ML103090613

From kanterella
Jump to navigation Jump to search
IR 05000336-10-008, 05000423-10-008, and 05000336-10-009, on 07/19/2010 - 09/22/2010, Millstone Power Station, Units 2 and 3, Triennial Fire Protection and Millstone Power Station, Unit 2; Temporary Instruction 2515/181 Inspection
ML103090613
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 11/05/2010
From: Rogge J
Engineering Region 1 Branch 3
To: Heacock D
Dominion Resources
References
EA-10-175, FOIA/PA-2011-0115 IR-10-008, IR-10-009
Download: ML103090613 (43)


See also: IR 05000336/2010008

Text

EA-10-175

Mr. David Heacock

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

475 ALLENDALE ROAD

KING OF PRUSSIA, PA 19406-1415

November 5, 2010

President and Chief Nuclear Officer

Dominion Resources

5000 Dominion Boulevard

Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION - NRC TRIENNIAL FIRE PROTECTION

INSPECTION REPORT 05000336/2010008 AND 05000423/2010008 AND

NOTICE OF VIOLATION AND TEMPORARY INSTRUCTION 2515/181

INSPECTION REPORT 05000336/2010009

Dear Mr. Heacock:

On September 22,2010, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at your Millstone Power Station Unit 2 and Unit 3. In addition to the triennial fire

protection inspection results, these inspection reports also document the results of an inspection

performed on Unit 2 in accordance with Temporary Instruction (TI) 2515/181, "Validate the

Effectiveness of the Regulatory Infrastructure Related to Fire Induced Circuit Failures and

Operator Manual Actions. The preliminary results of these inspections were discussed on

August 5,2010, with Mr. A. J. Jordan and other members of your staff. Following additional in-

office and on-site reviews an exit meeting was conducted by telephone with Mr. A. J. Jordan

and other members of your staff on September 22, 2010.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commission's rules and regulations and with the conditions of your license.

In conducting the inspection, the team reviewed selected procedures, calculations and records,

observed activities, and interviewed station personnel.

One violation is cited in the enclosed Notice of Violation and the circumstances surrounding it

are described in detail in the subject inspection report. The violation was evaluated in

accordance with the NRC Enforcement Policy. The current Enforcement Policy is included on

the NRC's Web site at http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html.

The violation involved the use of unapproved manual operator actions to mitigate post-fire safe

shutdown equipment malfunctions caused by a single spurious actuation on Millstone Unit 2, in

lieu of protecting the equipment in accordance with 10 CFR Part 50 Appendix R, Section III.G.2

(EA-10-175). Although determined to be of very low safety significance (Green), this violation is

being cited in the Notice because not all of the criteria specified in section 2.3.2.a of the NRC

Enforcement Policy for a noncited violation were satisfied. Specifically, Dominion Nuclear

Connecticut, Inc. failed to restore compliance within a reasonable amount of time after the

violation was identified in condition report 119114 in November 2008. You are required to

D. Heacock

2

respond to this letter and should follow the instructions specified in the enclosed Notice when

preparing your response. The NRC will use your response, in part, to determine whether further

enforcement action is necessary to ensure compliance with regulatory requirements.

One additional finding of very low safety significance (Green) was also identified. This finding

was also determined to be a violation of NRC requirements. However, because of the very low

safety significance, and because the issue was entered into your corrective action program, the

NRC is treating this finding as a non-cited violation (NCV) consistent with section 2.3.2.a of the

NRC Enforcement Policy. If you contest the NCV in this report, you should provide a written

response within 30 days of the date of this inspection report with the basis for your denial, to the

Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington D.C.

20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of

Enforcement; and the NRC Senior Resident Inspector at Millstone. In addition, if you disagree

with the characterization of any finding in this report, you should provide a response within

30 days of the date of this inspection report, with the basis for your disagreement, to the

Regional Administrator, .Region I, and the Senior Resident Inspector at Millstone. The

information you provide will be considered in accordance with Inspection Manual Chapter 0305.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response will be available electronically for public inspection in the NRC

Public Document Room or from the Publicly Available Records (PARS) component of the

NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room). To the extent

possible, your response should not include any personal privacy, proprietary, or safeguards

information so that it can be made available to the Public without redaction.

Docket Nos:

50-336,50-423

License Nos: DPR-65, NPF-49

Enclosures:

1. Notice of Violation

Sincerely,

John F. Rogge, Chief

Engineering Branch 3

Division of Reactor Safety

2. Inspection Report 05000336/2010008; 05000423/2010008; and,

05000336/2010009

w/Attachment: Supplemental Information

cc w/encl:

Distribution via ListServ

D. Heacock

2

respond to this letter and should follow the instructions specified in the enclosed Notice when

preparing your response. The NRC will use your response, in part, to determine whether further

enforcement action is necessary to ensure compliance with regulatory requirements.

One additional finding of very low safety significance (Green) wasoalso identified. This finding

was also determined to be a violation of NRC requirements. However, because of the very low

safety significance, and because the issue was entered into your corrective action program, the

NRC is treating this finding as a non-cited violation (NCV) consistent with section 2.3.2.a of the

NRC Enforcement Policy. If you contest the NCV in this report, you should provide a written

response within 30 days of the date of this inspection report with the basis for your denial, to the

Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington D.C.

20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of

Enforcement; and the NRC Senior Resident Inspector at Millstone. In addition, if you disagree

with the characterization of any finding in this report, you should provide a response within

30 days of the date of this inspection report, with the basis for your disagreement, to the

Regional Administrator, Region I, and the Senior Resident Inspector at Millstone. The

information you provide will be considered in accordance with Inspection Manual Chapter 0305.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response will be available electronically for public inspection in the NRC

Public Document Room or from the Publicly Available Records (PARS) component of the

NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html(the Public Electronic Reading Room). To the extent

possible, your response should not include any personal privacy, proprietary, or safeguards

information so that it can be made available to the Public without redaction.

Docket Nos:

50-336,50-423

License Nos: DPR-65, NPF-49

Enclosures:

1. Notice of Violation

Sincerely,

IRA!

John F. Rogge, Chief

Engineering Branch 3

Division of Reactor Safety

2. Inspection Report 05000336/2010008; 05000423/2010008; and,

05000336/2010009

w/Attachment: Supplemental Information

cc w/encl:

Distribution via ListServ

ADAMS ACCESSION: ML 103090613

SUNSI Review Complete:

JFR

(Reviewer's Initials)

DOCUMENT NAME: Y:\\Division\\DRS\\Engineering Branch 3\\Scholl\\MS 2010-08 Fire Report Finaldb.docx

After declaring this document "An Official Agency Record" it will be released to the Public.

T*

f h* d

. d*

. h b

'C' C

. h

h

V

I

'E" C

. h

h

V

I

'N' N

o receive a copy 0 t IS ocument, In Icate In t e ox:

= opy Wit out attac men enc osure

= op' Wit attac men enc osure

= 0 copy

OFFICE

RI/DRS

I

RI/DRS

!

RI/DRS

I

RI/DRS

I

RI/ORA

NAME

LScholl/lls*

JRichmond/jr*

MPatel/mp*

WSchmidtlwls*

ADeFrancisco/aed*

DATE

11/03/10

11/03/10

11/03/10

11/03/10

11/04/10

OFFICE

RI/DRP

I

RI/DRS

I

RI/ORA

I

RI/DRS

I

NAME

DJackson/dej*

JRogge/lfr

KFarrar/klf*

DRoberts/djr*

DATE

11/03/10

11/05/10

11/04/10

11/04/10

  • see prior concurrence

OFFICIAL RECORD COPY

I

I

D. Heacock

3

Distribution w/enci: (via email)

W. Dean, RA

(R10RAMAILRESOURCE) .

M. Dapas, DRA

(R10RAMAIL RESOURCE)

D. Lew, DRP

(R1 DRPMAIL RESOURCE)

J. Clifford, DRP

(R1 DRPMAIL RESOURCE)

D. Roberts, DRS

(R1 DRSMAIL RESOURCE)

P. Wilson, DRS

(R1DRSMAIL RESOURCE)

D. Screnci, RI

N. Sheehan, RI

K. Farrar, RI

D. Holody, RI

A. DeFrancisco, RI

M. McLaughlin, RI

C. O'Daniell, RI

R1 DRPMailResource

Region I OE Files (with concurrences)

D. Jackson, DRP

T. Setzer, DRP

D. Dodson, DRP

S. Shaffer, DRP, SRI

B. Haagensen, RI

J. Krafty, DRP, RI

C. Kowalyshyn, OA

G. Miller, RI OEDO

D. Bearde, DRS

RidsNRRPM Millstone Resource

RidsNRRDor1Lp11-2 Resource

ROPreportsResource@nrc.gov

Dominion Nuclear Connecticut, Inc.

Millstone Nuclear Station, Unit 2

NOTICE OF VIOLATION

Docket No: 50-336

License No: DPR-65

EA-10-175

During an NRC inspection conducted July 19 through September 22, 2010, a violation of NRC

requirements was identified. In accordance with the NRC Enforcement Policy, the violation is

listed below:

License Condition 2.C.(3) specifies, in part, Dominion shall implement and maintain in effect

all provisions of the approved fire protection program as described in the Final Safety

Analysis Report and as approved in the Safety Evaluation Report (SER) dated

September 19, 1978, and a supplement dated July 17, 1990.

The Final Safety Analysis Report, Section 9.10.6 specifies that Dominion will meet the

requirements of 10 CFR Part 50, Appendix R, Section III.G.2, which requires, in part, except

as provided for in paragraph G.3 of this section, where cables or equipment, including

associated non-safety circuits that could prevent operation or cause maloperation due to hot

shorts, open circuits, or shorts to ground, of redundant trains of systems necessary to

achieve and maintain hot shutdown conditions are located within the same fire area outside

of primary containment, one of the means of ensuring that one of the redundant trains is free

of fire damage shall be provided, per the requirements in G.2.a-G.2.f.

Contrary to the above, through September 22, 2010, Dominion failed to implement all

provisions of the approved fire protection program as described in the Final Safety Analysis

Report and as approved in the SER dated September 19, 1978, and a supplement dated

July 17, 1990. Specifically, the safe shutdown strategy for Millstone Unit 2 relied upon

unapproved manual operator actions to mitigate post-fire safe shutdown equipment

malfunctions caused by a single spurious actuation, in lieu of protecting the equipment in

accordance with 10 CFR Part 50 Appendix R, Section III.G.2, per the requirements in G.2.a-

G.2.f. The use of manual actions in lieu of providing the required protection requires prior

NRC approval. Dominion had not requested or received NRC approval for the use of

manual actions affecting components that included the following: charging header

containment isolation valve 2-CH-249, steam generator main steam isolation valves

2-MS-64A1B, steam generator blowdown control valves 2-MS-220AlB, charging system

isolation valve 2-CH-192, auxiliary feedwater flow control valves 2-FW-43 AlB and turbine

driven auxiliary feedwater pump 2-FW-P4.

This violation is associated with a Green Significance Determination Finding.

Pursuant to the provisions of 10 CFR 2.201, Dominion Nuclear Connecticut, Inc. is hereby

required to submit a written statement or explanation to the U.S. Nuclear Regulatory

Commission, ATTN: Document Control Desk, Washington, DC 20555-0001 with a copy to the

Regional Administrator, Region I, and a copy to the NRC Resident Inspector at the facility that is

the subject of this Notice, within 30 days of the date of the letter transmitting this Notice of

Violation (Notice). This reply should be clearly marked as a "Reply to a Notice of Violation;

EA 10-175" and should include for each violation: (1) the reason for the violation, or, if

Enclosure 1

2

contested, the basis for disputing the violation or severity level, (2) the corrective steps that

have been taken and the results achieved, (3) the corrective steps that will be taken, and (4) the

date when full compliance will be achieved. Your response may reference or include previous

docketed correspondence, if the correspondence adequately addresses the required response.

If an adequate reply is not received within the time specified in this Notice, an order or a

Demand for Information may be issued as to why the license should not be modified,

suspended, or revoked, or why such other action as may be proper should not be taken. Where

good cause is shown, consideration will be given to extending the response time.

If you contest this enforcement action, you should also provide a copy of your response, with

the basis for your denial, to the Director, Office of Enforcement, United States Nuclear

Regulatory Commission, Washington, DC 20555-0001.

Because your response will be made available electronically for public inspection in the NRC

Public Document Room or from the NRC's document system (ADAMS), accessible from the

NRC Web site at http://www.nrc.gov/reading-rm/adams.html. to the extent possible, it should not

include any personal privacy, proprietary, or safeguards information so that it can be made

available to the public without redaction. If personal privacy or proprietary information is

necessary to provide an acceptable response, then please provide a bracketed copy of your

response that identifies the information that should be protected and a redacted copy of your

response that deletes such information. If you request withholding of such material, you must

specifically identify the portions of your response that you seek to have withheld and provide in

detail the bases for your claim of withholding (e.g., explain why the disclosure of information will

create an unwarranted invasion of personal privacy or provide the information required by

10 CFR 2.390(b) to support a request for withholding confidential commercial or financial

information). If safeguards information is necessary to provide an acceptable response, please

provide the level of protection described in 10 CFR 73.21.

In accordance with 10 CFR 19.11, you may be required to post this Notice within two working

days of receipt.

Dated this 5th day of November, 2010

Enclosure 1

Docket Nos:

License Nos:

Report Nos:

Licensee:

Facility:

Location:

Dates:

Inspectors:

Approved by:

U. S. NUCLEAR REGULATORY COMMISSION

REGION I

50-336,50-423

DPR-65, NPF-49

05000336/2010008; 05000423/2010008; and

05000336/2010009

Dominion Nuclear Connecticut, Inc.

