Other: CNL-15-189, Decommissioning Funding Update, ML090770757, ML091250151, ML092470504, ML101740152, ML101740157, ML101820478, ML102110075, ML102360283, ML102600474, ML103160419, ML110260321, ML111010165, ML111250430, ML111890037, ML11291A095, ML12069A330, ML12073A391, ML12073A392, ML12073A393, ML12081A073, ML13044A113
|
MONTHYEARML0815601832008-05-29029 May 2008 Cable Issues Corrective Action Program for the Completion of WBN Unit 2 Project stage: Request ML0830900462008-10-30030 October 2008 Preservice Inspection Program Plan and Request for Relief No. WBN-2/PDI-4 Project stage: Request ML0905707412009-02-28028 February 2009 NUREG-0847, Supp. 21, Safety Evaluation Report, Related to the Operation of Watts Bar Nuclear Plant, Unit 2 Project stage: Request ML0907003782009-03-0404 March 2009 Operating License Application Update Project stage: Request ML0907707572009-04-22022 April 2009 Notice of Receipt of Update to Application for Facility Operating License and Notice of Additional Opportunity for Hearing and Order Project stage: Other ML0907708072009-04-27027 April 2009 Federal Register Notice- Watts Bar Nuclear Plant, Unit 2 - Notice If Receipt of Update to Application for Facility Operating License and Notice of Additional Opportunity for Hearing Project stage: Request ML0912501512009-05-0808 May 2009 Public Notice of Receipt of Updated Application for Facility Operating License Project stage: Other ML0918900382009-07-21021 July 2009 Request for Additional Information Regarding Financial Information Related to Operating License Application Update Project stage: RAI ML0924705042009-08-26026 August 2009 Additional Information Regarding Financial Information Related to Operating License Application Update Project stage: Other ML0935209672009-12-15015 December 2009 TVA Meeting Presentation Project stage: Request ML0935600192009-12-22022 December 2009 Summary of Meeting with Tennessee Valley Authority (TVA) Regarding Digital Instrumentation and Controls Review Project stage: Meeting ML1002703512010-02-18018 February 2010 Request for Additional Information Regarding Physical Security Plan Project stage: RAI ML1006300192010-03-11011 March 2010 Request for Additional Information Regarding Radiological Emergency Response Plan Project stage: RAI ML1009700722010-04-0505 April 2010 Response to NRC Request for Additional Information Regarding Physical Security Plan Project stage: Response to RAI ML1012302482010-04-27027 April 2010 Staff Information Requests Resulting from NRC December 15, 2009, Meeting with TVA Regarding Digital Instrumentation and Controls Review and NRC Clarifications to the Requests Provided During February 18, 2010. Project stage: Meeting ML1013406982010-05-28028 May 2010 Supplement to Request for Additional Information Regarding Radiological Emergency Response Plan (Tac No. ME0853) Project stage: RAI ML1015504882010-06-11011 June 2010 Request for Additional Information Regarding Fire Protection Program Project stage: RAI ML1015404772010-06-15015 June 2010 Review of Radiological Emergency Response Plan Project stage: Approval ML1017401572010-06-24024 June 2010 Notice of Receipt of Update Antitrust Information and Opportunity for Public Comment Project stage: Other ML1017401522010-06-24024 June 2010 Letter, Notice of Receipt of Update Antitrust Information and Opportunity for Public Comment Project stage: Other ML1018204782010-07-0101 July 2010 Revised Notice of Receipt of Update Antitrust Information and Opportunity for Public Comment Project stage: Other ML1018904062010-07-13013 July 2010 Request for Additional Information Regarding Antitrust Review Project stage: RAI ML1019703112010-07-16016 July 2010 Request for Additional Information Regarding Fire Protection Program Project stage: Request ML1021100752010-07-29029 July 2010 Jcn No: 4201, (TAC No. ME0853) Q4011 Task Order Number 9, Tennessee Valley Authority, Watts Bar Unit 2. Evacuation Time Estimate (ETE) Review Project stage: Other ML1021600852010-07-29029 July 2010 Response to Request for Additional Information Regarding Antitrust Review Project stage: Response to RAI ML1023602832010-08-20020 August 2010 Fire Protection Program, Commitment to Provide Additional Information on Multiple Spurious Operation Scenarios Project stage: Other ML12081A0732010-08-20020 August 2010 Enclosure 1 (W/Apps a, B, & C): Watts Bar, Unit 2, Fire Protection Program, Commitment to Provide Additional Information on Multiple Spurious Operation Scenarios Project stage: Other ML1026004742010-09-17017 September 