Shine Medical Technologies, Inc., Application for Construction Permit Response to Environmental Requests for Additional Information, Enclosure 2 Attachment 18 - Permits and Approvals Required for Construction and Operation
ML13309B012
Person / Time
Site: SHINE Medical Technologies
Issue date: 10/04/2013
From:
SHINE Medical Technologies
To:
Office of Nuclear Reactor Regulation
Shared Package
ML13303A887 List:
References
SMT-2013-034
Download: ML13309B012 (4)


Text

3 pages follow ENCLOSURE 2 ATTACHMENT 18 SHINE MEDICAL TECHNOLOGIES, INC.

SHINE MEDICAL TECHNOLOGIES, INC. APPLICATION FOR CONSTRUCTION PERMIT RESPONSE TO ENVIRONMENTAL REQUESTS FOR ADDITIONAL INFORMATION PERMITS AND APPROVALS REQUIRED FOR CONSTRUCTION AND OPERATION

Page 1 of 3 Agency Regulatory Authority Permit or Approval Activity Covered Expected Timeframe of Receipt Status Regulatory or Other Milestone Dependency U.S. Nuclear Regulatory Commission Atomic Energy Act 10 CFR 50.50 Construction Permit Construction of the SHINE facility Q1 2015 Preliminary Safety Analysis Report (PSAR) submitted Q2 2013 Final EIS and Record of Decision; safety evaluation report (SER) for the Construction Permit 10 CFR 50.57 Operating License Operation of the SHINE facility Q1 2016 SER for the Operating License 10 CFR 40 Source Material License Possession, use, and transfer of radioactive source material Q1 2016 10 CFR 30 By-Product Material License Production, possession, and transfer of radioactive by-product material Q1 2016 10 CFR 70 Special Nuclear Material License Receipt, possession, use, and transfer of special nuclear material Q1 2016 National Environmental Policy Act (NEPA) 10 CFR 51 Environmental Impact Statement (EIS) in accordance with NEPA Site approval for construction and operation of a radioisotope facility Q1 2015 Environmental Review (ER) submitted Q1 2013 Federal Aviation Administration (FAA)

Federal Aviation Act 14 CFR 77 Construction Notice FAA Form 7460-2 Construction of structures that potentially may impact air navigation Q2 2014 FAA Form 7460-1 submitted in 2011; Determination of No Hazard received 11/2011; Determination of No Hazard extension received 04/2012; plan to submit FAA Form 7460-2 within 5 days of construction reaching its greatest height When building reaches its highest planned height.

U.S. Environmental Protection Agency Clean Water Act 40 CFR 112, Appendix F Spill Prevention, Control and Countermeasure (SPCC) Plans for Construction and Operation Storage of oil during construction and operation Q2 2014 Baseline plan is to begin SPCC Plan development Q1 2014 and self-certify U.S. Department of Transportation (DOT)

Hazardous Material Transportation Act 40 CFR 107 Certificate of Registration Transportation of hazardous materials Q1 2016 Baseline plan is to submit DOT Form F 5800.2 Q1 2016 Wisconsin Department of Natural Resources (WDNR)

Federal Clean Air Act Wisconsin Statutes Chapter 285 Wisconsin Administrative Code Chapter NR 406 Air Pollution Control Construction Permit Construction of an air pollution emission source that is not specifically exempted Q2 2014 Baseline plan is to submit Application for Type A Registration Construction Permit Q4 2013 Federal Clean Air Act Wisconsin Statutes Chapter 285 Wisconsin Administrative Code Chapter NR 406 Air Pollution Control Operation Permit Operation of an air pollution emission source that is not specifically exempted Q2 2014 Baseline plan is to submit Application for Type A Registration Operation Permit with Construction Permit Application Q4 2013

Page 2 of 3 Agency Regulatory Authority Permit or Approval Activity Covered Expected Timeframe of Receipt Status Regulatory or Other Milestone Dependency Federal Clean Water Act Wisconsin Statutes Chapter 283 Wisconsin Administrative Code Chapter NR 216 Construction Storm Water Discharge Permit Discharge of storm water runoff from the construction site Q2 2014 Baseline plan is to submit a Water Resource Application for Project Permits (WRAPP) to request coverage under a General Permit Q2 2014, at least 14 working days before construction begins Federal Clean Water Act Wisconsin Statutes Chapter 283 Wisconsin Administrative Code Chapter NR 216 Industrial Storm Water Discharge Permit Discharge of storm water runoff from the site during facility operation Q1 2016 Baseline plan is to submit No Exposure Certification at least 14 working days prior to initiation operations, Q3 2015 Wisconsin Statutes Chapters 280 and 281 Wisconsin Administrative Code Chapter NR 809 Approval Letters Construction by the City of Janesville of water and sanitary sewer extensions to the SHINE facility Q2 2014 Permit to be requested by the City of Janesville Wisconsin Statutes Chapter 291 Wisconsin Administrative Code Chapter NR 660, 662, and/or 666 Compliance with hazardous waste notification, record keeping, and reporting requirements Generation of hazardous waste Q1 2016 Baseline plan is to notify of decision to claim WDNR of Storage and Treatment Conditional Exemption (NR 666 Subchapter N) Q1 2016 or within 90 days of LLMW generation Wisconsin Department of Safety and Professional Services Wisconsin Statutes Chapter 101 Wisconsin Administrative Code Chapters SPS 361 and 362 Building Plan Review Compliance with state building codes; required before a local building permit can be issued for a commercial building Q1 2014 Baseline plan is to submit Building Plan Q4 2013 Final building plan complete.