Millstone Power Station, Units 2 and 3

P.O. Box 128

Waterford, CT 06385

July 19 through September 22, 2010

L. Scholl, Senior Reactor Inspector (Team Leader)

W. Schmidt, Senior Reactor Analyst

G. Replogle, Region IV, Senior Reactor Analyst

J. Richmond, Senior Reactor Inspector

R. Fuhrmeister, Senior Reactor inspector

M. Patel, Reactor Inspector

E. Huang, Reactor Inspector

J. Rady, Reactor Inspector

G. Pick, Region IV, Senior Reactor Inspector

D. Frumkin, NRR (Observer)

G. Cooper, NRR (Observer)

John F. Rogge, Chief

Engineering Branch 3

Division of Reactor Safety

Enclosure 2

SUMMARY OF FINDINGS

IR 05000336/2010008,05000423/2010008, and 05000336/2010009; 07/19/2010 - 09/22/2010;

Millstone Power Station, Units 2 and 3; Triennial Fire Protection and Millstone Power Station,

Unit 2; Temporary Instruction 2515/181 Inspection.

These reports covered an initial two week on-site triennial fire protection team inspection and a

one week on-site inspection of regulatory infrastructure related to fire-induced circuit failures

and operator manual actions by NRC Regions I and IV specialist inspectors. Additional in-office

and site inspections were performed following the initial inspection. One cited and one non-

cited finding of very low significance (Green) was identified. The significance of most findings is

indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter

(IMC) 0609, "Significance Determination Process (SDP)." The cross-cutting aspects were

determined using IMC 0305, "Operating Reactor Assessment Program." Findings for which the

SDP does not apply may be Green or be assigned a severity level after NRC management

review. The NRC's program for overseeing the safe operation of commercial nuclear power

reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 4, dated

December 2006.

A.

NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

Green. The team identified a non-cited violation of Millstone Unit 2 Operating License

Condition 2.C.(3), and Unit 3 Operating License Condition 2.H, for the failure to

implement all provisions of the approved Fire Protection Programs. Specifically,

Dominion did not implement adequate review, approval and distribution of fire fighting

strategies to provide for the adequate development and maintenance of effective

strategies. As a result, the team found that Dominion did not provide adequate guidance

in the fire fighting strategies for several areas that included the Unit 2 "8" emergency

diesel generator (EDG) room, and the Unit 3 west switchgear room. This issue was

entered into Dominion's corrective action program as condition report (CR) 388786.

The team determined that the failure to administratively control fire fighting strategies as

required by the fire protection program was a performance deficiency. This finding was

more than minor because it adversely affected the availability and capability objectives

of the protection against external events (i.e., fire) attribute under the Mitigating Systems

Cornerstone. Specifically, the above examples would likely cause delays in manual fire

fighting activities and, therefore, adversely affected the defense-in-depth aspect of the

fire protection program to limit fire damage by quick suppression of those fires that

occur. The team performed a Phase 1 SDP screening, in accordance with NRC

IMC 0609, Appendix F, "Fire Protection Significance Determination Process." This

finding affected fire prevention and administrative controls, and was screened to very

low safety significance (Green) because this failure to control fire fighting strategies was

determined to represent a low degradation rating. This finding had a cross-cutting

aspect in the area of human performance because Dominion failed to ensure complete

and accurate fire fighting strategies were available to the fire brigade to support timely

extinguishment of fires. H.2(c) (Section 1 R05.03)

ii

Enclosure 2

Green. The team identified a cited violation of 10 CFR Part 50, Appendix R,

Section III.G.2 for the failure to protect required post-fire safe shutdown components and

cabling to ensure one of the redundant trains of equipment remains free from fire

damage. In lieu of providing the required separation, Dominion utilized unapproved

operator manual actions to mitigate component malfunctions or spurious operations

caused by a single fire induced circuit fault (hot short, open circuit or short to ground).

Dominion has entered this issue into the corrective program for resolution. The team

found the manual actions to be reasonable interim compensatory measures pending

final resolution by Dominion.

Dominion's failure to protect components credited for post-fire safe shutdown from fire

damage caused by single spurious actuation is considered a performance deficiency.

The performance deficiency was more than minor because it affected the Mitigating

Systems cornerstone objective to ensure the availability, reliability, and capability of

systems that respond to an external event to prevent undesirable consequences in the

event of a fire. Specifically, the use of operator manual actions during post-fire

shutdown is not as reliable as normal systems operation which could be utilized had the

separation requirements of 10 CFR 50, Appendix R, Section III.G.2 been met and

therefore prevented fire damage to credited components and/or cables. The team used

IMC 0609, Appendix F, "Rre Protection Significance Determination Process (SDP),"

Phase 1 and an SRA conducted Phase 3 evaluation, to determine that this finding was

of very low safety significance (Green). The team determined the finding had a low

degradation rating because the manual actions were reviewed by the team and were

found to be acceptable interim compensatory measures (pending licensee actions to

resolve the non-compliances or obtain exemptions) because they did not require

complicated actions, adequate time was available to accomplish the actions and the

actions were properly included in the appropriate abnormal operating procedures. This

finding had a cross cutting aspect in the area of problem identification and resolution

associated with the corrective action program because Dominion did not completely and

accurately identify deficiencies related to single spurious actuations of credited post-fire

safe shutdown components. [P.1.(a)] (Section 1 R05.06)

B.

Licensee-Identified Violations

None.

iii

Enclosure 2

REPORT DETAILS

Background

This report presents the results of a triennial fire protection inspection conducted in accordance

with NRC Inspection Procedure (IP) 71111.05T, "Fire Protection." The objective of the

inspection was to assess whether Dominion Nuclear Connecticut, Inc. (Dominion) had

implemented an adequate fire protection program and whether post-fire safe shutdown

capabilities had been established and were properly maintained at Millstone Power Station

Unit 2 and Unit 3 (Millstone). The following fire areas and fire zones were selected for detailed

review based on risk insights from the Millstone Individual Plant Examination of External Events,

past inspection results, recent operational experience, and resident inspector input:

Unit 2 Fire Areas / Fire Zones

R-1 / A-1B, Reactor Building Closed Cooling Water (RBCCW) Pump & Heat Exchanger

Area

R-2 / T-10, Upper 4 kV Switchgear (SWGR)

R-8 / A-16, "B" EDG Room

R-13 / T-6, West 480 Volt Load Center Room

Unit 3 Fire Areas / Fire Zones

AB-5, East Motor Control Center and Rod Control Area

CB-1, West SWGR Area

CB-7, Battery Room 5

CB-8, Cable Spreading Area

Inspection of these fire areas/zones fulfilled the inspection procedure requirement to inspect a

minimum of three samples on each unit.

The team evaluated Dominion's fire protection program (FPP) against applicable requirements

which included Unit 2 Operating License Conditions 2.C.(3) and 2.C.(13), Unit 3 Operating

License Conditions 2.C.(10) and 2.H, NRC Safety Evaluation Reports (SERs), 10 CFR 50.48,

10 CFR 50 Appendix R, and the NRC Branch Technical Position (BTP) Chemical Engineering

Branch (CMEB) 9.5-1. The team also reviewed related documents that included the Updated

Final Safety Analysis Report (UFSAR), Fire Protection Program, Fire Hazards Analyses (FHA),

and post-fire Safe Shutdown Analyses Reports.

Section 4.0.A.5.2 presents the results of an inspection of Unit 2 conducted in accordance with

Temporary Instruction (TI) 2515/181, 'Validate the Effectiveness of the Regulatory Infrastructure

Related to Fire Induced Circuit Failures and Operator Manual Actions:'

Specific documents reviewed by the team are listed in the attachment to this report.

Enclosure 2

2

1.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity

1 R05 Fire Protection (IP 71111.05T)

.01

Protection of Safe Shutdown Capabilities

a.

Inspection Scope

The team reviewed the FHA, safe shutdown analyses, and supporting drawings and

documentation, to evaluate the fire protection of safe shutdown equipment and

capabilities. The team compared the separation requirements described in the UFSAR

and in 10 CFR 50, Appendix R, Section III.G to the designed and installed fire protection

features for credited safe shutdown equipment, including their supporting power, control,

and instrumentation cables to assess the protection adequacy of safe shutdown

capabilities. The team's review included an assessment of the adequacy of the selected

systems for reactivity control, reactor coolant makeup, reactor heat removal, process

monitoring, and associated support system functions.

The team reviewed procedures and programs for the control of ignition sources and

transient combustibles to assess their effectiveness in preventing fires and in controlling

combustible loading less than the analyzed limits established in the FHA. The team

reviewed selected hot work permits, transient combustible control, and fire protection

program evaluations to assess the adequacy of the fire protection program

administrative controls. During plant walkdowns, the team observed permanent and

transient combustible loading and potential ignition sources to independently verify

whether the installed protective features were being properly maintained and

administrative controls were being adequately implemented.

b.

Findings

No findings were identified .

. 02

Passive Fire Protection

a.

Inspection Scope

The team walked down accessible portions of the selected fire areas to evaluate

whether the observed material conditions of the fire area boundaries were adequate for

the fire hazards in the area. The team compared the fire area boundaries, including

walls, fire doors, fire dampers, penetration fire barrier seals, electrical raceway fire

barriers, and redundant equipment fire barriers to design basis requirements, industry

standards, and the Millstone FPP, as approved by the NRC, to identify any potential

degradation or non-conformances.

The team reviewed selected engineering evaluations, installation work orders, and

qualification records for a sample of penetration fire barrier seals to determine whether

Enclosure 2

3

the fill material was properly installed and whether the as-left configuration satisfied

design requirements for the intended fire rating. For Unit 2, there were no credited fire

protection wraps in the selected fire areas.

In addition, the team reviewed the most recent test results for fire damper functionality

tests and inspection records of penetration fire barrier seals and fire separation barriers

for the selected fire areas, to verify whether the inspection and testing was adequately

conducted, the acceptance criteria were met, and any potential performance degradation

was identified.

b.

Findings

No findings were identified .

. 03

Active Fire Protection

a.

Inspection Scope

The team evaluated the fire detection and suppression systems in the selected fire areas

to determine whether they were installed, tested, maintained, and operated in

accordance with NRC requirements and approved exemptions, National Fire Protection

Association (NFPA) codes of record, and the fire protection program, as approved by the

NRC. The team also assessed whether the suppression systems capabilities were

adequate to control and/or extinguish fires associated with the hazards in the selected

areas. The team reviewed initial discharge testing, design specifications, modifications,

and engineering evaluations for Unit 3 carbon dioxide (C02) suppression systems for the

west switchgear room, east motor control center and rod control area, and cable

spreading room. The team also reviewed and walked down the associated fire fighting

strategies and CO2 system operating procedures.

The team reviewed the design capability of the fire water supply system to verify whether

the design basis and NFPA code requirements for the hazards involved were adequately

satisfied. The team reviewed the fire water system hydraulic analyses and assessed the

adequacy of the underground fire loop flow tests to verify whether the tests adequately

demonstrated that the flow distribution circuits were able to meet design basis

requirements. The team evaluated the motor-driven and diesel-driven fire pump

capacity tests to assess the adequacy of the test acceptance criteria. In addition, the

team reviewed the most recent pump and loop flow test results to verify whether the

testing was adequately conducted, the acceptance criteria were met, and any potential

performance degradation was identified.

The team walked down accessible portions of the detection and suppression systems in

the selected areas and major portions of the fire water supply system, including motor

and diesel driven fire pumps, fire water storage tank, interviewed system and program

engineers, and reviewed selected open condition reports (CRs) to assess the material

condition of the systems and components. In addition, the team reviewed the most

recent test results

Enclosure 2

4

for the Unit 2 "B" emergency diesel generator (EDG) room deluge system, and for the

smoke and heat detectors for the selected fire areas, to verify whether the testing was

adequately conducted, the acceptance criteria were met, and any potential performance

degradation was identified.

The team assessed the fire brigade capabilities by reviewing training, qualification, and

drill critique records. In addition, the team interviewed fire brigade members, fire brigade

leaders, a fire brigade advisor, and the site Fire Marshall, to better assess the site fire

fighting capabilities. The team reviewed Dominion's fire fighting strategies (Le., pre-fire

plans) and smoke removal plans for the selected fire areas to determine if appropriate

information was provided to fire brigade members and plant operators to identify safe

shutdown equipment and instrumentation, and to facilitate suppression of a fire that

could impact post-fire safe shutdown capability. The team independently inspected the

fire brigade equipment, including personnel protective gear (e.g., turnout gear) and

smoke removal equipment, to determine operational readiness for fire fighting.

b.

Findings

Introduction. The team identified a finding of very low safety significance (Green),

involving a non-cited violation of Millstone Unit 2 Operating License Condition 2.C.(3),

and Unit 3 Operating License Condition 2.H, to implement and maintain all aspects of

the approved fire protection programs (FPPs), in that Dominion had not adequately

controlled fire fighting strategies as required by the FPPs. Specifically, Dominion did not

implement adequate review, approval and controlled distribution of fire fighting strategies

to provide for the adequate development and maintenance of effective strategies. As a

result, the team determined that the guidance in the fire fighting strategies for several

Unit 2 and 3 fire areas would likely result in a delay in manual fire suppression activities.

Description. The team reviewed eight fire fighting strategies, and identified multiple

issues with the strategies. The team determined that the fire fighting strategies were not

controlled as required by CM-AA-FPA-1 00, "Fire Protection/Appendix R (Fire Safe

Shutdown) Program," and CM-AA-FPA-102, "Fire Protection and Fire Safe Shutdown

Review and Preparation Process and Design Change Process." Specifically,

CM-AA-FPA-102, Attachment 12A, required Dominion to maintain effective fire fighting

strategies, including review, approval, and controlled distribution of fire fighting

strategies. The team identified that fire fighting strategies were being updated and

informally distributed by the site Fire Marshall in lieu of the implementation of appropriate

independent reviews, approvals, and controlled distribution.

