MONTHYEARML0921703692009-08-19019 August 2009 Reed College - Acknowledgement of Technical Specification Amendment Request to Be Incorporated Into License Renewal Application Review (Tac ME1583) Project stage: Other ML1008204402009-10-27027 October 2009 Reed Institutes Financial Statements June 30, 2009 and 2008 Project stage: Other ML0934304002009-12-10010 December 2009 Reed College, Request for Additional Information Regarding Financial Qualifications for the Renewed License and Power Upgrade for the Reed College Research Reactor Project stage: RAI ML1005701782010-02-0606 February 2010 Reed College Request for 60-day Extension to Respond to RAI TAC No. ME1583 Project stage: Request ML1006101302010-02-24024 February 2010 Reed College Request for 60-Day Extension on Time to Respond to RAI TAC No. ME1583 Project stage: Request ML1004903252010-03-0808 March 2010 Reed College Request for Additional Information Regarding License Renewal Application Project stage: RAI ML1008204392010-03-11011 March 2010 Letter from Reed College Continue Funding of Decommissioning Activities for Triga Mark I Research Reactor Project stage: Other ML1008204382010-03-15015 March 2010 Response and Attachments to RAI TAC No. ME1583 Project stage: Other ML1011700592010-04-19019 April 2010 Letter from Reed College Enclosed Self Guarantee Letter Requested by the RAI Dated December 10, 2009 Project stage: Other ML1013106022010-05-0505 May 2010 Reed College - Request for Extension on Time to Respond to RAI Re TAC ME1583, Dated March 8, 2010 Project stage: Request ML1015302092010-05-25025 May 2010 Reed College Corrected Self Guarantee Letter Required by RAI TAC No. ME1583 Dated December 10, 2009 Project stage: Other ML1014704122010-06-0101 June 2010 Reed College, Approval of Request for an Extension of Response Time for the NRC Request for Additional Information Dated March 8, 2010 Project stage: RAI ML1019403242010-07-0606 July 2010 Response to Request for Additional Information for TAC No. ME1583 Project stage: Response to RAI ML1023600162010-07-30030 July 2010 Reed Response to Request for Additional Information with a Revised Safety Analysis Report and Technical Specifications Project stage: Response to RAI ML1023711812010-08-18018 August 2010 Transmittal of Response to Request for Additional Information Regarding Request for Self-Guarantee Pursuant to 10 CFR Part 50, 10 CFR Part 70 and NUREG/1757, Vol. 3 Project stage: Response to RAI ML1029904892010-10-15015 October 2010 Reed College Research Reactor Submittal of Proposed Technical Specifications for Relicensing, in Partial Response to RAI TAC No. ME1583, Dated March 8, 2010 Project stage: Response to RAI ML1030604612010-10-26026 October 2010 Reed College - Requests for an Additional Extension to Respond to RAI TAC No. ME1583, Dated March 8, 2010, Until December 31, 2010 Project stage: Other ML1033405142010-11-22022 November 2010 Reed College Submittal of Self-Guarantee Letter with the Updated Decommissioning Costs Project stage: Other ML11130A1092011-04-19019 April 2011 Reed College, Notification of Responses to RAI TAC No. ME1583 by June 15, 2011 Project stage: Response to RAI ML1115205592011-05-20020 May 2011 Reed College - Responses to RAIs Dated May 20, 2011 - Redacted Version (ME1583) Project stage: Response to RAI ML1117900972011-07-21021 July 2011 Reed College - Letter to Licensee Notice of Acceptance for Docketing of Application and Opportunity to Provide Written Comments And/Or Request a Hearing and Order Imposing Procedures for Access to SUNSI License Renewal (Tac No. ME1583) Project stage: Acceptance Review ML11222A0262011-08-0303 August 2011 Reed College, Notification of Stainless Steel Clad Fuel Use as of 02/04/2011 at the Reed Research Reactor Project stage: Request ML1117901102011-08-15015 August 2011 FRN: General Notice. Reed College - Notice of Acceptance for Docketing of Application and Opportunity to Provide Written Comments And/Or Request a Hearing and Order Imposing Procedures for Access to SUNSI License Renewal Project stage: Acceptance Review ML1123719392011-08-15015 August 2011 Reed College Responses to RAIs Dated August 15, 2011 Project stage: Response to RAI ML1131800572011-11-10010 November 2011 Reed College - E-mail from M. Krahenbuhl, Director to