Other: CNL-15-189, Decommissioning Funding Update, ML090700378, ML090770757, ML090770807, ML091250151, ML092470504, ML101740152, ML101740157, ML101820478, ML102110075, ML102290258, ML102360283, ML102600474, ML103160419, ML110260321, ML111010165, ML111250430, ML111890037, ML11291A095, ML12069A330, ML12073A391, ML12073A392, ML12073A393, ML12081A073, ML13044A113
|
MONTHYEARML0815601832008-05-29029 May 2008 Cable Issues Corrective Action Program for the Completion of WBN Unit 2 Project stage: Request ML0824207792008-08-29029 August 2008 Notice of Meeting with Tennessee Valley Authority to Discuss Hydrology Code Project stage: Request ML0830900462008-10-30030 October 2008 Preservice Inspection Program Plan and Request for Relief No. WBN-2/PDI-4 Project stage: Request ML0834402242008-12-0505 December 2008 Units 1 & 2 - TVAs Nuclear Quality Assurance Plan (TVA-NQA-PLN89-A) Project stage: Request ML0905707412009-02-28028 February 2009 NUREG-0847, Supp. 21, Safety Evaluation Report, Related to the Operation of Watts Bar Nuclear Plant, Unit 2 Project stage: Request ML0907003782009-03-0404 March 2009 Operating License Application Update Project stage: Other ML0907707572009-04-22022 April 2009 Notice of Receipt of Update to Application for Facility Operating License and Notice of Additional Opportunity for Hearing and Order Project stage: Other ML0907708072009-04-27027 April 2009 Federal Register Notice- Watts Bar Nuclear Plant, Unit 2 - Notice If Receipt of Update to Application for Facility Operating License and Notice of Additional Opportunity for Hearing Project stage: Other ML0912501512009-05-0808 May 2009 Public Notice of Receipt of Updated Application for Facility Operating License Project stage: Other ML0918900382009-07-21021 July 2009 Request for Additional Information Regarding Financial Information Related to Operating License Application Update Project stage: RAI ML0924705042009-08-26026 August 2009 Additional Information Regarding Financial Information Related to Operating License Application Update Project stage: Other ML1001204872009-11-12012 November 2009 Application for Special Nuclear Material License in Accordance with 10 CFR 70, Domestic Licensing of Special Nuclear Material Project stage: Request ML0932800342009-11-25025 November 2009 Notice of Forthcoming Meeting with Tennessee Valley Authority to Discuss the Proposed Utilization of Digital Instrumentation and Controls Platforms at Watts, Unit 2 and to Discuss the Content of TVAs 11/27/2009, Submittal Project stage: Request ML0935600192009-12-22022 December 2009 Summary of Meeting with Tennessee Valley Authority (TVA) Regarding Digital Instrumentation and Controls Review Project stage: Meeting ML1005506512009-12-31031 December 2009 WCAP-17035-NP, Revision 2, Watts Bar, Unit 2, Heatup and Cooldown Limit Curves for Normal Operation and PTLR Support Documentation Project stage: Request ML1001916842010-01-11011 January 2010 Final Safety Analysis Report, Amendment 97, Section 3 - Design of Structures, Components, Equipment, and Systems, Page 3.8.5-1 Through Page 3.11-9 Project stage: Request ML1002703512010-02-18018 February 2010 Request for Additional Information Regarding Physical Security Plan Project stage: RAI ML1006300192010-03-11011 March 2010 Request for Additional Information Regarding Radiological Emergency Response Plan Project stage: RAI ML1009700722010-04-0505 April 2010 Response to NRC Request for Additional Information Regarding Physical Security Plan Project stage: Response to RAI ML1012302482010-04-27027 April 2010 Staff Information Requests Resulting from NRC December 15, 2009, Meeting with TVA Regarding Digital Instrumentation and Controls Review and NRC Clarifications to the Requests Provided During February 18, 2010 Project stage: Meeting ML1013406982010-05-28028 May 2010 Supplement to Request for Additional Information Regarding Radiological Emergency Response Plan (Tac No. ME0853) Project stage: RAI ML1015504882010-06-11011 June 2010 Request for Additional Information Regarding Fire Protection Program Project stage: RAI ML1015404772010-06-15015 June 2010 Review of Radiological Emergency Response Plan Project stage: Approval ML1017401572010-06-24024 June 2010 Notice of Receipt of Update Antitrust Information and Opportunity for Public Comment Project stage: Other ML1017401522010-06-24024 June 2010 Letter, Notice of Receipt of Update Antitrust Information and Opportunity for Public Comment Project stage: Other ML1018204782010-07-0101 July 2010 Revised Notice of Receipt of Update Antitrust Information and Opportunity for Public Comment Project stage: Other ML1018904062010-07-13013 July 2010 Request for Additional Information Regarding Antitrust Review Project stage: RAI ML1019703112010-07-16016 July 2010 Request for Additional Information Regarding Fire Protection Program Project stage: Request ML1021100752010-07-29029 July 2010 Jcn No: 4201, (TAC No. ME0853) Q4011 Task Order Number 9, Tennessee Valley Authority, Watts Bar Unit 2. Evacuation Time Estimate (ETE) Review Project stage: Other ML1021600852010-07-29029 