Unit 2 Issues

The team reviewed the fire fighting strategy and the relevant fire zone design features

for Unit 2 fire zone A-16, the "B" EDG room. The team noted that the",t{'and "B" EDG

rooms shared a common ventilation system that included fan F-27 to circulate air

between the two rooms. The team also noted that the fire detection systems in the two

rooms utilize heat detectors and that normal personnel access to the "B" room is via the

'~room. Based on the ventilation, fire detection (Le., heat vs. smoke detection) and

personnel access design features, the team concluded that the first indication of a fire, in

Enclosure 2

5

particular a small or slowly developing fire, in the "B" EDG room would likely be the

observation of smoke in the "A" EDG room. The team identified that the fire fighting

strategy did not alert the fire brigade to the possibility that smoke in the "A" EDG room

could be due to a fire in the "B" EDG room, did not provide any guidance regarding

operations of recirculation fan F-27, and did not provide any guidance for additional fire

location diagnostics, such as early verification of conditions in adjacent areas. The team

also noted that the fire fighting strategy for EDG rooms did not provide guidance for

operators to consider securing of a running EDG prior to initiation of manual suppression

activities.

The team also identified an inconsistency in the fire fighting strategy for the Unit 2 west

480V load center room, in that the strategy did not appropriately identify the fire

suppression equipment. Specifically, the strategy's "Fire Suppression Capabilities"

section specified one specific fire hose station that included a hose that was not long

enough to reach the areas covered by the specific strategy, while the "Initial Actions"

section listed a different hose station that did include a hose of sufficient length.

As a result, the team determined that manual suppression in these Unit 2 areas could

reasonably be delayed as a result of the fire fighting strategy deficiencies.

Unit 3 Issues

The team reviewed the fire fighting strategy for Unit 3 fire zone CB-1, west switchgear

room, and determined that the strategy provided inadequate guidance for manual

discharge of CO2. The strategy for the west switchgear room provided instructions for

aligning fire dampers prior to initiating the CO2 suppression system. However, the

section of the strategy erroneously referred to the damper alignment as if the strategy

was dealing with a fire in the east switchgear room. In addition, the team discussed this

issue with a fire brigade leader and interviewed a fire brigade advisor. The team

determined that the information provided in the strategy, which referenced both west and

east switchgear rooms, was sufficiently inconsistent and misleading to result in the

brigade members delaying the initiation of the CO2 suppression system until they could

verify the damper operation instructions were correct.

The team also identified an error in the fire fighting strategy for the Unit 3 main

transformer area, in that the specified fire hydrant for manual fire fighting had been

removed by a modification, and a new hydrant, installed in an adjacent area, was not

listed.

As a result, the team determined that manual suppression in these Unit 3 areas could

reasonably be delayed as a result of the fire fighting strategy deficiencies.

Analysis. The team determined that the failure to control fire fighting strategies as

required by the fire protection program was a performance deficiency. Specifically,

CM-AA-FPA-100 and CM-AA-FPA-102 required Dominion to maintain effective fire

fighting strategies, and required review, approval, and controlled distribution of fire

fighting strategies. As a result, Dominion had not provided fully effective guidance in the

Enclosure 2

6

fire fighting strategies for the Unit 2 "B" EDG room, and the Unit 3 west switchgear room,

such that delays in manual fire fighting activities would likely occur.

This finding was more than minor because it adversely affected the availability and

capability objectives of the protection against external events (Le., fire) attribute under

the Mitigating Systems Cornerstone. Specifically, the above examples would likely

cause delays in manual fire fighting activities and, therefore, adversely affected the

defense-in-depth aspect of the fire protection program to limit fire damage by quick

suppression of those fires that occur. The team performed a Phase 1 SDP screening, in

accordance with NRC IMC 0609, Appendix F, "Fire Protection Significance

Determination Process." This finding affected fire prevention and administrative

controls, and was screened to very low safety significance (Green) because this failure

to control fire fighting strategies was determined to represent a low degradation rating.

A low degradation rating was assigned because there was only a minimum impact to the

performance of manual fire fighting activities, such that those activities were expected to

display nearly the same level of effectiveness and reliability as they would have the

degradation not been present. In addition, this issue did not affect the likelihood that a

fire might occur. The team concluded that this performance deficiency was reasonably

within Dominion's ability to foresee and prevent.

This finding had a cross-cutting aspect in the area of Human Performance, Resources

component, because Dominion failed to ensure complete and accurate fire fighting

strategies were available to the fire brigade to support timely extinguishment of fires.

[H.2.(c)]

Enforcement. Unit 2 License Condition 2.C.(3), and Unit 3 License Condition 2.H, in

part, require that Dominion implement and maintain in effect all provisions of the

approved FPP as described in the Final Safety Analysis Report. Dominion's FPP as

implemented by CM-AA-FPA-100 and CM-AA-FPA-102 require the maintenance of

effective fire fighting strategies, through a program that includes appropriate review,

approval, and controlled distribution of fire fighting strategies. Contrary to above, fire

fighting strategies for Unit 2 and 3 were not controlled as required by Dominion's Fire

Protection Program. Because this finding was of very low safety significance (Green)

and was entered into Dominion's corrective action program (CR 388786), this violation is

being treated as a non-cited violation (NCV), consistent with section 2.3.2.a. of the NRC

Enforcement Policy. NCV 05000336/2010008*01; 05000423/2010008*01, Failure to

Properly Control Fire Fighting Strategies.

Enclosure 2

7

.04

Protection from Damage from Fire Suppression Activities

a.

Inspection Scope

The team walked down the selected fire areas and adjacent areas, and reviewed

selected documents to determine whether redundant safe shutdown trains could be

potentially damaged from fire suppression activities or from the rupture or inadvertent

operation of fire suppression systems. Specifically, to determine whether a potential

existed to damage redundant safe shutdown trains, the team evaluated whether:

A fire in one of the selected fire areas would not release smoke, heat, or hot

gases that could cause unintended activation of suppression systems in adjacent

fire areas which could potentially damage all redundant safe shutdown trains;

A fire suppression system rupture, inadvertent actuation, or actuation due to a

fire, in one of the selected fire areas, could not directly damage all redundant

trains (e.g., sprinkler caused flooding of other than the locally affected train); and,

Adequate drainage was provided in areas protected by water suppression

systems.

b.

Findings

No findings were identified .

. 05

Alternative Shutdown Capability

a.

Inspection Scope

Methodology

The team reviewed the safe shutdown analysis, operating procedures, piping and

instrumentations drawings (P&IDs), electrical drawings, the UFSAR, and other

supporting documents to evaluate whether Dominion could achieve and maintain hot

and cold shutdown from outside the control room, for fire scenarios that rely on a

shutdown methodology from outside the control room. The team assessed Dominion's

ability to shutdown the plant from outside the control room both with and without the

availability of offsite power. Plant walkdowns were also performed to independently

verify whether the plant configuration was consistent with that described in the FHA and

safe shutdown analysis. The team's review focused on systems selected for reactivity

control, reactor coolant make-up, reactor decay heat removal, process monitoring

instrumentation, and support system functions to assess the adequacy of the selected

systems. In addition, the team assessed the systems and components credited for use

during the shutdown to determine whether they would remain free from fire damage.

The team reviewed the transfer of control from the control room to the alternative

shutdown locations to verify whether it would be affected by fire-induced circuit faults

(e.g., by the provision of separate fuses and power supplies for alternative shutdown

control ci rcu its).

Enclosure 2

8

Similarly, for fire scenarios that relied on a shutdown from the control room, the team

also evaluated the shutdown methodology to verify the adequacy of the selected

components and systems to achieve and maintain safe shutdown conditions.

Operational Implementation

The team reviewed the training program for licensed and non-licensed operators to

assess training adequacy for alternative shutdown systems and procedures. In addition,

the team evaluated operator minimum shift staffing requirements to verify whether an

adequate number of operators were available on-site at all times, exclusive of those

assigned as fire brigade members, to perform fire related safe shutdown activities using

either the normal or alternative shutdown systems.

The team reviewed the procedures utilized for post-fire safe shutdown, walked down key

equipment and control stations, and performed a tabletop walk through of selected

procedure steps to independently assess human factor elements and procedure

adequacy. The team also evaluated the available time to assess whether operators

could reasonably perform the specific actions needed to maintain plant parameters

within specified limits. Specifically, the team evaluated the time critical operator actions

to restore alternating current (AC) electrical power, transfer operational command and

control from the main control room to the remote shutdown panel, establish reactor

coolant make-up, and establish decay heat removal.

The team reviewed selected operator manual actions to determine whether Dominion

had adequately validated and verified that the actions could be implemented in

accordance with approved procedures, and in the time necessary to support the safe

shutdown method for each fire area. In addition, the team reviewed the most recent test

results for alternative shutd'own transfer capability, and instrumentation and control

functions, to verify whether the testing was adequately conducted, the acceptance

criteria were met, and any potential performance issues were identified, to ensure the

alternative shutdown capability remained functional.

b.

Findings

No findings were identified .

. 06

Circuit Analysis

a.

Inspection Scope

The team reviewed Dominion's post-fire safe shutdown analysis for the selected fire

areas to determine whether the analysis appropriately identified the structures, systems,

and components important to achieving and maintaining safe shutdown. In addition, the

team evaluated the analysis to assess whether the necessary electrical circuits were

properly protected and whether circuits that could adversely impact safe shutdown due

to hot shorts, shorts to ground, or other failures were identified, evaluated, and properly

dispositioned to ensure spurious actuations would not prevent safe shutdown.

Enclosure 2

9

The team's review considered fire and cable attributes, potential undesirable

consequences, and common power supply or bus issues. Specific review aspects

included fire threat credibility, cable insulation properties, cable failure modes, and

potential spurious actuations which could result in flow diversion or loss of coolant

events.

The team also reviewed cable routing data bases for a sample of components required

for post-fire safe shutdown to determine whether the cables were routed as described in

the safe shutdown analyses.

Cable failure modes were reviewed for the following components:

3RCS*Ll459C, Pressurizer Level Indicator

3RCS*PI455B, Pressurizer Pressure Indicator

3RCS*MV8000A, Pressurizer Relief Isolation Valve

3RHS*MV8701A, Residual Heat Removal Inlet Isolation Valve

3CHS*MV8438C, Charging Header Isolation Valve

A-EDG, Emergency Diesel Generator

LI-1123B, Steam Generator Level Indicator

LI-110X, Pressurizer Level Indicator

In addition, the team reviewed circuit breaker coordination studies to assess whether

equipment needed to support post-fire safe shutdown activities could be impacted due to

inadequate over-current coordination. Additionally, the team reviewed a sample of

circuit breaker maintenance records to verify whether the circuit breakers for

components required for post-fire safe shutdown were properly maintained in

accordance with approved procedures.

b.

Findings

Introduction. The team identified a finding of very low safety significance (Green),

involving a cited violation of Millstone Unit 2 Operating License Condition 2.C.(3) to

implement and maintain all aspects of the approved fire protection program.

Specifically, Dominion failed to protect required post-fire safe shutdown components and

cabling to ensure one of the redundant trains of equipment remained free from fire

damage as required by 10 CFR Part 50, Appendix R, Section III.G.2. In lieu of providing

the required separation, Dominion utilized unapproved operator manual actions to

mitigate component malfunctions or spurious operations caused by potential single fire

induced circuit faults (hot short, open circuit or short to ground).

Description. As a result of a self-assessment (Self-Assessment Report 000506),

Dominion initiated condition report (CR) 119114 in November 2008 to identify the lack of

Enclosure 2

10

documentation concerning a review of their use of operator manual actions against the

guidance contained in Regulatory Issue Summary (RIS) 2006-10, "Regulatory

Expectations with Appendix R Paragraph III.G.2 Operator Manual Actions,"

dated June 30, 2006. The CR also identified that exemption requests may be needed to

obtain NRC approval for the use of operator manual actions.

In addition to information provided to the licensees in RIS 2006-010, the NRC issued

several enforcement guidance memoranda (EGM) to promulgate interim enforcement

guidance to the staff while the issues of non-compliant manual actions and fire induced

circuit faults were being resolved. Specifically, EGM 07-004 defined March 6,2009, as

the date by which corrective actions were to have been completed for non-compliances

involving the use of unapproved post-fire manual actions. If corrective actions were

completed by this date the licensees would be eligible to receive enforcement discretion

for the associated violations of NRC requirements. The scope of this EGM included use

of manual actions to mitigate component malfunctions that resulted from fire-induced

single spurious actuations but did not include malfunctions due to multiple spurious

actuations. The NRC subsequently issued EGM 09-002 to describe the conditions

limiting enforcement during the resolution of fire protection concerns involving multiple

spurious actuations. EGM 09-002 made enforcement discretion available provided

licensees entered these non-compliances into their corrective action program and

implemented interim compensatory measures within six months of the issuance of NRC

Regulatory Guide (RG) 1.189, Rev. 2, and then implemented corrective actions within

three years of the issuance of RG 1.189, Rev. 2. Accordingly, based on the issuance

date of the RG, May 2, 2010, was established as the date by which non-compliances

associated with multiple spurious actuations were to be entered into the corrective action

program and November 2,2012, is the date by which corrective actions must be

completed for licensees to be eligible to receive enforcement discretion for the

associated non-compliances. At the time of this inspection, a fleet wide Dominion

project for identification and resolution of multiple spurious operation issues was in

progress.

