ML102240384
ML102240384 | |
Person / Time | |
---|---|
Site: | Watts Bar |
Issue date: | 08/02/2010 |
From: | Webb W Nuclear Power Group |
To: | Office of Nuclear Reactor Regulation |
References | |
WB-DC-30-29 | |
Download: ML102240384 (59) | |
Text
ENCLOSURE2 WATTS BAR NUCLEAR PLANT (WBN) UNIT 2 - NRC MEETING HELD ON AUGUST 4,2010 - INSTRUMENTATION AND CONTROL -
REQUEST FOR ADDITIONAL INFORMATION Nuclear Power Group Calculation titled "Segmentation Analysis for WBN Unit 2 DCS (Distributed Control System)"
dated August 2, 2010, Revision 0
NPG CALCULATION COVERSHEETICCRIS. UPDATE Page 1 REV 0 EDMS/RIMS NO. EDMS TYPE: EDMS ACCESSION NO (N/A for REV. 0) calculations(nuclear)
Calc
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS CALC ID TYPE ORG PLANT BRANCH NUMBER CUR REV NEW REV CURRENT CN NUC REVISION APPLICABILITY NEW CN NUC WBN EEB DCSSEGMENT 000 Entire calc
______ ___________________Selected pages 0 No CCRIS Changes 0 ACTION NEW 0 DELETE 0 SUPERSEDE 01 CCRIS UPDATE ONLY - (For calc revision, CCRIS REVISION 0 RENAME 0 DUPLICATE I (Verifier Approval Signatures Not I been reviewed and no
___ _Required) CCRIS changes required)
UNITS SYSTEMS UNIDS 2 001 003 062 063 068 085 092 098 NA DCN.EDC.N/A APPLICABLE DESIGN DOCUMENT(S) NA CLAS IFICATION EDCR 54504 D QUALITY SAFETY RELATED? UNVERIFIED SPECIAL REQUIREMENTS DESIGN OUTPUT SARTS and/or ISFSI RELATED? (If yes, QR = yes) ASSUMPTION AND/OR LIMITING CONDITIONS? ATTACHMENT? SAR/CoC AFFECTED Yes 0 No 0 Yes[I No 0 Yes 0 No[I Yes 0 No[] YesO0 No 0 Yes 0 No,-0 PREPARERID PREPARER PHONE NO PREPARING ORG (BRANCHI VERIFICATION NEW METHOD OF ANALYSIS wdwebb 632-8245 EEB METHOD 0J Yes Ea No
- Design Verification PREPARER SIGNATURE W. D. Webb VERIFIER SIGNATURE 1 #i/4 ,
DATE j'7-2f-/D DATE CHECKER SIGNATURE J.T. Kepler APPROVAL SINT, RE
,,. L j 7/Zif/
DATE DATE J. T. Kepler " ho7-z STATEMENT OF PROBLEM/ABSTRACT The obsolete analog control systems for WBN unit 2 are being replaced with a Foxboro IA Distributed Control System (DCS) for control and monitoring of most non-safety related NSSS and BOP systems. The controls are distributed among 15 control groups, each with a redundant processor pair. For those control system functions which are important to plant operation, this analysis evaluates the distribution (segmentation) of the inputs/outputs among these control groups to confirm that no new failures are introduced which could adversely impact plant safety analyses. The analysis includes confirmation that the DCS configuration maintains the functional diversity.and independence of the original control systems design.
Based on this analysis, the design of the WBN unit 2 DCS does not introduce new control system failures which could adversely impact the safety analyses as described in the FSAR. Functional diversity and independence are provided for the critical control systems as required by the design basis and in a manner consistent with the original design.
MICROFICHE/EFICHE Yes [I No 0 FICHE NUMBER(S)
[0 LOAD INTO EDMS AND DESTROY Z LOAD INTO EDMS AND RETURN CALCULATION TO CALCULATION LIBRARY. ADDRESS:EQB 1M-WBN
[I LOAD INTO EDMS AND RETURN CALCULATION TO:
TVA 40532 [10-20081 Page I of 2 NEDP-2-1 [10-20-20081
NPG CALCULATION COVERSHEETICCRIS UPDATE Page 2 Cf-AI P In TVDPI ADt* IDI AhIm DAP M"&
IftA0 I D~1I I
%/r%lu */ iiJ I I I t9 I Lit EEB DCSSEGMENT 000 Page CN NUC WBN I Al TCOMATC O1Al 9111 ATIAMk 1nCLhi1'nIt'AVlfK BLDG ROOM ELEV COORD/AZIM.
NA FIRM Bechtel Print Report Yes NA NA NA CATEGORIES NA KEY NOUNS (A-add, D-delete)
ACTION KEY NOUN AID KEY NOUN (A/DQ DCS SEGMENT "
CONTROL ANALYSIS I_____ IFOXBORO II CROSS-REFERENCES (A-add, C-change, D-delete)
ACTION XREF XREF XREF XREF XREF XREF (A/C/D) CODE TYPE PLANT BRANCH NUMBER REV P DN WBN EEB EDCR 52378 P DC WBN MEB WB-DC-40-70 P DC WBN MEB WB-DC-40-58 P DG WBN EEB DG-E181.25 P SD WBN MEB WBN2-1-4002 P SD WBN MEB WBN2-3A-4002 P SD WBN MEB WBN2-6-4002 P SD WBN MEB WBN2-47-4002 P SD WBN MEB WBN2-62-4001 P SD WBN MEB WBN2-63-4001 P SD WBN MEB WBN2-68-4001 P SD WBN EEB WBN2-85-4003 P SD WBN EEB WBN2-92-4003 P SD WBN EEB WBN2-99-4003 P CN WBN MEB EPMFBN072892 CCRIS ONLY UPDATES:
Following are required only when making keyword/cross reference CCRIS updates and page 1 of form NEDP-2-1 is not included:
PREPARER SIGNATURE DATE CHECKER SIGNATURE DATE PREPARER PHONE NO. EDMS ACCESSION NO.
