Letter Sequence Other |
---|
|
Results
Other: ML12079A036, ML12095A224, ML12095A225, ML12095A226, ML12095A227, ML12095A228, ML12095A229, ML12095A230, ML12095A231, ML12095A251, ML12095A252, ML12095A253, ML12095A254, ML12095A255, ML12095A257, ML12095A258, ML12095A259, ML12095A260, ML12095A274, ML12095A275, ML12095A276, ML12095A347, ML12095A348, ML12095A349, ML12095A350, ML12095A353, ML12095A354, ML12095A370, ML12095A371, ML12095A372, ML12095A373, ML12095A374, ML12095A375, ML12095A376, ML12096A059, ML12096A060, ML12096A061, ML12096A062, ML12096A227, ML12101A089, ML12101A090, ML12101A091, ML12101A092, ML12101A093, ML12101A094, ML12101A095, ML12101A096, ML12101A097, ML12101A098, ML12101A099... further results
|
MONTHYEARML12074A0322012-03-0909 March 2012 G20120172/EDATS: OEDO-2012-0147 - Paul Gunter 2.206 Petition & Letter 2.206 - Fitzpatrick Emergency Enforcement Petitions Project stage: Request ML12079A0362012-03-13013 March 2012 G20120172/EDATS: OEDO-2012-0147 - Paul Gunter E-mail Treatment of FitzPatrick Emergency Enforcement Petition, March 9, 2012 Project stage: Other ML1228303422012-03-13013 March 2012 G20120172, EDATS: OEDO-2012-0147, E-mail to Mr. Gunter to Acknowledge the Receipt of the Petition Project stage: Other ML13017A3552012-03-15015 March 2012 from Bhalchandra Vaida to Joseph Pechacek: Fitzpatrick Emergency Enforcement Project stage: Other ML13162A6312012-03-22022 March 2012 from Andrea Russell to Brice Bickett: Action for Your Review/Comment Project stage: Other ML13022A2922012-03-22022 March 2012 from Andrea Russell to Samson Lee: FYI-G20120172 (Fitzpatrick 2.206): Supplements and New Co-Petitioner Project stage: Other ML1228303322012-03-27027 March 2012 G20120172, EDATS: OEDO-2012-0147, E-mail to Petitioner - Communication of Prb'S Decision on the Request for Immediate Action Project stage: Other ML13162A6322012-03-27027 March 2012 from Andrea Russell to Samson Lee: FYI-G20120172 Project stage: Other ML13162A6332012-03-29029 March 2012 from Brice Bickett to Bhalchandra Vaidya: Re PRB Decision on Request for Immediate Action Project stage: Other ML12095A2272012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12101A1442012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3532012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2252012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML13162A7422012-04-0303 April 2012 from Andrea Russell to Samson Lee: Update-G20120172 Project stage: Other ML12095A3472012-04-0303 April 2012 ME8189 - G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3732012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2602012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2542012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3482012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A2282012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2512012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A2262012-04-0303 April 2012 ME8189 - G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2522012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML13022A2932012-04-0303 April 2012 from Bhalchandra Vaidy to Jessica Azulay: Re PRB Decision Project stage: Other ML12095A3702012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A2572012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3502012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3542012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2582012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3712012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2242012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A3492012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3752012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2552012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A3742012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2592012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2532012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A3762012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - e-mail from Additional Co-Petitioner Project stage: Other ML12095A2312012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A3722012-04-0303 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2302012-04-0404 April 2012 ME8189 - G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2752012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12096A0612012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12096A2272012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12101A1452012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2742012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12096A0622012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2292012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12095A2762012-04-0404 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other ML12096A0592012-04-0404 April 2012 ME8189 - G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner Project stage: Other 2012-03-27
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML16343A0432016-12-0606 December 2016 NRR E-mail Capture - (External_Sender) November 2016 FPL Marine Turtle Removal Monthly Report ML13133A1372013-05-13013 May 2013 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner, Janet Azarovitz ML12108A2542012-04-11011 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner, M. Sharon Gambocorto ML12107A2922012-04-10010 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner, Edna Litten ML12104A3282012-04-10010 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner, Carl Swidorski 2016-12-06
[Table view] Category:2.206 Petition
MONTHYEARML13133A1372013-05-13013 May 2013 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner, Janet Azarovitz ML12108A2542012-04-11011 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner, M. Sharon Gambocorto ML12107A2922012-04-10010 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner, Edna Litten ML12104A3282012-04-10010 April 2012 ME8189 -G20120172/EDATS: OEDO-2012-0147 - E-mail from Additional Co-Petitioner, Carl Swidorski 2013-05-13
[Table view] |
Text
Vaidya, Bhalchandra From: Carl Swidorski [swidl9l9@aol.com]
Sent: Tuesday, April 10, 2012 8:53 PM To: Vaidya, Bhalchandra
Subject:
In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 VIA email to Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York
Dear Mr. Borchardt:
I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.
- The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.
- In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.
. The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.
- Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.
Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:
- 1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
- 2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.
. The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.
1
-It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting
, that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.
I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public.
The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.
Thank you Carl Swidorski 53 Cardinal Avenue Albany, NY 12208 2