In June 2010, during the performance of a fire protection self-assessment (SAR001 036),

Dominion initiated CR 383734 which documented that CR 119114 had been improperly

closed to the multiple spurious operations evaluation process. Further review by the

team confirmed that issues opened in CR 119114 associated with the use of

unapproved manual actions to address single spurious actuation had not yet been

resolved. Additional licensee reviews during this inspection subsequently identified

numerous components that did not meet the separation requirements of 10 CFR Part 50,

Appendix R,Section III,G.2. This issue was entered into Dominion's corrective action

program as CR 388775.

Specifically, the team reviewed information provided by Dominion concerning potential

unapproved manual operator actions in seven fire areas (R-2, R-4, R-9, R-10, R-13,

R-14, and R-17). The team focused on actions that needed to be completed in a

relatively short period of time to ensure core cooling, specifically feeding of the steam

generators (SG) using the available auxiliary feedwater system (AFW). The team

reviewed the Fire Safe Shutdown Analysis and procedures to reach hot shutdown for

each of these areas, identifying the credited path that would need to be free of fire

Enclosure 2

11

damage to be in compliance with Appendix R,Section III.G.2. This included

identification of the required pump or pumps and flow path including the SG flow control

valve (FCV) to one of the two SGs, referred to as the required path. The team then

identified any

flow path to the other SG using the other FCV, referred to as the redundant path.

The team identified the post-fire safe shutdown required paths and the associated

components that were operated by procedures from outside the control room using

manual actions to restore/maintain the required safe shutdown function because of

potential fire damage. This review identified five general types of actions needed to

maintain decay heat removal with the SGs that could be subject to exemption. These

included: 1) operating the required flow path FCV locally or from the fire safe shutdown

panel; 2) closure of the required SG blowdown valve; 3) restoration of instrument air, if

offsite power is lost, to allow continued operation of the FCVs from the control room or

fire safe shutdown panel; 4) operation of the turbine driven (TO) AFW pump from the fire

safe shutdown panel including not over filling the SGs; and 5) actions to protect the

required 4160 volt AC bus and DC power supplies. This resulted in 11 actual individual

unapproved manual actions for which the licensee had not requested exemption.

Analysis. The team identified a performance deficiency in that Dominion failed to protect

components credited for post-fire safe shutdown from fire induced damage that could

result in a single spurious actuation. The performance deficiency was more than minor

because it affected the Mitigating Systems Cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events to

prevent undesirable consequences in the event of a fire. Specifically, the use of

operator manual actions during post-fire shutdown is not as reliable as normal systems

operation which could be utilized had the separation requirements of 10 CFR 50,

Appendix R,Section III.G.2 been met and therefore prevented fire damage to credited

components and/or cables. The team used IMC 0609, Appendix F, "Fire Protection

Significance Determination Process (SOP):' Phase 1 and an SRA conducted Phase 3

analyses, to determine that this finding was of very low safety significance (Green).

In six of the identified fire areas actions were needed to maintain AFW flow to the

required SG within 30 to 45 minutes. The actions to restore charging flow were not

needed until over three hours and were not reviewed. Actions needed to operate SG

atmospheric dump valves to control the plant cooldown were not reviewed, because

steam generator safety valves were the assumed path for decay heat removal. Simple

actions to isolate components such as repositioning switches at the bottle-up panel to

force isolations and prevent spurious actuations to isolate the SGs were not reviewed,

because th~y were essentially equivalent to actions from the control room. Actions

needed to restore instrument air to support control room operation of the AFW FCVs

were not reviewed because of installed two-hour air bottles on each FCV. As such, fire

areas R-4, R-9, R-10, and R-17 were screened as having low degradation in the Phase

1 of the Fire SOP, Inspection Manual Chapter 0609, Appendix F.

The SRA conducted Phase 3 risk evaluations for the unapproved manual action in fire

areas R-2, R-13, and R-14. The individual analyses reviewed the increase in risk due to

the unapproved manual actions. These evaluations allowed for use of the available flow

Enclosure 2

12

path to the redundant steam generator. The bases case assumed conformance with

III,G.2 (Le., operation from the required flow path components from the control room)

and the condition case assumed non-conforming manual actions taking place outside

the control room. SPAR H was used to model both the conforming and non-conforming

manual actions. Specifically:

R-2 - the required path to the #1 steam generator with operation of the "IX'MD AFW

pump from the control room with local manual operation of the "IX' FCV vice operation

from the control room.

R-13 - the required path to the #2 steam generator with operation of the TDAFW

pump and the "B" FCV from the fire safe shutdown panel vice the control room.

R-14 - the required path to the #2 steam generator with either the TDAFW pump or

the "B" MDAFW pump operating from the control room, with:

local manual action to isolate the 24D safety bus, and align the "B" EDG, vice

no action needed

local manual operation of the "B" FCV vice operation from the control room.

Based on the fire frequencies specified in the Individual Plant Evaluation of External

Events (IPEEE) for these areas, the total conditional core damage probability increase

given the local manual actions vice control room was estimated to be in the range of 1

core damage accident in 1.1 million years (high E-7 range).

The team found the unapproved manual actions in fire areas R-2, R-4, R-9, R-10, R-13,

R-14, and R-17 to be reasonable interim compensatory measures (pending licensee

actions to resolve the non-compliances or obtain exemptions) because they did not

require complicated actions, adequate time was available to accomplish the actions and

the actions were properly included in the appropriate abnormal operating procedures.

This finding has a cross cutting aspect in the area of problem identification and

resolution associated with the corrective action program because Dominion did not

completely and accurately identify deficiencies related to single spurious actuations of

credited post- fire safe shutdown components. As a result, appropriate actions were not

taken to address the use of unapproved manual actions as described above. (P.1.a)

Enforcement. License Condition 2.C.(3) specifies, "The licensee shall implement and

maintain in effect all provisions of the approved fire protection program as described in

the Updated Final Safety Analysis Report and as approved in the SER dated

September 19,1978, and supplements dated October 21,1980, November 11,1981,

October 31,1985, April 15, 1986, January 15, 1987, April 29, 1988, July 17, 1990,

and November 3, 1995:' Final Safety Analysis Report, Section 9.10.6 specifies that the

licensee will meet the requirements of 10 CFR Part 50, Appendix R, Section III,G.2 that

identifies three methods of protecting post-fire safe shutdown equipment from fire

damage. Additionally, by letter B17399, dated March 17, 1999, Dominion informed the

NRC staff of variances between the SER supplement (dated July 17, 1990) related to

post-fire alternative shutdown capability, and their current (1999) safe shutdown strategy

for Millstone Unit 2. Letter B17399, in part, clarified that only four fire areas (R-1, R-3,

R-11, and R-16) relied on alternative shutdown capability. As a result, use of manual

Enclosure 2

13

operator actions in lieu of protecting the equipment in accordance with 10 CFR 50,

Appendix R, III.G.2 would only be allowed if approved by the NRC.

Contrary to the above, through September 22,2010, Dominion failed to implement their

fire protection program by using one of the three methods described in Appendix R,

Section III.G.2 to protect circuits required for post-fire safe shutdown from fire induced

circuit damage. Specifically, Dominion continued to use unapproved manual actions to

mitigate post-fire safe shutdown equipment malfunctions caused by a single spurious

actuation without having obtained NRC approval. This finding is being cited because not

all of the criteria specified in section 2.3.2.a of the NRC Enforcement Policy for a non-

cited violation were satisfied. Specifically, Dominion failed to restore compliance within a

reasonable amount of time after the violation was identified in CR 119114 in November

2008. Additionally, because the violations were not corrected by March 6, 2009,

Dominion is not eligible to receive enforcement discretion previously available by EGM 07-004. VIO 05000336/2010008-02, Failure to Protect Safe Shutdown Equipment

From the Effects of Fire .

. 07

Communications

a.

Inspection Scope

The team reviewed selected fire related safe shutdown procedures, the FHA, the safe

shutdown analysis, and associated documents to assess whether the expected method

of communications would be available during and following a fire. During this review, the

team considered the effects of ambient noise levels, clarity of reception, reliability, and

coverage patterns. The team inspected the designated emergency storage lockers to

verify whether sufficient portable radios would be available for the fire brigade and

operators. In addition, the team assessed whether communications equipment, such as

sound powered phone system cables, repeaters, transmitters, and uninterruptable and

back-up power supplies would be adversely affected by a fire.

b.

Findings

No findings were identified.

08

Emergency Lighting

a.

Inspection Scope

The team walked down the emergency lights in the selected fire areas to independently

evaluate the placement and coverage areas of the lights. The team assessed whether

the lights provided adequate illumination on local equipment and instrumentation,

required for post-fire safe shutdown, to ensure local operations could be reliably

performed under expected post-fire conditions. Emergency light placement was also

evaluated to determine adequate illumination of local area access and egress pathways.

Enclosure 2

14

The team verified whether the emergency light batteries were rated for at least an eight-

hour capacity. Preventive maintenance procedures, the vendor manual, completed

surveillance tests, and battery replacement practices were also reviewed to evaluate

whether the emergency lighting was being maintained in a manner that would ensure

reliable operation.

b.

Findings

No findings we~e identified .

. 09

Cold Shutdown Repairs

a.

Inspection Scope

The team reviewed dedicated repair procedures for selected components which might

be damaged by the fire, to determine whether the a cold shutdown could be achieved

within the time specified in the design and licensing bases. The team also reviewed the

associated equipment, materials, and tools needed to perform the repairs (e.g., pre-cut

cables with lugs attached), to determine whether they were available and accessible on-

site.

b.

Findings

No findings were identified .

. 10

Compensatory Measures

a.

Inspection Scope

The team reviewed selected fire protection and post-fire safe shutdown equipment,

systems, or features that were out-of-service, degraded, or inoperable (e.g., detection

and suppression systems, passive fire barriers, pumps or valves, or electrical devices

providing safe shutdown functions or capabilities) to determine whether Dominion had

implemented appropriate compensatory measures. The team also evaluated selected

short term compensatory measures to assess whether the degraded function or feature

was adequately compensated until appropriate corrective action could be taken to return

the equipment to service. In addition, the team assessed Dominion's effectiveness to

return equipment to service in a reasonable period of time.

b.

Findings

No findings were identified.

Enclosure 2

15

.11

Large Fires and Explosions Mitigation Strategies

a.

Inspection Scope

The team reviewed Dominion's preparedness to handle large fires or explosions by

reviewing two mitigating strategies on each unit to verify they continue to meet the

requirements of the Unit 2 and Unit 3 license conditions 2.C.(13) and 2.C.(10),

respectively by determining that:

-Procedures are being maintained and adequate;

-Equipment is properly staged and is being maintained and tested; and,

-Station personnel are knowledgeable and can implement the procedures.

b.

Findings

The results of this inspection are document in NRC Inspection Report 05000336/2010011 and 05000423/2010011.

4.

OTHER ACTIVITIES

40A2 Identification and Resolution of Problems (IP 71152)

a.

Inspection Scope

The team reviewed a sample of CRs associated with the FPP and post-fire safe

shutdown issues to determine whether Dominion was appropriately identifying,

characterizing, and correcting problems associated with these areas and whether the

planned or completed corrective actions were appropriate. The CRs reviewed are listed

in the attachment.

The team determined that the licensee had identified several multiple spurious operation

(MSO) scenarios for further review. Dominion placed the identified scenarios into their

corrective action program and implemented alternate compensatory measures prior to

May 2,2010.

b.

Findings

No findings were identified.

40A5 Other Activities

.1

(Closed) URI 50-423/2003-02-03, Generic Industry and NRC Resolution of Fire Safe

Shutdown Issues

NRC Inspection Report 50-423/2003-002 closed Licensee Event Report 50-423/2002-00

Supplement 01, which was associated with inadequate validation of fire safe shutdown

assumptions (fire-induced circuit fault). In addition, that inspection report also closed a

previous NRC unresolved item (URI) 50-423/2002-05-07 which tracked the resolution of

Enclosure 2

16

an NRC and industry initiative to develop generic guidance to evaluate fire-induced

circuit failures. That URI was closed because it was considered too narrow in scope, in

that it only addressed the resolution of an issue related to power operated relief valves.

That inspection report opened a new URI (50-423/2003-02-01) to track the broader

resolution of the issue. (Note: The NRC tracking number was subsequently

administratively changed to URI 50-423/2003-02-03.)

There were two specific aspects of fire-induced circuit faults that the NRC subsequently

addressed. The first issue involved fire-induced single circuit cable faults and

associated operator manual actions, not specifically approved by the NRC, which

licensees relied upon as compensatory measures to mitigate potential adverse effects

on equipment required for post-fire safe shutdown. NRC EGM 2007-004 authorized

enforcement discretion for such issues, provided that licensees entered those issues into

their corrective action programs, instituted appropriate compensatory measures until the

issues were corrected, and either (a) corrected the conditions or (b) submitted an

exemption request to the NRC, by March 6, 2009. The EGM also stated that non-

compliances involving single fire-induced circuit faults identified after March 6, 2009

would be subject to enforcement actions.

The second issue involved fire-induced multiple circuit cable faults and associated

operator manual actions. EGM 2009-002, dated May 14,2009, authorized enforcement

discretion for such issues, provided that licensees identified those issues, entered them

into their corrective action programs, and instituted appropriate compensatory measures

until the issues were corrected, within the six month period following a planned revision

to RG 1.189, "Fire Protection for Nuclear Power Plants." RG 1.189, Rev. 2, issued in

October 2009, provided a method acceptable to the NRC to evaluate and resolve

multiple fire-induced circuit faults. After the 6 month period for identification of issues,

the EGM further authorized enforcement discretion an additional 30 month period, for

licensees to resolve the identified multiple fire-induced circuit fault issues.

