Pacific Gas and Electric Company, Updated Best Estimate Schedule for Seismic Studies
ML13134A485
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 05/14/2013
From: Post J
Pacific Gas & Electric Co
To: Abramson P, Karlin A, Nicholas Trikouros
Atomic Safety and Licensing Board Panel
SECY RAS
References
RAS 24522, 50-275-LR, 50-323-LR, ASLPB 10-900-01-LR-BD01
Download: ML13134A485 (3)


Text

May 14, 2013 by Electronic Information Exchange Administrative Judge Alex S. Karlin Administrative Judge Nicholas G. Trikouros Administrative Judge Paul B. Abramson Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Two White Flint North 11545 Rockville Pike Mail Stop: T-3F23 Rockville, MD 20852 In the Matter of PACIFIC GAS AND ELECTRIC COMPANY (Diablo Canyon Power Plant, Units 1 and 2)

Docket Nos. 50-275-LR and 50-323-LR RE: Status Report

Dear Administrative Judges:

As directed by the Licensing Board Order of June 7, 2011, Pacific Gas and Electric Company (PG&E) hereby provides its monthly report specifying its current best estimate of the dates on which it expects to complete milestones related to 3D seismic studies for Diablo Canyon Power Plant (DCPP) and the coastal zone consistency certification associated with NRC license renewal for DCPP.

The schedule for implementation of the seismic studies has changed since PG&Es last submittal on April 9, 2013. PG&E has revised the Ocean Bottom Seismometer (OBS) Study schedule to reflect that all necessary permits to implement the OBS Study have been issued. PG&E will continue to provide specific dates in the monthly reports to the extent practicable, recognizing that these dates may be modified as more accurate information becomes available. PG&E wishes to assure the Licensing Board that it is making every effort to minimize the extent of the delay in the NRC license renewal process.

Executed in accord with 10 CFR 2.304(d),

/s/ signed electronically by Jennifer K. Post Attorney Pacific Gas and Electric Company 77 Beale St., B30A San Francisco, CA 94105 (415) 973-9809 jklm@pge.com

/s/ signed electronically by David A. Repka Winston & Strawn LLP 1700 K Street, NW Washington, DC 20006 (202) 282-5726 drepka@winston.com cc: Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Service List (via Electronic Information Exchange)

Pacific Gas and Electric Company Updated Best Estimate Schedule for Seismic Studies Description of Activity Prior Estimate New Estimate Shoreline Fault Submit Final Report to the NRC January 2011(a) January 2011(a)

NRC Review Complete October 12, 2012(a) October 12, 2012(a)

Ocean Bottom Seismometer Study Permit Application Submitted to California State Lands May 6, 2011(a) May 6, 2011(a)

Commission (CSLC)

Permits Issued April 2013 May 2013(a)

Installation Complete August 2013 August 2013 2D/3D Low Energy Marine Studies Permits Issued N/A N/A Surveys Complete October 2012(a) October 2012(a)

Data Processing and Interpretation Complete October 2013 October 2013 2D Onshore High Energy Studies Permit Pre-Application Meeting May 4, 2011(a) May 4, 2011(a)

Use Permits Issued Not Required Not Required December 2011(a) and December 2011(a) and Surveys Complete December 2012(a) December 2012(a)

Data Processing and Interpretation Complete June 2014 June 2014 3D High Energy Marine Studies Permit Application Submitted to CSLC April 29, 2011(a) April 29, 2011(a)

CSLC Environmental Impact Report Scoping Meeting July 21, 2011(a) July 21, 2011(a)

Permits Denied November 14, 2012(a) November 14, 2012(a)

Issue Final Seismic Report to the NRC and ASLB June 2014 June 2014 CZMA or Coastal Consistency File Coastal Development Permit TBD TBD Coastal Consistency Issued TBD TBD (a)

Note: - Actual Date Completed SF:349580.1