Letter Sequence Approval |
---|
|
Results
Other: ML100820438, ML100820439, ML100820440, ML101170059, ML101530209, ML103060461, ML103340514, ML120390013, ML120530011, ML120530021, ML120960070, ML12143A181, ML12143A182
|
MONTHYEARML1008204402009-10-27027 October 2009 Reed Institute'S Financial Statements June 30, 2009 and 2008 Project stage: Other ML1005701782010-02-0606 February 2010 Reed College Request for 60-day Extension to Respond to RAI TAC No. ME1583 Project stage: Request ML1006101302010-02-24024 February 2010 Reed College Request for 60-Day Extension on Time to Respond to RAI TAC No. ME1583 Project stage: Request ML1008204392010-03-11011 March 2010 Letter from Reed College Continue Funding of Decommissioning Activities for Triga Mark I Research Reactor Project stage: Other ML1008204382010-03-15015 March 2010 Response and Attachments to RAI TAC No. ME1583 Project stage: Other ML1011700592010-04-19019 April 2010 Letter from Reed College Enclosed Self Guarantee Letter Requested by the RAI Dated December 10, 2009 Project stage: Other ML1013106022010-05-0505 May 2010 Reed College - Request for Extension on Time to Respond to RAI Re TAC ME1583, Dated March 8, 2010 Project stage: Request ML1015302092010-05-25025 May 2010 Reed College Corrected Self Guarantee Letter Required by RAI TAC No. ME1583 Dated December 10, 2009 Project stage: Other ML1019403242010-07-0606 July 2010 Response to Request for Additional Information for TAC No. ME1583 Project stage: Response to RAI ML1023600162010-07-30030 July 2010 Reed Response to Request for Additional Information with a Revised Safety Analysis Report and Technical Specifications Project stage: Response to RAI ML1023711812010-08-18018 August 2010 Transmittal of Response to Request for Additional Information Regarding Request for Self-Guarantee Pursuant to 10 CFR Part 50, 10 CFR Part 70 and NUREG/1757, Vol. 3 Project stage: Response to RAI ML1029904892010-10-15015 October 2010 Reed College Research Reactor Submittal of Proposed Technical Specifications for Relicensing, in Partial Response to RAI TAC No. ME1583, Dated March 8, 2010 Project stage: Response to RAI ML1030604612010-10-26026 October 2010 Reed College - Requests for an Additional Extension to Respond to RAI TAC No. ME1583, Dated March 8, 2010, Until December 31, 2010 Project stage: Other ML1033405142010-11-22022 November 2010 Reed College Submittal of Self-Guarantee Letter with the Updated Decommissioning Costs Project stage: Other ML11130A1092011-04-19019 April 2011 Reed College, Notification of Responses to RAI TAC No. ME1583 by June 15, 2011 Project stage: Response to RAI ML1115205592011-05-20020 May 2011 Reed College - Responses to RAIs Dated May 20, 2011 - Redacted Version (ME1583) Project stage: Response to RAI ML11222A0262011-08-0303 August 2011 Reed College, Notification of Stainless Steel Clad Fuel Use as of 02/04/2011 at the Reed Research Reactor Project stage: Request ML1123719392011-08-15015 August 2011 Reed College Responses to RAIs Dated August 15, 2011 Project stage: Response to RAI ML12039A1472012-01-27027 January 2012 Reed College, Submittal of Technical Specifications Proposed for the Reed Research Reactor Project stage: Request ML1205300212012-01-31031 January 2012 Reed College - License Renewal Technical Specifications Project stage: Other ML1203900132012-02-0707 February 2012 Reed College - E-mail Dated February 7, 2012 from M. Krahenbuhl, Director to G. Wertz, NRC Project Manager Acknowledgment of Renewed License Possession Limits Project stage: Other ML1209600702012-03-0101 March 2012 Reed College - E-mail Dated 3/1/2012 from M. Krahenbuhl, Director to G. Wertz, NRC Project Manager Confirming Typographical Errors in TS for License Renewal (Tac No. ME1583) Project stage: Other ML1205300112012-03-21021 March 2012 Reed College - Letter to Licensee Environmental Assessment Availability in Federal