Letter Sequence Request |
---|
TAC:ME4679, Clarify Application of Setpoint Methodology for LSSS Functions (Open) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting
Results
Other: GNRO-2012/00150, Final Report for Replacement Steam Dryer, GNRO-2017/00039, Steam Dryer Visual Inspection Results for the First Two Scheduled Refueling Outages, ML102660403, ML111720830, ML112560396, ML12167A257, ML12167A269, ML12177A287, ML13108A217, NRC-2012-0105, Environmental Assessment and Finding of No Significant Impact Related Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt
|
MONTHYEARML1026604002010-08-20020 August 2010 GE-Hitachi Nuclear Energy Americas LLC - Affidavit of Edward Schrull Withholding from Public Disclosure Proprietary Report NEDC-33477P Project stage: Request ML1026603992010-08-31031 August 2010 NEDO-33477, Revision 0, Safety Analysis Report for Grand Gulf Nuclear Station Constant Pressure Power Uprate. Project stage: Request ML1026604032010-09-0808 September 2010 License Amendment Request Extended Power Uprate Project stage: Other GNRO-2010/00056, NEDO-33601, Revison 0, Engineering Report Grand Gulf Replacement Steam Dryer Fatigue Stress Analysis Using Pble Methodology. Appendix E Through Appendix G2010-09-30030 September 2010 NEDO-33601, Revison 0, Engineering Report Grand Gulf Replacement Steam Dryer Fatigue Stress Analysis Using Pble Methodology. Appendix E Through Appendix G Project stage: Request ML1026604062010-09-30030 September 2010 NEDO-33601, Revison 0, Engineering Report Grand Gulf Replacement Steam Dryer Fatigue Stress Analysis Using Pble Methodology. Appendix B Through Appendix D Project stage: Request ML1026604012010-09-30030 September 2010 NEDO-33601, Revison 0, Engineering Report Grand Gulf Replacement Steam Dryer Fatigue Stress Analysis Using Pble Methodology. Cover Through Appendix a Project stage: Request ML1030102002010-11-0909 November 2010 Supplemental Information Needed for Acceptance of License Amendment Request, Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Megawatts Thermal Project stage: Acceptance Review GNRO-2010/00071, Supplemental Information, License Amendment Request, Extended Power Uprate2010-11-18018 November 2010 Supplemental Information, License Amendment Request, Extended Power Uprate Project stage: Supplement GNRO-2010/00073, Supplemental Information License Amendment Request, Extended Power Uprate2010-11-23023 November 2010 Supplemental Information License Amendment Request, Extended Power Uprate Project stage: Supplement ML1034201082010-12-16016 December 2010 Request for Withholding Information from Public Disclosure, 9/7/10 Affidavit Executed by E. Schrull, GEH Re NEDC-33601P Project stage: Withholding Request Acceptance ML1034705862011-01-0505 January 2011 Request for Withholding Information from Public Disclosure, 11/19/10 Affidavit Executed by E. Schrull, GE-Hitachi, Regarding NEDC-33621P Project stage: Withholding Request Acceptance ML1102602812011-01-26026 January 2011 E-mail, Request for Additional Information Instrument and Controls, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1102602872011-01-26026 January 2011 E-mail, Request for Additional Information Fire Protection, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1102701872011-01-27027 January 2011 Request for Additional Information, Emcb Non-Steam Dryer Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1103103902011-01-31031 January 2011 E-mail, Request for Additional Information, Vessels and Internal Integrity Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1103901732011-02-0808 February 2011 Email, Request for Additional Information, Nrr/Dci/Csgb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00012, Request for Additional Information Regarding Extended Power Uprate2011-02-23023 February 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request GNRO-2011/00011, Request for Additional Information Regarding Extended Power Uprate2011-02-23023 February 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1105407052011-02-23023 February 2011 E-mail, Request for Additional Information, Nrr/Dirs/Ihpb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1105407122011-02-23023 February 2011 E-mail, Request for Additional Information, Nrr/Dra/Apla Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00013, Request for Additional Information Regarding Extended Power Uprate2011-02-23023 February 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1034200962011-02-25025 February 2011 Request for Withholding Information from Public