iVA 40532 [10-20081° Page 2 of 2 NEDP-2-1 [10-20-2008]
b 4
NPG CALCULATION COVERSHEETICCRIS UPDATE Page 2a CALC ID ITYPE ORG PLANT BRANCH NUMBER I'~ REV II S Page CN NUC I WBN EEB DCSSEGMENT 000 ALTERNATE CALCULATION IDENTIFICATION ND ROOM ELEV COORDIAZIM FIRM Print Report Yes NA NA NA NA Bechtel KEY NOUNS (A-add, D-delete)
ACTION KEY NOUN A/D KEY NOUN CROSS-REFERENCES (A-add, C-change, D-delete)
ACTION XREF XREF XREF XREF XREF XREF (A/C/D) CODE TYPE PLANT BRANCH NUMBER REV P VD WBN EEB 08F802403-FD-2004-1 P VD WBN EEB 08F802403-FD-2005-1 P VD WBN EEB 08F802403-FD-2006-1 P VD WBN EEB 08F802403-FD-2006-2 P VD WBN EEB 08F802403-FD-2006-4 P VD WBN EEB 08F802403-FD-2006-5 P VD WBN EEB 08F802403-FD-2012-1 P VD WBN EEB 08F802403-FD-2101-1 P VD WBN EEB 08F802403-FD-2101-4 P VD WBN EEB 08F802403-FD-2102-1 P VD WBN EEB 08F802403-FD-2103-1 P VD WBN EEB 08F802403-FD-2103-3 P VD WBN EEB 08F802403-FD-2104-1 P VD WBN EEB 08F802403-FD-2104-3 P VD WBN EEB 08F802403-FD-2105-1 P VD WBN EEB 08F802403-FD-2105-2 P VD WBN EEB 08F802403-FD-2105-4 P VD WBN EEB 08F802403-FD-2107-1 CCRIS ONLY UPDATES:
Following are required only when making keyord/cross reference CCRIS updates and page 1 of form NEDP-2-1 is not included:
PREPARER SIGNATURE DATE CHECKER SIGNATURE DATE PREPARER PHONE NO. EDMS ACCESSION NO.
TVA 40532 (10-2008] Page 2 of 2 NEDP-2-1 [10-20-2008]
NPG CALCULATION COVERSHEETICCRIS UPDATE Page 2b CALC ID I TYPE "
I "----------...
ORG I PLANT I ,,,--,----BRANCH I NUMBER I REV F--
EEB DCSSEGMENT 000 CN NUC I WBN I ALTERNATE CALCULATION IDENTIFICATION BLDG ROOM ELEV COORDIAZIM FIRM Bechtel PrintReport PitRb Yes 0 NA NA NA NA CATEGORIES NA KEY NOUNS (A-add, D-delete)
ACTION KEY NOUN AID KEY NOUN CROSS-REFERENCES (A-add, C-change, D-delete)
ACTION XREF XREF XREF XREF XREF XREF ia/CD .. CODE TYPE PLANT BRANCH ,NUMBER REV P VD WBN EEB 08F802403-FD-2107-2 P VD WBN EEB 08F802403-FD-2107-4 P VD WBN EEB 08F802403-FD-2109-1 P VD WBN EEB 08F802403-FD-2109-2 P VD WBN EEB 08F802403-FD-2110-1 P VD WBN EEB 08Fe02403-FD-2111-1 P VD WBN EEB 08F802403-FD-2111-2 P VD WBN EEB 08F802403-FD-2201-1 P VD WBN EEB 08F802403-FD-2202-1 P VD WBN EEB 08FS02403-FD-2203-1 P VD WBN EEB 08F802403-FD-2205-1 P VD WBN EEB 08F802403-FD-2205-2 P VD WBN EEB 08F802403-FD-2300-1 P VD WBN EEB 08F802403-FD-2300-6 P VD WBN :EEB 08F802403-FD-2301-1 P VD WBN EEB 08F802403-FD-2301-6 P VD WBN EEB 08F802403-FD-2302-1 P VD WBN EEB 08F802403-FD-2302-6 CCRIS ONLY UPDATES:
Following are required only when making keyword/cross reference CCRIS updates and page 1 of form NEDP-2-1 is not included:
PREPARER SIGNATURE DATE CHECKER SIGNATURE DATE PREPARER PHONE NO. EDMS ACCESSION NO.
TVA 40532 r10-20081 Page 2 of 2 NEDP-2-1 [10-20-2008]A
NPG CALCULATION COVERSHEET/CCRIS UPDATE PIage 2c CALC ID I I I=~a Nr-v Iý-
age NUC WBN EEB DCSSEGMENT 000 1 CN I ALTERNATE CALCULATION IDENTIFICATION BLDG ROOM ELEV COORD/AZIM F FIRM Print Report Yes NA NA NA NA Bechtel CATEGORIES NA KEY NOUNS (A-add, D-delete)
ACTION KEY NOUN ND KEY NOUN CROSS-REFERENCES (A-add, C-change, D-delete)
ACTION XREF XREF XREF XREF XREF XREF (A/CID) CODE TYPE PLANT BRANCH NUMBER REV P VD WBN EEB 08F802403-FD-2303-1 P VD WBN EEB 08F802403-FD-2303-6 P VD WBN EEB 08F802403-FD-2304-1 P VD WBN EEB 08F802403-FD-2304-3 P VD WBN EEB 08F802403-FD-2304-4 P VD WBN EEB 08F802403-FD-2304-8 P VD WBN EEB 08F802403-FD-2304-9 P VD WBN EEB 08F802403-FD-2304-10 P VD WBN EEB 08F802403-FD-2400-1 P VD WBN EEB 08F802403-FD-2400-3 P VD WBN EEB 08F802403-FD-2400-5 P VD WBN EEB 08F802403-FD-2400-6 P VD WBN EEB 08F802403-FD-2400-7 P VD WBN EEB 08F802403-FD-2401-1 P VD WBN EEB 08F802403-FD-2401-5 P VD WBN EEB 08F802403-FD-2401-6 P VD WBN EEB 08F802403-FD-2401-12 CCRIS ONLY UPDATES:
Following are required only when making keyword/cross reference CCRIS updates and page 1 of form NEDP-2-1 is not included:
PREPARER SIGNATURE DATE CHECKER SIGNATURE DATE PREPARER PHONE NO. EDMS ACCESSION NO.