The two EGMs and RG 1.189, discussed above, provide adequate technical guidance

and an acceptable time table to evaluate and resolve the issues tracked by

URI 50-423/2003-02-03, regarding fire-induced cable faults. The adequacy of licensee

actions to address these issues will continue to be reviewed within the framework of the

NRC's reactor oversight process which includes the triennial fire protection team

inspections and problem identification and resolution inspections. Therefore,

URI 50-423/2003-02-03 is no longer necessary to track these issues and is closed .

. 2

Temporary Instruction (Tn 2515/181! 'Validate the Effectiveness of the Regulatory

Infrastructure Related to Fire-Induced Circuit Failures and Operator Manual Actions'

Background

This TI is intended to verify that the regulatory infrastructure is sufficient for licensees to

achieve compliance in the areas of fire induced circuit failures and post-fire operator

manual actions for spurious actuations due to fire-induced failures. 10 CFR Part 50,

Appendix R,Section III.G.2, identifies three acceptable methods to meet the requirement

for maintaining one of the redundant trains in the same fire area, outside of primary

Enclosure 2

17

containment, free of fire damage. The three methods include a combination of physical

barriers, spatial separation, and fire detection and automatic suppression systems.

In October 2009, the NRC issued guidance in Regulatory Guide 1.189, "Fire Protection

for Nuclear Power Plants;' Revision 2, to identify acceptable methods for resolving issues

related to circuits required for post-fire safe shutdown and circuits important to

post-fire safe shutdown. Equipment required post-fire safe shutdown (credited train)

must use one of the three methods identified in Section III.G.2 to protect the circuits

located within the same fire area from fire damage, including single and multiple

spurious operations. For important to post-fire safe shutdown circuits, the licensee may

use operator manual actions if the licensee demonstrates they can be shown to be

feasible and reliable or resolve issues using other analysis methods including fire

modeling.

a. Inspection Scope

During this inspection, the team reviewed a representative sampling of single and

multiple spurious issues for Unit 2 to:

1) Determine if the licensee used the guidance in Regulatory Guide 1.189, Revision 2

and Nuclear Energy Institute (NEI) 00-01, "Guidance for Post Fire Safe Shutdown

Analysis;' Revision 2, to successfully address single and multiple spurious issues in

a manner that met the regulations. This included equipment required for safe

shutdown and equipment important for safe shutdown.

2) Evaluate the adequacy of the licensee's method for determining that the required

trains of safe shutdown equipment do not rely on operator manual actions.

3) Evaluate the adequacy of the licensee's method for determining if redundant trains

of post fire safe shutdown equipment (required and important to post fire safe

shutdown equipment) are made inoperable or nonfunctional due to Single or

multiple spurious actuations.

4) Evaluate the adequacy of the licensee's multiple spurious actuation evaluation in

accordance with RG 1.189 and NEI 00-01 for alternative or dedicated shutdown

areas.

5) Evaluate the licensee's understanding of the requirements related to allowed

operator manual actions. (Note: The team added this question to assure sufficient

information was available related to Task 4 of the fire protection stabilization plan.)

The team reviewed the Unit 2 post-fire safe shutdown analysis, Unit 2 licensing basis,

project instructions, drawings, and corrective action documents. The team interviewed

the multiple spurious operation project expert panel chairman, the fire protection safe

shutdown engineer, the fire protection system engineer, and a reviewer who participated

in the screening circuit analysis and disposition of the expert panel questions. Two NRC

staff with expertise in circuit analysis and the requirements related to multiple spurious

Enclosure 2

18

operations from the Fire Protection Branch in the Office of Nuclear Reactor Regulation

provided assistance to the team during this inspection.

b.

Findings

No findings were identified.

Licensee Process

Dominion established a process that followed the guidelines established in NEI 00-01.

This process included the following components:

Establishment of an expert panel that reviewed the generic list of multiple

spurious operations established in NEI 00-01, Appendix G, "Generic List of

MSOs;'for pressurized water reactors. The expert panel identified the multiple

spurious operations that could be applicable based on the Unit 2 plant-specific

design;

Evaluation of the identified applicable multiple spurious operation scenarios to

determine whether the existing post-fire safe shutdown analysis and safe

shutdown strategy already included measures that adequately addressed any

potential adverse impacts of the particular scenario;

Identification of cables for the components within the scope of the multiple

spurious operations scenario evaluation and identification of their physical

routing by fire areas;

Performance of an initial circuit analysis to determine which of the cables

selected in the previous step could cause a component to actuate from their

initial state to an undesired state due to fire induced circuit damage;

Performance of fire area analyses to identify fire areas that contained the

cables for each of the components whose combinations are necessary to result

in a multiple spurious operation of concern;

Documentation and evaluation of multiple spurious operation scenarios that

require resolution in the corrective action program and implement compensatory

measures;

Performance of additional circuit and fire area analyses for those multiple

spurious operation scenarios that have been entered into the corrective action

program to confirm which scenarios could realistically occur and implement

corrective for final resolution; and,

Documentation of the multiple spurious operation project process, evaluations

and results.

Enclosure 2

19

At the time of this inspection, the team determined that Dominion had not implemented

this process for their alternative or dedicated shutdown areas. Dominion indicated that

they had plans to evaluate their alternative or dedicated shutdown areas following the

same process described above.

1) Determine if the licensee used the guidance contained in Regulatory Guide 1.189.

Rev. 2. and NEI 00-01. Rev. 2. to successfully address single and multiple spurious

operations in a manner that met regulations. This includes equipment required for safe

shutdown and equipment important for safe shutdown.

The team found that Dominion established appropriate project instructions for

conducting their expert panel and for conducting their circuit analysis. The project

instructions utilized the guidance contained in NEI 00-01, Section 3 for evaluating the

different circuit failure combinations and utilized the guidance contained in NEI 00-01,

Appendix F for conducting the expert panel evaluations of potential MSO scenarios

including the generic multiple spurious operations listed for pressurized water reactors in

NEI 00-01, Appendix G. The team also found that Dominion programs were adequate to

identify single spurious operations. However, the team found that unapproved operator

manual actions were being used to mitigate previously identified equipment spurious

actuations that could be caused by single fire induced circuit failures. Refer to section

1 R05.06 above for details.

The team concluded Dominion used the guidance in RG 1.189 and NEI 00-01 to conduct

their review for single and multiple spurious operations. The team concluded that these

documents provided sufficient guidance for Dominion to establish an appropriate review

process that evaluated spurious operations of both required and important post fire safe

shutdown equipment.

2) Evaluate the adequacy of the licensee's method for determining that the redundant

trains of safe shutdown equipment do not rely on operator manual actions.

The team found that Dominion's eXisting safe shutdown analysis program adequately

determined where required trains of post-fire safe shutdown equipment relied upon

operator manual actions. The use of manual operator actions to address single spurious

actuation issues are identified and documented in 25203-SP-M2-SU-1046, MP 2,

Appendix R Compliance Report, Rev. 01. However, the team also found that the

licensee had not corrected conditions that resulted in reliance on operator manual

actions, nor had Dominion obtained NRC approval for the use of operator manual

actions that involved equipment required for safe shutdown. Refer to section 1 R05.06

for details.

The team also noted that Dominion has not yet identified MSO scenarios whose

resolution may require reliance on operator manual actions. At the time of this

inspection Dominion's MSO program had progressed to the point where CRs have been

initiated for multiple spurious operation scenarios for which their initial reviews

determined to be potential viable concerns. As a result, additional licensee reviews and

evaluations will be necessary to determine which MSO scenarios may require corrective

Enclosure 2

20

actions and whether operator manual actions would be considered as a viable corrective

action.

Based on these reviews, the team concluded that Dominion's methods are adequate to

identify where the redundant trains of safe shutdown equipment do not meet the

separation requirements of 10 CFR 50, Appendix R and the safe shutdown methodology

for single or multiple spurious operations may rely on operator manual actions.

3) Evaluate the adequacy of the licensee's method for determining if redundant trains of

safe shutdown equipment are made inoperable or nonfunctional due to single or multiple

spurious actuations.

Dominion does not consider safe shutdown equipment to be inoperable or nonfunctional

due to a potential single spurious actuation if they have determined that an acceptable

operator manual action has been established. However, Dominion did acknowledge the

need to take actions to establish compliance with the requirements of 10 CFR 50,

Appendix R,Section III.G.2. Refer to section 1 R05.06 for details of the violation.

Dominion performed a functionality assessment for potential component failures as a

result of multiple spurious operations on a fire area basis. Dominion considered these

components as "operable but degraded and nonconforming:' Consequently, Dominion

evaluated the components using the guidance described in Regulatory Information

Summary 2005-20, "Revision to NRC Inspection Manual Part 9900 Technical Guidance,

Operability Determinations & Functionality Assessments for Resolution of Degraded or

Nonconforming Conditions Adverse to Quality or Safety;' Rev. 1. Dominion determined

that the types ofissues identified by the multiple spurious operation review would not

significantly affect the plant margin of safety and that these multiple spurious operations

did not constitute a degraded fire protection feature within the scope of the Millstone

Unit 2 Technical Requirements Manual (TRM).

Dominion has determined the impact of multiple spurious operations had low risk and

safety consequences. Dominion based this conclusion, in part, on the following

technical factors: (1) a large fire lasting longer than 20 minutes would likely be

necessary to result in a multiple spurious operation; (2) the fire will likely have been

detected prior to reaching a damaging level; (3) the suppression systems will actuate

long before the temperatures reach the levels required to damage thermoset cables

(500-700 OF); (4) the fire must continue in the area of the cables for long periods to

result in maloperation; and, (5) multiple hot shorts would need to occur.

Based on the above assessment, Dominion implemented interim compensatory

measures in the form of enhanced operator rounds as described in their functional

assessment prior to May 2, 2010 to provide an additional level of awareness. Dominion

enhanced the operator rounds by: (1) training operators on the fire hazards to increase

their awareness, (2) adding statements to the rounds for the types of items to monitor

(e.g., degraded fire features and increased combustibles), and (3) requiring the

operators to routinely document that these items were reviewed. In addition to the

changes to the operator rounds, additional monitoring of fire detection system operability

Enclosure 2

21

has been implemented. Upon final confirmation that specific multiple spurious operation

scenarios are valid concerns that require corrective actions.

Dominion specified that they would initiate individual corrective action documents and

implement compensatory measures specified in their TRM for the identified

nonconformance.

The team concluded Dominion had an adequate method for evaluating the operability

and functionality of components subject to multiple spurious operations. However,

actions to ensure compliance with Appendix R for single spurious actuation issues were

not timely (refer to section 1 R05.06 above).

4) Evaluate the adequacy of the licensee's multiple spurious actuation evaluation in

accordance with Regulatory Guide 1.189 and NEI 00-01 for alternative or dedicated

shutdown areas.

The team determined that Dominion had established a process to evaluate their

alternative or dedicated shutdown areas. Dominion planned to implement this review

following the steps used for evaluating the 10 CFR Part 50, Appendix R, Section IILG.2

multiple spurious operation evaluations.

5) Evaluate the licensee's implementation of the requirements related to allowed

operator manual actions.

The team reviewed Dominion's implementation of guidance and requirements involving

the use of operator manual actions for post-fire safe shutdown. Aspects reviewed

included the differences regarding the use of operator manual actions contained in

10 CFR Part 50, Appendix R, Sections IILG.2 and IILG.3, including the circumstances

under which an NRC exemption would be required. The team confirmed that Dominion

understood that when reviewing the acceptability of specific manual actions associated

with a licensing action, the NRC would utilize the guidelines contained in NUREG-1852,

'Demonstrating the Feasibility and Reliability of Operator Manual Actions in Response to

Fire:'

The team also reviewed Dominion's program for addressing the use of operator manual

actions to resolve MSO issues. Specifically, the team confirmed that Dominion's

program was consistent with the guidance specified in RG 1.189 and NEI 00-01,

including differentiation between required' and '~mportant' to safe shutdown equipment.

40A6 Meetings. including Exit

The team presented the preliminary inspection results to Mr. A. J. Jordan, Site Vice

President, and other members of Dominion's staff on August 5, 2010. Following

additional in-office and on-site reviews, an exit meeting was conducted by telephone

with Mr. A. J. Jordan and other members of your staff on September 22, 2010. The

team verified that this report does not contain proprietary information.