Disclosure, 8/20/10 Affidavit Executed by E. Schrull, GEH, for NEDC-33477P Project stage: Withholding Request Acceptance ML1106007172011-03-0101 March 2011 Email Request for Additional Information, Round 2, Nrr/Dci/Cvib Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00016, Request for Additional Information Regarding Extended Power Uprate2011-03-0909 March 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1107501322011-03-16016 March 2011 Email, Dose Assessment Branch, Request for Additional Information, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1108202242011-03-23023 March 2011 Email, Request for Additional Information, Nrr/Dss/Srxb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1108202272011-03-23023 March 2011 Request for Additional Information, Nrr/Dss/Srxb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00018, Request for Additional Information Regarding Extended Power Uprate2011-03-30030 March 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request GNRO-2011/00021, Response to Request for Additional Information Regarding Extended Power Uprate2011-03-31031 March 2011 Response to Request for Additional Information Regarding Extended Power Uprate Project stage: Response to RAI ML1109401362011-04-0404 April 2011 Email, Request for Additional Information, Nrr/Dci/Csgb Review, Round 2, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1109502722011-04-0505 April 2011 Email, Request for Additional Information, Nrr/De/Eeeb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1109502812011-04-0505 April 2011 Request for Additional Information, Nrr/De/Eeeb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1110301112011-04-12012 April 2011 Email, Request for Additional Information, Nrr/Dss/Snpb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00024, Response to Request for Additional Information Regarding Extended Power Uprate2011-04-14014 April 2011 Response to Request for Additional Information Regarding Extended Power Uprate Project stage: Response to RAI ML11112A0982011-04-21021 April 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1110401002011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 3/28/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00018 Project stage: Withholding Request Acceptance ML1110401252011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 2/20/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00013 Project stage: Withholding Request Acceptance ML1110401132011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 2/20/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00011 Project stage: Withholding Request Acceptance ML1110401072011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 2/17/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00012 Project stage: Withholding Request Acceptance ML1110401162011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 3/30/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00021 Project stage: Withholding Request Acceptance GNRO-2011/00035, Response to Request for Additional Information Regarding Extended Power Uprate2011-05-0505 May 2011 Response to Request for Additional Information Regarding Extended Power Uprate Project stage: Response to RAI ML1113001562011-05-10010 May 2011 Email, Request for Additional Information, Nrr/Dss/Scvb Review, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00037, Request for Additional Information Regarding Extended Power Uprate2011-05-11011 May 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request ML1114002992011-05-20020 May 2011 E-mail, Request for Additional Information, Nrr/Dci/Emcb Review, Round 2, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1113905252011-05-31031 May 2011 Request for Withholding Information from Public Disclosure, 4/21/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00025 Project stage: Withholding Request Acceptance ML1115204582011-06-0101 June 2011 Email, Request for Additional Information, Nrr/Dra/Aadb Review, Round 2, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI ML1115304392011-06-0606 June 2011 (Redacted) Request for Additional Information from Nrr/De/Emcb Steam Dryer, Round 2, Amendment Request for Extended Power Uprate to Increase the Maximum Reactor Core Power Operating Limit from 3898 to 4408 Mwt Project stage: RAI GNRO-2011/00043, Request for Additional Information Regarding Extended Power Uprate2011-06-0808 June 2011 Request for Additional Information Regarding Extended Power Uprate Project stage: Request GNRO-2011/00046, Response to Request for Additional Information Regarding Extended Power Uprate2011-06-15015 June 2011 Response to Request for Additional Information Regarding Extended Power Uprate Project stage: Response to RAI ML1117200422011-06-20020 June 2011 Licensee Response Regarding Request for Additional Information on Training for Prnms (TAC No. 4679) Project stage: Request 2011-03-30