G. Wertz, NRC Project Manager Requesting an Extension to NRC Request for Additional Information Project stage: Request ML1136301452011-12-12012 December 2011 Reed College - *Redacted* License Renewal Application Request for Additional Information Responses Dated December 12, 2011 (Tac No. ME1583) Project stage: Request ML12039A1472012-01-27027 January 2012 Reed College, Submittal of Technical Specifications Proposed for the Reed Research Reactor Project stage: Request ML1205300212012-01-31031 January 2012 Reed College - License Renewal Technical Specifications Project stage: Other ML1203900132012-02-0707 February 2012 Reed College - E-mail Dated February 7, 2012 from M. Krahenbuhl, Director to G. Wertz, NRC Project Manager Acknowledgment of Renewed License Possession Limits Project stage: Other ML1209600702012-03-0101 March 2012 Reed College - E-mail Dated 3/1/2012 from M. Krahenbuhl, Director to G. Wertz, NRC Project Manager Confirming Typographical Errors in TS for License Renewal (Tac No. ME1583) Project stage: Other ML1205300112012-03-21021 March 2012 Reed College - Letter to Licensee Environmental Assessment Availability in Federal Register Project stage: Other ML12100A0752012-03-26026 March 2012 Reed College, Proposed Changes to Technical Specifications 3.4 Project stage: Request ML1205300192012-04-25025 April 2012 Reed College - License Renewal Safety Evaluation Project stage: Approval ML12143A1822012-04-25025 April 2012 Reed College - Corrected Technical Specifications to Reflect Correct Date of April 2012 Vs. January 2012 (Tac No. ME1583) Project stage: Other ML1205300182012-04-25025 April 2012 Reed College - Letter to Licensee Transmitting Renewed License Dated April 24, 2012, Technical Specifications and Safety Evaluation (TAC No. ME1583) Revised 03/10/2016 Project stage: Approval ML12143A1812012-05-24024 May 2012 Reed College - Transmittal Letter for Correction to Appendix a, Technical Specifications Date for Renewed Facility Operating License No. R-112 (Tac ME1583) Project stage: Other 2010-07-06
[Table View] |
Text
REED COLLEGE REED RESEARCH REACTOR LICENSE NO. R-112 DOCKET NO. 50-288 RESPONSES TO THE REQUEST FOR ADDITIONAL INFORMATION DATED AUGUST 15, 2011 REDACTED VERSION*
SECURITY-RELATED INFORMATION REMOVED
- REDACTED TEXT AND FIGURES BLACKED OUR OR DENOTED BY BRACKETS
REED COLLEGE REACTOR FACILITY 3203 Southeast August 15, 2011 Woodstock Boulevard Portland, Oregon Document Control Desk 97202-8199 U.S. Nuclear Regulatory Commission telep..one Washington, DC 20555-0001 503/777-7222 Docket: 50-288 fax License No: R-112 503/777-7274 RE: Clarifications in Response to phone calls on July 7, 2011, and July 15, 2011 email
@reed.edu The following are clarifications requested in phone calls on July 7 and July 15.
The responses reference the numbering from the original request for additional http://reactor.reed.edu information.
RAI 7. Please make a statement regarding the use of stainless steel clad fuel.
The RRR is a water-cooled, water moderated TRIGA reactor loaded with NRC qualified TRIGA fuel. The core is currently loaded with stainless steel clad "original" fuel as described in NUREG -1282.
RAI 11. Please clarify the core support structure is suitable for use of the requested license.
The core structure was visually inspected July 18, 2011 to verify the condition.
During the inspection there were no visible signs of corrosion, cracking or deformation of the core support structure. Images obtained during the inspection are attached. The condition of pool, core structure, and fuel is observed and noted in the daily start up and shutdown as part of normal operations. The core support structure is deemed acceptable for continued use over the requested license period.
RAI 40. Change the Safety Limit to be consistent with NUREG 1537 part 1.
The safety limit has been set to 1150 1C.
RAI 18. Change the range of the pH to NUREG 1537 part 1 section 5.4 vs. being consistent with NUREG 1537 part I appendix 14.
The pH range has been changed to 5.5 to 7.5 as suggested in NUREG 1537 part 1 section 5.4.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on I
ZSZ) d/
Melin a P. Krahensbuhl, Ph.D.
Director, Reed Research Reactor.
Figure 1. Lower grid plate - Reed Figure 2. Legs - Reed Research Reactor