MONTHYEARIR 05000182/20244102024-09-0606 September 2024 Purdue University - U.S. Nuclear Regulatory Commission Security Inspection Report 05000182/2024410 ML24162A2312024-06-10010 June 2024 Purdue Univ., Notification of Change in Operator Status for OP-505673 ML24162A2292024-06-10010 June 2024 Purdue Univ., Notification of Change in Operator Status for OP-505672 ML24162A2302024-06-10010 June 2024 Purdue Univ., Notification of Change in Operator Status for OP-505670 ML24089A2422024-03-29029 March 2024 Purdue Univ., Submittal of 2023 Annual Report ML24024A2472024-02-10010 February 2024 Examination Report No. 50-182/OL-24-01, Purdue University ML24024A2462024-02-10010 February 2024 Examination Results No. 50-182/OL-24-01, Purdue University ML23268A0752023-09-18018 September 2023 Purdue Univ., Submittal of Revised License Renewal Request ML23227A2462023-08-16016 August 2023 Examination Confirmation Letter No. 50-182/OL-24-01, Purdue University ML23171B0272023-06-13013 June 2023 Purdue Univ., Reply to Notice of Violation in NRC Inspection Report 05000182/2023201 IR 05000182/20232012023-05-23023 May 2023 Purdue University - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000182-2023201 and Notice of Violation ML23090A2012023-03-31031 March 2023 Purdue Univ., Submittal of 2022 Annual Report ML22238A2492022-09-0808 September 2022 Examination Confirmation Letter No. 50-182/OL-23-01, Purdue University IR 05000182/20212042021-12-0202 December 2021 Purdue University U.S. Nuclear Regulatory Commission Follow-Up Safety Inspection Report 05000182/2021204 ML21306A1602021-11-11011 November 2021 Examination Confirmation Letter No. 50-182/OL-22-02, Purdue University ML21267A4272021-09-21021 September 2021 Purdue Univ., Reply to Notice of Violation in NRC Special Inspection Report No. 05000182/2021202 ML21267A4052021-09-14014 September 2021 Purdue Univ., Reply to Notice of Violation in NRC Special Inspection Report No. 05000182/2021203 IR 05000182/20212032021-07-29029 July 2021 Purdue Safety HP - Safety Inspection Report No. 05000182/2021203 and Notice of Violation IR 05000182/20212022021-07-28028 July 2021 Purdue University Nuclear Regulatory Commission Security Inspection Report No. 05000182/2021202 (Cover Letter) ML21173A3102021-06-25025 June 2021 Purdue University Additional Training Preformed in Lieu of Annual Operating Test ML21153A4272021-06-24024 June 2021 Examination Confirmation Letter No. 50-182/OL-21-01, Purdue University ML21172A1562021-06-0303 June 2021 Request to Compensate for a Missed Annual Operating Test by Utilizing 10 CFR 55.59(b) for SOP-70830 at Purdue Univ ML21148A1132021-05-0707 May 2021 Update to Facility Personnel at Purdue University Reactor, PUR-1, Docket 50-182 ML21139A1242021-05-0707 May 2021 Update to Facility Personnel at Purdue University Reactor, PUR-1, Docket 50-182 IR 05000182/20212012021-05-0606 May 2021 Purdue University, Routine Safety Inspection 050182/2021201 ML21118A0232021-03-31031 March 2021 Purdue University - Report on Reactor Operations for the Period January 1, 2020 to December 31, 2020 IR 05000182/20202012021-02-16016 February 2021 Purdue University Reactor Notice of Violation and Special Inspection Report 05000182/2020-201 ML21029A0562021-01-21021 January 2021 Purdue University Reactor, Update to Facility Personnel ML21035A0142021-01-0606 January 2021 Response to Apparent Violations in NRC Special Inspection Report 05000182/2020201 ML20336A3242020-12-11011 December 2020 Purdue University - Issuance of Amendment No. 16 to Renewed Facility Operating License No. R-87, for the Purdue University Research Reactor to Modify the Technical Specifications to Allow Startup of the Purdue University Reactor to Calibrat ML20332A0832020-12-0707 December 2020 Purdue University, Special Inspection Report 05000182/2020201 ML20330A2312020-11-27027 November 2020 Purdue University - Acceptance of the Application for a License Amendment Modification of Technical Specifications to Allow Startup of the Purdue University Reactor to Calibrate Nuclear Instrumentation (EPID A11010//L-2020-PPM-0000) ML20337A1042020-11-24024 November 2020 Purdue University Submission of License Amendment Request, PUR-1, Docket 50-182 ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards ML20311A2642020-11-0303 November 2020 Purdue Univ. School of Nuclear Engineering - Written Conveyance of 14-Day Special Report, PUR-1 ML20045E4522020-02-18018 February 2020 Purdue University - Acknowledgement of Withdrawal of the Application for a License Amendment Request for Management Chain Change ML20038A2872020-02-0606 February 2020 Purdue University - Withdrawal of License Amendment Request, PUR-1, Docket 50-182 - Management Chain ML20017A2632020-01-17017 January 2020 Purdue University, Indiana - Letter Regarding Dean Mung Chiang New Position Assignment as a Science and Technology Adviser to the Secretary of State ML19345F2712019-12-11011 December 2019 Examination Confirmation Letter No. 50-182/OL-20-01, Purdue University ML19345F3782019-12-11011 December 2019 Examination Confirmation Letter No. 50-020/OL-20-01, Massachusetts Institute of Technology IR 05000182/20192022019-10-30030 October 2019 Purdue University U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000182/2019-202 ML19274C4472019-10-0808 October 2019 Examination Report No. 50-182/OL-19-01, Purdue University ML19142A2722019-05-24024 May 2019 Purdue University - Issuance of Amendment No. 15 Regarding Implementation Date Change for Licensing Amendment No. 14 for Facility Operating License No. R-87 ML19143A3842019-05-21021 May 2019 LAR Implementation Extenstion - PUR1 - 20190521 ML18262A4342019-04-0101 April 2019 Purdue University Transmittal Letter for Issuance of Amendment No. 14 to Renewed Operating