[Table View] |
|
---|
Category:Letter type:GNRO
MONTHYEARGNRO-2023/00014, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0606 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GNRO-2023/00015, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-06-0606 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors GNRO-2021/00037, 2021 Annual Report of Changes and Errors to 10 CFR 50.46 Analysis Grand Gulf Nuclear Station, Unit 12021-11-30030 November 2021 2021 Annual Report of Changes and Errors to 10 CFR 50.46 Analysis Grand Gulf Nuclear Station, Unit 1 GNRO-2021/00017, Notification of Readiness for Supplemental Inspection2021-06-22022 June 2021 Notification of Readiness for Supplemental Inspection GNRO-2021/00014, Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency2021-06-0101 June 2021 Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency GNRO-2021/00015, Annual Radioactive Effluent Release Report2021-04-28028 April 2021 Annual Radioactive Effluent Release Report GNRO-2021/00011, Revision of Original Report of 10CFR50.59 and Commitments Change Evaluations - July 1, 2018 Through May 21, 20202021-04-19019 April 2021 Revision of Original Report of 10CFR50.59 and Commitments Change Evaluations - July 1, 2018 Through May 21, 2020 GNRO-2021/00012, Annual Report of Individual Monitoring - NRC Form 5 for 2020 Per 10 CFR 20.22062021-04-13013 April 2021 Annual Report of Individual Monitoring - NRC Form 5 for 2020 Per 10 CFR 20.2206 GNRO-2020/00045, 2020 Report of Changes and Errors to 10 CFR 50.46 Analysis2020-12-16016 December 2020 2020 Report of Changes and Errors to 10 CFR 50.46 Analysis GNRO-2020/00034, Notification of Spent Fuel Cask Use2020-10-0808 October 2020 Notification of Spent Fuel Cask Use GNRO-2020/00033, Response to NRC Integrated Inspection Report 05000416/20200022020-09-10010 September 2020 Response to NRC Integrated Inspection Report 05000416/2020002 GNRO-2020/00029, Report of 10 CFR 72.48 Evaluations July 1, 2018 Through June 30, 20202020-08-18018 August 2020 Report of 10 CFR 72.48 Evaluations July 1, 2018 Through June 30, 2020 GNRO-2020/00022, Report of Technical Specification Bases Changes2020-07-21021 July 2020 Report of Technical Specification Bases Changes GNRO-2020/00027, Core Operating Limits Report (COLR) Cycle 23 Revision 1 for Grand Gulf Nuclear Station, Unit 1 (GGNS)2020-07-16016 July 2020 Core Operating Limits Report (COLR) Cycle 23 Revision 1 for Grand Gulf Nuclear Station, Unit 1 (GGNS) GNRO-2020/00023, Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies2020-06-26026 June 2020 Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies GNRO-2020/00020, Core Operating Limits Report (COLR) Cycle 23, and Pressure and Temperature Limits Report (PTLR) Update for Grand Gulf Nuclear Station, Unit 1 (GGNS)2020-05-0505 May 2020 Core Operating Limits Report (COLR) Cycle 23, and Pressure and Temperature Limits Report (PTLR) Update for Grand Gulf Nuclear Station, Unit 1 (GGNS) GNRO-2020/00018, Annual Radiological Effluent Release Report2020-04-30030 April 2020 Annual Radiological Effluent Release Report GNRO-2020/00016, Annual Report of Individual Monitoring -NRC Form 5 for 2019 Per 10 CFR 20.22062020-04-16016 April 2020 Annual Report of Individual Monitoring -NRC Form 5 for 2019 Per 10 CFR 20.2206 GNRO-2020/00015, Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test2020-04-0707 April 2020 Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test GNRO-2020/00007, Spent Fuel Storage Radioactive Effluent Release Report for 20192020-02-20020 February 2020 Spent Fuel Storage Radioactive Effluent Release Report for 2019 GNRO-2020/00006, License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies2020-02-19019 February 2020 License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies GNRO-2019/00052, Report of Changes and Errors to 10 CFR 50.46 Analysis2019-12-13013 December 2019 Report of Changes and Errors to 10 CFR 50.46 Analysis GNRO-2019/00051, Notification of Readiness of 92723 Inspection2019-12-11011 December 2019 Notification of Readiness of 92723 Inspection GNRO-2019/00045, Emergency Plan, Revision 792019-10-29029 October 2019 Emergency Plan, Revision 79 GNRO-2019/00037, Notification of