July 2010 Response to Request for Additional Information Regarding Antitrust Review Project stage: Response to RAI ML1022902582010-07-31031 July 2010 Final Safety Analysis Report - Response to Preliminary Requests for Additional Information and Requests for Additional Information Project stage: Other ML1023602832010-08-20020 August 2010 Fire Protection Program, Commitment to Provide Additional Information on Multiple Spurious Operation Scenarios Project stage: Other ML12081A0732010-08-20020 August 2010 Enclosure 1 (W/Apps a, B, & C): Watts Bar, Unit 2, Fire Protection Program, Commitment to Provide Additional Information on Multiple Spurious Operation Scenarios Project stage: Other ML1026004742010-09-17017 September 2010 Response to NRC Question Regarding Emergency Plan Project stage: Other ML1028502462010-10-11011 October 2010 Transition from American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code Section III Division I to Section XI Project stage: Request ML1031604192010-11-0505 November 2010 Watts, Unit 2, Fire Protection Program (TAC ME0853) - Commitment to Provide Multiple Spurious Operation (MSO) Evaluation Project stage: Other ML1102603212011-03-22022 March 2011 Notice of No Significant Antitrust Changes and Time for Filing Requests for Reevaluation Project stage: Other ML1109604072011-04-0101 April 2011 Response to Request for Additional Information on Final Safety Analysis Report Section 9.3.2.6 for the Post Accident Sampling System (PASS) Project stage: Response to RAI ML1109806372011-04-0606 April 2011 Safety Evaluation Report Supplement 22 - Response to NRC Required Action Items Project stage: Request ML1110101652011-04-13013 April 2011 Status of Operating License Application Review and Project Schedule Implications Project stage: Other ML1107000312011-04-15015 April 2011 Notice of Meeting with Tennessee Valley Authority to Discuss Responses to NRC Requests for Additional Information for Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accident at Pre Project stage: RAI ML1112604712011-05-0606 May 2011 Petitioners Motion for Modification of the Commissions April 19, 2011, Order to Permit a Consolidated Reply Project stage: Request ML11146A0442011-05-20020 May 2011 Response to Final Safety Analysis Report, Chapter 11 and Final Supplemental Environmental Impact Statement Request for Additional Information Project stage: Supplement ML1118900372011-07-20020 July 2011 Schedule of Licensing Activities Project stage: Other ML1112504302011-08-12012 August 2011 Transition of Components to American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI Project stage: Other ML1125900462011-09-21021 September 2011 Request for Additional Information Regarding Supplemental Safety Evaluation Report Open Item 80 Project stage: Approval ML11291A0952011-10-13013 October 2011 Instrumentation and Controls Staff Information Requests Project stage: Other ML1131204382011-11-18018 November 2011 Request for Additional Information Regarding Supplemental Evaluation Report Open Item 26 Project stage: RAI ML1131302182011-11-18018 November 2011 Request for Additional Information Regarding Supplemental Safety Evaluation Report Open Items 80, 81, 105, and 108 Project stage: Approval ML12069A3302012-01-19019 January 2012 Instrumentation and Controls Staff Information Requests Project stage: Other 2010-05-28
[Table View] |
Text
Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 October 11, 2010 10 CFR 50.55a U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391
Subject:
Watts Bar Nuclear Plant (WBN) Unit 2 - Transition from American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code Section III Division I to Section XI
References:
- 1. TVA letter to NRC, Watts Bar Nuclear Plant (WBN) Unit 2 - Request to Use American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Code Case N-520-2, Alternative Rules for Renewal of Active or Expired N-Type Certificates for Plants not in Active Construction,Section III, Division 1, dated February 1, 2008
- 2. NRC letter to TVA, "Watts Bar Nuclear Plant, Unit 2 - Request for Additional Information Regarding Renewal of Active or Expired N-Type Certificates for Plants not in Active Construction (TAC No. MD8314)," dated May 22, 2008
- 3. NRC letter to TVA, Watts Bar Nuclear Plant, Unit 2 - Request for Relief Regarding Alternative Rules for Renewal of Active or Expired N-Type Certificates (TAC No. MD8314), dated September 29, 2010
- 4. TVA letter to NRC, Watts Bar Nuclear Plant (WBN) Unit 1 -
Completion of Construction Activities and Submittal of the ASME N-3 Code Data Reports, dated December 8, 1995 The purpose of this submittal is to describe the planned WBN Unit 2 transition from ASME Boiler and Pressure Vessel Code Section III Division 1 to Section XI.
WBN Unit 2 is completing installation, nondestructive examination, inspection, and hydrostatic testing, N-5 Code Data Reports, and N-Stamping of ASME piping systems per ASME Division 1 Section III 1971 Edition through Summer 1973 Addenda and Code Case N-520-2 (References 1, 2, and 3).
