16016 May 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-032, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 412023-04-27027 April 2023 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 41 CNL-23-030, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2023-04-27027 April 2023 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-23-033, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-04-24024 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-029, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-04-11011 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-23-012, Revision to the Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, (TS-19-02)2023-04-11011 April 2023 Revision to the Application to Revise Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis, (TS-19-02) CNL-23-023, Annual Insurance Status Report2023-03-30030 March 2023 Annual Insurance Status Report CNL-23-024, TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report2023-03-29029 March 2023 TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report CNL-23-022, Decommissioning Funding Status Report2023-03-29029 March 2023 Decommissioning Funding Status Report CNL-23-021, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-03-0808 March 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-22-037, Application to Revise Technical Specifications to Adopt TSTF-541-A, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position (BFN TS-533)2023-01-31031 January 2023 Application to Revise Technical Specifications to Adopt TSTF-541-A, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position (BFN TS-533) CNL-23-003, Browns Nuclear Plant, Units 1, 2 & 3; Sequoyah Nuclear Plant, Units 1 & 2; and Watts Bar Nuclear Plant, Units 1 & 2 - Organizational Topic Report TVA-NPOD89-A2023-01-30030 January 2023 Browns Nuclear Plant, Units 1, 2 & 3; Sequoyah Nuclear Plant, Units 1 & 2; and Watts Bar Nuclear Plant, Units 1 & 2 - Organizational Topic Report TVA-NPOD89-A CNL-23-011, Steam Generator Tube Inspection Report to Reflect TSTF-577 Reporting Requirements2023-01-18018 January 2023 Steam Generator Tube Inspection Report to Reflect TSTF-577 Reporting Requirements CNL-23-009, Response to Request for Additional Information Request to Revise Technical Specification 3.4.122023-01-0404 January 2023 Response to Request for Additional Information Request to Revise Technical Specification 3.4.12 CNL-23-008, Tennessee Valley Authority – Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2022-12-22022 December 2022 Tennessee Valley Authority – Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-22-106, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-14, Revision 38, Nuclear Emergency Public Information Organization and Operat2022-11-28028 November 2022 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision. Includes CECC EPIP-14, Revision 38, Nuclear Emergency Public Information Organization and Operatio CNL-22-099, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2022-10-31031 October 2022 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-22-104, Correction to Response to Request for Additional Information Regarding Sequoyah Nuclear Plant, Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alternative RV-022022-10-31031 October 2022 Correction to Response to Request for Additional Information Regarding Sequoyah Nuclear Plant, Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alternative RV-02 CNL-22-098, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC EPIP-7, Rev. 45 & CECC EPIP-8, Rev. 552022-10-17017 October 2022 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC EPIP-7, Rev. 45 & CECC EPIP-8, Rev. 55 CNL-22-084, Response to Request for Additional Information Regarding License Amendment Request to License Amendment Request to Modify Approved 10 CFR 50.69 Categorization Process (SQN-TS-21-07)2022-09-16016 September 2022 Response to Request for Additional Information Regarding License Amendment Request to License Amendment Request to Modify Approved 10 CFR 50.69 Categorization Process (SQN-TS-21-07) CNL-22-085, Response to Request for Additional Information Regarding Sequoyah Nuclear Plant (Sqn), Units 1 and 2 and Watts Bar Nuclear Plant (Wbn), Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Al2022-09-0202 September 2022 Response to Request for Additional Information Regarding Sequoyah Nuclear Plant (Sqn), Units 1 and 2 and Watts Bar Nuclear Plant (Wbn), Units 1 and 2, American Society of Mechanical Engineers Operation and Maintenance Code, Request for Alte CNL-22-053, Response to Request for Additional Information Regarding Application to Revise Sequoyah Nuclear Plant Units 1 and 2 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis - Second Partial Response to Additional Requ2022-08-22022 August 2022 Response to Request for Additional Information Regarding Application to Revise Sequoyah Nuclear Plant Units 1 and 2 Updated Final Safety Analysis Report Regarding Changes to Hydrologic Analysis - Second Partial Response to Additional Reques CNL-22-077, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2022-08-11011 August 2022 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 2024-09-24