Spent Fuel Cask Use2019-09-20020 September 2019 Notification of Spent Fuel Cask Use GNRO-2019/00036, Correction to Gnro 2019-00017 Emergency Plan Revision 782019-08-0808 August 2019 Correction to Gnro 2019-00017 Emergency Plan Revision 78 GNRO-2019/00027, Notification of Readiness of 95001 Supplemental Inspections2019-07-0303 July 2019 Notification of Readiness of 95001 Supplemental Inspections GNRO-2019/00031, Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 - Corrected Report2019-06-25025 June 2019 Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 - Corrected Report GNRO-2019/00028, Supplement to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation.2019-06-13013 June 2019 Supplement to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation. GNRO-2019/00026, Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval2019-05-0606 May 2019 Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval GNRO-2019/00024, Annual Radioactive Effluent Release Report2019-04-30030 April 2019 Annual Radioactive Effluent Release Report GNRO-2019/00020, Annual Radiological Operating Report (AREOR)2019-04-30030 April 2019 Annual Radiological Operating Report (AREOR) GNRO-2019/00022, Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.22062019-04-22022 April 2019 Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 GNRO-2019/00017, Emergency Plan, Revision 782019-03-14014 March 2019 Emergency Plan, Revision 78 GNRO-2019/00014, Snubber Testing Program for Fourth Inspection Interval2019-03-13013 March 2019 Snubber Testing Program for Fourth Inspection Interval GNRO-2019/00012, Internal Events Probabilistic Risk Assessment (PRA) Sensitivity Study Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program2019-03-0606 March 2019 Internal Events Probabilistic Risk Assessment (PRA) Sensitivity Study Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program GNRO-2019/00016, Spent Fuel Storage Radioactive Effluent Release Report for 20182019-02-21021 February 2019 Spent Fuel Storage Radioactive Effluent Release Report for 2018 GNRO-2019/00003, Application to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation2019-01-23023 January 2019 Application to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation GNRO-2018/00057, Submittal of Revision 17 to the Grand Gulf Nuclear Station Physical Security, Safeguards Contingency, and Training and Qualification Plan2018-12-0404 December 2018 Submittal of Revision 17 to the Grand Gulf Nuclear Station Physical Security, Safeguards Contingency, and Training and Qualification Plan GNRO-2018/00055, Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ...2018-11-30030 November 2018 Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ... GNRO-2018/00054, Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval2018-11-30030 November 2018 Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval GNRO-2018/00052, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information2018-10-24024 October 2018 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information GNRO-2018/00051, Supplement to Revise Technical Specifications to Adopt Technical Specification Task Force Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-10-23023 October 2018 Supplement to Revise Technical Specifications to Adopt Technical Specification Task Force Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control GNRO-2018/00046, Submittal of 2018 Report of Changes and Errors to 10CFR50.462018-10-16016 October 2018 Submittal of 2018 Report of Changes and Errors to 10CFR50.46 GNRO-2018/00047, Submittal of 2018 Inservice Inspection Summary Report2018-10-16016 October 2018 Submittal of 2018 Inservice Inspection Summary Report GNRO-2018/00048, Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 62018-10-10010 October 2018 Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6 GNRO-2018/00042, Core Operating Limits Report Cycle 22, Revision 12018-09-18018 September 2018 Core Operating Limits Report Cycle 22, Revision 1 GNRO-2018/00043, Revised Offsite Dose Calculation Manual2018-09-18018 September 2018 Revised Offsite Dose Calculation Manual GNRO-2018/00039, Report of Technical Specification Bases Changes2018-08-20020 August 2018 Report of Technical Specification Bases Changes GNRO-2018/00040, Report of 10CFR50.59 Evaluations and Commitment Change Evaluations - July 1, 2016 Through June 30, 20182018-08-20020 August 2018 Report of 10CFR50.59 Evaluations and Commitment Change Evaluations - July 1, 2016 Through June 30, 2018 2023-06-06
[Table view] |
Text
Entergy Operations, Inc.
