Units, 1 & 2 - Nuclear Liability Insurance Endorsements
ML111080541
Person / Time
Site: Millstone, Kewaunee, Surry, North Anna  Dominion icon.png
Issue date: 04/14/2011
From: Funderburk C
Dominion, Dominion Energy Kewaunee, Dominion Nuclear Connecticut, Dominion Resources Services, Virginia Electric & Power Co (VEPCO)
To:
NRC/FSME, Office of Nuclear Reactor Regulation
References
11-200
Download: ML111080541 (10)


Text

Dominion Resources Services, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard, 2SE, Glen Allen, VA 23060 April 14, 2011 Director of Nuclear Reactor Regulation Serial No.: 11-200 United States Nuclear Regulatory Commission NLOS/GLR:

Washington, DC 20555-0001 Docket Nos.: 50-305 50-245/336/423 50-338/339 50-280/281 License Nos.: DPR-43 DOMINION ENERGY KEWAUNEE, INC. DPR-21/65 DOMINION NUCLEAR CONNECTICUT, INC. NPF-49 VIRGINIA ELECTRIC AND POWER COMPANY NPF-4/7 KEWAUNEE POWER STATION DPR-32/37 MILLSTONE POWER STATION UNITS 1, 2 & 3 NORTH ANNA POWER STATION UNITS 1 & 2 SURRY POWER STATION UNITS 1 & 2 NUCLEAR LIABILITY INSURANCE ENDORSEMENTS Pursuant to 10 CFR 140.15(e), Dominion Energy Kewaunee, Inc., Dominion Nuclear Connecticut, Inc., and Virginia Electric and Power Company, (DEK, DNC, and Dominion) hereby submit certified copies of nuclear liability insurance endorsements for Kewaunee, Millstone, North Anna and Surry Power Stations.

A summary of this submittal is enclosed. No new commitments are intended by this letter. If you have any questions concerning this information, please contact Mr. David Sommers at (804) 273-2823.

Very truly yours,

@/7 --

C. L. FuHderburk Director - Nuclear Licensing & Operations Support Dominion Resources SerVices, Inc.

For Dominion Energy Kewaunee, Inc.,

Dominion Nuclear Connecticut, Inc. and Virginia Electric and Power Company

Attachment:

Nuclear Liability Endorsements

SN 11-200 Nuclear Liability Insurance Endorsements page 2 of 3 cc: U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406-1415 U.S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Avenue, NE, Suite 1200 Atlanta, GA 30303-1257 U.S. Nuclear Regulatory Commission Region III 2443 Warrenville Road, Suite 210 Lisle, II 60532-4352 Mr. J. D. Hughey Project Manager U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 08 B-1A Rockville, MD 20852,.2738 Mr. S. J. Giebel Project Manager U.S. Nuclear Regulatory Commission Two White Flint North 11545 Rockville Pike Mail Stop T-8 F5 Rockville, MD 20852-2738 Mr. J. S. Wiebe Project Manager U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 08 G-9A Rockville, MD 20852-2738

SN 11-200 Nuclear Liability Insurance Endorsements page 3 of 3 Ms. K. R. Cotton Project Manager U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 08 G-9A Rockville, MD 20852-2738 Mr. K. D. Feintuch Project Manager U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike Mail Stop 08 H-4A Rockville, MD 20852-2738 NRC Senior Resident Inspector Kewaunee Power Station NRC Senior Resident Inspector Millstone Power Station NRC Senior Resident Inspector North Anna Power Station NRC Senior Resident Inspector Surry Power Station Mr. J. E. Reasor, Jr.

Old Dominion Electric Cooperative Innsbrook Corporate Center 4201 Dominion Blvd.

Suite 300 Glen Allen, VA 23060

SN 11-200 Nuclear Liability Insurance Endorsements Attachment page 1 of 5 Summary of Attached Insurance Endorsements Policy Description Policy Number Endorsement Number North Anna Facility Form (ANI) NF-240 155, 156 Surry Facility Form (ANI) NF-186 184 Millstone Facility Form (ANI) NF-173 219,220 Kewaunee Facility Form (ANI) NF-204 187

NUCLEAR ENERGY LIABILITY INSURANCE NUCLEAR ENERGY LIABILITY INSURANCE ASSOCIATION CHANGES IN SUBSCRIBING COMPANIES AND IN THEIR PROPORTIONATE LIABILITY ENDORSEMENT CALENDAR YEAR 2011

1. It is agreed that with respect to bodily injury, property damage, environmental damage or evacuation of the public caused, during the effective period of this endorsement, by the nuclear energy hazard:
a. The word "companies" wherever used in the policy means the subscribing companies listed below.
b. The policy shall be binding on such companies only.
c. Each such company shall be liable for its proportion of any obligation assumed or expense incurred under the policy because of such bodily injury, property damage, environmental damage or evacuation of the public as designated below.
2. It is agreed that the effective period of this endorsement is from the beginning of the effective date of this endorsement stated below to the close of December 31, 2011 or to the time of the termination or cancellation of the policy, if sooner.