2010 Response to NRC Question Regarding Emergency Plan Project stage: Other ML1031604192010-11-0505 November 2010 Watts, Unit 2, Fire Protection Program (TAC ME0853) - Commitment to Provide Multiple Spurious Operation (MSO) Evaluation Project stage: Other ML1102603212011-03-22022 March 2011 Notice of No Significant Antitrust Changes and Time for Filing Requests for Reevaluation Project stage: Other ML1109604072011-04-0101 April 2011 Response to Request for Additional Information on Final Safety Analysis Report Section 9.3.2.6 for the Post Accident Sampling System (PASS) Project stage: Response to RAI ML1110101652011-04-13013 April 2011 Status of Operating License Application Review and Project Schedule Implications Project stage: Other ML11146A0442011-05-20020 May 2011 Response to Final Safety Analysis Report, Chapter 11 and Final Supplemental Environmental Impact Statement Request for Additional Information Project stage: Supplement ML1118900372011-07-20020 July 2011 Schedule of Licensing Activities Project stage: Other ML1112504302011-08-12012 August 2011 Transition of Components to American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI Project stage: Other ML11291A0952011-10-13013 October 2011 Instrumentation and Controls Staff Information Requests Project stage: Other ML1131302182011-11-18018 November 2011 Request for Additional Information Regarding Supplemental Safety Evaluation Report Open Items 80, 81, 105, and 108 Project stage: Approval ML12069A3302012-01-19019 January 2012 Instrumentation and Controls Staff Information Requests Project stage: Other ML12073A3922012-02-29029 February 2012 WNA-VR-00283-WBT-NP, Rev. 7, Nuclear Automation Watts Bar Unit 2 NSSS Completion Program I&C Projects Iv&V Summary Report for the Post Accident Monitoring System. Attachment 2 Project stage: Other ML12073A3932012-03-0808 March 2012 TVA White Paper Common Q Pams Design Basis Conformance to the Requirements of IEEE 603-1991, Dated March 8, 2012 (Letter Items 1 and 3, Sser 23 Appendix Hh Item Numbers 94 and 105). Attachment 4 Project stage: Other ML12073A3912012-03-0909 March 2012 Instrumentation and Controls Staff Information Requests Project stage: Other ML12160A3512012-06-0707 June 2012 Submittal of Additional Information Requested to NUREG-0847 Supplemental Safety Evaluation Report Related to Appendix Hh Open Item 26 - Diesel Generator Project stage: Supplement ML13044A1132013-02-0707 February 2013 Fire Protection Program (TAC No. ME0853) - Commitment to Provide Additional Information on Multiple Spurious Operation (MSO) Scenarios Project stage: Other CNL-15-017, Decommissioning Funding Status Report2015-03-31031 March 2015 Decommissioning Funding Status Report Project stage: Request CNL-15-189, Decommissioning Funding Update2015-09-10010 September 2015 Decommissioning Funding Update Project stage: Other 2010-07-01
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000390/20250102024-11-0404 November 2024 Notification of an NRC (FPTI) (NRC Inspection Report 05000390/2025010 0500039/ 2025010) (RFI) CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20243012024-10-17017 October 2024 Operator Licensing Examination Approval 05000390/2024301 and 05000391/2024301 ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24261C0062024-10-0404 October 2024 Correction to Amendment No. 134 to Facility Operating License No. NPF-90 and Amendment No. 38 to Facility Operating License No. NPF-96 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000390/LER-2024-002, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-09-0505 September 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 ML24218A1442024-08-27027 August 2024 Issuance of Amendment Nos. 169 and 75 Regarding Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), ML24219A0262024-08-12012 August 2024 Request for Withholding Information from Public Disclosure IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev ML24204A2652024-07-25025 July 2024 Regulatory Audit Summary Related to Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24170A8002024-07-15015 July 2024 Issuance of Amendment Nos. 168 and 74 Regarding Revision to Technical Specification Table 1.1-1 for Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter 05000391/LER-2024-003, Inoperability of Both Trains of Unit 2 Low Head Safety Injection2024-07-11011 July 2024 Inoperability of Both Trains of Unit 2 Low Head Safety Injection ML24131A0012024-07-0202 July 2024 Issuance of Amendment Nos. 167 and 73 Regarding Adoption of Technical