Enclosure 2

A-1

ATTACHMENT

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

P. Anastas, Safe Shutdown Program Engineer

J. Armstrong, Fire Protection Engineer

R. Beal, Senior Reactor Operator

R. Bonner, Supervisor, Electrical and I&C System Engineering

C. Chatman, Senior Reactor Operator

K. Cyr, Electrical Design Engineer

P. Dillon, Diesel System Engineer

P. Freeman, Electrical Design Engineer

W. Harrelson, Senior Reactor Operator

C. Karpinski, Fire Brigade Training

L. LeBaron, System Engineer

J. Lupa, Reactor Operator

J. Mangeno, Fire Protection Engineer

J. Martin, MSO Project Manger

T. McNatt, System Engineer

R. Patel, Electrical Design Engineer

B. Pinkowitz, Simulator Instructor

J. Powers, System Engineer

J. Rigatti, Manager, Nuclear Engineering

T. Ryan, System Engineer

S. Wainio, Engineering Supervisor

B. Wilkens, Site Fire Marshal

NRC Personnel

S. Shaffer, Senior Resident Inspector- Millstone

B. Haagensen, Resident Inspector- Millstone

J. Krafty, Resident Inspector- Millstone

Attachment

A-2

LIST OF ITEMS OPENED, CLOSED AND DISCUSSED

Opened

05000336/201 0008-02

NOV

Failure to Protect Safe Shutdown Equipment From the

Effects of Fire. (Section 1 R05.06)

Opened and Closed

05000336/201 0008-01

05000423/201 0008-01

Closed

NCV

Failure to Control Fire Fighting Strategies

(Section 1 R05.03)05000423/2003002-03

URI

Generic Industry and NRC Resolution of Fire Safe

Shutdown Issues (Section 40A5.1)

LIST OF DOCUMENTS REVIEWED

Fire Protection Licensing Documents

25203-SP-M2-SU-1046, Unit 2 Appendix R Compliance Report, Rev. 1

25212-BTP-9.5-1, Unit 3 Branch Technical Position 9.5-1 Compliance Report, Rev. 3

Unit 3 FSAR Fire Protection Evaluation Report, Rev. 23

Unit 2 Fire Hazards Analysis Report, Rev. 11

Unit 2 FHA Boundary Dwg., Sh. 1, Auxiliary & Containment Bldg, Elev. minus 45 ft., Rev. 3

Unit 2 FHA Boundary Dwg., Sh. 2, Auxiliary & Containment Bldg, Elev. minus 25 ft., Rev. 2

Unit 2 FHA Boundary Dwg., Sh. 3, Auxiliary & Containment Bldg, Elev. minus 5 ft., Rev. 3

Unit 2 FHA Boundary Dwg., Sh. 4, Auxiliary & Containment Bldg, Elev. 14 ft., Rev. 5

Unit 2 FHA Boundary Dwg., Sh. 5, Auxiliary & Containment, Elev. 25 ft., Rev. 3

Unit 2 FHA Boundary Dwg., Sh. 6, Auxiliary & Containment, Elev. 38 ft., Rev. 6

Unit 2 FHA Boundary Dwg., Sh. 7, Turbine Bldg, Elev. 14 ft., Rev. 4

Unit 2 FHA Boundary Dwg., Sh. 8, Turbine Bldg, Elev. 31 ft., Rev. 3

Unit 2 FHA Boundary Dwg., Sh. 9, Turbine Bldg, Elev. 54 ft., Rev. 2

Unit 2 FHA Boundary Dwg., Sh. 10, Outside Buildings, Rev. 4

Unit 2 FHA Boundary Dwg., Sh. 11, Yard Areas, Rev. 4

Fire Protection Program Procedures

CM-AA-FPA-100, Fire Protection 1 Appendix R (Fire Safe Shutdown) Program, Rev. 1

CM-AA-FPA-101, Control of Combustible and Flammable Materials, Rev. 2

CM-AA-FPA-102, Fire Protection, Fire Safe Shutdown Review, and Preparation Process and

Design Change Process, Rev. 0

Unit 2 Technical Requirements Manual, Section 7.1, Appendix R Safe Shutdown Requirements,

2/02/10

Attachment

A-3

Calculations and Engineering Evaluation Reports

25203-ER-08-0042, Unit 2 Delayed AFW Following a Fire in Area R-2, Rev. 0

25205-ER-09-0002, Unit 2 & 3 Fire Protection Time Critical Operator Actions, Rev. 0

25203-ER-99-0092, Unit 2 App- R Cooldown Analysis Assumptions and Results, Rev. 3

25212-ER-97-0302, Section 6.4, Communications, Rev. 3

98-ENG-02411-C2, Flooding Outside of Containment Evaluation, Rev. 1

98-ENG-02621-M2, Instrument Air Requirement for Certain Safety Related Valves, Rev. 3 99-026, Millstone Site Fire Loop Hydraulic Model, Rev. 1

ACE 1392-CR1 07561, Potential for Water Relief through Pressurizer Safety Valves from a

Control Room Fire, Rev. 0

C OP 200.18, Time Critical Action Validation and Verification, Rev. 0

M2-EV-970061, Unit 2 Compensatory Actions, Loss of Ventilation in Electric Switchgear Areas,

Rev. 3

M2-EV-97-0061, Compensatory Actions for Loss of Ventilation to SWitchgear Areas, Rev. 3

M2-EV-98-0013, 120 VAC Vital Bus Coordination Study, Rev. 0

M2-EV-99-0093, Compensatory Measures for Loss of Ventilation, Rev. 4

MP2-CD-1457, MEPL Determination, Rev. 0

P1164-MP2-COORD, Breaker & Fuse Coordination for Panels D11, D12, D21, and D22, Rev. 0

P1117-025, Unit 2 NFPA Code Compliance Deviation Closeout Review, 1/98

PA84-065-0753GE, Unit 2 480V Breaker Over-current Trip Devices, Rev. 2

PA85-082-0812GE, Unit 2 125VDC Coordination Study, Rev. 2

RAS 121147, Reasonable Assurance of Safety for CR 121147,12/18/08

RAS 000159, Emergency Lighting Units with Melted & Discolored Lens, 7/21/10

RAS 000066, Potential for Fire Damage to LCV112B/C, VCT Outlet Valves, Could Result in

Damage to "A" CHS PP Credited for Post Fire Shutdown, Rev. 1

S2-EV-99-0103, Safety Evaluation forTRM Change-99-2-16, Minimum Shift Staffing Required

to Implement App-R Manual Actions, Rev. 0

SP-GEE-6, Specification for 600 Volt Switchboard Wire, Rev. 2

SP-GEE-19, Specification for 600 Volt Control Cable, Rev. 4

SP-GEE-20, Specification for 600 Volt Instrument Cable, Rev. 3

SP-GEE-22, Specification for 600 Volt Power Cable, Rev. 4

SP-M3-EE-269, Appendix R Breaker Coordination Study, Rev. 2

W2-517-744-RE, Unit 2 App-R Cooldown, Rev. 3

Drawings and Wiring Diagrams

25203-24071, Sh. 5, Unit 2 Fire Damper Schedule, Rev. 2

25203-24091, Sh. C0102, Unit 2 Conduit Fire Seal Foam for Floor & Wall Detail, Rev. 2

25203-24091, Sh. G0002, Unit 2 Fire Grout Seal Detail, Rev. 2

25203-24092, Sh. T1 OF12, Unit 2 Penetration Seal Survey Map & Inspection Record, Rev. 1

25203-28200, Sh. 69, Unit 2 LT-110X, LT-110Y Pressurizer Level Functional Diagram, Rev. 3

25203-28500, Sh. 69A, Unit 2 L T -11 OX & 11 OY Pressurizer Level Loop Diagram, Rev. 11

25203-28500, Sh. 69B, Unit 2 L T -11 OX & 11 OY Pressurizer Level Loop Diagram, Rev. 7

25203-28500, Sh. 69C, Unit 2 L T-11 OX, 11 OY Pressurizer Level Loop Diagram, Rev. 9

25203-28500, Sh. 69D, Unit 2 L T-11 OX, 11 OY Pressurizer Level Loop Diagram, Rev. 7

25203-28500, Sh. 381, Unit 2 L T1123B Steam Generator Level Loop Diagram, Rev. 10

25203-29550, Sh. 1, Unit 2 EDG Rooms Pre-action Systems, Rev. 1

Attachment

A-4

25203-30001, Unit 2 Main Single Line Diagram, Rev. 30

25203-30101, Unit 2 Fire Shutdown Panel C10, Rev. 3

25203-31148, Sh. 3, Unit 2 Process Instruments Level Transmitters Connection Diag., Rev. 7

25203-32020, Sh. 27, Unit 2 ADV PV4224 Schematic, Rev. 1

25203-32020, Sh. 61, Unit 2 ADV Quick Open Control Schematic, Rev. 6

25203-32021, Sh. 5, Unit 2 Cable Vault Recirculating Fan MF19 Schematic, Rev. 4

25203-32023, Sh. 33, Unit 2 Cable Vault Fan MF123 Schmidt, Rev. 8

25203-32041, Sh. 3, Unit 2 Diesel Generator 15G-12U Engine Control, Rev. 12

25203-32041, Sh. 4, Unit 2 Diesel Generator 15G-12U Engine Control, Rev. 10

25203-32041, Sh. 5, Unit 2 Diesel Generator 15G-12U Engine Control, Rev. 6

25203-32041, Sh. 6, Unit 2 Diesel Generator 15G-12U Engine Control, Rev. 8

25203-32041, Sh. 7, Unit 2 Diesel Generator 15G-12U Engine Control, Rev. 8

25203-32041, Sh. 8, Unit 2 Diesel Generator 15G-12U Engine Control, Rev. 2

25203-32041, Sh. 9, Unit 2 Diesel Generator 15G-12U Engine Control, Rev. 6

25203-32041, Sh. 10, Unit 2 Diesel Generator 15G-12U Engine Control, Rev. 7

25203-32041, Sh. 11, Unit 2 Diesel Generator 15G-12U Engine Control, Rev. 10

25203-32041, Sh. 12, Unit 2 Diesel Generator 15G-12U Engine Control, Rev. 6

25203-32041, Sh. 13, Unit 2 Diesel Generator 15G-12U Engine Control, Rev. 10

25203-34060, Unit 2 Conduit Plan Fire Detail, Aux Bldg Elev. minus 14 ft., Rev. 7

25203-37076, Sh. 1, Unit 2 Instrumentation System Cable Routing, Rev. 1

25203-37076, Sh. 4, Unit 2 Instrumentation System Cable Routing, Rev. 1

25203-39212, Sh. 1, Unit 2 "A" EDG Panel C26H Connection Diagram, Rev. 2

25203-39212, Sh. 2, Unit 2 "B" EDG Panel C26G Connection Diagram, Rev. 2

25212-30343, Sh. 70, Unit 3 PZR 3RCS*TK1 Pressure Indication Test Loop Diag., Rev. 6

25212-30343, Sh. 75A, Unit 3 PZR Level Alarm, Indication, and Control Test Loop Diag., Rev. 4

25212-30343, Sh. 75B, Unit 3 PZR Level Alarm, Indication, and Control Test Loop Diag., Rev. 4

25212-30343, Sh. 75C, Unit 3 PZR Level Alarm, Indication, and Control Test Loop Diag., Rev. 3

25212-30343, Sh. 75D, Unit 3 PZR Level Alarm, Indication, and Control Test Loop Diag., Rev. 3

25212-30343, Sh. 75E, Unit 3 PZR Level Alarm, Indication, and Control Test Loop Diag., Rev. 1

25212-30343, Sh. 75F, Unit 3 PZR Level Alarm, Indication, and Control Test Loop Diag., Rev. 1

25212-30343, Sh. 75G, Unit 3 PZR Level Alarm, Indication, and Control Test Loop Diag., Rev. 3

25212-30343, Sh. 75H, Unit 3 PZR Level Alarm, Indication, and Control Test Loop Diag., Rev. 1

25212-30343, Sh. 76, Unit 3 PZR Level Indication Test Loop Diag., Rev. 6

25212-32001, Sh. 6AJS, Unit 3 Charging Header Isolation Valve Elementary Diag., Rev. 12

25212-32001, Sh. 60T, Unit 3 RHR Inlet Isolation Valve 3RHS*MV8701A Elementary, Rev. 17

25212-32001, Sh. 6TD, Unit 3 PZR Relief Isolation Valve 3RCS*MV8000A Elementary, Rev. 20

25212-32001, Sh. 8KC, Unit 3 EDG A Start Circuit 3EGSA01 3EGS*EG-A, Rev. 12

25212-32001, Sh. 8KD, Unit 3 EDG A Stop Circuit 3EGSA03 3EGS*EG-A, Rev. 15

25212-32001, Sh. 8KE, Unit 3 EDG A Governor Control Circuit 3EGSA05 3EGS*EG-A, Rev. 14

25212-32001, Sh. 8KJ, Unit 3 EDG A Shutdown Circuit 3EGSA06 3EGS*EG-A, Rev. 12

25212-32404, Unit 3 PZR Relief Isolation Valve 3RCS*MV8000A Cable Block Diag., Rev. 9

25212-32414, Unit 3 Charging Header Isolation Valve 3CHS*MV8438C Cable Diag., Rev. 3

25212-32449, Unit 3 RHS Inlet Isolation Valve 3RHS*MV8701A Cable Block Diagram, Rev. 6

25212-32722, Unit 3 EDG Excitation 3EGS*~G-A Cable Block Diag., Rev. 4

25212-32722, Unit 3 EDG 3EGS*EG-A Start Circuit Cable Block Diag., Rev. 3

25212-32722, Unit 3 EDG 3EGS*EG-A Engine Control Cable Block Diag., Rev. 6

25212-32722, Unit 3 EDG Governor ControI3EGS*EG-A Cable Block Diag., Rev. 5

25212-32722, Unit 3 EDG 3EGS*EG-A Engine Shutdown Cable Block Diag., Rev. 2

Attachment

A-5

25212-34032, Sh. 2, Unit 3 Conduit Plan Containment Structure Elev. 51 ft., Rev. 12

25212-34035, Unit 3 Conduit Plan Containment Structure Elev. 3 ft, Rev. 14

25212-34042, Unit 3 Containment Outer Annulus Elevation Safe Shutdown Review, Rev. 1

25212-34085, Unit 3 Conduit Plan, Auxiliary Building Elev. 24 ft., Rev. 17

K-13942, Actuator Fail in Last Position for 2-SW-3.1 AlB, 2-SW-3.2A1B, 2-SW-97 AlB, Rev. 3

Piping and Instrumentation Diagrams

25203-26027, Sh. 1, EDG HVAC, Rev. 47

25205-25003, Fire Loop operating & Hydraulic Schematic, Rev. 9

25203-26002, Sh. 1, Unit 2 Main Steam System, Rev. 73

25203-26005, Sh. 3, Unit 2 Condensate Storage & Auxiliary Feedwater System, Rev. 57