Register Project stage: Other ML12100A0752012-03-26026 March 2012 Reed College, Proposed Changes to Technical Specifications 3.4 Project stage: Request ML1205300182012-04-25025 April 2012 Reed College - Letter to Licensee Transmitting Renewed License Dated April 24, 2012, Technical Specifications and Safety Evaluation (TAC No. ME1583) Revised 03/10/2016 Project stage: Approval ML1205300192012-04-25025 April 2012 Reed College - License Renewal Safety Evaluation Project stage: Approval ML12143A1822012-04-25025 April 2012 Reed College - Corrected Technical Specifications to Reflect Correct Date of April 2012 Vs. January 2012 (Tac No. ME1583) Project stage: Other ML12143A1812012-05-24024 May 2012 Reed College - Transmittal Letter for Correction to Appendix a, Technical Specifications Date for Renewed Facility Operating License No. R-112 (Tac ME1583) Project stage: Other 2010-07-06
[Table View] |
|
---|
Category:Letter
MONTHYEARML24018A0862024-02-0101 February 2024 Examination Confirmation Letter No. 50-288/Ol-24-02, Reed College ML24017A0312024-01-18018 January 2024 Reed College, Examination Confirmation Letter 50-288/Ol-24-01 ML23289A1562023-10-25025 October 2023 Reed College 2022 Financial Test for Self-Guarantee for Decommissioning Funding ML23263B1622023-09-20020 September 2023 Reed Research Reactor 2022-2023 Annual Report ML23163A0132023-07-18018 July 2023 Examination Result Letter No. 50-288/OL-23-03, Reed College ML23163A0122023-07-18018 July 2023 Examination Report Letter No. 50-288/OL-23-03, Reed College ML23165A2312023-06-14014 June 2023 Reed Research Reactor (Docket No. 50-288/License No. R-112) 2022 Financial Assurance Update ML23139A1322023-05-16016 May 2023 Reed Research Reactor (Docket No. 50-288/License No. R-112) 2022 Financial Assurance ML23053A2402023-03-0606 March 2023 Examination Confirmation Letter No. 50-288/OL-23-03, Reed College ML23024A1732023-02-27027 February 2023 Examination Confirmation Letter No. 50-288/OL-23-02, Reed College ML23020A9372023-01-20020 January 2023 Reed College, Letter Intended to Fulfill the 14-day Written Report Requirement of Technical Specification 6.7.2, Special Reports, Following Operation in Violation of Limiting Conditions of Operation ML22241A1382022-09-0606 September 2022 Us Nuclear Regulatory Commission Staff Review Re Reed College 2021 Financial Test for Self-Guarantee for Decommissioning Funding ML22230B8022022-08-18018 August 2022 Annual Report for Reed College (Docket 50-288, License No. R-112) for the Period July 1, 2021 Through June 30, 2022 ML22229A5632022-08-17017 August 2022 Reed Research Reactor 2021-2022 Annual Report ML22199A2932022-07-28028 July 2022 Examination Confirmation Letter No. 50-288. OL-23-01, Reed College IR 05000288/20222022022-06-15015 June 2022 Reed College - U.S. Nuclear Regulatory Commission Routine Safety Inspection Report No. 05000288/2022202 IR 05000288/20222012022-06-14014 June 2022 Cover Letter - Reed College Nuclear Regulatory Commission Inspection Report No. 05000288/2022201 (Public) ML22019A1022022-02-0707 February 2022 Examination Confirmation Letter No. 50-288/OL-22-02, Reed College ML21258A3962021-10-0404 October 2021 U. S. Nuclear Regulatory Commission Staff Review Re Reed College 2020 Financial Test for Self-Guarantee for Decommission Funding NRC Ltr Rrr 2020 Financial Self Guarantee Draft ML21242A2362021-09-0808 September 2021 Reed College Regarding U.S. Nuclear Regulatory Commission Staff Review and Approval of the Revised Reed Research Reactor Requalification Plan ML21224A2032021-08-16016 August 2021 Examination Confirmation Letter No. 50-288/OL-22-01, Reed College ML21216A4392021-08-0404 August 2021 Reed College - Reed Research Reactor, Annual Report, July 1, 2020 - June 30, 2021 ML21174A1942021-06-23023 June 2021 Revised Reed Research Reactor Requalification Plan in ML21160A1792021-06-0808 June 2021 Reed