Specification Task Force Traveler TSTF-427-A, Revision 2 CNL-24-052, Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-06-27027 June 2024 Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-24-018, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS2024-06-25025 June 2024 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24100A7642024-05-16016 May 2024 Issuance of Amendment No. 166 Regarding Revision to Technical Specification 3.8.2, AC Sources-Shutdown, to Remove Reference to C-S Diesel Generator (CNL-23-062) IR 05000390/20240012024-05-14014 May 2024 Integrated Inspection Report 05000390/2024001 and 05000391/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000391/LER-2024-002, Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO2024-05-0606 May 2024 Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO IR 05000391/20240072024-04-30030 April 2024 Assessment Follow-up Letter for Watts Bar Nuclear Plant, Unit 2 – Report 05000391/2024007 ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A1912024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-010, License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19)2024-04-17017 April 2024 License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19) CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24072A0052024-04-15015 April 2024 Issuance of Amendment Nos. 165 and 72 Regarding Increase in the Maximum Number of Tritium Producing Burnable Absorber Rods and Supporting Changes, and Revision to the Updated Final Safety Analysis Report CNL-24-004, Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13)2024-04-0404 April 2024 Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13) IR 05000390/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000390/2024401 and 05000391/2024401 - (Public) CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements 05000391/LER-2024-001, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-03-27027 March 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation CNL-24-007, Annual Insurance Status Report2024-03-27027 March 2024 Annual Insurance Status Report CNL-24-008, Guarantee of Payment of Deferred Premiums - 2023 Annual Report2024-03-27027 March 2024 Guarantee of Payment of Deferred Premiums - 2023 Annual Report CNL-24-025, Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule2024-03-25025 March 2024 Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule ML24081A0262024-03-21021 March 2024 Emergency Plan Implementing Procedure Revisions ML24079A0312024-03-19019 March 2024 Wb 2024-301, Corporate Notification Letter (210-day Ltr) 2024-09-05
[Table view] |
Text
Attachment 1 is to be withheld from public disclosure under 10 CFR § 2.390.
When separated from this attachment, this letter is decontrolled.
Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 March 9, 2012 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 10 CFR 50.4 NRC Docket No. 50-391
Subject:
WATTS BAR NUCLEAR PLANT (WBN) UNIT 2 - INSTRUMENTATION AND CONTROLS STAFF INFORMATION REQUESTS
References:
- 1. Supplemental Safety Evaluation Report (SSER) 22, 23, 24 and 25 Appendix HH Watts Bar Unit 2 Action Items Table
- 2. NRC to TVA letter dated November 18, 2011, "Watts Bar Nuclear Plant, Unit 2 -
Request for Additional Information Regarding Supplemental Safety Evaluation Report Open Items 80, 81, 94, 105, and 108" (TAC NO. ME0853)
- 3. NRC to TVA e-mail (J. Poole, NRC, to G. Arent, TVA), "Draft Request for Additional Information Regarding Open Item 98," sent December 12, 2011 The purpose of this letter is to answer NRC requests for additional information (RAIs) provided in References 2 and 3. These RAIs are related to open items in Reference 1. to this letter provides TVA's responses to the information requested by NRC. contains a list of attachments that support the TVA's responses provided in . Enclosure 3 provides the list of new regulatory commitments contained in this letter. contains information proprietary to Westinghouse Electric Company LLC (WEC). contains the necessary information supporting the request for withholding such information. TVA requests that the WEC proprietary information be withheld from public disclosure in accordance with 10 CFR § 2.390.
If you have any questions, please contact Gordon Arent at (423) 365-2004.
- ý() C5,2-)
-(ý)
U.S. Nuclear Regulatory Commission Page 2 March 9, 2012 I declare under penalty of perjury that the foregoing is true and correct to the best of my knowledge. Executed on the 9 th day of March 2012.
Respectfully, Raymond A. Hruby, Jr.
