March 4, 2014
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR LIMERICK UNITS 1 AND 2 (REPORT 05000352/2013001 AND 05000353/2013001)
Dear Mr. Pacilio:
On February 13, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Limerick Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators in addition to inspection results and enforcement actions from January 1, 2013 through December 31, 2013. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Limerick Units 1 and 2, operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Limerick Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all performance indicators demonstrated that your performance was within the nominal, expected range (i.e, green).
Therefore, the NRC plans to conduct Reactor Oversight Process baseline inspections at your facility.
As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised beginning in calendar year (CY) 2014. New cross-cutting aspects identified in CY 2014 will be coded under the latest revision to IMC 0310. Cross-cutting aspects identified in the last six months of 2013 using the previous terminology will be converted to the latest revision in accordance with the cross-reference in IMC 0310. The revised cross-cutting aspects will be evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305 starting with the CY 2014 mid-cycle assessment review.
The enclosed inspection plan lists the inspections scheduled through June 30, 2015. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. In addition to baseline inspections, the NRC will perform Inspection Procedure 92709, Licensee Plans for Coping with Strikes (security contract expires October 31, 2014). The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence.
Additionally, an NRC audit of licensee efforts towards compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, is ongoing. This audit includes an onsite component in order for the NRC to evaluate mitigating strategies as described in licensee submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRC's Agencywide Document Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (610)337-5200 with any questions you have regarding this letter.
Sincerely,
/RA/
Fred L. Bower, III, Chief Projects Branch 4 Division of Reactor Projects
Docket Nos.: 50-352, 50-353 License Nos.: NPF-39, NPF-85
Enclosure: Inspection Plan
cc w/encl: Distribution via ListServ
SUNSI Review
Non-Sensitive Sensitive
Publicly Available Non-Publicly Available
OFFICE RI/DRP RI/DRP RI/DRP
NAME mmt EDiPaolo/ GSB for SBarber/ GSB FBower/ FLB
DATE 02/25/14 02/25/14 02/26/14
Page 1 of 3 02/13/2014 09:00:46 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Limerick Inspection / Activity Plan 01/10/2014 - 06/30/2015 71124.08
- RADWASTE
1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 02/10/2014 02/14/2014 71124
- RAD SAFETY INSPECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 02/24/2014 02/28/2014 1, 2 IP Occupational ALARA Planning and Controls 71124.02 02/24/2014 02/28/2014 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 02/24/2014 02/28/2014 1, 2 IP Occupational Dose Assessment 71124.04 02/24/2014 02/28/2014 1, 2 IP Radiation Monitoring Instrumentation 71124.05 02/24/2014 02/28/2014 7111108G
- U1 INSERVICE INSPECTION
1 IP Inservice Inspection Activities - BWR 7111108G 03/31/2014 04/04/2014 71124
- RAD SAFETY INSPECTION
1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/31/2014 04/04/2014
IP Occupational ALARA Planning and Controls 71124.02 03/31/2014 04/04/2014
IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 03/31/2014 04/04/2014
IP Occupational Dose Assessment 71124.04 03/31/2014 04/04/2014
IP Radiation Monitoring Instrumentation 71124.05 03/31/2014 04/04/2014 7111111B
- LIM LSRO REQ INSP WITH P/F RESULTS
1, 2 IP Licensed Operator Requalification Program 7111111B 06/02/2014 06/06/2014 71124
- RAD EFFLUENTS MONITORING PROGRAM
1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 06/02/2014 06/06/2014 INSP
- RADIATION PROTECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 07/07/2014 07/11/2014 1, 2 IP Occupational ALARA Planning and Controls 71124.02 07/07/2014 07/11/2014 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 07/07/2014 07/11/2014 1, 2 IP Occupational Dose Assessment 71124.04 07/07/2014 07/11/2014 1, 2 IP Radiation Monitoring Instrumentation 71124.05 07/07/2014 07/11/2014 7111107T
- TRIENNIAL HEAT SINK
1, 2 IP Heat Sink Performance 7111107T 07/14/2014 07/18/2014 71152B
- PI&R BIENNIAL
1, 2 IP Problem Identification and Resolution 71152B 09/15/2014 09/20/2014 1, 2 IP Problem Identification and Resolution 71152B 09/29/2014 10/03/2014 10/6EXAM
- LIMERICK INITIAL EXAM
1 FY15-LIMERICK INITIAL OPERATOR LICENSING EXAM U01892 12/15/2014 12/19/2014
FY15-LIMERICK INITIAL OPERATOR LICENSING EXAM U01892 01/12/2015 01/21/2015 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 3 02/13/2014 09:00:46 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Limerick Inspection / Activity Plan 01/10/2014 - 06/30/2015 INSP
- RADIATION PROTECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 09/08/2014 09/12/2014 1, 2 IP Occupational ALARA Planning and Controls 71124.02 09/08/2014 09/12/2014 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 09/08/2014 09/12/2014 1, 2 IP Occupational Dose Assessment 71124.04 09/08/2014 09/12/2014 1, 2 IP Radiation Monitoring Instrumentation 71124.05 09/08/2014 09/12/2014 1, 2 IP Performance Indicator Verification 71151 09/08/2014 09/12/2014 7111111B
- LIMERICK REQUAL INSP WITH P/F RESULTS
1, 2 IP Licensed Operator Requalification Program 7111111B 11/17/2014 11/21/2014 MODS
- PERMANENT PLANT MODIFICATIONS
1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 7111117T 11/03/2014 11/07/2014 1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 7111117T 11/17/2014 11/21/2014 7111111B
- LIMERICK REQUAL INSP WITH P/F RESULTS
1, 2 IP Licensed Operator Requalification Program 7111111B 01/19/2015 01/23/2015 EP PROG
- EP PROGRAM INSPECTION
1, 2 IP Alert and Notification System Testing 7111402 12/01/2014 12/05/2014 1, 2 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 12/01/2014 12/05/2014 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 12/01/2014 12/05/2014 71124
- RADIATION PROTECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/16/2015 03/20/2015 1, 2 IP Occupational ALARA Planning and Controls 71124.02 03/16/2015 03/20/2015 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 03/16/2015 03/20/2015 1, 2 IP Occupational Dose Assessment 71124.04 03/16/2015 03/20/2015 1, 2 IP Radiation Monitoring Instrumentation 71124.05 03/16/2015 03/20/2015 7111108G
- U2 INSERVICE INSPECTION
2 IP Inservice Inspection Activities - BWR 7111108G 04/13/2015 04/17/2015 71124
- RADIATION PROTECTION
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 04/13/2015 04/17/2015 1, 2 IP Occupational ALARA Planning and Controls 71124.02 04/13/2015 04/17/2015 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 04/13/2015 04/17/2015 1, 2 IP Occupational Dose Assessment 71124.04 04/13/2015 04/17/2015 1, 2 IP Radiation Monitoring Instrumentation 71124.05 04/13/2015 04/17/2015 7111121
- CDBI
1, 2 IP Component Design Bases Inspection 7111121 06/08/2015 06/12/2015 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 3 of 3 02/13/2014 09:00:46 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Limerick Inspection / Activity Plan 01/10/2014 - 06/30/2015 7111121
- CDBI
1, 2 IP Component Design Bases Inspection 7111121 06/22/2015 06/26/2015 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.