Purdue University - Request for Additional Information Regarding the Purdue University Reactor License Renewal, Responses to RAIs (ML103400115 and ML103400250)
ML121850004
Person / Time
Site: Purdue University
Issue date: 06/29/2012
From: Joel Jenkins
Purdue University
To: Cindy Montgomery
Document Control Desk, Licensing Processes Branch (DPR)
References
TAC ME1594
Download: ML121850004 (3)


Text

PURDUE U N I V E R S I T Y SCHOOL OF NUCLEAR ENGINEERING 29 June 2012 Document Control Desk US Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Rockville, MD 20852 Attn: Ms. Cindy Montgomery, Research & Test Reactors (NRR/DPR/PRLB), Mailstop 012 D20

SUBJECT:

PURDUE UNIVERSITY - REQUEST FOR ADDITIONAL INFORMATION REGARDING THE PURDUE UNIVERSITY REACTOR LICENSE RENEWAL (TAC NO. ME 1594), RESPONSES TO RAIs (ML103400115 and ML103400250)

Dear Ms. Montgomery:

Enclosed please find the responses to the Request for Additional Information regarding the Purdue University Reactor License Renewal dated 6 July 2011. Included with this submission are responses to questions 48, 58, 96, 97 and 98. Should you have any questions or require further information, please don't hesitate to call me at 765.496.3573, or e-mail at jere@purdue.edu.

I hereby certify under penalty of perjury with my signature below that the information contained in this submission is true and correct to the best of my knowledge.

Director of Radiation Laboratories Attachments: As described.

Cc: Duane Hardesty, USNRC Project Manager for PUR-1 Leah Jamieson; Purdue University College of Engineering Jim Schweitzer, Purdue University REM Ahmed Hassanein, Purdue NE N

~~~ School~~.....

~~~~~ of Nu Engneein.

..a .......... ~-..~....

Nuclear Engineering Building

  • 400 Central Drive
  • West Lafayette, IN 47907-2017

-...

(765) 494-5739

  • Fax: (765) 494-9570
  • https:l/engineering.purdue.edu/NE

PUR-1: Partial Response to RAIs for license renewal (ML103400115 and ML103400250)

REQUESTED ADDITIONAL INFORMATION IN RESPONSE TO RAIs REGARDING THE PURDUE UNIVERSITY REACTOR LICENSE RENEWAL (TAC NO. ME 1594) 48 NUREG-1537, Part 1, Section 1.7, states the applicant should briefly describe how they meet the requirements of the Nuclear Waste Policy Act of 1982, Section 302(b)(1)(B). Please provide details for the Purdue University Research Reactor (PUR-1) contract for disposition of fuel.

Include the contractnumber and with whom the contractexists.

Response

Purdue meets the requirements of the Nuclear Waste Policy Act of 1982, Sec. 302(b)(1)(B). PUR-1 has fuel owned by the U.S. Department of Energy (DOE), and it is supported by a Standard Fuels Support Contract. The Prime Contractor for DOE is Battelle Energy Alliance, with a contract number of DE-AC07-051D14517. The specific sub-contract for Purdue University is sub-contract number 78286.

58. NUREG-1537 states in part that importantprocess variables reflecting the physical condition of the reactor should be monitored. Section 7 of the SAR describes the PUR-1 instrumentation, but does not discuss any potential impact of the proposed power uprate on safe operation of the system. Please discuss if any of the nuclear instrumentation used to monitor the power level of the reactor have to be recalibratedor replaced if the requested power uprate is granted. Also discuss any potential impacts of the power uprate on any nuclear or process parametersimportant to safe and effective operation of the PUR-1 reactor and facility.

Response

The power uprate to 12 kW would require adjustment of the LogN (ch 2) and CSA 1 to the new power levels at 100%. The I&C system was designed for a reactor of higher power (typical Lockheed MTR reactors of this type were built for operation from 100-250 kW), and would be capable of the new operation parameters. Normal calibration procedures would be adhered to ensure the safety, operability and accuracy of the instrumentation.

96. SAR, Section 13.2.1 discusses calculation of the reactor building. Please explain if the area evacuated within the stated time constitutes the operations or site boundary. Additionally, pleaseprovide documentationsubstantiatingthe "pastexperience" for the evacuation time.

Response

The area to be evacuated is the reactor room.

The average person's walking speed is 3 miles per hour, which is 4.4 feet per second. The farthest distance that would have to be walked in the reactor room during an evacuation is approximately fifty (50) feet. Based on the average person's walking speed, it should take approximately 12 seconds to reach an exit.

Page 1 of 2 15 June 2012

PUR-1: Partial Response to RAIs for license renewal (ML103400115 and ML103400250)

97. SAR, Section 7.5.4 designates the hallway immediately outside the reactor room as B76A.

This room appearsto be an interiorroom within the Nuclear Engineeringlaboratories.Please update the SAR for consistency of designatedareas.

Response

Section 7.5.4 of the SAR as submitted discusses the instrumentation and control system of PUR-1, not any of the information contained within this question.

98. SAR, Section 13.2.1, page 13-9 states "This radiation exposure approaches the limits established in the Technical specifications, Sec 3.5.f for a singly encapsulatedexperiment."

The proposed PUR-1 TSs do not contain a TS 3.5.f. Pleasepropose a TS to establish limits for a singly encapsulated experiments, reference the applicable TS, or justify why a TS is not required.

Response

3.5(f) was omitted inadvertently from the relicensing submission inadvertently. It has been reinserted.

Please see the response to question 8, submitted 15 November 2011.

Page 2 of 2 15 June 2012