ML14295A769

From kanterella
Jump to navigation Jump to search
Erratum to October 2014 Seismic Study Update Letter
ML14295A769
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 10/22/2014
From: Post J, Tanya Smith
Pacific Gas & Electric Co, Winston & Strawn, LLP
To: Abramson P, Karlin A, Nicholas Trikouros
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-275-LR, 50-323-LR, ASLBP 10-900-01-LR-BD01, RAS 26740
Download: ML14295A769 (2)


Text

October 22, 2014 by Electronic Information Exchange Administrative Judge Alex S. Karlin Administrative Judge Nicholas G. Trikouros Administrative Judge Paul B. Abramson Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Two White Flint North 11545 Rockville Pike Mail Stop: T-3F23 Rockville, MD 20852 In the Matter of PACIFIC GAS AND ELECTRIC COMPANY (Diablo Canyon Power Plant, Units 1 and 2)

Docket Nos. 50-275-LR and 50-323-LR RE: Status Report - Correction

Dear Administrative Judges:

Pacific Gas and Electric Company (PG&E) has identified an error in its monthly report, dated October 14, 2014. The final seismic report was issued on September 10, 2014, not September

12. The accompanying table has been revised to reflect the correct date.

Executed in accord with 10 CFR 2.304(d),

/s/ signed electronically by Jennifer K. Post Attorney Pacific Gas and Electric Company 77 Beale St., B30A San Francisco, CA 94105 (415) 973-9809 jklm@pge.com

/s/ signed electronically by Tyson R. Smith Winston & Strawn LLP 1700 K Street, NW Washington, DC 20006 (202) 282-5726 trsmith@winston.com cc: Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Service List (via Electronic Information Exchange)

Pacific Gas and Electric Company Updated Best Estimate Schedule for Seismic Studies Description of Activity Prior Estimate Current Estimate Shoreline Fault Submit Final Report to the NRC January 2011(a) January 2011(a)

NRC Review Complete October 12, 2012(a) October 12, 2012(a)

Ocean Bottom Seismometer Study Permit Application Submitted to California State May 6, 2011(a) May 6, 2011(a)

Lands Commission (CSLC)

Permits Issued May 2013(a) May 2013(a)

OBS System Installed August 2013(a) August 2013(a)

OBS Equipment Repair and Adjustment November 2013(a) November 2013(a) 2D/3D Low Energy Marine Studies Permits Issued N/A N/A Surveys Complete October 2012(a) October 2012(a)

Data Processing and Interpretation Complete October 2013(a) October 2013(a) 2D Onshore High Energy Studies Permit Pre-Application Meeting May 4, 2011(a) May 4, 2011(a)

Use Permits Issued Not Required Not Required Surveys Complete December 2011 & 2012(a) December 2011 & 2012(a)

Data Processing and Interpretation Complete September 2014 September 2014(a) 3D High Energy Marine Studies Permit Application Submitted to CSLC April 29, 2011(a) April 29, 2011(a)

CSLC Environmental Impact Report Scoping Meeting July 21, 2011(a) July 21, 2011(a)

Permits Denied November 14, 2012(a) November 14, 2012(a)

Final Seismic Report Issued September 12, 2014 September 10, 2014(a)

Response to NRC Request for Additional December 2014(b) December 2014(b)

Information for Safety and Environmental Reviews CZMA or Coastal Consistency File Coastal Development Permit TBD TBD Coastal Consistency Issued TBD TBD (a) (b)

Note: - Actual Date Completed - Reference PG&E Letter DCL-14-043 dated June 4, 2014