General Manager, Technical Services Watts Bar Unit 2
Enclosures:
- 1. TVA Responses to Instrumentation and Controls Staff Information Requests
- 2. List of Attachments
- 3. List of New Regulatory Commitments cc (Enclosures):
U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381
Enclosure I TVA Letter Dated March 9, 2012 TVA Responses to Instrumentation and Controls Staff Information Requests ACRONYMS AND ABBREVIATIONS The following acronyms/abbreviations are used in this letter:
ABB ASEA Brown Boveri CIT/FAT Channel Integration Test/Factory Acceptance Test Common Q Common Qualified Platform CRC Cyclic Redundancy Check EDMS Enterprise Document Management System TM
'IEEEE Institute of Electrical and Electronics Engineers IV&V Independent Verification and Validation MTP Maintenance and Test Panel NRC Nuclear Regulatory Commission PAMS Post Accident Monitoring System PLC Programmable Logic Controller QMS Quality Management System RAI Request for Additional Information RG Regulatory Guide RVLIS Reactor Vessel Level Indicating System SDOE Secure Development and Operating Environment SER Safety Evaluation Report SRR Software Release Record SRS Software Requirements Specification SSER Supplemental Safety Evaluation Report SysRS System Requirements Specification TVA Tennessee Valley Authority V&V Verification and Validation WBN Watts Bar Nuclear Plant WEC Westinghouse Electric Company LLC NOTE
- 1. For the NRC RAIs in this letter, a response has been provided in previous TVA letters. The NRC subsequently requested additional information. Previous TVA responses are not repeated below. Additional NRC information requests are identified in this letter as "NRC Follow-up Request." TVA responses to these items are identified as "TVA Response to NRC Follow-up Request."
IEEE is a registered trademark of the Institute of Electrical and Electronics Engineers Inc.
E1-1
Enclosure 1 TVA Letter Dated March 9, 2012 TVA Responses to Instrumentation and Controls Staff Information Requests RAI RESPONSES NRC Follow-up Request (SSER 23 Appendix HH Item Number 94)
By letter dated September 1, 2011, TVA provided a response to Open Item Number 94.
The response provided by TVA is incomplete since it only addressed Institute of Electrical and Electronics Engineering Standard 603-1991 Clause 4; the response was silent on the other clauses (e.g., Clauses 5 & 6). The response also did not identify how the Common Q Post-Accident Monitoring System (PAMS) design meets the documented design basis requirements.
- a. Please provide detail and specific design basis information for core exit thermocouple and subcooled margin monitor indications associatedwith "Type A" manual actions.
- b. Please provide to the staff information that demonstrates that the Watts Bar Nuclear Plant (WBN), Unit 2 Common Q PAMS design meets the applicabledesign basis requirements (e.g., trace from design basis to design).
Note: Clauses 5.2, 6.1, 6.6, 7, & 8 are not applicable to the technicalreview of the Common Q PAMS.
TVA Response to NRC Follow-up Request The response to this item is contained in Attachment 4, TVA white paper "Common Q PAMS Design Basis Conformance to the Requirements of 2IEEE 603"-1991," dated March 8, 2012.
- 2. NRC Follow-up Request (SSER 23 Appendix HH Item Number 98)
Note: TVA responded to the initial NRC RAI by letter dated September 1, 2011. With the exception of item 2.h.,TVA responded to the follow-up NRC information requests by letters dated December 22, 2011, and March 2, 2012.
2.h In Section 2.5.3, IV&V Phase Summary Report and Software Release Records are given as outputs of the implementation phase. Please confirm if WNA-VR-00283-WBT P, Rev. 4 (ML110770540) is the appropriateIV&V Phase Summary Report Record. Please provide a reference for Software Release Records documents and submit on docket.
TVA Response to NRC Follow-up Request WNA-VR-00283-WBT-P is the appropriate IV&V Phase Summary Report Record; however, the Software Release Record (SRR) listing provided in revision 4 was not complete.