Wisconsin Department of Transportation Wisconsin Statutes Chapter 85 Wisconsin Administrative Code Chapter Trans 231 Permit for Connection to State Trunk Highway Construction of driveway connection to U.S. Route 51 Q2 2014 Baseline plan is to request permit simultaneously or before the submission of the Site Plan, Q4 2013 Wisconsin Statutes Chapter 85 Wisconsin Administrative Code Chapters Trans 231 Right of Entry Permit Construction by the City of Janesville of utility extensions across U.S. Route 51 Q2 2014 Permit to be requested by the City of Janesville Wisconsin Statutes Chapter 114 Wisconsin Administrative Code Chapter Trans 56 Variance from Height Limitation Zoning Ordinances Construction of structures that exceed height limitations established for Southern Wisconsin Regional Airport Q2 2014 It is not anticipated this variance will be needed based on the refined building and stack heights developed during Preliminary Design City of Janesville Community Development Department City of Janesville Ordinance 18.24.050.A Site Plan Approval (includes Building Site Permit for the Southern Wisconsin Regional Airport Overlay District)

Administrative approval of the site layout and plans for parking, lighting, landscaping, etc.

Q1 2014 Baseline plan is to submit Site Plan and building elevations Q4 2013 Final site plan complete.

Page 3 of 3 Agency Regulatory Authority Permit or Approval Activity Covered Expected Timeframe of Receipt Status Regulatory or Other Milestone Dependency City of Janesville Ordinance 15.06.070 Storm Water Plan Approval (may be included in Site Plan Approval)

Administrative approval of grading and drainage plans Q1 2014 Baseline plan is to submit Stormwater Management Plan with Site Plan Q4 2013 Final storm water plan complete.

City of Janesville Ordinance 15.05.080 Erosion Control Permit (may be included in Site Plan Approval)

Administrative approval of erosion control plans Q1 2014 Baseline plan is to submit erosion control plan with site plan Q4 2013 Final erosion control plan complete.

City of Janesville Ordinance 13.16 Sanitary Sewer and Water Supply Facility Approvals Administrative approval of construction, installation, and operation of connections to the municipal sewer and water supply systems Q1 2014 Construction and installation approved via the Plumping Plan. For operation, baseline plan is to provide baseline monitoring report to Wastewater Treatment Plant at least 90 days prior to discharge Q2 2015 Final plans complete.

City of Janesville Ordinance 15.01.100.A Plumbing Plan Approval Installation of plumbing systems Q1 2014 Baseline plan is to submit Plumbing Plan with Building Plan Q3 2013.

Final plumbing plan complete.

City of Janesville Ordinance 15.04.010.A HVAC Plan Approval Installation of heating, ventilation, and air conditioning systems Q1 2014 Baseline plan is to submit HVAC Plan with Building Plan Q3 2013 Final HVAC plan complete.

City of Janesville Ordinance 8.32.010 Fire Sprinkler and Alarm Permit Installation of sprinkler and alarm systems Q1 2014 Baseline plan is to submit Fire Sprinkler and Alarm Plan with Building Plan Q3 2013 Final sprinkler and alarm design complete.

City of Janesville Ordinance 15.01.100.A Building Permit Construction of buildings Q1 2014 Baseline plan is to submit Building Plan Q3 2013 All of the above City of Janesville permits.

City of Janesville Ordinance 15.01.190.A Occupancy Permit Occupancy of completed buildings Q1 2016 Each building will be inspected post-construction to allow occupancy.

Baseline plan is to complete Q4 2015 Completion of construction.

Rock County Highway Department Wisconsin Statutes Chapter 84 Rock County Utility Accommodation Policy 96.00 Permit to Construct, Maintain, and Operate Utilities within Highway Right-of-Way Construction by the City of Janesville of utility extensions across County Trunk Highway G Q2 2014 Plans and specifications to be submitted by the City of Janesville once Site Plan is approved, likely Q1 2014