[Table view] Category:Status Report
MONTHYEARCNL-24-007, Annual Insurance Status Report2024-03-27027 March 2024 Annual Insurance Status Report IR 05000259/20230062024-02-28028 February 2024 Annual Assessment Letter for Sequoyah Nuclear Plant, Units 1, 2 - Report 05000259/2023006, 05000260/2023006 and 05000296/2023006 CNL-23-022, Decommissioning Funding Status Report2023-03-29029 March 2023 Decommissioning Funding Status Report CNL-22-099, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2022-10-31031 October 2022 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-22-070, Status Regarding the Improved Flood Mitigation System Project2022-06-30030 June 2022 Status Regarding the Improved Flood Mitigation System Project CNL-22-052, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status2022-04-27027 April 2022 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status CNL-21-097, Status Regarding the Improved Flood Mitigation System Project2021-12-21021 December 2021 Status Regarding the Improved Flood Mitigation System Project CNL-21-048, Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Miilstone Status Update2021-04-29029 April 2021 Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Miilstone Status Update CNL-21-032, Watt Bar Nuclear Plant, Units 1 and 2 - Annual Insurance Status Report2021-03-25025 March 2021 Watt Bar Nuclear Plant, Units 1 and 2 - Annual Insurance Status Report CNL-21-030, Decommissioning Funding Status Report2021-03-25025 March 2021 Decommissioning Funding Status Report IR 05000327/20200062021-03-0303 March 2021 Annual Assessment Letter for Sequoyah Nuclear Plant, Units 1 and 2 - Report 05000327/2020006 and 05000328/2020006 CNL-20-088, Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update2020-10-29029 October 2020 Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update CNL-20-020, Annual Insurance Status Report2020-03-20020 March 2020 Annual Insurance Status Report CNL-19-094, Status Regarding the Improved Flood Mitigation System Project2019-09-30030 September 2019 Status Regarding the Improved Flood Mitigation System Project CNL-19-046, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update and Commitment Changes2019-04-29029 April 2019 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update and Commitment Changes CNL-18-136, Plants: Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update2018-12-27027 December 2018 Plants: Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update CNL-18-122, Status Regarding the Improved Flood Mitigation System Project2018-09-28028 September 2018 Status Regarding the Improved Flood Mitigation System Project CNL-18-093, Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update2018-06-22022 June 2018 Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update CNL-18-025, Annual Insurance Status Report2018-03-28028 March 2018 Annual Insurance Status Report CNL-17-072, Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update2017-06-27027 June 2017 Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update CNL-17-021, Decommissioning Funding Status Report2017-03-30030 March 2017 Decommissioning Funding Status Report CNL-17-031, Annual Insurance Status Report2017-03-30030 March 2017 Annual Insurance Status Report CNL-15-259, Eleventh Progress Update on Improved Flood Mitigation System Project2015-12-22022 December 2015 Eleventh Progress Update on Improved Flood Mitigation System Project CNL-15-175, Fifth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-08-28028 August 2015 Fifth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) CNL-15-082, Tennessee Valley Authority (TVA) Nuclear Power Group Commercial Grade Dedication Recovery Project - April 2015 Status Report2015-04-30030 April 2015 Tennessee Valley Authority (TVA) Nuclear Power Group Commercial Grade Dedication Recovery Project - April 2015 Status Report CNL-15-058, Fifth Status Update of Planned Actions to Facilitate Maintenance of 6.9 Kilovolt and 480 Volt Shutdown Boards at Sequoyah, Units 1 and 22015-03-27027 March 2015 Fifth Status Update of Planned Actions to Facilitate Maintenance of 6.9 Kilovolt and 480 Volt Shutdown Boards at Sequoyah, Units 1 and 2 CNL-15-037, Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) CNL-15-038, Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2015-02-27027 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) CNL-15-018, Nuclear Power Group Commercial Grade Dedication Recovery Project - January 2015 Status Report2015-01-30030 January 2015 Nuclear Power Group Commercial Grade Dedication Recovery Project - January 2015 Status Report