2 IEEE 603 is a registered trademark of the Institute of Electrical and Electronics Engineers Inc.
E1-2
Enclosure 1 TVA Letter Dated March 9, 2012 TVA Responses to Instrumentation and Controls Staff Information Requests In response to item 2.h, a review was performed of WNA-LI-00058-WNA, Revision 3, "Post-Accident Monitoring System (PAMS) Licensing Technical Report," and WNA-VR-00283-WBT-P, Revision 6, "IV&V Summary Report for the Post Accident Monitoring System." The review determined that no single complete listing of SRRs existed and the listings in the two documents were inconsistent. As a result, the decision was made to revise both documents. The complete listing of SRRs was incorporated into WEC proprietary document WNA-VR-00283-WBT-P (Attachment 1), Revision 7, "IV&V Summary Report for the Post Accident Monitoring System," dated February 2012 as Tables 5-1, 5-2 and 5-3. The partial listing in WNA-LI-00058-WNA was replaced by a reference to WNA-VR-00283-WBT-P.
Attachment 2 contains WEC non-proprietary document WNA-VR-00283-WBT-NP, Revision 7, "IV&V Summary Report for the Post Accident Monitoring System," dated February 2012. Attachment 3 contains WEC non-proprietary document CAW 12-3425, "Application for Withholding Information From Public Disclosure WNA-VR-00283-WBT-P, Revision 7, 'IV&V Summary Report for the Post Accident Monitoring System,'
(Proprietary)," dated March 1, 2012.
- 3. NRC Follow-up Request (SSER 23 Appendix HH Item Number 105)
TVA did not provide the information requested. The intent of Action Item Number 105 was to request an explicit mapping between the design bases (providedin response to Action Item Number 94) and the detailed design requirements. This mapping has not been provided.
Please provide an explicit mapping between the design bases and the detailed design requirements (i.e., between the informationprovided in response to Action Item Number 94 and the WBN Unit 2 Common Q PAMS SysRS).
TVA Response to NRC Follow-up Request The response to this item is contained in Attachment 4, TVA white paper "Common Q PAMS Design Basis Conformance to the Requirements of IEEE 603-1991," dated March 8, 2012.
E1-3
Enclosure 2 TVA Letter Dated March 9, 2012 List of Attachments Note: While project coversheets have not been included, the attachments have been reviewed and approved by Engineering prior to submittal.
- 1. WEC proprietary document WNA-VR-00283-WBT-P, Revision 7, "IV&V Summary Report for the Post Accident Monitoring System," dated February 2012 (Letter Item 2, SSER 23 Appendix HH Item Number 98)
- 2. WEC non-proprietary document WNA-VR-00283-WBT-NP, Revision 7, "IV&V Summary Report for the Post Accident Monitoring System," dated February 2012 (Letter Item 2, SSER 23 Appendix HH Item Number 98)
- 3. WEC non-proprietary document CAW 12-3425, "Application for Withholding Information From Public Disclosure WNA-VR-00283-WBT-P, Revision 7, 'IV&V Summary Report for the Post Accident Monitoring System,' (Proprietary)," dated March 1, 2012 (Letter Item 2, SSER 23 Appendix HH Item Number 98)
- 4. TVA white paper "Common Q PAMS Design Basis Conformance to the Requirements of IEEE 603-1991," dated March 8, 2012 (Letter Items 1 and 3, SSER 23 Appendix HH Item Numbers 94 and 105)
E2-1
Enclosure 3 TVA Letter Dated March 9, 2012 List of New Regulatory Commitments The following new regulatory commitments are contained in TVA white paper "Common Q PAMS Design Basis Conformance to the Requirements of IEEE 603-1991," dated March 8, 2012 (Attachment 4).
- 1. RVLIS will be included as a Type A variable in the next revision of TVA calculation WBNOSG4047, "PAM Type 'A' Variables Determination."
- 2. WBN Unit 2 FSAR,, Table 7.5-2, "Regulatory Guide 1.97 Post Accident Monitoring Variables Lists," will be updated to show RVLIS as a Type "A" variable in a future amendment.
- 3. WVA Design Criteria Document WB-DC-30-7, Revision 24, "Post Accident Monitoring Instrumentation," will be updated to show RVLIS as a Type "A" variable in a future revision.
- 4. WBN Unit 2 Technical Specifications Table 3.3.3-1 Line item 6 Reactor Vessel Water Level will be revised to remove the reference to note (g).
- 5. WBN Unit 2 Technical Specification Bases will be revised to identify RVLIS as a Type "A" variable.