TVA 40532 *[10-2008]o Page 2 of 2 NEDP-2-1 [10-20-20081
NPG CALCULATION COVERSHEETICCRIS UPDATE P age 2d
- r* ,Al1P itl II VDTVI 1PAhT K RPAIH MI IRPFR I FVI a6 "U6 I I ir& I
- age 000 CN A EEB RNUC C DCSSEGMENT I ALTERNATE CALCULATION IDENTIFICATION BLDG ROOM r ELEV COORD/AZIM FIRM Pnnt Report Yes NA NA- NA NA Bechtel CATEGORIES NA KEY NOUNS (A-add, D-delete)
ACTION KEY NOUN A/D KEY NOUN CROSS-REFERENCES (A-add, C-change, D-delete)
ACTION XREF XREF XREF XREF XREF XREF (NC/DI CODE TYPE PLANT BRANCH NUMBER REV P VD WBN EEB 08F802403-FD-2402-1 P VD WBN EEB 08F802403-FD-2402-3 P VD WBN EEB 08F802403-FD-2403-1 P VD WBN EEB 08F802403-FD-2403-3 P VD WBN EEB 08F802403-FD-2404-1
'P VD WBN EEB 08F802403-FD-2404-6 P VD WBN EEB 08F802403-FD-2404-8 P VD WBN EEB 08F802403-FD-2404-10 P VD WBN EEB 08F802403-FD-2501-1 P VD WBN EEB 08F802403-FD-2600-1 P VD WBN EEB 08F802403-FD-2601-1 P VD WBN EEB 08F802403-FD-2603-1 P VD WBN EEB 08F802403-FD-2603-2 P VD WBN EEB 08F802403-FD-2603-3 P VD WBN EEB 08F802403-FD-2604-1 P VD WBN EEB 08F802403-FD-2605-1 P VD WBN EEB 08F802403-FD-2607-1 CCRIS ONLY UPDATES:
Following are required only when making keyword/cross reference CCRIS updates and page 1 of form NEDP-2-1 is not included:
PREPARER SIGNATURE DATE CHECKER SIGNATURE DATE PREPARER PHONE NO. EDMS ACCESSION NO.
TVA 40532 [10-2008] Page 2 of 2 NEDP-2-1 [10-20-2008]
L . °
2e NPG CALCULATION COVERSHEETICCRIS UPDATE Page 2e trACl In Tvop It A*-( 0P1AT AMT AMC K1ilIMRID .1 F:V I ag a ;6 I -I Ia..__
age NUC I WBN EEB DCSSEGMENT 000 CN ALTERNATE CALCULATION IDENTIFICATION BLDG ROOM ELEV COORD/AZIM FIRM Bechtel print Report Yes NA NA NA NA CATEGORIES NA KEY NOUNS (A-add, D-delete)
CROSS-REFERENCES (A-add, C-change, D-delete)
ACTION XREF XREF XREF XREF XREF XREF (NC/D) CODE TYPE PLANT BRANCH NUMBER REV P VD WBN EEB 08F802403-FD-2608-1 P VD WBN EEB 08F802403-FD-2609-1 P VD WBN EEB 08F802403-FD-2616-1 P VD WBN EEB 08F802403-FD-2818-1 P VD WBN EEB 08F802403-FD-2908-1 P VD WBN EEB 08F802403-FD-2909-1 P VD WBN EEB 08F802403-FD-2910-1 P VD WBN EEB 2-65717-108D408-5 P VD WBN EEB 2-65717-1080408-6 P VD WBN EEB 108D408-23 P VD WBN EEB 108D408-24 P VD WBN EEB 1080408-25 P VD WBN EEB 108D408-26 P VD WBN EEB 1080408-27 P VD WBN EEB 108D408-28 P VD WBN EEB 108D408-31 P Vo WBN EEB 1081408-32 CCRIS ONLY UPDATES:
Following are required only when making keyword/cross reference CCRISupdates and page 1 of form NEDP-2-1 is not included:
PREPARER SIGNATURE DATE CHECKER SIGNATURE DATE PREPARER PHONE NO. EDMS ACCESSION NO.
TVA 40532 [10-20081 Page 2 of 2 NEDP-2-1 [10-20-2008]
NPG CALCULATION COVERSHEETICCRIS UPDATE P age 2f CALC ID I I
- I'*'I*
I I ll'<l ,'i I*'*~* I I I*II I I*I I,,4II I*
I IPage 000 IOTN .RITNUC ICWBN IOEEB IEDCSSEGMENT 1 000 1 ALTERNATE CALCULATION IDENTIFICATION, BLDG ROOM ELEV COORDIAZIM FIRM Print Report Yes [I NA NA NA NA Bechtel CATEGORIES NA KEY NOUNS (A-add, D-delete)
ACTION KEY NOUN A/D KEY NOUN CROSS-REFERENCES (A-add, C-change, D-delete)
ACTION XREF XREF XREF XREF XREF XREF (A/C/D) CODE TMPE PLANT BRANCH NUMBER REV P VD WBN EEB 1080408-33 P VD WBN EEB 2-65717-108D408-36 P VD WBN EEB 108D408-41 P VD WBN EEB 2-54114-1-5655D87-9 P VD WBN EEB 2-54114-1-5655D87-10 P VD WBN EEB 2-54114-1-5655D87-11 P VD WBN EEB 2-54114-1-5655D87-12 P VD WBN EEB 2-54114-1-5655D87-13 P VD WBN EEB 2-54114-1-5655D87-14 P DW WBN EEB 1-47W610-1-1 P DW WBN EEB 1-47W610-1-1A P DW WBN EEB 1-47W610-1-2 P DW WBN EEB 1-47W610-1-2A P DW WBN EEB 1-47W610-1-3 P DW WBN EEB 1-47W610-1-3A P DW WBN EEB 2-47W610-1-1 P DW WBN EEB 2-47W610-1-1A CCRIS ONLY UPDATES:
Following are required only when making keyword/cross reference CCRIS up dates and page I of form NEDP-2-1 is not included:
PREPARER SIGNATURE DATE CHECKER SIGNATURE DATE PREPARER PHONE NO. EDMS ACCESSION NO.