College, Submitting Information Inadvertently Omitted from Letter Dated October 28, 2020 (ML21014A437) ML21202A1792021-06-0808 June 2021 Reed College - Submitting Information Inadvertently Omitted from Letter Dated October 28, 2020 (ML21014A437) IR 05000288/20212012021-06-0303 June 2021 Reed College U.S. Nuclear Regulatory Commission Routine Safety Inspection Report 05000288/2021201 ML21028A0922021-01-27027 January 2021 Examination Confirmation Letter No. 50-288/OL-21-02, Reed College ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards ML20304A3152020-10-28028 October 2020 Self-report of a Violation of Reed Research Reactor'S Requalification Plan ML21014A4372020-10-28028 October 2020 Reed College - Financial Assurance for Reed Institute Dba Reed College and Financial Statements for the Reed Institute June 30, 2020 and 2011 9 ML20290A6802020-10-27027 October 2020 U.S. Nuclear Regulatory Commission Staff Review Reed College 2019 Financial Assurance (Self-Guarantee)(EPID No. L-2019-LLL-0034 ML20265A3972020-09-21021 September 2020 Reed College - Response to Notice of Violation 05000288/2020201 ML20266G5442020-09-21021 September 2020 Reed College - Change of Management Staff ML20247J6032020-09-0303 September 2020 Examination Confirmation Letter No. 50-288/OL-21-001, Reed College IR 05000288/20202012020-09-0202 September 2020 Reed College - U.S. Nuclear Regulatory Commission Routine and Confirmatory Order Follow-Up Inspection Report No. 05000288/2020201 ML20216A6772020-08-0303 August 2020 Reed Research Reactor Annual Report July 1, 2019 -- June 30, 2020 (Rev. 1) ML20189A3002020-07-0808 July 2020 Completion of Required Actions Under Confirmatory Order EA-19-071 Related to U.S. Nuclear Regulatory Commission Investigation Reports 4-2016-022 and 4-2017-023 ML20175A8322020-06-23023 June 2020 Reed College - Change of Management Staff ML20162A1902020-06-10010 June 2020 Reed College - Actions Under Confirmatory Order EA-19-071 ML20136A4062020-04-27027 April 2020 Transmittal of Proposed Security Plan at Reed College ML20098F1312020-04-0202 April 2020 NRC Reed TR 20200402 Request for Rvw Officials Ellis and Sams 4.2.20 ML20108F5312020-04-0101 April 2020 Reed College, Notification of Personnel Change Update ML20010G1772020-01-14014 January 2020 Examination Confirmation Letter No. 50-288/OL-20-02, Reed College ML19317D7912019-10-30030 October 2019 Financial Assurance and Financial Statements for the Reed Institute June 30, 2019 and 2018 ML19282A3882019-10-0202 October 2019 Reed College - Requesting Termination of Quality Assurance Program Approval Form for Radioactive Material Packages No. 0949, Revision 0, Docket No.71-0949 IR 05000288/20192012019-08-16016 August 2019 Reed College - U.S. Nuclear Regulatory Commission Security Inspection Report 05000288/2019201 ML19225C1642019-07-31031 July 2019 Transmittal of Security Plan at Reed College ML19211C0072019-07-24024 July 2019 Reed College, Transmittal of Annual Report July 1, 2018 - June 30, 2019 ML19155A1752019-06-13013 June 2019 U.S. Nuclear Regulatory Commission Staff Review Reed College 2018 Financial Assurance (Self-Guarantee) Docket No. 50 288 ML23130A2532019-04-29029 April 2019 Reed College, Management Change Update 2024-02-01
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML1205300182012-04-25025 April 2012 Reed College - Letter to Licensee Transmitting Renewed License Dated April 24, 2012, Technical Specifications and Safety Evaluation (TAC No. ME1583) Revised 03/10/2016 ML1034404212011-01-0404 January 2011 Reed College - Amendment No. 8 Special Nuclear and Byproduct Material Possession Limits ML14204A6131968-07-0202 July 1968 TSAF50-00288 - Reed College, Current Facility Operating License R-112, Tech Specs, Revised 03/09/2016 2012-04-25
[Table view] |
Text
April 25, 2012 Dr. Melinda Krahenbuhl, Director The Reed Research Reactor Reed College 3203 SE Woodstock Blvd.
