Category:Letter
MONTHYEARIR 05000186/20232022023-12-12012 December 2023 the Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2023202 ML23198A0222023-08-29029 August 2023 Examination Report Letter No. 50-186/OL-23-02, University of Missouri - Columbia ML23198A0232023-08-29029 August 2023 Examination Result Letter No. 50-186/OL-23-02, University of Missouri-Columbia ML23221A1172023-08-0303 August 2023 Written Communication as Specified by 10 CFR 50.4(b)(4) Regarding the Submittal of the Physical Security Plan for the University of Missouri Research Reactor as a Part of the Process to Renew Amended Facility Operating License R-103 ML23213A0592023-08-0101 August 2023 Written Communication as Specified by University of Missouri Research Reactor Technical Specification 6.6.2(d) Regarding a Permanent Change in the Facility Organization Involving the Executive Director ML23186A2132023-07-31031 July 2023 Examination Confirmation Letter No. 50-186/OL-23-03, University of Missouri - Columbia IR 05000186/20232012023-07-31031 July 2023 the Curators of the University of Missouri U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000186/2023201 ML23124A0422023-05-0808 May 2023 Examination Confirmation Letter 50-186/OL-23-02, University of Missouri - Columbia ML23103A0742023-04-10010 April 2023 University of Missouri, Columbia Research Reactor, Shipment of Radioactive Material Shipment Identifier MURR 23-01 Highway Route Controlled Quantity ML23024A2772023-04-0707 April 2023 Cover Letter for the Security Inspection Report for the University of Missouri (Public) - October 2022 ML23089A3162023-03-29029 March 2023 Letter Notifying Univ. of Missouri That Us Dept. of Energy Funding Will Not Be Available in Fiscal Year 2023 to Complete the Conversion of MURR to LEU Fuel ML23087A1142023-03-29029 March 2023 Examination Results Letter No. 50-186/OL-23-01, University of Missouri - Columbia ML23087A1132023-03-29029 March 2023 Examination Report No. 50-186/OL-23-01, University of Missouri-Columbia ML23055B1372023-02-24024 February 2023 Submittal of Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e IR 05000186/20222022023-02-23023 February 2023 the Curators of the University of Missouri - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000186/2022202 - Cover Letter and Enclosure ML23031A0132023-02-14014 February 2023 Examination Confirmation Letter No. 50-186/OL-23-01, University of Missouri-Columbia ML23017A2072023-01-13013 January 2023 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 6.1.f ML22349A0422022-12-0808 December 2022 Written Communication as Specified in 10 CFR 50.54(b)(5) Regarding Changes to the University of Missouri-Columbia Research Reactor Facility Emergency Plan Without Prior Commission Approval Pursuant to 10 CFR 50.54(q)(3) ML22314A2102022-11-0909 November 2022 Written Communication as Required by Technical Specification 6.6.d(2), Other Reports, Regarding a Change in University of Missouri-Columbia Research Reactor Organization Involving the Reactor Facility Director ML22304A0042022-10-27027 October 2022 University of Missouri - Columbia, Shipment of Radioactive Material, Highway Route Controlled Quantity ML22291A0322022-10-14014 October 2022 University of Missouri Written Communication as Required by 10 CFR 73, Appendix G Regarding a Deviation from the MURR Physical Security Plan ML22290A0042022-10-12012 October 2022 University of Missouri-Columbia Research Reactor, Reportable Event Report Pursuant to 20.2201(a)(ii) Regarding Loss of Licensed Material During Shipment ML22266A2772022-09-29029 September 2022 Letter to P. Noss Re Revision No. 10 of Certificate of Compliance No. 9341 for the Model No. Brr Transportation Package ML22180A2412022-06-27027 June 2022 Orano Federal Services, LLC, Letter from Nishka Devaser to Philip Noss of June 10, 2022, Transmittal of Response to Request for Additional Information (RAI) IR 05000186/20222012022-06-14014 June 2022 the Curators of the University of Missouri - U.S. NRC Routine Inspection Report No. 05000186/2022201 ML22146A3412022-06-10010 June 2022 Letter to P. Noss Application for Amendment Request of Certificate of Compliance No. 9341 for the Model No. Brr - Request for Additional Information W/Enclosure ML22158A0792022-06-0606 June 2022 Submittal of Revised Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e ML22097A0592022-04-0707 April 2022 Approval for Spent Nuclear Fuel Highway Route Application - NRC Route No. 182D - Docket Number 050-0186 ML22088A0782022-03-25025 March 2022 Univ. of Missouri, Federal Funding for the Conversion of the Columbia Research Reactor from Highly-Enriched Uranium Fuel to Low-Enriched Uranium Fuel IR 05000186/20212032022-03-0202 March 2022 the Curators of the University of Missouri U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000186/2021203 ML22056A5162022-02-25025 February 2022 Submittal of Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e ML22038A6012022-02-0808 February 2022 Acceptance for Spent Nuclear Fuel