I V/A '4vu,1 L IU-/UUOJ r'age 2 of 2 INr-UP'--Z- I [ I U-zU-zuUoj
NPG CALCULATION COVERSHEETICCRIS UPDATE P age 2g UALIU in I iP- UI(U 01PA I DIIANUI-I NUMIFtK I KV I I I 000 age CN NUC WBN EEB UDONSSEGMENT ALTERNATE CALCULATION IDENTIFICATION BLDG ROOM ELEV COORDIAZIM FIRM Print Report Yes NA NA NA NA Bechtel CATEGORIES NA KEY NOUNS (A-add, D-delete)
ACTION KEY NOUN A/D KEY NOUN CROSS-REFERENCES (A-add, C-change, D-delete)
ACTION XREF XREF XREF XREF XREF XREF A/'C/D) CODE TYPE PLANT BRANCH NUMBER REV P DW WBN EEB 2-47W610-1-2 P DW WBN EEB 2-47W610-1-2A P DW WBN EEB 2-47W610-1-3 P DW WBN EEB 2-47W610-1-3A P DW WBN EEB 1-47W610-3-1 P DW WBN EEB 1-47W610-3-IA P DW WBN EEB 1-47W610-3-1B P DW WBN EEB 1-47W610-3-1C P DW WBN EEB 1-47W610-3-1D P DW WBN EEB 1-47W610-3-2 P DW WBN EEB 1-47W610-3-2A P DW WBN EEB 1-47W610-3-2B P DW WBN EEB 1-47W610-3-2C P DW WBN EEB 1-47W610-3-3 P DW WBN EEB 1-47W610-3-4 P DW WBN EEB 1-47W610-3-5 P DW WBN EEB 1-47W610-3-5A CCRIS ONLY UPDATES:
Following are required only when making keyword/cross reference CCRIS updates and page 1 of form NEDP-2-1 is not included:
PREPARER SIGNATURE DATE CHECKER SIGNATURE DATE PREPARER PHONE NO. EDMS ACCESSION NO.
I VA"40532 [10U-200U8 Page 2 of 2 NED.P-2-1 [10U-20-20U08
NPG CALCULATION COVERSHEETICCRIS UPDATE Page 2h CALCAID I TYPF I OR( I PLANT I RRANCH I Wll JMRF=R I RFV I NUMBER I RFV I NUC WBN EEB CACSSEGMENT I
CN 000 ALTERNATE CALCULATION IDENTIFICATION BLDG ROOM ELEV COORD/AZIM FIRM Print Report Yes NA NA NA NA Bechtel CATEGORIES NA KEY NOUNS (A-add, D-delete)
ACTION KEY NOUN A/D KEY NOUN CROSS-REFERENCES (A-add, C-change, D-delete)
ACTION XREF XREF XREF XREF XREF XREF
,(AC/DQ CODE TYPE PLANT BRANCH NUMBER REV P DW WBN EEB 2-47W610-3-1 P DW WBN EEB 2-47W61 0-3-lA P DW WBN EEB 2-47W610-3-lB P DW WBN EEB 2-47W610-3-iC P DW WBN EEB 2-47W610-3-1D P DW WBN EEB 2-47W610-3-2 P DW WBN EEB 2-47W610-3-2A P DW WBN EEB 2-47W610-3-2B P DW WBN EEB 2-47W610-3-2C P DW WBN EEB 2-47W610-3-3 P DW WBN EEB 2-47W610-3-4 P DW WBN EEB 2-47W610-3-5 P DW WBN EEB 2-47W610-3-5A P DW WBN EEB 1-47W610-62-1 P DW WBN EEB 1-47W610-62-2 P DW WBN EEB 1-47W610-62-3 P DW WBN EEB 2-47W610-62-1 CORIS ONLY UPDATES:
Following are required only when making keyword/cross reference CCRIS updates and page 1 of form NEDP-2-1 is not included:
PREPARERSIGNATURE DATE CHECKER SIGNATURE DATE PREPARER PHONE NO. EDMS ACCESSION NO.
TVA 40532 [10-2008] Page v
2 of 2 NEDP-2-1 [1 0-20-2008]
NPG CALCULATION COVERSHEETICCRIS UPDATE Page 2i CALC ID I TI'*P I JKt*
SI l~ I I)age NUC WBN EEB DCSSEGMENT 000 CN ALTERNATE CALCULATION IDENTIFICATION BLDG ROOM ELEV COORD/AZIM FIRM Print Report Yes NA NA NA NA Bechtel CATEGORIES NA KEY NOUNS (A-add, D-delete)
ACTION KEY NOUN A/D KEY NOUN CROSS-REFERENCES (A-add, C-change, D-delete)
ACTION XREF XREF XREF XREF XREF XREF QkA/C/D) CODE TYPE PLANT BRANCH NUMBER REV P DW WBN EEB 2-47W610-62-2 P DW WBN EEB 2-47W610-62-3 P DW WBN EEB 1-47W610-68-1 P DW WBN EEB 1-47W610-68-2 P DW WBN EEB 1-47W610-68-3 P DW WBN EEB 1-47W610-68-4 P DW WBN EEB 1-47W610-68-5 P DW WBN EEB 1-47W610-68-5A P DW WBN EEB 1-47W610-68-6 P DW WBN EEB 1-47W610-68-8 P DW WBN EEB 1-47W610-68-9 P DW WBN EEB 1-47W610-68-10 P DW WBN EEB 1-47W610-68-11 P DW WBN EEB 2-47W610-68-1 P DW WBN EEB 2-47W610-68-2 P DW WBN EEB 2-47W61 0-68-3 P DW WBN EEB 2-47W610-68-4 CCRIS ONLYUPDATES:
Following are required only when making keyword/cross reference CCRIS updates and page 1 of form NEDP-2-1 is not included:
PREPARER SIGNATURE DATE CHECKER SIGNATURE DATE PREPARER PHONE NO. EDMS ACCESSION NO.
