Grants Util Request to Implement ATWS Mods in Cycle 11 Refueling Outage Instead of Cycle 10 Refueling Outage.Delays Incurred in Preparing QA Guidance & Resolving Complex Issues Associated W/Development of Review Criteria
ML13322B028
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 09/01/1989
From: Trammell C
Office of Nuclear Reactor Regulation
To: Ray H
SOUTHERN CALIFORNIA EDISON CO.
References
TAC-59138, NUDOCS 8909130296
Download: ML13322B028 (3)


Text

September 1, 1989 Docket No.:

50-206 Mr. Harold B. Ray Vice President Southern California Edison Company Irvine Operations Center 23 Parker Irvine, California 92718

Dear Mr. Ray:

SUBJECT:

ATWS IMPLEMENTATION SCHEDULE (TAC NO. 59138)

Re:

San Onofre Nuclear Generating Station, Unit No. 1 By letter dated September 29, 1988, Southern California Edison Company (SCE) requested that it be permitted to implement the ATWS modifications in the Cycle 11 refueling outage instead of the Cycle 10 refueling outage. This would be the third refueling outage after July 26, 1984, instead of the second refueling outage after that date. In an earlier letter to SCE dated July 24, 1987, the NRC staff indicated that it would consider favorably requests to extend the schedule for implementation to no later than the third refueling outage after July 26, 1984 because of various delays. Delays incurred in preparing the QA guidance, the extensive time and effort required to resolve complex issues associated with the development of review criteria, interpretation of the supplementary information published with the rule, and the review of generic ATWS designs all impacted utility schedules and justify extending implementa tion. SCE's request is therefore approved.

Sincerely, original signed by Charles Trammell Charles M. Trammell, Senior Project Manager Project Directorate V Division of Reactor Projects -

III, IV, V and Special Projects cc: See next page DISTRIBUTION Docket File PD5 Plant File NRC & LPDRs EJordan CTrammell (2)

BGrimes MVirgilio ACRS (10)

OF*/

JLee DLynch OGC JTatum It DHichman

[01 WS SKED]

D PD5 ATWS/LPM

.5 rammell:dr DLynch ton 8A \\/89 8s, /89 1/ /89

9091:30296 E:9090 1 PDR ADCOCK 050CK:20,t.

P PIDC

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 September 1, 1989 Docket No.:

50-206 Mr. Harold B. Ray Vice President Southern California Edison Company Irvine Operations Center 23 Parker Irvine, California 92718 Dear Mr.

Ray:

SUBJECT:

ATWS IMPLEMENTATION SCHEDULE (TAC NO. 59138)

Re:

San Onofre Nuclear Generating Station, Urit No. 1 by letter dated September 29, 1988, Southern California Edison Company (SCE) requested that it be permitted tc implement the ATWS modifications in the Cycle 11 refueling outage instead of the Cycle 10 refueling outage. This would be the third refueling outage after July 26, 1984, instead of the second refueling outage after that date.

in an earlier letter to SCE dated July 24, 1987, the NRC staff indicated that it would consider favorably requests to extend the schedule for, implementation to no later than the third refueling outage after July 26, 1984 because of various delays. Delays incurred in preparing the QA guidance, the extensive time and effort required to resolve complex issues associated with the development of review criteria, interpretation of the supplementary information published with the rule, and the review of generic ATWS designs all impacted utility schedules and justify extending implementa tion. SCE's request is therefore approved.

Sincerely, Charles M. Trammell, Senior Project Manager Project Directorate V Division of Reactor Projects -

III, IV, V and Special Projects cc:

See next page

Mr. Harold B. Ray San Onofre Nuclear Generating Southern California Edison Company Station, Unit No. 1 cc David R. Pigott Mr. F. B. Marsh, Project Manager Orrick, Herrington & Sutcliffe Bechtel Power Corporation 600 Montgomery Street P. 0. Box 60860 San Francisco, California 94111 Terminal Annex Los Angeles, California 90060 Mr. Robert G. Lacy Manager, Nuclear San Diego Gas & Electric Company P. 0. Box 1831 San Diego, California 92112 Resident Inspector/San Onofre NPS U.S. NRC P. 0. Box 4329 San Clemente, California 92672 Mayor City of San Clemente San Clemente, California 92672 Chairman Board of Supervisors County of San Diego 1600 Pacific Highway Room 335 San Diego, California 92101 Regional Administrator, Region V U.S. Nuclear Regulatory Commission 1450 Maria Lane, Suite 210 Walnut Creek, California 94596 Mr. John Hickman Senior Health Physicist Environmental Radioactive Management Unit Environmental Management Branch State Department of Health Services 714 P Street, Room 616 Sacramento, California 95814 Mr. Don Womeldorf Chief Environmental Management California Department of Health 714 P Street, Room 616 Sacramento, California 95814 (9)