Portland, OR 97202-8199
SUBJECT:
REED COLLEGE - ISSUANCE OF RENEWED FACILITY OPERATING LICENSE NO. R-112 FOR THE REED RESEARCH REACTOR (TAC NO.
ME1583)
Dear Dr. Krahenbuhl:
The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Renewed Facility Operating License No. R-112 for Reed College in response to the application for license renewal dated August 29, 2007, as supplemented on January 26, July 30, and October 15, 2010, and May 20, August 3, and December 12, 2011, and January 27, and March 26, 2012. The renewed facility operating license is effective as of the date of the license and shall expire at midnight, twenty years from the date of issuance, unless terminated sooner.
In accordance with agency practice, the NRC has restated the license in its entirety, incorporating all changes and amendments made since the issuance of the original license.
Also enclosed with the renewed facility operating license is the safety evaluation report associated with the license renewal. A Notice of Issuance of Renewed Facility Operating License No. R-112 is being sent to the Office of the Federal Register for publication. The environmental assessment was sent to you under separate cover.
If you have any questions, please contact me at 301-415-0893 or by electronic mail at Geoffrey.Wertz@nrc.gov.
Sincerely,
/RA/
Geoffrey A. Wertz, Project Manager Research and Test Reactors Licensing Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-288
Enclosures:
- 1. Facility Operating License No. R-112
- 2. Safety Evaluation Report cc: See next page
Pkg: ML120530017; Ltr:ML120530018; App. A (TS):ML120530021; SER:ML120530019
- Concurrence via email NRR-106 OFFICE PRLB:PM* Tech Editor PRLB:LA OGC PRLB:BC NAME GWertz JDoughtery GLappert BMizuno JQuichocho DATE 3/7/2012 3/1/2012 3/8/2012 3/19/2012 4/8/12 OFFICE DPR:D NRR:D PRLB/PM NAME TMcGinty ELeeds GWertz DATE 4/12/12 4/24/2012 4/25/2012 Reed College Docket No. 50-288 cc:
Mayor of the City of Portland 1220 Southwest 5th Avenue Portland, OR 97204 Reed College ATTN: Dr. Ellen Stauder, Dean of Faculty 3203 S.E. Woodstock Boulevard Portland, OR 97202-8199 Reed College ATTN: Dr. Colin Diver, President 3203 S.E. Woodstock Boulevard Portland, OR 97202-8199 Director Oregon Department of Energy 625 Marion Street NE Salem, OR 97301-3737 Program Director Radiation Control Program Oregon Health Services Department of Human Services 800 NE Oregon Street, Suite 640 Portland, OR 97232-2162 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611
Enclosure 1 Reed College Docket No. 50-288 Facility Operating License ADAMS Accession No. ML120530018
REED COLLEGE DOCKET NO. 50-288 FACILITY OPERATING LICENSE License No. R-112
- 1. The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A. The application for renewal of Facility Operating License No. R-112 filed by Reed College (the licensee), dated August 29, 2007, as supplemented on January 26, July 30, and October 15, 2010, and May 20, August 3, and December 12, 2011, and January 27, and March 26, 2012, (the application), complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in Title 10, Chapter I, of the Code of Federal Regulations (10 CFR);
B. Construction of the Reed Research Reactor (the facility) was completed in substantial conformity with the Construction Permit No. CPRR-101, the provisions of the Act, and the rules and regulations of the Commission; C. The facility will operate in conformity with the application, as supplemented, the provisions of the Act, and the rules and regulations of the Commission; D. There is reasonable assurance that (i) the activities authorized by this license can be conducted at the designated location without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; E. The licensee is technically and financially qualified to engage in the activities authorized by this license in accordance with the rules and regulations of the Commission; F. The applicable provisions of 10 CFR Part 140, Financial Protection Requirements and Indemnity Agreements, have been satisfied;
G. The issuance of this license will not be inimical to the common defense and security or to the health and safety of the public; H. The issuance of this license is in accordance with 10 CFR Part 51, Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions, of the Commissions regulations and all applicable requirements; and I. The receipt, possession and use of byproduct and special nuclear materials as authorized by this facility operating license will be in accordance with the Commission's regulations in 10 CFR Part 30, Rules of General Applicability to Domestic Licensing of Byproduct Material, and 10 CFR Part 70, Domestic Licensing of Special Nuclear Material.