P. O. Box 756 Port Gibson, MS 39150 Michael A. Krupa Director, Extended Power Uprate Grand Gulf Nuclear Station Tel. (601) 437-6684 GNRO-2011/00087 October 10, 2011 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
Request for Additional Information Regarding Extended Power Uprate Grand Gulf Nuclear Station, Unit 1 Docket No. 50-416 License No. NPF-29
REFERENCES:
- 1. Email from A. Wang to F. Burford dated October 6, 2011, GGNS EPU Request for Additional Information Related to Mechanical and Civil Engineering Branch Review Excluding the Steam Dryer (ME4679)
- 2. License Amendment Request, Extended Power Uprate, dated September 8, 2010 (GNRO-2010/00056, NRC ADAMS Accession No. ML102660403)
Dear Sir or Madam:
The Nuclear Regulatory Commission (NRC) requested additional information (Reference 1) regarding certain aspects of the Grand Gulf Nuclear Station, Unit 1 (GGNS) Extended Power Uprate (EPU) License Amendment Request (LAR) (Reference 2). Attachment 1 provides responses to the additional information requested by the Mechanical and Civil Engineering Branch.
No change is needed to the no significant hazards consideration included in the initial LAR (Reference 2) as a result of the additional information provided. There are no new commitments included in this letter.
If you have any questions or require additional information, please contact Jerry Burford at 601-368-5755.
GNRO-2011/00087 Page 2 of 2 I declare under penalty of perjury that the foregoing is true and correct. Executed on October 10, 2011.
Sincerely, MAK/FGB/dm Attachments:
- 1. Response to Request for Additional Information, Mechanical and Civil Engineering Branch cc: Mr. Elmo E. Collins, Jr.
Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 612 East Lamar Blvd., Suite 400 Arlington, TX 76011-4125 U. S. Nuclear Regulatory Commission ATTN: Mr. A. B. Wang, NRR/DORL (w/2)
ATTN: ADDRESSEE ONLY ATTN: Courier Delivery Only Mail Stop OWFN/8 B1 11555 Rockville Pike Rockville, MD 20852-2378 State Health Officer Mississippi Department of Health P. O. Box 1700 Jackson, MS 39215-1700 NRC Senior Resident Inspector Grand Gulf Nuclear Station Port Gibson, MS 39150
Attachment 1 GNRO-2011/00087 Grand Gulf Nuclear Station Extended Power Uprate Response to Request for Additional Information Mechanical and Civil Engineering Branch to GNRO-2011/ 00087 Page 1 of 2 Response to Request for Additional Information Mechanical and Civil Engineering Branch By letter dated September 8, 2010, Entergy Operations, Inc. (Entergy) submitted a license amendment request (LAR) for an Extended Power Uprate (EPU) for Grand Gulf Nuclear Station, Unit 1 (GGNS). By letters dated February 23, 2011 (NRC ADAMS Accession No. ML110540545), June 15, 2011 (NRC ADAMS Accession No. ML111670059), and August 25, 2011 (NRC ADAMS Accession No. ML112370770) Entergy submitted responses to the request for additional information (RAI) from the Mechanical and Civil Engineering Branch excluding the steam dryer. Subsequently, the U.S. Nuclear Regulatory Commission (NRC) staff has determined that the following additional information is needed for the NRC Mechanical and Civil Engineering Branch staff to complete their review of the amendment. Entergys response to each item is provided below.