American Commerce Insurance Company 11.206897 %

AXIS Reinsurance Company 15.517241 %

Employers Mutual Casualty Company 3.448276 %

Federal Insurance Company 32.327586 %

Liberty Mutual 17.241379 %

State Farm Mutual Automobile Insurance Company 10.344828 %

Zurich American Insurance Company 9.913793 %

Total 100.000000 % NE-2011 This is to certify that this is a true copy of the original Endorsement having the endorsement number and being made part of the Nuclear Energy Liability Policy (Facility Form) as designated hereon. No insurance is afforded hereunder.

Gary S. Uricchio, Vice President - Underwriting, American Nuclear Insurers Effective Date of this Endorsement: January 1, 2011 To form a part of Policy No. NF -0240 (12:01 A.M. Standard Time)

Issued to: Virginia Electric & Power Company Date of Issue: February 18, 2011 For the subscribing companies By~0QJ PreSident Endorsement No.: 155 Countersigned by ---...,L.~~~(...Ll.L--l4e1&~~~~=--

CERTIFIED COpy

NUCLEAR ENERGY LIABILITY INSURANCE NUCLEAR ENERGY LIABILITY INSURANCE ASSOCIATION ADVANCE PREMIUM AND STANDARD PREMIUM ENDORSEMENT CALENDAR YEAR 2010 It is agreed that Items 1 and 2 of Endorsement No. 152 are amended to read:

1. ADVANCE PREMIUM: It is agreed that the Advance Premium due the companies for the period designated above is: $1,141,901.00
2. STANDARD PREMIUM AND RESERVE PREMIUM: In the absence of a change in the Advance Premium indicated above, it is agreed that, subject to the provisions of the Industry Credit Rating Plan, the Standard Premium is said Advance Premuim and the Reserve Premium is: $876,260.00 RETURN PREMIUM: $18,623.00 This is to certify that this is a true copy of the original Endorsement having the endorsement number and being made part of the Nuclear Energy Liability Policy (Facility Form) as designated heron. No insurance is afforded hereunder.

G§~~J!fifd£.rit;og

~~~~~Iear Insurers Effective Date of this Endorsement: January 1, 2010 To form a part of Policy No. NF -0240 (12:01 A.M. Standard Time)

Issued To: Virginia Electric & Power Company Date of Issue: March 10, 2011 For the subscribing companies By o

fe<y. ';) r;LJ President Endorsement No: 156 Countersigned bY~.L. ~..t;r CERTIFIED COPY NE-36

NUCLEAR ENERGY LIABILITY INSURANCE NUCLEAR ENERGY LIABILITY INSURANCE ASSOCIATION CHANGES IN SUBSCRIBING COMPANIES AND IN THEIR PROPORTIONATE LIABILITY ENDORSEMENT CALENDAR YEAR 2011

1. It is agreed that with respect to bodily injury, property damage, environmental damage or evacuation of the public caused, during the effective period of this endorsement, by the nuclear energy hazard:
a. The word "companies" wherever used in the policy means the subscribing companies listed below.
b. The policy shall be binding on such companies only.
c. Each such company shall be liable for its proportion of any obligation assumed or expense incurred under the policy because of such bodily injury, property damage, environmental damage or evacuation of the public as designated below.
2. It is agreed that the effective period of this endorsement is from the beginning of the effective date of this endorsement stated below to the close of December 31, 2011 or to the time of the termination or cancellation of the policy, if sooner.

American Commerce Insurance Company 11.206897 %

AXIS Reinsurance Company 15.517241 %

Employers Mutual Casualty Company 3.448276 %

Federal Insurance Company 32.327586 %

Liberty Mutual 17.241379 %

State Farm Mutual Automobile Insurance Company 10.344828 %

Zurich American Insurance Company 9.913793 %

Total 100.000000 % NE-2011 This is to certify that this is a true copy of the original Endorsement haVing the endorsement number and being made part of the Nuclear Energy Liability Policy (Facility Form) as designated hereon. No insurance is afforded hereunder.

Gary S. Uricchio, Vice President - Underwriting, American Nuclear Insurers Effective Date of this Endorsement: January 1, 2011 To form a part of Policy No. NF -0186 (12:01 A.M. Standard Time)

Issued to: Virginia Electric & Power Company Date of Issue: February 18, 2011 For the subscribing companies By -A 0. QJ President Endorsement No.: 184 Countersigned by ----.,~-'"

CERTIFIED COpy

NUCLEAR ENERGY LIABILITY INSURANCE NUCLEAR ENERGY LIABILITY INSURANCE ASSOCIATION CHANGES IN SUBSCRIBING COMPANIES AND IN THEIR PROPORTIONATE LIABILITY ENDORSEMENT CALENDAR YEAR 2011

1. It is agreed that with respect to bodily injury, property damage, environmental damage or evacuation of the public caused, during the effective period of this endorsement, by the nuclear energy hazard:
a. The word "companies" wherever used in the policy means the subscribing companies listed below.
b. The policy shall be binding on such companies only.
c. Each such company shall be liable for its proportion of any obligation assumed or expense incurred under the policy because of such bodily injury, property damage, environmental damage or evacuation of the public as designated below.
2. It is agreed that the effective period of this endorsement is from the beginning of the effective date of this endorsement stated below to the close of December 31, 2011 or to the time of the termination or cancellation of the policy, if sooner.

American Commerce Insurance Company 11.206897 %

AXIS Reinsurance Company 15.517241 %

Employers Mutual Casualty Company 3.448276 %

Federal Insurance Company 32.327586 %

Liberty Mutual 17.241379 %

State Farm Mutual Automobile Insurance Company 10.344828 %

Zurich American Insurance Company 9.913793 %

Total 100.000000 % NE-2011 This is to certify that this is a true copy of the original Endorsement having the endorsement number and being made part of the Nuclear Energy Liability Policy (Facility Form) as designated hereon. No insurance is afforded hereunder.

Gary S. Uricchio, Vice President - Underwriting, American Nuclear Insurers Effective Date of this Endorsement: January 1, 2011 To form a part of Policy No. NF -0173 (12:01 A.M. Standard Time)

Issued to: Dominion Nuclear Connecticut, Inc.

Date of Issue: February 18, 2011 For the sUbscribing companies Endorsement No.: 219 Countersigned by_~

CERTIFIED COpy

NUCLEAR ENERGY LIABILITY INSURANCE NUCLEAR ENERGY LIABILITY INSURANCE ASSOCIATION ADVANCE PREMIUM AND STANDARD PREMIUM ENDORSEMENT CALENDAR YEAR 2010 It is agreed that Items 1 and 2 of Endorsement No. 215 are amended to read:

1. ADVANCE PREMIUM: It is agreed that the Advance Premium due the companies for the period designated above is: $1,795,477.00
2. STANDARD PREMIUM AND RESERVE PREMIUM: In the absence ofa change in the Advance Premium indicated above, it is agreed that, subject to the provisions of the Industry Credit Rating Plan, the Standard Premium is said Advance Premuim and the Reserve Premium is: $1,378,152.00 RETURN PREMIUM: $8,337.00 This is to certify that this is a true copy of the original Endorsement having the endorsement number and being made part of the Nuclear Energy Liability Policy (Facility Form) as designated heron. No insurance is afforded hereunder.

§°:C!viJ~cw,mog

