Email from R. Guzman, NRR/DORL/LPL1-1 to S. Elkins, Res/Dsa/Rsab, Et. Al., Subject: Communication Plan - Rev 5 - Dse (1)
ML11255A316
Person / Time
Site: Peach Bottom, Surry  Constellation icon.png
Issue date: 06/08/2010
From: Richard Guzman
Plant Licensing Branch 1
To: Elkins S
NRC/RES/DSA/RSAB
References
FOIA/PA-2011-0083
Download: ML11255A316 (2)


Text

From: Guzman, Richard '- -i .

To: Elkins. Scott; Burnell. Scott Cc: Barr. Jonathan

Subject:

RE: Communication Plan - Rev 5 -dse(1).docx Date: Tuesday, June 08, 2010 3:33:00 PM Good suggestion. I'll get the word to the respective PMs (Karen Cotton and John Hughey).

Is the expectation that we have the public meeting near the sites or at HQ?

Rich From: Elkins, Scott Sent: Tuesday, June 08, 2010 3:03 PM To: Burnell, Scott Cc: Barr, Jonathan; Guzman, Richard

Subject:

RE: Communication Plan - Rev 5 -dse(1).docx Thanks for the quick turnaround on the Communication Plan review Scott.

I believe Jimi is working to bring in someone to assist with the coordination of the public meeting tasks for the SOARCA team.

Jon you may want to talk with Jimi about that and see if that is still the plan and if someone has been identified to help out.

Scott E.

From: Burnell, Scott Sent: Tuesday, June 08, 2010 2:59 PM To: Elkins, Scott; Barr, Jonathan; Guzman, Richard

Subject:

RE: Communication Plan - Rev 5 -dse(1).docx Hi Scott, Jonathan; No additional comments from me. Jonathan, we need to start coordinating for the public meetings scheduled for August, since we'll need to announce them when the draft NUREG goes public at the end of July. I'd suggest you and Rich check with the Surry and Peach Bottom PMs to determine what venues are available/suitable. Thanks.

Scott B.

From: Elkins, Scott Sent: Tuesday, June 08, 2010 2:00 PM To: Burnell, Scott Cc: Barr, Jonathan

Subject:

Communication Plan - Rev 5 -dse(1).docx Hi Scott, Though I am officially not the PM any longer for SOARCA I did promise Jimi I would try my best to get Rev. 5 of the Communication plan into concurrence this week. The attached is merely an updated version of Rev. 4. I intend to send an updated GANTT chart schedule when it goes into concurrence but won't complete that until I get your input on the main

report, including the proposed new milestone dates. Fundamentally there are no surprises here. I added a task for briefing the regions and HQ personnel, based on feedback from the Steering Committee. Also some of the interim milestones dates have "sloshed" around a little to make things work overall.

Can you please take a look at this and give me any comments? Jimi has seen it already and this version includes his comments.

Thanks, Scott