CNL-14-195, the Tennessee Valley Authority (TVA) Nuclear Power Group Commercial Grade Dedication Recovery Project - October 2014 Status Report2014-10-31031 October 2014 the Tennessee Valley Authority (TVA) Nuclear Power Group Commercial Grade Dedication Recovery Project - October 2014 Status Report CNL-14-133, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)(TAC Nos..2014-08-28028 August 2014 Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)(TAC Nos.. CNL-14-063, the Tennessee Valley Authority Nuclear Power Group Commercial Grade Dedication Recovery Project - April 2014 Status Report2014-04-30030 April 2014 the Tennessee Valley Authority Nuclear Power Group Commercial Grade Dedication Recovery Project - April 2014 Status Report CNL-14-050, Fourth Quarterly Status Report to the Flooding Hazard Reevaluation Report Extension Request2014-03-31031 March 2014 Fourth Quarterly Status Report to the Flooding Hazard Reevaluation Report Extension Request CNL-14-029, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant2014-02-28028 February 2014 Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant CNL-14-008, the Tennessee Valley Authority (TVA) Nuclear Power Group Commercial Grade Dedication Recovery Project - January 2014 Status Report2014-01-31031 January 2014 the Tennessee Valley Authority (TVA) Nuclear Power Group Commercial Grade Dedication Recovery Project - January 2014 Status Report CNL-13-144, Third Quarterly Status Report to the Flooding Hazard Reevaluation Report Extension Request2013-12-31031 December 2013 Third Quarterly Status Report to the Flooding Hazard Reevaluation Report Extension Request ML13247A2862013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML13247A2912013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant ML13093A3702013-04-0101 April 2013 Annual Insurance Status Report ML12024A3762011-12-28028 December 2011 State-of-the-Art Reactor Consequence Analyses, Current Status and Next Steps ML1009500642010-04-0101 April 2010 Annual Insurance Status Report ML0909302852009-04-0101 April 2009 Watts Barr (WBN) Nuclear Plants - Insurance Status ML0709306892007-04-0202 April 2007 (Bfn), Sequoyah (Sqn), and Watts Bar (WBN) Nuclear Plants - Insurance Status ML0711705732007-03-28028 March 2007 TVA - Decommissioning Funding Status Report ML0509402222005-03-30030 March 2005 TVA- Decommissioning Funding Status Report - Browns Ferry (Bfn), Sequoyah (SQN) and Watts Bar (WBN) Nuclear Plants ML0330701382003-10-30030 October 2003 TVA - Decommissioning Funding Status Report - Browns Ferry (Bfn), Sequoyah (Sqn), and Watts Bar (WBN) Nuclear Plants - Supplemental Information ML0309202232003-03-31031 March 2003 Decommissioning Funding Status Report for Browns Ferry, Sequoyah, and Watts Bar Nuclear Plants ML0224007812002-01-18018 January 2002 E-mail from Jacob Zimmerman, Bulletin 2001-01 Status Report 2024-03-27
[Table view] |
Text
L44 140228 004 Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-14-029 February 28, 2014 10 CFR 2.202 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328
Subject:
Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant (TAC Nos. MF0794 and MF0795)
References:
- 1. NRC Order Number EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 (ML12054A679)
- 2. NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation, Revision 0, dated August 29, 2012 (ML12221A339)
- 3. NEI 12-02, Industry Guidance for Compliance with NRC Order EA-12-051, To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, Revision 1, dated August 2012 (ML12240A307)
- 4. Letter from TVA to NRC, Tennessee Valley Authority (TVA) - Initial Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated October 29, 2012 (ML12307A105)
U.S. Nuclear Regulatory Commission Page 2 February 28, 2014
- 5. Letter from TVA to NRC, Tennessee Valley Authority (TVA) - Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant, dated February 28, 2013 (ML13063A011)
- 6. Letter from NRC to TVA, Sequoyah Nuclear Plant, Units 1 and 2 -
Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051)
(TAC Nos. MF0794 and MF0795), dated July 17, 2013 (ML13198A354)
- 7. Letter from TVA to NRC, Response to NRC Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) (TAC Nos. MF0794 and MF0795), dated August 16, 2013 (ML13235A007)
- 8. Letter from TVA to NRC, First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant, dated August 28, 2013 (ML13247A291)
- 9. Letter from NRC to TVA, Sequoyah Nuclear Plant, Units 1 and 2 - Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC Nos. MF0794 and MF0795),
dated November 21, 2013 (ML13312A415)
On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued an order (Reference 1) to Tennessee Valley Authority (TVA). Reference 1 was immediately effective and directs TVA to install reliable spent fuel pool level instrumentation (SFPLI). Specific requirements are outlined in Attachment 2 of Reference 1.
Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document Nuclear Energy Institute (NEI 12-02), Revision 1 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the TVA initial status report regarding SFPLI strategies. Reference 5 provided the TVA Sequoyah Nuclear Plant, Units 1 and 2 overall integrated plan. On July 17, 2013, the NRC issued a request for additional information (RAI) (Reference 6) and TVA provided its response on August 16, 2013 (Reference 7).
Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. TVA submitted the first six-month update on August 28, 2013 (Reference 8).
U.S. Nuclear Regulatory Commission Page 3 February 28, 2014 The NRC issued its Interim Staff Evaluation and RAls regarding TVA's overall integrated plan on November 21 , 2013 (Reference 9).
- The purpose of this letter is to provide the second six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The enclosed report provides an update of milestone accomplishments since submittal of the first six-month status report, including any changes to the compliance method or schedule. The enclosed report also provides a status of the response to the RAls submitted in Reference 9.
The enclosure describes the plans that TVA will use to meet the regulatory requirements outlined in Attachment 2 of Reference 1, but does not identify any additional actions to be taken by TVA. Therefore, this letter contains no regulatory commitments.
If you have any question regarding this submittal , please contact Kevin Casey at (423) 751-8523.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 28th day of February 2014.
ice President, Nuclear Licensing
Enclosure:
Tennessee Valley Authority Sequoyah Nuclear Plant's Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) cc (Enclosure):
NRR Director - NRC Headquarters NRO Director - NRC Headquarters NRC Regional Administrator - Region II NRC Project Manager - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant
ENCLOSURE TENNESSEE VALLEY AUTHORITY SEQUOYAH NUCLEAR PLANTS SECOND SIX-MONTH STATUS REPORT IN RESPONSE TO THE MARCH 12, 2012, COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO RELIABLE SPENT FUEL POOL INSTRUMENTATION (ORDER NUMBER EA-12-051) 1 Introduction Sequoyah Nuclear Plant (SQN) developed an Overall Integrated Plan (Reference 1 in Section 8 of this Enclosure), documenting the requirements to install reliable spent fuel pool level instrumentation (SFPLI), in response to Reference 2. This attachment provides an update of milestone accomplishments since submittal of the first six-month status report (Reference 5),
including any changes to the compliance method or schedule. This enclosure also provides a response to the request for additional information (RAI) issued by the NRC in its Interim Staff Evaluation (Reference 6).
2 Milestone Accomplishments The following milestone(s) have been completed since the development of the first six-month status report (Reference 5), and are current as of February 10, 2014.
10% design impact review of Design Change Notice (DCN) 23195, for design of SFPLI, was completed on December 4, 2013.
3 Milestone Schedule Status The following updates the milestone schedule to support the Overall Integrated Plan. This section provides the activity status of each item, and the expected completion date noting any change. The dates are planning dates subject to change as design and implementation details are developed.
The milestone target completion dates do not impact the order implementation date.