TVA 40532 [10-2008] Page 2 of 2 NEDP-2-1 [10-20-20081J
NPG CALCULATION COVERSHEETICCRIS UPDATE Page 2j CALC ID I TYPE I ORG PLANT I BRANCH I NI IMBER I REV CN NUC WBN EEB DCSSEGMENT IDENTIFICATION CALCULATION 000 ALTERNATE I ALTERNATE CALCULATION IDENTIFICATION
- BLDG ROOM ELEV COORD/AZIM FIRM Print Report Yes NA NA NA NA Bechtel CATEGORIES NA KEY NOUNS (A-add, D-delete)
ACTION KEY NOUN AID KEY NOUN Q{ND_
CROSS-REFERENCES (A-add, C-change, D-delete)
ACTION XREF XREF XREF XREF XREF XREF (AICID} CODE TYPE PLANT BRANCH NUMBER REV P DW WBN EEB 2-47W610-68-5 P DW WBN EEB 2-47W610-68-5A P DW WBN EEB 2-47W610-68-6 P DW WBN EEB 2-47W610-68-8 P DW WBN EEB 2-47W610-68-9 P DW WBN EEB 2-47W610-68-10 P DW WBN EEB 2-47W610-68-11 P DW WBN EEB 1-47W611-1-1 P DW WBN EEB 1-47W611-1-2 P DW WBN EEB 2-47W611-1-1 P DW WBN EEB 2-47W611-1-2 P DW WBN EEB 1-47W611-3-1 P DW WBN EEB 1-47W611-3-2 P DW WBN EEB 1-47W611-3-6 P DW WBN EEB 2-47W611-3-1 P DW WBN EEB 2-47W611-3-2 P DW WBN EEB 2-47W611-3-6 CCRIS ONLY UPDATES:
Following are required only when making keyword/cross reference CCRIS updates and page 1 of form NEDP-2-1 is not included:
PREPARER SIGNATURE DATE CHECKER SIGNATURE DATE PREPARER PHONE NO. EDMS ACCESSION NO.
TVA 40532 [10U-2008]* Page 2-Of 2 NEDUP-2-1 [10-20-20081
2k NPG CALCULATION COVERSHEETICCRIS UPDATE Page 2k CALC ID TYPE ORG PLANT BRANCH NUIMBER I REV CN NUC WBN EEB DCSSEGMENT Page 000 ALTERNATE CALCULATION IDENTIFICATION BLDG ROOM ELEV COORD/AZIM FIRM 7Print Reoort Yes NA NA NA NA Bechtel CATEGORIES NA KEY NOUNS (A-add, D-delete)
ACTION KEY NOUN A/D KEY NOUN Q(/D)
CROSS-REFERENCES (A-add, C-change, D-delete)
ACTION XREF XREF XREF XREF XREF XREF (A/C/D) CODE TYPE PLANT BRANCH NUMBER REV P DW WBN EEB 1-47W611-62-1 P DW WBN EE8 1-47W611-62-2 P DW WBN EEB 1-47W611-62-3 P DW WBN EEB 1-47W611-62-4 P DW WBN EEB 2-47W611-62-1 P DW WBN EEB 2-47W611-62-2 P DW WBN EEB 2-47W611-62-3 P DW WBN EEB 2-47W611-62-4 P DW WBN EEB 1-47W611-68-i P DW WBN EEB 1-47W611-68-2 P DW WBN EEB 1-47W611-68-3 P DW WBN EEB 2-47W611-68-1 P DW WBN EEB 2-47W611-68-2 P DW WBN EEB 2-47W611-68-3 CCRIS ONLY UPDATES:
Following are required only when making keyword/cross reference CCRIS updates and page 1 of form NEDP-2-1 is not included:
PREPARER SIGNATURE DATE CHECKER SIGNATURE DATE PREPARER PHONE NO, EDMS ACCESSION NO.
I VA* 4053.2 110-2008J P-age 2 OT 2 NEED-2U--1 [10U-20-20081
Page 3 NPG CALCULATION RECORD OF REVISION CALCULATION IDENTIFIER: DCSSEGMENT Title SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS Revision DESCRIPTION OF REVISION No. I 0 Initial issue for EDCR 52378 and related FCRs for installation of the Foxboro I/A distributed control system.
Page Count:
Main body of calculation (including 2a-2k) 36 Appendices A and B 19 and Attachments 3 Total pages 58 SAR changes submitted in support of EDCR 52378 were incorporated into the Unit 2 UFSAR Amendment 97. The need for additional SAR or Technical Specification changes will be evaluated in implementation of FCRs for EDCR 52378.
[10-2008]
40709 [10-2008] Page 1 of 1 NEOP-2-2 [10-20-20081 iVA 40709 TIVA Page I of I NEDP-2-2 (10-20-20081
Page 4 NPG CALCULATION VERIFICATION FORM Calculation Identifier: DCSSEGMENT Revision 0 Method of verification used:
- 1. Design Review "
- 2. Alternate Calculation El Verifier ,T. \.-.tel Date ( 0ijA
- 3. Qualification Test El Comments:
Comments: See Attachment 1, Design Verification Report and Checklist, 25402-3DP-GO4G-00027-003 for calculation DCSSEGMENT RO.
NEDP-2-4 [10-20-2008]
Page 1 of 1 40533 [10-2008]
TVA 40533 [10-2008) Page 1 of 1 NEDP-2-4 [10-20-20081
Page 5 NPG CALCULATION TABLE OF CONTENTS Calculation Identifier: DCSSEGMENT Revision: 0 TABLE OF CONTENTS SECTION TITLE PAGE Coversheet 1 Record of Revision 3 Design Verification Form 4 Table of Contents 5 1.0 Purpose 6 2.0 Sources of Design Inputs I References 6 3.0 Assumptions 9 4.0 DCS Design Description 10 5.0 Analysis 13 5.1 Feedwater/SG Level 15 5.2 Main Feedwater Pumps 16 5.3 SG PORVs 17 5.4 Rod Control 18 5.5 Steam Dump 19 5.6 Pressurizer Pressure 20 5.7 Pressurizer Level, Charging and Letdown 21 5.8 Volume Control Tank Level 23 5.9 BOP Turbine Runback 23 6.0 Conclusions 24 Appendix A (Figures)
- 1. Shared Signals
- 2. Feedwater/SG Level
- 3. Feedwater Pumps
- 5. Rod Control
- 6. Steam Dump
- 7. Pressurizer Pressure
- 8. Cold Overpressure Mitigation
- 9. Pressurizer Level
- 10. Volume Control Tank Appendix B: Safety Analysis Review Attachment 1: Design Verification Report NEDP-2-3 ~10~20-20081 Page 1 of~~
TVA 40710 TVA E1O-20081 40710 [10-20081 Page I of I NEDP-2-3 [10-20-20081
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS 1.0 Purpose The existing analog control systems for WBN Unit 2 are being replaced with a Foxboro (Invensys) I/A Distributed Control System (DCS) for control and monitoring of most non-safety related NSSS and BOP systems. The controls are distributed among 15 control groups, each with a redundant processor pair. The purpose of this analysis is to evaluate the distribution (segmentation) of the inputs/outputs of those control systems important to plant operation among these control groups to confirm that no new failures are introduced which could adversely impact plant safety analyses.