- 2. Accordingly, Facility Operating License No. R-112 is hereby renewed in its entirety to read as follows:
A. This license applies to the Reed Research Reactor (herein the facility) owned by Reed College (herein the licensee), located on the licensees campus in Portland, Oregon, and described in the licensees application for license renewal, dated August 29, 2007, as supplemented.
B. Subject to the conditions and requirements incorporated herein, the Commission hereby licenses Reed College as follows:
(1) Pursuant to subsection 104c of the Act and 10 CFR Part 50, Domestic Licensing of Production and Utilization Facilities, to possess, use, and operate the facility as a utilization facility at the designated location in accordance with the procedures and limitations described in the application and set forth in this license.
(2) Pursuant to the Act and 10 CFR Part 70, the following activities are included:
- a. to receive, possess, use, but not separate, in connection with operation of the facility, up to 3600 grams of contained uranium-235 enriched to less than 20 percent in the form of TRIGA fuel;
- b. to receive, possess, use, but not separate, in connection with operation of the facility, up to 16 grams of contained uranium-235 enriched to any enrichment in the form of nuclear fission chambers or fission foils;
- c. to receive and possess, but not use or separate, up to 40 grams of uranium-235 enriched to less than 20 percent in the form of demountable TRIGA fuel element number 2898; and
- d. to receive, possess, use, but not separate, in connection with operation of the facility, such special nuclear material as may be produced by the operation of the facility.
(3) Pursuant to the Act and 10 CFR Part 30, the following activities are included:
- a. to receive, possess, and use, in connection with the operation of the facility, a 1.64-curie sealed americium-beryllium neutron startup source;
- b. to receive, possess, and use, but not separate, in connection with operation of the facility, such byproduct material as may be produced by operation of the reactor.
C. This license shall be deemed to contain and is subject to the conditions specified in 10 CFR Parts 20, 30, 50, 51, 55, 70 and 73 of the Commissions regulations; is subject to all applicable provisions of the Act, and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1) Maximum Power Level The licensee is authorized to operate the facility at a steady-state power level not in excess of 250 kilowatts (thermal) as specified in the Technical Specifications.
(2) Technical Specification The Technical Specifications contained in Appendix A, as revised through Amendment No. 10, are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications.
(3) Physical Security Plan The licensee shall maintain and fully implement all provisions of the Commission-approved physical security plan, including amendments and changes made pursuant to the authority of 10 CFR 50.54(p). The approved physical security plan entitled Physical Security Plan for Reed College Reactor Facility, dated June 1983, submitted by letter dated November 10, 1983, as supplemented by letter dated February 22, 1984, consists of documents withheld from public disclosure pursuant to 10 CFR 2.390(d).
Amendment No. 10
D. This license is effective as of the date of issuance and shall expire at midnight, twenty years from the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Eric J. Leeds, Director Office of Nuclear Reactor Regulation
Attachment:
Appendix A, Technical Specifications Date of Issuance: April 24, 2012