25203-26008, Sh. 2, Unit 2 Service Water, Rev. 94

25203-26011, Sh. 1, Unit 2 Fire Protection System, Rev. 52

25203-26011, Sh. 4, Unit 2 Halon & Exciter C02 Fire Protection, Rev. 6

25203-26011, Sh. 5, Unit 2 Fire Protection Auto Sprinkler Valve Details, Rev. 8

25203-26011, Sh. 7, Unit 2 Fire Protection Auto Sprinkler Valve Details, Rev. 1

25203-26017, Sh. 1, Unit 2, Charging System, Rev. 60

25203-26027, Sh. 1, Unit 2 HVAC for EDG Rooms, Rev. 47

25212-24036, Unit 3 Fire Stop & Seals Map Locations, Rev. 0

25212-26902, Sh. 3, Unit 3 Reactor Coolant System, Rev. 23

25212-26904, Sh. 1, Unit 3 Chemical and Volume Control, Rev. 50

25212-26912, Sh. 1, Unit 3 Low Pressure Safety Injection, Rev. 48

'25212-26946, Sh. 1, Unit 3 Fire Protection, Rev. 29

25212-26946, Sh. 2, Unit 3 Fire Protection, Rev. 49

25212-26946, Sh. 3, Unit 3 Fire Protection, Rev. 21

25212-26946, Sh. 4, Unit 3 Fire Protection, Rev. 25

25212-26946, Sh. 5, Unit 3 Fire Protection System Details, Rev. 2

25212-26951, Sh. 2, Unit 3 Control Building Heating, Ventilation and Air Conditioning, Rev. 20

25212-26951, Sh. 3, Unit 3 Control Building Heating, Ventilation and Air Conditioning, Rev. 0

Modifications and Fire Protection Engineering Evaluations

DCR-M3-08024, Unit 3 Main Transformer Fire Detection and Deluge Building, Rev. 0

DM2-00-0073, Roof Hatch Se~1 Installation in Fire Area T-6, Rev. 10

DM2-00-0343, Replace 24-inch Service Water Cross Connect Valve 2-SW-97 A, Rev. 8

DM3-00-0045-09, Charging Valve Control Circuit Appendix R Modification, Rev. 1

DMG-00-0280, Fire Penetration Seal Installation in Fire Areas T-6 and T-10, Rev. 9

DMG-00-0015-09, Power Supply Changes and Lighting Control, Rev. 0

Transient Combustible Evaluations

24991-04-FP

26660-07 -FP

26675-07 -FP

26676-07 -FP

26756-07 -FP

27077 -08-FP

28018-09-FP

37167 -07 -FP

37175-07-FP

37178-07-FP

37191-07-FP

37195-07 -FP

37981-08-FP

Attachment

A-6

Hot Work Permits

26656-07 -IS

26657 -07 -IS

26870-07 -IS

27655-09-IS

37262-07 -IS

37262-07 -IS

37402-07 -IS

37626-07 -IS

37672-07 -IS

38350-08-IS

38351-08-IS

38461-08-IS

39454-10-IS

System Health Reports

Unit 3, 4.16KV, 1 st Quarter 2010

Unit 3, Load Centers, 1st Quarter 2010

Unit 3, Motor Control Centers, 1 st Quarter 2010

Unit Common, Safe Shutdown Lighting - Category B, 1 st Quarter 2010

Procedures

C MP 790, Emergency Lighting Inspection and Testing, Rev. 3

C OP 200.17, Fire Watch and Impairment Tracking, Rev. 0

C SP 600.8, Diesel Fire Pump M7-7 Monthly Operability Demonstration, Rev. 3

C SP 600.9, Diesel Fire Pump M7-7 Annual Operability Demonstration, Rev. 4

C SP 600.6, Electric Fire Pump M7-8 Monthly Operability Demonstration, Rev. 3

C SP 600.7, Electric Fire Pump M7-8 Annual Operability Demonstration, Rev. 4

C SP 600.13, Electric Fire Pump P-82 Monthly Operability Demonstration, Rev. 2

C SP 600.14, Electric Fire Pump P-82 Annual Operability Demonstration, Rev. 2

C SP 600.16, Fire Protection System Underground Main Flush & Flow Test, Rev. 0

CY-AA-AUX-310, Diesel Fuel Oil Sampling and Testing, Rev. 3

SAIC 2.4, Fire PRA Cable Selection, Routing, Circuit Analysis, Rev. 0

SAIC 4.1, Identification and Evaluation of Multiple Spurious Operations of Equipment Using

Expert Panel, Rev. 0

SAIC 4.2, Draft SECY 08-0093 Analysis Process, Rev. 0

SFP 31, Fire Water System Back-up Supply Plan, Rev. 4

SP 2618C, Fire Protection System Smoke and Heat Detector Test, Rev. 13

SP 2618D, "B" EDG Deluge System Function Test, Rev. 0

SP 2669A, PEO Rounds, Rev. 17

SP 3442A02, RCS Wide Range Temperature Calibration, Rev. 6

SP 3446C20, Appendix R Instrumentation Calibration, Rev. 0

SP 3641 D.5, Fire Damper Operability Verification, Rev. 10

SP 3646A.1, EDG A Operability Test, Rev. 18

Operations Procedures

AOP 2559, Fire, Rev. 7

AOP 2571, Inadvertent ESFAS Actuation, Rev. 5

AOP 2579A, Hot Standby for Fire Area R-1, Rev. 9

AOP 2579B, Hot Standby for Fire Area R-2, Rev. 6

AOP 2579H, Hot Standby for Fire Area R-8, Rev. 6

AOP 2579L, Hot Standby for Fire Area R-13, Rev. 6

AOP 2579AA, Cooldown and Cold Shutdown for Fire Area R-1, Rev. 4

Attachment

A-7

AOP 2579BB, Cooldown and Cold Shutdown for Fire Area R-2, Rev. 5

AOP 2579FF, Cooldown and Cold Shutdown for Fire Areas R-8 and R-10, Rev. 5

AOP 2579LL, Cooldown and Cold Shutdown for Fire Area R-13, Rev. 5

EOP 2525, Standard Post Trip Actions, Rev. 23

EOP 2541, App-41, Aligning Compensatory Cooling for Switchgear Rooms, Rev. 1

EOP 3509, Fire Emergency, Rev. 24

EOP 3509.1, Control Room, Cable Spreading Area, or Instrument Rack Room Fire, Rev. 13

EOP 3509.2, Aux Bldg. Elev. 24 ft. South Floor, Elev. 43 ft. & 66 ft. Fire, Rev. 4

EOP 3509.5, Aux Bldg, East MCC & Rod Control Area Fire, Rev. 2

EOP 3509.5, EOP 3509.5 Basis Information, Rev. 2

EOP 3509.8, Control Bldg. Elev. 4 ft., West SWGR Area Fire, Rev. 3

EOP 35 GA-14, Establish Head Vent Letdown, Rev. 0

MP-14-0PS-GDL400, Operations Administrative Procedures, Rev. 9

MP-26-EPI-FAP06-002, Unit 2 Emergency Action Levels (EALs), Rev. 6

MP-26-EPA-REF02, Unit 2 EAL Technical Basis Document, Rev. 15

OP-AA-100, Conduct of Operations, Rev. 9

OP-AA-102, Operability Determination, Rev. 5

OP 2315K, Vital 480V Electrical Switchgear Room Cooling Systems, Rev. 1

OP 2315L, Vital 125V DC Electrical Switchgear Room Cooling Systems, Rev. 1

SP3670.1-009, Primary Plant Equipment Rounds, Rev. 6

SP3670.1-014, Radwaste Plant Equipment Rounds, Rev. 8

Cold Shutdown Repair Procedures

MP 2720U1, Cold Shutdown Fire Damage Repair for Fire Area R-1, Rev. 4

MP 2720U2, Cold Shutdown Fire Damage Repair for Fire Area R-3, Rev. 4

MP 2720U3, Cold Shutdown Fire Damage Repair for Fire Area R-11, Rev. 4

MP 2720U4, Cold Shutdown Fire Damage Repair for Fire Area R-16, Rev. 4

MP 2720U5, Splicing Fire-Damaged Power Cables and Connecting Pump Motors Needed for

Cold Shutdown, Rev. 3

MP 3783EA, Component Cooling Pump Motor Replacement for Fire Protection, Rev. 5

EOP 3509.1 Attachment-I, BAT "A" Level Instrument installation, Rev. 13

Operator Safe Shutdown Training

C01216N, Auxiliary Shutdown Panel Operations, Rev. 0

C01217C, PEO Briefing S01306C, Fire Emergency! Control Room Evacuation, Rev. 0

C04602L, Operating Experience PowerPoint Presentation, Rev. 0

C98205L, Fire Safe Shutdown Overview, Rev. 0

C98027L, EOP 3509.1 In-Plant Walkdown, Rev. 1

C9888206L, EOP 3509.1 Procedure Overview, Rev. 0

E09809C, Chapter 0, Fire Emergency, Rev. 2

FPS086C, Chapter 2, Fire Protection, Detection and Control, Rev. 4

JIT-302-002, Just In Time Training for DCR M3-01008, Rev. 0

JIT-304-001, Chapter 2, Just In Time Training for DCRs M3-02006 & 01008, Rev. 0

JPM-052, Manual Operation of a 4160 Volt Breaker, Rev. 3

JPM-088, Commence Shutdown from Outside the Control Room, Rev. 3

JPM-092, Transfer Controls from the Control Room to C-10, Rev. 5

Attachment

A-8

JPM-093, Local Manual Operation of the "A" Atmospheric Dump Valve, Rev. 9

JPM-141, Removellnstall opening and Closing Coils for 480V MCC Breaker, Rev. 1

JPM-206, Shutdown from Outside the Control Room (Alt. Path), Rev. 2

JPM-207, Local Manual Operation of the "A" Atmospheric Dump Valve, Rev. 1

JPM-217, Manual Operation of RBCCW SDC HX Outlet Valves, Rev. 2

P07602N, PEO In-Plant Walkdown, Cycle 07-6, Rev. 0

P08101JPM, Cycle 08-1 LORT/NLCT In-Plant JPMs, Rev. 0

P09101JPM, In-Plant JPMs, Rev. 0

PEO-04-J, Plant Equipment Operator On-the-Job Training, Rev. 6

S01306C, Simulator Scenario 6, Fire Emergency, Control Room Evacuation, Rev. 1

S03702L, Simulator Scenario 2, Fire Emergency, Control Room Evacuation, Rev. 0

S04405L, Cycle 04-4 Simulator Session 5, Rev. 0

S05105, Cycle 05-1 Simulator Session 5, Rev. 0

S05206L, Cycle 05-2 Simulator Session 6, Rev. 0

S05405L, CTMT Fire and Loss of Shutdown Cooling andlor RCS Inventory, Rev. 0

S05501 L, Cycle 05-5 Simulator Session 1, Rev. 0

S07405L, Cycle 07-4 Simulator Session 5, Rev. 0

S98202L, Cycle 98-2 Simulator Session 2, Rev. 0

S99306L, Simulator Scenario 6, Fire Emergency, Control Room Evacuation, Rev. 0

Fire Fighting Strategies (Le., Pre-Fire Plans)

Unit 2 Zone A-16, "B" EDG Room, 4/30105

Unit 2 Zone T-6, West 480 Volt Load Center Room, 4/01/01

Unit 2 Zone A-1B, Auxiliary Bldg RBCCW & Heat Exchanger Area, 4/01/01

Unit 2 Zone T-10, Turbine Bldg 6.9 and 4.16 kV Switchgear Room, 4/01/01

Unit 3 Zone AB-5, East MCC and Rod Control Area, March 1998

Unit 3 Zone CB-1, West Switchgear Room, January 2002

Unit 3 Zone CB-7, East Switchgear Room, March 1998

Unit 3 Zone CB-8, Cable Spreading Area, April 2004

Fire Brigade Training, Drills, and Drill Critiques

TPD-7.209, Fire Protection Programs, Rev. 1

Unannounced Drills:

Site Bldg 428, 12/23/08

Unit 3 Turb. Bldg Enclosure, 3/16/09

Unit 2 Turbine Bearing, 5/14/09

Unit 1 14H Bus, 9/13/09

Unit 3 Cable Spreading Area, 12/03/09

Unit 2 4160 Switchgear, 12/27109

Unit 3 East Elect. Rm Batt. Charger, 9111/08

Unit 2 Turb. Deck Wooded Bldg, 12/12/08

Unit 3 Cable Spreading Room, 12/16/08

Unit 2 Control Room AlC Area, 6128108

Unit 2 DC SWGR "A" MG set, 9/14/07 .

