ML13330B236

From kanterella
Jump to navigation Jump to search

Submits Info Re Implementation Schedules for Compliance W/ Requirements of ATWS Rule (10CFR50.62).Request for Delay Beyond Third Outage Will Be Handled on Case to Case Basis,If Presented in Timely Fashion & If Adequately Justified
ML13330B236
Person / Time
Site: San Onofre 
Issue date: 07/24/1987
From: Dudley R
Office of Nuclear Reactor Regulation
To: Baskin K
SOUTHERN CALIFORNIA EDISON CO.
References
TAC-59138, NUDOCS 8707290016
Download: ML13330B236 (4)


Text

Docket Nos.:

50-206 DISJRIBUTION Docket File GWKnighton Mr. Kenneth P. Baskin NRC & Local"PDRs OGC-Bethesda Vice President, Nuclear Engineering PD #5 Plant EJordan Safety and Licensing Department JPartlow GMHolahan Southern California Edison Company ACRS (10)

JLee 2244 Walnut Grove Avenue HRood RDudley Post Office Box 800 ICSB Plant Rosemead, California 91770

Dear Mr. Baskin:

SUBJECT:

SCHEDULE FOR IMPLEMENTATION OF THE ATWS RULE SAN ONOFRE, UNIT 1 (TAC NO. 59138)

The purpose of this letter is to provide you information concerning implementa tion schedules for compliance with the requirements of the ATWS rule (10 CFR 50.62). The specific requirements are listed in paragraphs (c)(1) through (c)(5) of the rule. Paragraph (d) of the rule addresses implementation schedules.

The ATWS rule was published in the Federal Register on June 26, 1984. Quality Assurance (QA) guidance for non-safety related ATWS equipment was issued by Generic Letter (GL) 85-06 dated April 16, 1985. Therefore, plant specific schedules for meeting the requirements of the ATWS rule were required to be submitted to NRR by October 15, 1985 (180 days after issuance of the QA guidance). Many utilities responded by stating that final schedules for meeting the requirements of the rule could not be determined until the staff completed its reviews of generic ATWS designs. The generic reviews have either only recently been completed or are still ongoing. Delays incurred in preparation of the QA guidance, and the extensive time and effort required to resolve complex issues associated with the development of review criteria, interpretation of the supplementary information published with the rule, and the review of generic ATWS designs have all impacted utility schedules.

Because of the cumulative effect of these delays, and in recognition that a sound and thorough engineering approach to resolve ATWS concerns is preferred to a rushed effort forced by schedular constraints, the NRC will consider favorably requests to extend the schedule for implementation of the ATWS rule.

Pursuant to 10 CFR 50.62(d) the delays referred to above justify extending implementation of the ATWS rule requirements to no later than the third refueling outage after July 24, 1984. A request for a delay beyond the third outage will be handled on a case-by-case basis if it is presented in a timely fashion, and if it is adequately justified.

8707290016 870724' PDR ADOCK 05000206 PDR

-2 By letter dated October 27, 1986, Southern California Edison (SCE) stated that the ATWS mitigation system (turbine trip) at San Onofre 1 would be installed during the Cycle X refueling outage pending NCR review and approval prior to the outage. Since the Cycle X outage is the second outage beginning since July 24, 1984, this schedule is clearly acceptable in accordance with the guidance given above.

However, please contact me if you find it necessary to change the implementation schedule for ATWS equipment at San Onofre 1 in accordance with the guidance provided above.

Sincerely, Original signed by Richard F. Dudley, Project Manager Project Directorate V Division of Reactor Projects III, IV, V and Special Projects cc:

See next page DRSP/PDV

" RS /PDV ing B C OGCe( DR

. DV RDudley:cd H d CSB G

on 7/ /87 7/ 87 7/2487 7/1</87 7/V87 OFFICIAL RECORD OPY

-2 By letter dated October 27, 1986, Southern California Edison (SCE) stated that the ATWS mitigation system (turbine trip) at San Onofre 1 would be installed during the Cycle X refueling outage pending NRC review and approval prior.to the outage. Since the Cycle X outage is the second outage beginning since July 24, 1984, this schedule is clearly acceptable.

However, please contact me if you find it necessary to change the implementation schedule for ATWS equipment at San Onofre 1 in accordance with the guidance provided above.

Sincerely, Richard F. Dudley, Project Manager Project Directorate V Division of Reactor Projects III, IV, V and Special Projects cc:

See next page

  • See previous concurrence
  • DRSP/PDV
  • OGC DRSP/D:PDV RDudley:cd ICSB GKnighton 7/1/87 7/2/87 7/15/87 7/ /87 OFFICIAL RECORD COPY

Mr. Kenneth P. Baskin San Onofre Nuclear Generating Southern California Edison Company Station, Unit No. 1 cc Charles R. Kocher, Assistant Mr. Joseph 0. Ward, Chief General Counsel Radiological Health Branch James Beoletto, Esquire State Department of Health Southern California Edison Company Services Post Office Box 800 714 P Street, Office Bldg. 8 Rosemead, California 91770 Sacramento, California 95814 David R. Pigott Mr. Hans Kaspar, Executive Director Orrick, Herrington & Sutcliffe Marine Review Committee, Inc.

600 Montgomery Street 531 Encinitas Boulevard, Suite 105 San Francisco, California 94111 Encinitas, California 92024 Mr. Stephen B. A1lman Dennis M. Smith, Chief San Diego Gas & Electric Company Radiolcgical Programs Division P. 0. Box 1831 Governor's Office of Emergency Svcs.

San Diego, California 92112 State of California 2800 Meadowview Road Sacramento, CA 95832 Resident Inspector/San Onofre NPS c/o U.S. NRC P. 0. Box 4329 San Clemente, California 92672 Mayor City of San Clemente San Clemente, California 92672 Chairman Board of Supervisors County of San Diego San Diego, California 92101 Director Energy Facilities Siting Division Energy Resources Conservation &

Development Commission 1516 -

9th Street Sacramento, California 95814 Regional Administrator, Region V U.S. Nuclear Regulatory Commission 1450 Maria Lane Walnut Creek, California 94596