2.0 Sources of Design Inputs I References 1 EDCR 52378, Replace Obsolete Non-Safety Analog NSSS and BOP Control Systems with a Foxboro I/A Distributed Control System 2 Invensys Letter INV-WBN2-802403-239 dated July 19, 2010, Drawing Submittal for post-FAT changes.
3 Design Criteria A. WB-DC-40-70 R18, Accident Analysis Parameters Checklist B. WB-DC-40-58 R5, Auxiliary Control System 4 Unit 2 UFSAR, Amendment 99 5 Unit 2 Technical Specifications 6 DG-E18.1.25 R2, Digital System Development, Procurement, and Implementation 7 Draft revision of "Effects of Common Cause Failure" prepared by Altran Solutions for the NRC Task Working Group on Defense-in-Depth & Diversity, August 2007 8 System Descriptions C. WBN2-1-4002 R2, Main Steam System D. WBN2-3A-4002 R2, Main Feedwater, Feedwater Control And Injection Water E. WBN2-6-4002 R1, Heater Drains and Vents F. WBN2-47-4002 R1, Turbogenerator System (Part 1) and Turbogenerator Control and Protection System (Part 2)
G. WBN2-62-4001 R1, Chemical-And Volume Control System H. WBN2-63-4001 R1, Safety Injection System I. WBN2-68-4001 RO, Reactor Coolant System J. WBN2-85-4003 R1, Control Rod Drive System K WBN2-92-4003 R1, Neutron Monitoring System L. WBN2-99-4003 RO, Reactor Protection System 9 Foxboro Functional Diagrams (contract 69247)
A. 08F802403-FD-2004-1 R2 6
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS B. 08F802403-FD-2005-1 R3 C. 08F802403-FD-2006-1 R3, -2 R2, -4 R3, -5 R4 D. 08F802403-FD-2012-1 R4 E. 08F802403-FD-2101-1 R2, -4 R2 F. 08F802403-FD-2102-1 R3 G. 08F802403-FD-2103-1 R2,-3 R2 H. 08F802403-FD-2104-1 R4, -3 R3 I. 08F802403-FD-2105-1 R3, -2 R3, -4 R2 J. 08F802403-FD-2107-1 R3, -2 R3, -4 R2 K. 08F802403-FD-2109-1 R2, -2 R2 L. 08F802403-FD-2110-1 R3 M. 08F802403-FD-2111-1 R3,-2 R2 N. 08F802403-FD-2201-1 R5
- 0. 08F802403-FD-2202-1 R6 P. 08F802403-FD-2203-1 R4 Q. 08F802403-FD-2205-1 R6, -2 R6 R. 08F802403-FD-2300-1 R3, -6 R3 S. 08F802403-FD-2301 -1 R2, -6 R3 T. 08F802403-FD-2302-1 R2, -6 R3 U. 08F802403-FD-2303-1 R2, -6 R3 V. 08F802403-FD-2304-1 R5, -3 R2, -4 R2, -8 R4, -9 R4, -10 R2 W. 08F802403-FD-2400-1 R5, -3 R5, -5 R4, -6 R5, -7 R4 X. 08F802403-FD-2401-1 R7, -5 R5, -6 R5, -12 RO Y. 08F802403-FD-2402-1 R5, -3 R6 Z. 08F802403-FD-2403-1 R5, -3 R4 AA. 08F802403-FD-2404-1 R6, -6 R7, -8 R6, -10 R7 BB. 08F802403-FD-2501 -1 R2 CC. 08F802403-FD-2600-1 R3 DD. 08F802403-FD-2601-1 R4 EE. 08F802403-FD-2603-1 R4, -2 R4, -3 R5 FF. 08F802403-FD-2604-1 R3 GG. 08F802403-FD-2605-1 R5 HH. 08F802403-FD-2607-1 R4 7
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS I1. 08F802403-FD-2608-1 R5 JJ. 08F802403-FD-2609-1 R4 KK. 08F802403-FD-2616-1 R3 LL. 08F802403-FD-2818-1 R3 MM. 08F802403-FD-2908-1 R3 NN. 08F802403-FD-2909-1 R4
- 00. 08F802403-FD-291 0-1 R4 10 Control Drawings A. 1-47W610-1-1 R30, -1A R16, -2 R29, -2A R20, -3 R10, -3A R7 B. 2-47W610-1-1 R2, -1A R2, -2 R2, -2A R2, -3 R1, -3A RO C. 1-47W610-3-1 R28, -1A R6, -1B R11, -1C R4, -1D R7, -2 R19, -2A R18, -28 R3, -2C R8, -3 R22, -4 R17, -5 R18, -5A R9 D. 2-47W610-3-1 R1, -1A RO, -1B RO, -1C RO, -1D R1, -2 RO, -2A Ri, -2B RO, -2C R1, -3 R2, -4 R1, -5 R1, -5A RI E. 1-47W610-62-1 R21, -2 R24, -3 R25 F. 2-47W610-62-1 R1, -2 R3, -3 RO G. 1-47W610-68-1 R18, -2 R15, -3 R21, -4 R18, -5 R22, -5A R4, -6 R12, -8 R8, -9 R5, -10 R5, -11 R9 H. 2-47W610-68-1 RO, -2 RO, -3 R1, -4 R1, -5 R1, -5A R1, -6 R1, -8 RO, -9 RO, -10 RO, -11 RO 11 Logic Drawings A. 1-47W611-1-1 R13,-2 R12 B. 2-47W611-1-1 R1, -2 R1 C. 1-47W611-3-1 R12,-2 R22,-6 R18 D. 2-47W611-3-1 R2, -2 R3, -6 R1 E. 1-47W611-62-1 R6, -2 R8, -3 R9, -4 R11 F. 2-47W611-62-1 R1,-2 R1,-3 R1, -4 R1 G. 1-47W611-68-1 R10, -2 R7, -3 R8 H. 2-47W611-68-1 R1, -2 R1, -3 R1 12 Westinghouse Functional Diagrams, 5655D87 series (contract 54114-01)
A. 2-54114-1-5655D87-9 RO B. 2-54114-1-5655D87-10 RO C. 2-54114-1-5655D87-11 RO D. 2-54114-1-5655D87-12 RO E. 2-54114-1-5655D87-13 RO 8
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS F. 2-54114-1-5655D87-14 RO 13 Westinghouse Process Control Block Diagrams, 108D408 series (contract 54114-01 and 65717)
A. 1.08D408-5 RE, 2-65717-108D408-5 RO B. 108D408-6 RE, 2-65717-108D408-6 RO C. 108D408-23 RF D. 108D408-24 RE E. 108D408-25 RD F. 108D408-26 RD G. 108D408-27 RE H. 108D408-28 RD I. 108D408-31 RD J. 108D408-32 RD K. 108D408-33 RF L. 108D408-36 RF, 2-65717-108D408-36 RO M. 108D408-41 RD 14 Calculation EPMFBN072892 R3, "Maximum Feedwater Flow for Multiple Loop Failures."