U.S. Nuclear Regulatory Commission Page 2 October 11, 2010 Upon completion of system N-Stamping, the ASME Section III Owner, TVA Nuclear Generation Development and Construction (NGDC), will transfer jurisdiction of the ASME Section III Code piping system to TVA Nuclear Power Group (NPG), for control under their ASME Section XI Program, QA Program, TVA-NQA-PLN89-A, and related procedures.
Transfer of a system will occur upon verification that there are no remaining ASME Section III activities on a given system, the N-5 Data Report has been completed, and the N-Stamp(s) applied. All subsequent repair and replacement activities will be performed using the TVA NPG and WBN Unit 1 ASME Section XI Repair and Replacement Program procedures which comply with ASME Section XI 2001 Edition through 2003 Addenda. Refer to Interpretation III-1-83-61 in Enclosure 1. The Unit 2 ASME Section III N-3 Data Report for the entirety of Unit 2 Section III systems will be completed and submitted after all ASME Section III systems have been completed.
TVAs programmatic implementing procedures for these Section XI requirements are SPP-9.1, ASME Section XI, and TI-100.014, ASME Section XI Repairs and replacements. The ASME Section XI repair and replacement program has been used for WBN Unit 1 since TVA WBN Unit 1 issued the ASME N-3 Code Data Reports on December 8, 1995, per Reference 4. Repairs and replacements shall be performed and documented in accordance with the ASME Boiler and Pressure Vessel Code Section XI, Division 1, 2001 Edition through 2003 Addenda, Article IWX-4000, for the Repair and Replacement of Class 1, 2, and 3 and Class MC components.
This process will allow timely completion of ASME Section III activities on WBN Unit 2 support systems such as Essential Raw Cooling Water, Component Cooling Water, Service Air, and Spent Fuel Pool Cooling and Cleanup. These systems are currently governed by both ASME Section III (Unit 2 only portion) and ASME Section XI (Unit 1 and common portion) for modification, repair, and replacement and controlled by both TVA NGDC WBN Unit 2 and TVA NPG WBN Unit 1. Further, these support systems will be operated to support preoperational testing and turnover of other Unit 2 systems.
Following transfer of the Unit 2 portion of the system, all subsequent repair and replacement will be performed under the Unit 1 Section XI program.
The ASME Section XI Repair and Replacement program is currently being used to control modification, refurbishment, and repair of Unit 2 components that were installed under ASME Section III, and transitioned to ASME Section XI per Reference 4, but were not required for WBN Unit 1 operation.
ASME Section XI Repair and replacement shall be documented on Form NIS-2 and NIS-2A per IWA-6230, IWA-6240, or Code Case N-532-4. An Owners Summary Report shall be issued within 90 days following Unit 2 commercial operation for those repairs or replacements, if any, which were performed under Section XI on Unit 2 prior to commercial operation.
U.S. Nuclear Regulatory Commission Page 3 October 11,2010 The WBN Unit 2 Repair and Replacement Program Code of Record for WBN Unit 2 will be revised to conform with the ASME Section XI Code of Record for the first WBN Unit 2 Inservice Inspection Program 10-year Inspection Interval. identifies those actions committed to by TVA in this letter. If you have any questions, please contact William Crouch at (423) 365-2004.
Sincerely, t1.'13~*U:r~
Masoud B 'e tani Watts Ba it 2 Vice President
Enclosures:
1.
Code Interpretations 2.
List of Regulatory Commitments cc (Enclosures):
U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., N.E., Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381
E1-1 Code Interpretations Interpretation: III-1-83-61
Subject:
Jurisdiction of Section III, Division 1 and Section XI Requirements When Performing Repairs or Modifications Subsequent to N-Stamping, IWA-4000 Date Issued: January 26, 1983 File:
BC82-277 Question (1): Do the rules of Section III or Section XI apply to the repair or modification of a component, manufactured to Section III requirements, subsequent to its being N-Stamped but prior to the filing of the Form N-3 by the Owner?
Reply (1): The rules of either Section III or Section XI as determined by the Owner may be applied to the repair or modification of an N-Stamped component subsequent to stamping but prior to the filing of the Form N-3 by the Owner, or prior to start of plant operation where no N-3 Form has been filed.
Question (2): Who is authorized to perform these repairs or modifications?
Reply (2): For repairs performed to the rules of Section XI, the Owner or the Owner's designee may perform the repair or modification, provided the appropriate requirements of Section XI are met. When the use of Section III rules are selected as the basis for repairs or modification, only organizations holding appropriate Certificates of Authorization may certify that the work meets the requirements of Section III.
E2-1 List of Regulatory Commitments Tennessee Valley Authority Watts Bar Nuclear Plant - Unit 2, Docket No. 50-391 Commitment Committed Date An Owners Summary Report shall be issued within 90 days following Unit 2 commercial operation for those repairs or replacements, if any, which were performed under Section XI on Unit 2 prior to commercial operation.
90 days following Unit 2 commercial operation