RAI # 1 Page 2-266 of the power uprate safety analysis report (PUSAR), which was submitted as part of Reference 1 in support of the proposed extended power uprate (EPU) at the Grand Gulf Nuclear Station, Unit 1 (GGNS), states that the GGNS annulus pressurization (AP) loads were reconciled for original licensed thermal power (OLTP), current licensed thermal power (CLTP) and EPU conditions, in response to General Electric-Hitachi (GEH) Safety Communication (SC) 09-01. Additionally, page 2-266 of the PUSAR states that evaluations were performed to determine the effect of revising the AP loads on the dynamic structural response of the reactor pressure vessel (RPV), reactor internals, piping and containment structures. With respect to the impact of the revision of the aforementioned AP loads on the EPU evaluations, please address the following:
a) Page 2-269 of the PUSAR indicates that the methodology for calculating jet impingement (JI) and jet reaction (JR) loads on the RPV and the bioshield wall (BSW) was refined to address the issues identified in GEH SC 09-01. Section 2.2.1.2.3 of the PUSAR states that the dynamic effects loadings at EPU conditions, resulting from existing postulated HELBs in the aforementioned affected piping, are bounded by the current licensing basis. Please confirm that the conclusion reached in Section 2.2.1.2.3 of the PUSAR extends to the evaluations performed in Section 2.6.2 of the PUSAR, i.e.,
confirm that the dynamic effects loads calculated for the RPV and BSW, using the revised AP loads, remain bounded by those used in the current licensing basis requirements related to the ..
Response
GGNS EPU AP analysis compared the bounding EPU recalculated loads to the maximum design basis loads for each break analyzed on an element by element basis. The maximum ratio of the bounding EPU loads for all cases to the bounding values in the design basis is 0.89.
to GNRO-2011/ 00087 Page 2 of 2 As stated on page 2-271 of Attachment 5 of the GGNS EPU LAR (PUSAR) some components did experience more severe loading as a result of the change in methodology.
These load increases are seen in comparison to the original AP analysis at the same break location and reflect only the effects of changes in methodology on individual break results.
Increased loads were only seen on non-limiting break locations; in all cases the limiting OLTP loads for a component remained limiting for EPU.
The conclusions reached in Section 2.2.1.2.3 of the EPU LAR Attachment 5, stating that the dynamic effects of the proposed EPU have been adequately addressed, were extended correctly from the evaluations performed in Section 2.6.2. The calculated dynamic effects loads for the reactor pressure vessel and bio-shield wall, using the revised annulus pressurization loads, remain bounded by OLTP design basis values.
RAI # 2 Section 2.2.2.1.3 of the PUSAR states that safety-related thermowells and probes in the main steam (MS) and feedwater (FW) systems were evaluated in support of EPU implementation to demonstrate that failure of these components due to flow-induced vibration (FIV) will not occur at EPU conditions. Page 2-47 of the PUSAR provides the results of the evaluations demonstrating that the MS, FW and reactor recirculation system (RRS) thermowells are structurally adequate at EPU conditions. Please provide a quantitative summary of the results of the evaluations performed for the safety-related probes. This summary should identify the safety-related probes evaluated and the corresponding stresses and stress limits resulting from the analyses performed for each probe. Additionally, please confirm that the lock-in condition, where the vortex shedding frequency associated with the MS and FW flows, does not occur for any safety-related thermowell or probe at EPU conditions.
Response
GGNS has no safety-related probes in the MS or FW systems. There is a safety-related probe in the reactor recirculation system, which remains bounded by the CLTP analysis since there is insignificant change of recirculation flow due to EPU. There is no resonance lock-in at EPU conditions for the safety-related thermowells discussed in Section 2.2.2.1.3 of EPU LAR or in the reactor recirculation system sample probe discussed above.