Revised Review Schedule Regarding the Application from Florida Power Corporation for Renewal of the Operating License for Crystal River Unit 3 Nuclear Generating Plant
ML103070380
Person / Time
Site: Crystal River 
Issue date: 11/05/2010
From: David Wrona
License Renewal Projects Branch 2
To: Franke J
Crystal River, FL
Elaine Keegan (301) 415-8517
References
TAC ME0278
Download: ML103070380 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 5, 2010 Mr. Jon Franke, Vice President Crystal River Nuclear Plant (NA 1 B)

ATTN: Supervisor, Licensing & Regulatory Programs 15760 W. Power Line Street Crystal River, FL 34428-6708

SUBJECT:

REVISED REVIEW SCHEDULE REGARDING THE APPLICATION FROM FLORIDA POWER CORPORATION FOR RENEWAL OF THE OPERATING LICENSE FOR CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT (TAC NO. ME0278)

Dear Mr. Franke:

By letter dated December 16, 2008, the U.S. Nuclear Regulatory Commission (NRC or the staff) received the Florida Power Corporation application for renewal of Operating License No.

DPR-72 for Crystal River Unit 3 Nuclear Generating Plant (CR-3), in accordance with Title 10 of the Code of Federal Regulations Section 54.17. By letter dated May 22, 2009 (ADAMS Accession No. ML091200415), the staff issued a proposed schedule for the review of the CR-3 license renewal application.

By letter dated August 12,2010 (ADAMS Accession No. ML101460577), the NRC issued a revised schedule for the CR-3 license renewal application due to the ongoing analysis of the containment structure. The NRC has several ongoing license renewal reviews on similar schedules, and any delay in resolving technical issues in one project affects review schedules of other projects. Accordingly, the date for issuing the draft SEIS is being extended to January 21, 2011. The enclosed schedule contains the revised milestone dates. This change has been discussed with Mr. Mike Heath of your staff.

The extension on the environment review is not expected to adversely impact the schedule for a decision on license renewal. The final SEIS will be issued prior to the May 2011 meeting with the Advisory Committee on Reactor Safety.

J. Franke

- 2 If you have any questions, contact Ms. Elaine Keegan by telephone at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov, for the review of the CR-3 license renewal application.

Sincerely,

~r David J. Wrona, Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-302

Enclosure:

As stated cc w/encl: Distribution via Listserv

Crystal River Unit 3 Nuclear Generating Plant LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Milestones Schedule Actual Draft Supplemental Environmental Impact Statement (SEIS)

Issued 01/21/2011 EPA FRN Published - Availability 1Comment on draft SEIS 01/28/2011 Public Meeting - draft SEIS 02/16/2011 Safety Evaluation Report (SER) with Open Items - Issued 12/10/2010 End of draft SEIS Comment Period 03/14/2011 ACRS Subcommittee Meeting on SER with Open Items 01/12/2011 Final SEIS - Issued 04/08/2011 EPA FRN Published - Availability of Final SEIS 04/15/2011 SER -Issued 04/11/2011 ACRS Full Committee Meeting on SER 05/12/2011 Decision Director NRR - Approval (if no hearing) 07/15/2011 ENCLOSURE

  • .. ML103070380 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR NAME IKing EKeegan DWrona (LRegner for)

DATE 11/04/10 11/04/10 11/05/10

Letter to J. Franke from D. Wrona dated November 05,2010

SUBJECT:

REVISED REVIEW SCHEDULE REGARDING THE APPLICATION FROM FLORIDA POWER CORPORATION FOR RENEWAL OF THE OPERATING LICENSE FOR CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT (TAC NO. ME0278)

DISTRIBUTION:

HARDCOPY:

DLRRF E*MAll:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDraApla Resource RidsOgcMailCenter Resource EKeegan RKuntz AJones,OGC LLake, RII MSykes, RII TMorrissey, RII