15 NPG Critical Digital Review of the Foxboro I/A Series Platform (B43 090303 001) 3.0 Assumptions
- 1. Unverified assumption: The post-FAT functional logic changes submitted in reference 2 and evaluated in this calculation will be implemented by EDCR 52378 (reference 1) via FCR 55490.
- 2. Unverified assumption: A network data storm test will be performed with the system installed and prior to final commissioning. The test will confirm that the system will continue to function with a failed communication network without any plant upset.
9
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS 4.0 DCS Design Description The functional design of the WBN unit 2 control systems implemented in the DCS is similar to unit 1 but with changes which improve reliability and eliminate many significant single points of failure. The basic components of the DCS are redundant fault-tolerant processor pairs, redundant power supplies with diverse power sources, redundant communication networks, and redundant operator workstations. Redundant field-bus modules (FBMs) are utilized for critical inputs and outputs. The system is designed such that the control system functions most important to safe plant operation are not affected by the failure of a single device or component.
Functional Groups (CP Pairs)
The unit 2 DCS consists of 15 functional groups, each with a redundant control processor (CP) pair. This arrangement provides capability to maintain independence between redundant control functions and to limit the effects of failures on the critical control systems.
Table 1 identifies the primary functions of each of the DCS functional groups. Each group also includes other control and monitoring functions for which segmentation is not considered to be necessary as further discussed in section 5.0.
Table I FUNCTIONAL GROUPS Group Primary Functions (CP Pair) 01 Steam Generator I Level, FW Flow 02 Steam Generator 2 Level, FW Flow 03 Steam Generator 3 Level, FW Flow 04 Steam Generator 4 Level, FW Flow 05 Main FW Pump Speed Control & Steam Dump Loss of Load Interlock 06 Rod Control 07 Steam Generator 1 PORV (Atmospheric Dump) 08 Steam Generator 2 PORV (Atmospheric Dump) 09 Steam Generator 3 PORV (Atmospheric Dump) 10 Steam Generator 4 PORV (Atmospheric Dump) 11 Condenser Steam Dump 12 Pressurizer A (Pressure, Level, Charging, Letdown, Spray, COMS) 13 Pressurizer B (Pressure, Level, Charging, Letdown, Spray, COMS) 14 Auxiliary Control System A 15 Auxiliary Control System B 10
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS Auxiliary Control System Groups 14 and 15 are dedicated to the Auxiliary Control System (ACS) which is not required for normal plant operation. The ACS provides controls and instrumentation needed for plant shutdown from outside the Main Control Room (MCR) in the event that the MCR has to be abandoned. Isolation of the ACS from the normal controls is achieved either by dedicated control loops or by manually-operated transfer switches.
The safety related functions of the ACS are implemented independently of the DCS.
Groups 14 and 15 are isolated from the network during normal operation, except for maintenance purposes, to eliminate the possibility of events external to the auxiliary control room causing loss of these processor pairs.
Segmentation of the DCS functions of the ACS is not evaluated in this analysis since the ACS is not used for normal plant operation, DCS groups 14 and 15 are isolated from the network during normal operation, the unit will be shut down if the MCR has to be abandoned, and no other design basis event or abnormal plant condition is assumed concurrent with MCR evacuation except fire or design basis flood (reference 3B).
Power Supplies Each of the redundant power supplies for the control groups is fed from an inverter with battery and emergency diesel generator backup - typically the primary power supply from a 120 VAC Vital Inverter and the secondary from the 120 VAC TSC Inverter. This arrangement ensures that a single power supply or inverter failure will not result in loss of function, eliminating loss of power as a single point of failure. One significant benefit of this configuration is that an inverter failure will not cause a plant trip due to the main feedwater control valves closing.
Sigqnal Selection and Validation The use of multiple measurement channels for critical parameters such as turbine impulse pressure, steam header pressure, and feedwater pressure allows the use of various signal selectors to improve reliability and eliminate single point failures.
Redundant inputs are typically assigned to different input modules to provide additional hardware diversity and eliminate hardware common cause failure.
A median signal selector chooses the median value signal of three inputs for control use. With the median signal selector, a spurious high or low signal from any one channel will not :cause a control action. Where only two inputs are available, an average is computed, and a third correlated signal may be provided as a voter. The voter is never used for control. With four inputs, either the highest input (auctioneered) or the second highest input (higher median) is selected for control. The high quality of the median signal selector is documented in reference 15 of section 3.6.
The system also employs signal validation techniques which can remove bad or out-of-service signals from the algorithm and select from the remaining good signals or transfer control to manual in the event of multiple input signal failures. This includes input signals which deviate significantly from the selected signal (auctioneered or 11
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS median). These conditions will be alarmed and the bad signal removed from the control algorithm. Use of these techniques eliminates the potential for a transient initiated by the failure of a single input.