Unit 3 Fuel Pool Cooling Pumps, 10/10107

Unit 2 Turbine Aux Battery Room, 11/07107

Bldg 434 - Site Warehouse, 11/09/07

Unit 3 EDG, 12/12/07

Attachment

Announced Drills:

Unit 2 "B" Main Transformers, 6/10/08

Unit 2 "A" EDG, 7/15/08

Unit 2 "B" EDG, 7/24/08

Completed Tests and Surveillances

A-9

Unit 2 "B" EDG, 7/29/08

Unit 2 "A" EDG, 8/05/08

Unit 2 "A" EDG, 8/12/08

C SP 600.6, Electric Fire Pump M7-8 Monthly Operability Demo, Performed 5/16/10 & 6/15/10

C SP 600.7, Electric Fire Pump M7-8 Annual Operability Demo, Performed 5/14/09 & 6/15/10

C SP 600.8, Diesel Fire Pump M7-7 Monthly Operability Demo, Performed 5/19/10 & 6/17/10

C SP 600.9, Diesel Fire Pump M7-7 Annual Operability Demo, Performed 9/12/08 & 5/26/09

C SP 600.10, Diesel Fire Pump Fuel Oil Storage Tank Sample Results, Performed 2/16/10 &

4/27/10

C SP 600.13, Electric Fire Pump P-82 Monthly Operability Demo, Performed 5/26/10 & 6/24/10

C SP 600.14, Electric Fire Pump P-82 Annual Operability Demo, Performed 4/28/09 & 4/01/10

C SP 600.26-002, Appendix R Ventilation Fan Operational Check, Performed 3/6/10

C SP 600.26-001, Auxiliary Building Safe Shutdown Portable Emergency Ventilation Fan

MTE 1122, MTE-00613 Calibration, Performed 5/2/08

MTE 1122, MTE-00666 Calibration, Performed 10/2/08

SP 2601 M-01, Operability Test of Facility 2 Charging Pumps from C-10, Performed 3/4/10

SP 2601 P, CVS Valve Operability Tests from C-10 and C-02, Performed 10/16/09

SP 2610BO-05, TDAFW Operational Tests from C-10, Performed 3/28/09

SP 261 OE, Atmospheric Dump Valve Testing from C-10, C-70AlB, Performed 10/11/09

SP 2610E-03, Atmospheric Dump Valve Testing, Performed 11/18/04

SP 2618C-01, Unit 2 Fire Protection System Smoke & Heat Detector Test, Performed 9/27/09

SP 2618D-03, Unit 2 "B" EDG Deluge System Function Test, Performed 6/03/10 & 12/07/09

SP 2618G, Fire Damper Operability Verification, Performed 7/25/09,12/09/08,11/28/08, &

10/27/08

SP 2618L-01, Fire Protection Coating Inspection, Performed 1/27/09 & 9/09/08

SP 2618L-02, TSI (Thermo-Lag) Fire Wrap Inspection, Performed 1/29/10

SP 2619C-01, Control Room Weekly Checks, Performed 8/1/10

SP 2619E-01, Control Room Monthly Checks, Performed 7/10/10

SP 3641 D.5, Fire Damper Operability Verification, Performed 8/25/08, 9/4/09, & 9/26/06

SP 3641 D.6, Fire Rated Assemblies Inspection, Performed 11/29/08

SP 3646A.1, Local Operation Test of "A" EDG, Performed 8/16/05 & 5/20/08

SP 3673.2-02, Transfer Switch 3HVP*FN1A & FN1C Function Test, Performed 12/30/08

SP 3673.2-03, Transfer Switch 3HVR*FN14A Function Test, Performed 10/13/08

SP 3673.2-04, Transfer Switch 3HVR*MOD50A Function Test, Performed 10/8/08

SP 3673.2-05, Transfer Switch 3HVR*ACU1A Function Test, Performed 8/14/08

SP 3673.2-06, Transfer Switch 3HVY*FN2A & AOD23A Function Test, Performed 10/1/08

SP 3673.2-07, Transfer Switch 3SWP*MOV54A1C Function Test, Performed 11/24/09

SP 3673.2-08, Transfer Switch 3SWP*MOV71A Function Test, Performed 12/29/08

SP 3673.2-09, Transfer Switch 3SWP*MOV102A1C Function Test, Performed 12/28/08

SP 3673.2-10, Transfer Switch 3RCS*PCV455A Function Test, Performed 5/8/10

SP 3673.2-11, Transfer Switch 3RCS*HCV442A Function Test, Performed 12/4/07

SP 3673.2-12, Transfer Switch 3SIL*HCV943A Function Test, Performed 6/14/08

SP 3673.2-13, Transfer Switch 3CHS*HCV190A Function Test, Performed 5/13/08

Attachment

A-10

SP 3673.4-02, Aux. Shutdown Panel Operability Test RHR Isolation, Performed 4/22/10

SP 3673.4-10, Aux. Shutdown Panel Operability Test, Charging Header MOVS, Performed

1/21/09

SP 3673.4-11, Aux. Shutdown Panel Operability Test, PORV Block Valve, Performed 6/14/08

SP 3673.4-12, Aux. Shutdown Panel Operability Test, SIL Accumulator Vent Valves, Performed

8/9/08

SP 3673.4-13, Aux. Shutdown Panel Operability Test, Charging Pump Cooling Pump A,

Performed 1/20109

SP 3673.4-21, Aux. Shutdown Panel Operability Test, Charging Isolation Path, Performed

4/30/10

.

SP 3673.5-01, Remote Shutdown Monitoring Instrumentation, Performed 5/28/10

SFP 17-01, Unit 2 Group-1 Fire Penetration Seal Inspection, Performed 3/11/04 & 6/24/98

SFP 17-02, Unit 2 Group-2 Fire Penetration Seal Inspection, Performed 7/12/05, 7/11/05, &

9/24/98

SFP 17-04, Unit 2 Group-4 Fire Penetration Seal Inspection, Performed 12/05/06

SFP 17-09, Unit 2 Group-9 Fire Penetration Seal Inspection, Performed 4/18/01 & 1/17/00

SFP 6, Fire Protection System Underground Main Flow and Flush Test, Performed 9/26/03

SFP 6, Fire Protection System Underground Main Flow and Flush Test, Performed 2/22/07

SFP 21-01, Unit 2 Appendix R Fire Cage Inventory, Performed 9/4/09

SPROC 97-3-15, Unit 3 Emergency Lighting Test, Performed 12/5/97

T3341CP, Unit 3 Initial C02 Discharge Test, West Switchgear Room, Performed 11/06/85

T3341CP, Unit 3 Initial C02 Discharge Test, Cable Spreading Room, Performed 11/08/85

T3341CP, Unit 3 Initial C02 Discharge Test, East MCC/Rod Control Area, Performed 11116/85

Condition Reports (* denotes NRC identified during this inspection)

CR-03-00383

CR-03-00448

CR-05-08134

CR-05-08437

CR-06-01133

CR-06-02202

CR-06-03953

CR-07 -08455

CR-07-11917

CR-07-12142

CR-08-01677

CR-08-02674

CR-08-05317

CR-08-05851

CR-08-06786

CR-08-08323.

CR-08-08741

CR108620

CR109594

CR119114

CR119611

CR119667

CR119726

CR121019

CR121147

CR137203

CR316336

CR317567

CR320599

CR323868

CR327233

CR327631

CR331 009

CR332133

CR332754

CR334825

CR336063

CR337602

CR340225

CR343586

CR344375

CR348684

CR358414

CR377915

CR378579

CR378689

CR378691

CR378695

CR378699

CR378936

CR378939

CR378940

CR378941

CR378944

CR378945

CR378950

CR378951

CR378954

CR380609

CR382675

CR382835

CR382866

CR382968

CR382979

CR383130

CR383152

CR383154

CR383205

CR383276

CR383304

CR383357

CR383363

CR383687

CR383841

CR384105

CR384243

CR384258

CR384311

CR384372

CR384384

CR384443

CR384805

CR385501*

CR385687*

CR387120*

CR387186*

CR387227*

CR387870

Attachment

CR388484*

CR388508*

CR388646*

CR388756*

CR388775

Work Orders

53130710605

53102310955

53102200513

53102269887

53102269887

Vendor Manuals

CR388786*

CR388788*

CR388807

CR388969

CR389332

53102270437

53102274953

53102276397

53102291903

53102292975

A-11

CR389495

CR389590

CR389660

CR389736

CR389876*

53102304691

M2-04-12928

M3-02-11954

M3-04-17886

M3-05-11850

8M-1-70, Instructions for Fisher Actuators Types 4960, 496U, and 486L

MS2 Vendor Inspection Report for UPS System, dated 1/4/10 and 4/14/10

Industry Standards

CR389972

CR390069*

CR390295*

M2-98-01891

M3-05-14068

M3-06-08987

M3-06-00018

M2-07-02847

M3-07-03861

Electric Power Research Institute (EPRI) TR-100249, Emergency Battery Lighting Unit

Maintenance and Application Guide, Rev. 1

NEI 2000-01, Guidance for Post-Fire Safe Shutdown Circuit Analysis, Rev. 2

NFPA 13-1987, Installation of Sprinkler Systems

NFPA 27-1975, Private Fire Brigades

NRC RG 1.189, Fire Protection for Nuclear Power Plants, Rev. 2

NRC EGM 2007-004, Enforcement Discretion for Post-Fire Manual Actions Used as

Compensatory Measures for Fire induced Circuit Failures, 6/30107

NRC EGM 2009-002, Enforcement Discretion for Fire Induced Circuit Faults, 5/14/09

Miscellaneous Documents

Cable database printouts of cable routing for Valve 2-CH-429 in Fire Areas R1, R2 and R3

Cable database printouts of cable routing for Valve 2-MS-190B in Fire Areas R 1, R2 R 10

and R11

Calculation S-02824-S2, Millstone Unit 2, R-2 Fire, Appendix R Analysis, Rev. 2

Example of auxiliary building plant equipment operator rounds

Industry Position Paper on Use of Compensatory Measures for Multiple Spurious Operations,

4/16/2010

Letter B17399, 10CFR50, Appendix R Exemptions and Fire Protection Safety Evaluation Report

Comments, 3/17/1999

List of Millstone Power Station, Unit 2, expert panel members

Maintenance Rule Functional Failures Database Report on ELU Failures, 12/23/01 to 7122110

Millstone Power Station, Unit 2, Draft MSO Evaluation List

Millstone Power Station, Unit 2, Final Safety Analysis Report, Section 9.10

Millstone Power Station, Unit 2, Technical Requirements Manual, Sections 3.7.10 and 7.1

MP-2009-246, App-R ELU Recurring PM Tasks, 8/04/10

Attachment

A-12

N-2005-2208-E1, Review of NRC IN 05-14, Loss of Seal Cooling to Reactor Coolant Pumps

NEI 00-01, Guidance for Post Fire Safe Shutdown Analysis, Rev. 2

OE31606, Burn Mark on Plastic Lens Degrades Halogen Emergency Light, 7/19/10

Part 9900 Technical Guidance - Operability Determinations & Functionality Assessments for

Resolution of Degraded or Nonconforming Conditions Adverse to Quality or Safety

Reasonable Assurance of Safety RAS000117, Rev. 0

Regulatory Guide 1.189, Fire Protection for Nuclear Power Plants, Rev. 2

Results of component cable routing on a fire area basis for Generic Multiple Spurious

Operation 9 (MSO 9), Reactor Coolant System Makeup Isolation; MSO 18, Multiple

PORVs; MSO 19, Multiple PORV Block Valves; and MSO 28, AUXiliary Feedwater Flow

Isolation"

Safety Evaluation Report, Revocation of Exemption from 10 CFR Part 50, Appendix R,

Sections III.G and III.L for Certain Fire Areas - Millstone Nuclear Power Station, Unit 2,

7/17/1990

Self Assessment SAR000506, Triennial Fire Protection Preparation Assessment, 6/9/2010

Site Fire Protection Impairment Tracking Report (Active), 7/01/10 to 7/10/10

SO-08-024, Unit 2 Operations Standing Order, 12/3/08

Status update slides related to fire induced circuit failureslmultiple spurious operations,

6/16/2010

Unit 2 Fire Protection Active Impairment List, 7/20/10

Unit 3 Fire Protection Active Impairment List, 7/19/10

AC

ADAMS

AFW

ASME

ASSS

BAT

BTP

CCW

CDF

CFR

CMEB

CO2

CR

EDG

EGM

ELU

FCU

FHA

FPP

FW

HRR

IMC

IP

LIST OF ACRONYMS

Alternating Current

[NRC] Agency-wide Documents Access and Management System

Auxiliary Feedwater System

American Society of Mechanical Engineers

Alternate Safe Shutdown System

Boric Acid Tank

[NRC] Branch Technical Position

Component Cooling Water

Core Damage Frequency

Code of Federal Regulations

[NRC] Chemical Engineering Branch

Carbon Dioxide

Condition Report

Emergency Diesel Generator

[NRC] Enforcement Guidance Memorandum

Emergency Lighting Units

Flow Control Valve

Fire Hazards Analysis

Fire Protection Program

Feedwater

Heat Release Rate

[NRC] Inspection Manual Chapter

[NRC] Inspection Procedure

Attachment

IPEEE

IR

kV

LOCA

MOV

MSO

NEI

NFPA

NCV

NOV

NRC

P&ID

PAR

PARS

PRA

PZR

RAS

RBCCW

RCP

RCS

RG

RIS

RWST

SDP

SER

SG

SSAR

SSC

SW

SWGR

TD

TI

TRM

UFSAR

URI

VCT

A-13

Individual Plant Evaluation of External Events

[NRC] Inspection Report

kilo-volts

Loss of Coolant Accident

Motor Operated Valve

Multiple Spurious Operation

Nuclear Energy Institute

National Fire Protection Association

Non-Cited Violation

Notice of Violation

Nuclear Regulatory Commission

Piping and Instrumentation Drawing

Publicly Available Records

[NRC] Publicly Available Records

Probabilistic Risk Assessment

Pressurizer

Reasonable Assurance of Safety

Reactor Building Closed Cooling Water

Reactor Coolant Pump

Reactor Coolant System

[NRC] Regulatory Guide

Regulatory Issue Summary

Refuel Water Storage Tank

[NRC] Significance Determination Process

[NRC] Safety Evaluation Report

Steam Generator

Safe Shutdown Analysis Report

Structures, Systems and Components

Service Water

Switchgear

Turbine Driven

Temporary Instruction

Technical Requirements Manual

Updated Final Safety Analysis Report

[NRC] Unresolved Item

Volume Control Tank

Attachment