~~~~~Iear Insurers Effective Date of this Endorsement: January 1,2010 To form a part of Policy No. NF -0173 (12:01 A.M. Standard Time)

Issued To: Dominion Nuclear Connecticut, Inc.

March 1, 2011 For the subscribing companies o 4. ';) <;LJ Date of Issue:

By President Endorsement No: 220 Countersigned by ~1 ~

CERTIFIED COPY NE-36

NUCLEAR ENERGY LIABILITY INSURANCE NUCLEAR ENERGY LIABILITY INSURANCE ASSOCIATION CHANGES IN SUBSCRIBING COMPANIES AND IN THEIR PROPORTIONATE LIABILITY ENDORSEMENT CALENDAR YEAR 2011

1. It is agreed that with respect to bodily injury, property damage, environmental damage or evacuation of the public caused, during the effective period of this endorsement, by the nuclear energy hazard:
a. The word "companies" wherever used in the policy means the subscribing companies listed below.
b. The policy shall be binding on such companies only.
c. Each such company shall be liable for its proportion of any obligation assumed or expense incurred under the policy because of such bodily injury, property damage, environmental damage or evacuation of the public as designated below.
2. It is agreed that the effective period of this endorsement is from the beginning of the effective date of this endorsement stated below to the close of December 31, 2011 or to the time of the termination or cancellation of the policy, if sooner.

American Commerce Insurance Company 11.206897 %

AXIS Reinsurance Company 15.517241 %

Employers Mutual Casualty Company 3.448276 %

Federal Insurance Company 32.327586 %

Liberty Mutual 17.241379 %

State Farm Mutual Automobile Insurance Company 10.344828 %

Zurich American Insurance Company 9.913793 %

Total 100.000000 % NE-2011 This is to certify that this is a true copy of the original Endorsement having the endorsement number and being made part of the Nuclear Energy Liability Policy (Facility Form) as designated hereon. No insurance is afforded hereunder.

Gary S. Uricchio, Vice President - Underwriting, American Nuclear Insurers Effective Date of this Endorsement: January 1, 2011 To form a part of Policy No. NF -0204 (12:01 A.M. Standard Time)

Issued to: Dominion Energy Kewaunee, Inc.

Date of Issue: February 18, 2011 For the subscribing companies By ~ '0QJ PreSident Endorsement No.: 187 Countersigned by -.."",L~~~~..A.1..........j;4&~~~~--

CERTIFIED COPY