November 30, 2011 BW110140 U. S. Nuclear Regulatory Commission ATIN: Document Control Desk Washington, DC 20555-0001 Braidwood Station, Units 1 and 2 Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456 and STN 50-457

Subject:

Braidwood Station Readiness for Traditional Enforcement Violation Follow-up Inspection

References:

Letter from E. R. Duncan (U. S. NRC) to M. J. Pacilio (Exelon Generation Company, LLC), Mid-Cycle Letter for Braidwood Station, Units 1 and 2; 05000456/2011-006; 05000457/2011-006, dated September 1, 2011 On September 1, 2011, the NRC issued the mid-cycle assessment letter to Exelon Generation Company, LLC (EGC) for Braidwood Station, Units 1 and 2 (Reference 1). The NRC letter discusses plans to conduct a traditional enforcement violation follow-up inspection using Inspection Procedure 92723, "Follow-up Inspection for Three or More Severity Level IV Traditional Enforcement Violations in the Same Area in a 12-Month Period."

NRC Region III verbally requested that EGC provide written notification of readiness for a traditional enforcement violation follow-up inspection. This letter provides notification that EGC is prepared for this inspection.

There are no regulatory commitments contained in this letter.

Should you have any questions concerning this letter, please contact Mr. Chris VanDenburgh, Regulatory Assurance Manager, at (815) 417-2800.

Daniel J. Enrighr---

Site Vice President Braidwood Station cc: NRC Regional Administrator, Region "'

NRC Project Manager, NRR - Braidwood Station NRC Senior Resident Inspector - Braidwood Station