Errata for Wolf Creek Generating Station - NRC Integrated Inspection Report 05000482-11-002 Cover Letter Page 1
ML111580021
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 06/06/2011
From: Miller G B
NRC/RGN-IV/DRP/RPB-B
To: Matthew Sunseri
Wolf Creek
References
IR-11-002
Download: ML111580021 (3)


See also: IR 05000482/2011002

Text

June 6, 2011

Matthew Sunseri, President and Chief Executive Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 Subject: ERRATA FOR WOLF CREEK GENERATING STATION - NRC INTEGRATED INSPECTION REPORT 05000482/2011002

Dear Mr. Sunseri:

Please remove the first page of the cover letter for the Wolf Creek Generating Station - NRC Integrated Inspection Report 05000482/2011002 and replace it with the page enclosed with this letter. The purpose of this change is to correct the cover letter to reflect the licensee identified violations included in the inspection report. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response, if you choose to provide one for cases where a response is not required, will be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy or proprietary, information so that it can be made available to the Public without redaction.

Sincerely,/RA/ Geoffrey B. Miller Chief, Project Branch B Division of Reactor Projects Docket No. 50-482 License No. NPF-42

Enclosure:

NRC Inspection Report 05000482/2011002 ERRATA, Cover Letter Page 1 Distribution via Listserv Wolf Creek Nuclear Operating Corporation - 2 - Electronic distribution by RIV: Regional Administrator (Elmo.Collins@nrc.gov) Deputy Regional Administrator (Art.Howell@nrc.gov) DRP Director (Kriss.Kennedy@nrc.gov) DRP Deputy Director (Troy.Pruett@nrc.gov) DRS Director (Anton.Vegel@nrc.gov) Senior Resident Inspector (Chris.Long@nrc.gov) Resident Inspector (Charles.Peabody@nrc.gov) WC Administrative Assistant (Shirley.Allen@nrc.gov) Branch Chief, DRP/B (Geoffrey.Miller@nrc.gov) Senior Project Engineer, DRP/B (Rick.Deese@nrc.gov) Senior Project Engineer, DRP/B (Leonard.Willoughby@nrc.gov) Project Engineer, DRP/B (Greg.Tutak@nrc.gov) Project Engineer, DRP/B (Nestor.Makris@nrc.gov) Public Affairs Officer (Victor.Dricks@nrc.gov) Public Affairs Officer (Lara.Uselding@nrc.gov) Project Manager (Randy.Hall@nrc.gov) Branch Chief, DRS/TSB (Dale.Powers@nrc.gov) RITS Coordinator (Marisa.Herrera@nrc.gov) Regional Counsel (Karla.Fuller@nrc.gov) Congressional Affairs Officer (Jenny.Weil@nrc.gov) Executive Technical Assistant (Stephanie.Bush-Goddard@nrc.gov) OEMail Resource ROPreports DRS/TSB STA (Dale.Powers@nrc.gov) RSLO (Bill.Maier@nrc.gov) NSIR (Robert.Kahler@nrc.gov) NSIR/DPR/EP (Eric.Schrader@nrc.gov) R:\_REACTORS\_WC\2011\WC2011002-CML ERRATA.docx ADAMS: No Yes SUNSI Review Complete Reviewer Initials: GM Publicly Available Non-Sensitive Non-publicly Available Sensitive PE:DRP/B SRI:DRP/B C:DRP/B NJMakris CMLong GBMiller /RA/ /RA/via E-Mail /RA/ 6/6/2011 6/6/2011 6/6/2011 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax ERRATA May 9, 2011 Matthew Sunseri, President and Chief Executive Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 Subject: WOLF CREEK GENERATING STATION - NRC INTEGRATED INSPECTION REPORT 05000482/2011002

Dear Mr. Sunseri:

On March 31, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Wolf Creek Generating Station. The enclosed integrated inspection report documents the inspection findings, which were discussed on April 7, 2011, with you and other members of your staff.

The inspections examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. This report documents eight NRC-identified findings and three self-revealing findings of very low safety significance (Green). The NRC has determined that violations are associated with all of these issues. Additionally, three licensee-identified violations, which were determined to be of very low safety significance, are listed in this report. However, because of the very low safety significance and because they were entered into your corrective action program, the NRC is treating these findings as noncited violations, consistent with Section 2.3.2 of the NRC Enforcement Policy. If you contest the violations or the significance of the noncited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, D.C. 20555-0001, with copies to the Regional Administrator, U.S. Nuclear Regulatory Commission, Region IV, 612 E. Lamar Blvd, Suite 400, Arlington, Texas, 76011-4125; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, D.C. 20555-0001; and the NRC Resident Inspector at the facility. In addition, if you disagree with the crosscutting aspect assigned to any finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region IV, and the NRC Resident Inspector at the facility.