Highway Route Application NRC No. 182D-Docket No. 050-0186 ML22013B1412022-01-21021 January 2022 Examination Confirmation Letter No. 50-186-OL-22-02, University of Missouri-Columbia ML21327A3042021-11-23023 November 2021 Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.f.6 ML21313A2292021-11-0808 November 2021 Orano Federal Services, LLC - Brr Package Amendment Request, Docket No. 71-9341 ML21298A1972021-10-25025 October 2021 University of Missouri-Columbia Research Reactor - Written Communication as Required by University of Missouri Research Reactor Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specification 3.2.g.6 ML21253A2482021-09-23023 September 2021 Examination Confirmation Letter No. 50-186/OL-22-01, University of Missouri Columbia ML21221A3252021-08-0909 August 2021 University of Missouri-Columbia Research Reactor, Written Communication as Required by Technical Specification 6.6.c(3) Regarding a Deviation from Technical Specifications 3.2.a ML21217A2982021-08-0505 August 2021 University of Missouri-Columbia Research Reactor - Reportable Event Report Pursuant to 20.2203(a)(2)(iv) ML21215A4982021-07-0707 July 2021 Univ of Missouri, Submittal of Revised Road Transportation Security Plan for the Shipment of Irradiated Reactor Fuel ML21098A1992021-06-10010 June 2021 the Curators of the University of Missouri Issuance of Amendment No. 40 to Renewed Facility Operating License No. R 103 to Amend Technical Specifications 6.2 and 6.4 for the University of Missouri Columbia Research Reactor IR 05000186/20212022021-05-28028 May 2021 the Curators of the University of Missouri - U.S. Nuclear Commission Routine Inspection Report No. 05000186/2021202 IR 05000186/20212012021-05-27027 May 2021 University of Missouri-Columbia U. S. Nuclear Regulatory Commission Security Inspection Report No. 05000186/2021201 - Non-OUO-Sri Cover Letter ML21118A9682021-04-28028 April 2021 Examination Confirmation Letter No. 50-186/OL-21-01, University of Missouri-Columbia ML21092A1712021-04-0202 April 2021 University of Missouri-Columbia Research Reactor - Federal Funding for the Conversion of the University of Missouri-Columbia Research Reactor from Highly-Enriched Uranium Fuel to Low-Enriched Uranium Fuel ML21078A5002021-03-19019 March 2021 University of Missouri-Columbia Research Reactor Written Communication as Specified by 10 CFR 20.1007 Regarding a Reportable Event Pursuant to 20.2203(a)(2)(iv) ML21075A2922021-03-16016 March 2021 Written Communication as Specified by 10 CFR 50.4(b)(l) Requesting U.S. Nuclear Regulatory Commission Approval to Revise the Technical Specifications Appended to Renewed Facility Operating License No. R-103 Pursuant to 10 CFR 50.90 IR 05000186/20202022021-03-12012 March 2021 University of Missouri - Columbia - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000186/2020202 - Cover Letter and Enclosure ML21050A2512021-02-19019 February 2021 Submittal of Annual Operating Report for the University of Missouri-Columbia Research Reactor as Required by MURR Technical Specification 6.6.e ML21041A5402021-02-10010 February 2021 Univ. of Missouri-Columbia Research Reactor - Written Communication as Specified by Univ. of Missouri Research Reactor Tech Spec 6.6.d(2) Regarding a Permanent Change in the Facility Organization Involving the Office of the Chancellor 2023-08-03
[Table view] |
Text
1513 Research Park Drive Research Reactor Center Columbia, MO 65211 University of Missouri-Columbia PHONE (573) 882-4211 FAX (573) 882-6360 WEBSrrE http://web.missouri.edu/-murrwww June 3, 2011 ATTN: Document Control Desk Director, Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 RE: Notification prior to first use of package per 10 CFR 71.17 This letter is notification prior to first use of the BEA Research Reactor (BRR) package, USA/9341/B(U)F-96, by the University of Missouri-Columbia Research Reactor (MURR).
Package Number: USA/9341/B(U)F-96 Licensee Name: University of Missouri-Columbia Research Reactor (MURR)
License.No.: R-.103.
Background:
Test and Research Reactors throughout the United States have typically relied on the Department of Energy (DOE) to provide a shipping cask for returning irradiated fuel to the DOE. In 2008, Idaho National Lab's Research Reactor Infrastructure Program contracted with AREVA Federal Services to design and build a NRC-certified Type B shipping cask to replace the.now-expirediBMI-1 spent fuel shipping cask (Certificate No.
5957). This new cask will be used to ship irradiated nuclear fuel from various research reactors to spent fuel storage facilities at Idaho National Lab and Savannah River Site.
AREVA designed and built the BRR package with the MURR fuel as one of the four*
spent fuel types taken into consideration for performing the cask safety analysis.
If any additional information is needed, please contact me at (573)882-5226 or ernstj@missouri.edur..
Sinceirely,'
John Ernst Associate Director, Regulatory Assurance P~l 5Ls- 6(
FIGHTING CANCR wrrIH ToMoRROw's TECHNOLOGY