Page 1 of 4
Target Completion Revised Date as Activity Target Milestone Stated in the Status Completion First Six-Date Month Update (Reference 5)
Submit 60 Day Status Report 10/29/2012 Complete Submit Overall Integrated Plan 02/28/2013 Complete Submit 6 Month Updates:
Update 1 08/28/2013 Complete Update 2 02/28/2014 Complete Update 3 08/28/2014 Not Started Update 4 02/28/2015 Not Started Update 5 08/28/2015 Not Started Update 6 02/28/2016 Not Started Update 7 08/28/2016 Not Started July 17, 2013 RAI Response 08/16/2013 Complete NRC ISE RAI Response 06/30/2015 Started Modifications:
Unit 1 Design Engineering 10/14/2014 Design started 07/01/2014 Unit 1 Implementation 02/26/20151 Not Started 04/13/2015 Unit 2 Design Engineering 10/14/2014 Design started 07/01/2014 Unit 2 Implementation 02/26/20151 Not Started 04/13/2015 Procedures:
Create Procedures2 10/31/2014 Not Started Training:
Develop Training Plan2 10/31/2014 Not Started Training Complete2 04/30/2015 Not Started Full Site SFPLI Implementation 05/28/2015 Not Started Submit Completion Report 06/28/2015 Not Started Notes: 1. In the first six-month update dated August 28, 2013 (Reference 5), the target completion dates were revised to reflect implementation of the modifications on-line.
The implementation dates are further revised as shown in the column titled Revised Target Completion Date above. These revised dates fall within the schedule required by NRC Order EA-12-051.
- 2. These milestones were not included in the February 28, 2013, Overall Integrated Plan.
4 Changes to Compliance Method There are no other changes to the compliance method as documented in the Overall Integrated Plan (Reference 1) and the first six-month status report (Reference 5).
Page 2 of 4
5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Sequoyah Nuclear Plant (SQN) expects to comply with the order implementation date and no relief/relaxation is required at this time.
6 Open Items from Overall Integrated Plan and NRC Evaluation The following tables provide a summary of the open items documented in the Overall Integrated Plan or the NRC Evaluation and the status of each item.
Overall Integrated Plan Open Item Status OI-1) TVA will complete an instrument channel Engineering and vendor uncertainty calculation and document instrument documentation are in progress.
channel accuracy and calibration requirements. This will complete on the Design Engineering milestone shown in the table in Section 3.
OI-2) TVA plans to utilize Guided Wave Radar Engineering and vendor technology. Confirm final technology selection documentation are in progress.
after contracts are complete. This will complete on the Design Engineering milestone shown in the table in Section 3.
OI-3) Confirm that the sensor cable and light weight at Engineering and vendor the bottom of sensor cable will not damage the documentation are in progress.
SFP liner from impact during seismic event. This will complete on the Design Engineering milestone shown in the table in Section 3.
OI-4) After detailed engineering design is complete, Engineering and vendor confirm that SFP level channel components and documentation are in progress.
cable routing will be contained within seismic This will complete on the Design structures such that the installation will comply Engineering milestone shown in with the reasonable protection guidance of the table in Section 3.
NEI-12-06.
NRC Evaluation Open Item Status None N/A 7 Potential NRC Evaluation Impacts There are no potential impacts to the NRC Evaluation identified at this time.
Page 3 of 4
8 References The following references support the updates to the Overall Integrated Plan described in this enclosure.
- 1. Letter from TVA to NRC, Tennessee Valley Authority (TVA) - Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant, dated February 28, 2013. (ML13063A011)
- 2. NRC Order Number EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012. (ML1254A679)
- 3. Letter from NRC to TVA, Sequoyah Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Overall Integrated plan for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) (TAC Nos. MF0764 and MF0765), dated July 17, 2013. (ML13198A354)
- 4. Letter from TVA to NRC, Response to NRC Request for Additional Information Regarding Overall Integrated plan for Reliable Spent Fuel Pool Instrumentation (Order No.
EA-12-051) (TAC Nos. MF0764 and MF0765), dated August 16, 2013. (ML13235A007)
- 5. Letter from TVA to NRC, First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant, dated August 28, 2013. (ML13247A291)
- 6. Letter from NRC to TVA, Sequoyah Nuclear Plant, Units 1 and 2 - Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC Nos.
MF0794 and MF0795), dated November 21, 2013. (ML13312A415)
- 9. RAI Response On November 21, 2013, the NRC issued RAIs with its Interim Staff Evaluation (Reference 6). The NRC requested all RAI information be provided by June 30, 2015.
Page 4 of 4