License No. R-87 for the Purdue University Research Reactor Digital Instrumentation Control Upgrade IR 05000182/20192012019-03-20020 March 2019 Purdue University - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000182/2019-201 ML18282A1912018-10-0505 October 2018 Purdue University - Interlock Language Retention in Technical Specification Submission Supporting License Amendment Request, PUR-1, Docket 50-182 IR 05000182/20184102018-09-26026 September 2018 Purdue University - Transmittal Letter Regarding U.S. Nuclear Regulatory Commission Security-Related Inspection Report No. 05000182/2018-410 ML18263A1572018-09-20020 September 2018 Purdue University - Revisions to Technical Specification Submission Supporting License Amendment Request, PUR-1, Docket 50-182 ML18134A1612018-05-14014 May 2018 Purdue University - Notification of Level 1 Personnel Change 2024-09-06
[Table view] Category:Licensee Response to Notice of Violation
MONTHYEARML23171B0272023-06-13013 June 2023 Purdue Univ., Reply to Notice of Violation in NRC Inspection Report 05000182/2023201 ML21267A4272021-09-21021 September 2021 Purdue Univ., Reply to Notice of Violation in NRC Special Inspection Report No. 05000182/2021202 ML21267A4052021-09-14014 September 2021 Purdue Univ., Reply to Notice of Violation in NRC Special Inspection Report No. 05000182/2021203 ML21035A0142021-01-0606 January 2021 Response to Apparent Violations in NRC Special Inspection Report 05000182/2020201 ML13232A0092013-08-0606 August 2013 Purdue University - Reply to Notice of Violation 2023-06-13
[Table view] |
Text
January 06, 2020 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Re: Response to Apparent Violations in NRC Special Inspection Report 05000182/2020-201; EA-20-144
Dear Ms. Montgomery:
This letter is in response to two apparent violations and one Severity Level IV violation dated December 7, 2020 as a result of the special inspection conducted October 27 -November 6, 2020. The apparent violations are involved with the reactor exceeding the maximum licensed power level (License Condition 2.C. l) and operating the reactor prior to completing the applicable surveillance testing for replaced equipment (Technical Specification 4.2.g) The Severity Level IV violation is due to inadequately posting a radiation area pursuant to 10 CFR 20.
Response to Apparent Violations A. Operating the Purdue University research reactor (PUR-1) in excess of the maximum licensed power limit of 12 kilowatts.
- 1. The apparent violation was likely caused by a miscalculation of the absolute efficiency for the High Purity Germanium (HPGe) detector used in the calibration of the nuclear instrumentation (NI) by foil activation.
- 2. The following corrective actions have been taken
- 1. A written Standard Operating Procedure (SOP) for properly calibrating the HPGe detector and calculating the absolute efficiency has been reviewed and approved by the Committee on Reactor Operations (CORO).
- 11. A Restart Plan to safely perform calibration of the NI by foil activation has been reviewed and approved by the CORO.
111. A License Amendment Request (LAR) for proposed changes to the Technical Specifications (TS) to allow reactor operation for the purpose of performing calibration of the NI by foil activation has been approved by the NRC.
1v. Other facility procedures have been reviewed.
- 1. A procedure to perform the TS required electronic calibration has been drafted. It will be approved by CORO and performed as part of the required surveillances prior to restart.
- 2. The SOP for reactor startup will be revised to include verification of radiation area signs and will be approved by CORO prior to reactor restart.
- 3. The SOP for the HPGe detector and the Restart Plan were approved by CORO on November 14, 2020. The LAR was approved by the NRC on December 11, 2020.
B. Failure to complete the appropriate surveillance testing prior to returning the Purdue University research reactor back to into service following replacement of the NI system and detectors.
- 1. The apparent violation was caused by an oversight made by the PUR-1 staff.
- 2. The following corrective actions will be taken
- 1. Calibration of the NI by foil activation (0-100% of the licensed reactor power limit) using the SOP for the HPGe detector and Restart Plan
- 11. Reactor will not be returned to service until this and all applicable surveillance testing specified in the TS have been completed.
- 3. The NI calibration and all applicable surveillance testing specified in the TS will be completed at the earliest convenience of the PUR-1 staff no later than March 1, 2021.
Response to Severity Level IV Violation C. Failure to post a sign bearing the radiation symbol and the words "CAUTION, RADIATION AREA" for the PUR-1 reactor facility, where the radiation levels could result in an individual receiving a dose equivalent in excess of 5 mrem in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> at 30 centimeters from the top of the reactor.
- 1. The need to post a sign bearing the radiation symbol and the words, "CAUTION, RADIATION AREA" for the PUR-1 reactor facility was identified in an ALARA audit dated July 22, 2020, however, no actions were taken to post the sign.
- 2. The following corrective steps have been taken
- 1. A sign bearing the radiation symbol and the words, "CAUTION, RADIATION AREA" has been posted at the entrance to the PUR-1 facility
- 3. This was completed on November 10, 2020 We believe the measures implemented above bring Purdue University into compliance.
I declare under penalty of perjury that the foregoing is true and correct.
Sincerely, Dr. Robert Bean Facility Director Purdue University Radiation Laboratory School ofNuclear Engineering Page 2 of2