Shared Signals The signals listed in Table 2 are used in more than one functional group or processor pair. They may be provided to each processor as separate inputs, or they may be input to one processor for development of the control signal (auctioneered, median, etc.) which is then transmitted to other processors by either a hardwired analog connection, peer-to-peer network connection or both. No critical control function is dependent upon the network alone. This scheme eliminates the possibility that failure of a single input signal, a single processor pair, or both communication networks will disable multiple control systems or functions.
Figure 1 shows how these input signals or the derived control signals are distributed among multiple processor pairs. Simplified configuration sketches based on the referenced functional logic diagrams are shown in Figures 2 through 10.
External Communication Two communication links are provided from the DCS to the plant computer. Firewalls between the systems limit the volume of data traffic and ensure that common cause events, such as a data storm, do not impact multiple control systems within the DCS.
There is no digital communication between the control system and the protection system. The control system analog process inputs from the protection system are transmitted via qualified isolators as on unit 1.
Network Data Storm The impact of erroneous communication internal to the system, such as a data storm due to a processor failure, will be evaluated by test. A Sequoyah factory acceptance test for a Foxboro I/A DCS demonstrated that a data storm can disable the communication networks and cause one CP of a pair to become non-functional. The control groups, however, continued to operate. The network is disabled only during the datastorm event and full system redundancy can be restored by an online reboot of the secondary CP. A data storm test will be performed with the installed WBN Unit 2 system prior to final commissioning to confirm similar results. Further, as noted previously, the system is designed with hardwired analog control signal transmission between CP pairs so that no critical control functions are totally dependent upon the network and the system will continue to function if the network fails.
12
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS Table 2 SHARED SIGNALS Parameter Loops Function Turbine Impulse Press 2-P-1-72
- Rod Control, Steam Dump, Turb Runback Turbine Impulse Press 2-P-1 -73
- Rod Control, Steam Dump, Turb Runback Turbine Impulse Press 2-PT-1 -74 Rod Control, Steam Dump, Turb Runback Turbine Impulse Press 2-PT-1-81 Rod Control, Steam Dump, Turb Runback RCS Loop 1 Tavg 2-T-68-2
- Rod Control, Steam Dump, Pzr Level RCS Loop 2 Tavg. 2-T-68-25
- Rod Control, Steam Dump, Pzr Level RCS Loop 3 Tavg 2-T-68-44
- Rod Control, Steam Dump, Pzr Level RCS Loop 4 Tavg 2-T-68-67
- Rod Control, Steam Dump, Pzr Level NIS Reactor Power Ch I 2-LP-92-412
- Rod Control, SG Level NIS Reactor Power Ch II 2-LP-92-412
- Rod Control, SG Level NIS Reactor Power Ch III 2-LP-92-412
- Rod Control, SG Level NIS Reactor Power Ch IV 2-LP-92-412
- Rod Control, SG Level Pressurizer Press 2-P-68-322
- Pressurizer Pressure Pressurizer Press 2-P-68-323
- Pressurizer Pressure Pressurizer Press 2-P-68-334
- Pressurizer Pressure Pressurizer Press 2-P-68-340
- Pressurizer Pressure Pressurizer Level 2-L-68-320
- Pressurizer Level Pressurizer Level 2-L-68-335
- Pressurizer Level Pressurizer Level 2-L-68-339
- Pressurizer Level Steam Header Press 2-PT-I -33A Steam Dump, MFP Speed Control Steam Header Press 2-PT-1 -33B Steam Dump, MFP Speed Control Steam Header Press 2-PT-1 -33C Steam Dump, MFP Speed Control Steam Flow Loop 1 2-F-1-3A, 3B
- SG 4 Level, MFP Speed Control Volume Control Tank Level 2-LT-63-129A VCT Level Volume Control Tank Level 2-LT-63-130A VCT Level
- Input signals from isolated protection system channels.
5.0 Analysis Control systems which are important to safe plant operation and can affect the plant safety analyses and for which segmentation is necessary or can provide a significant benefit are evaluated in the sections following. Some functions, while important to plant operation, do not lend themselves to or would not be significantly improved by segmentation of inputs and outputs and are not evaluated.
The analysis verifies that no new control system failures are introduced which could adversely impact the safety analyses as described in the FSAR and WB-DC-40-70, Accident Analysis Parameters Checklist. Typically, the control systems are assumed to function only if their operation contributes to more severe accident results. The control 13
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS systems evaluated in this analysis are not credited for accident mitigation but their availability can enhance the plant response to an event. The focus of this safety analysis review then is to identify configurations wherein failure of a CP pair could result in plant conditions which are more limiting than those analyzed in the safety analysis. The results of this review are provided in Appendix B and the control system discussions following.
Design basis documents including design criteria, system descriptions and drawings were reviewed for functional and configuration requirements to minimize differences with unit 1 with respect to functional diversity and independence. The unit 1 design limits the effects of a component failure or loss of power by providing redundant hardware and power sources for certain functions. For example, the pressurizer heaters can be turned off by either of two independent channels which have different power sources. Maintaining this approach for unit 2 will limit the'effects of failures and requires that certain functions be processed in different CP pairs. Segmentation of important control systems and functions improves availability of these systems for both normal operation and transient/accident response.
The configuration of signals which are shared by more than one control system or functional group are also evaluated to verify that loss of any one signal or processor pair will not cause an unacceptable loss of multiple functions.
Simplified functional logic sketches are provided in Appendix A. These figures are based on the Foxboro functional diagrams listed in reference 9.
Failure Modes For this analysis, the unlikely failure of both processors of a redundant pair is assumed, with all outputs failing high, low or as-is. Failures resulting in output state changes are recognizable by their effects, e.g., plant components changing state or indicators going off-scale high or low. As-is failures are not likely to have an immediate effect and therefore would not result in a transient; but they may remain undetected until there is a demand failure or until a process parameter exceeds its normal range and actuates an alarm.
The following design and implementation strategies provide reasonable assurance of adequate protection against a common cause failure affecting multiple processor pairs:
- defensive design techniques including multiple processor pairs running asynchronously with different application software, deterministic software programs, redundant hardware and communication paths, system diagnostics, input signal redundancy and functional segmentation;
" design reviews performed during the design process, including a critical design review of the Foxboro I/A platform (reference 15);
- software quality assurance;
" testing before and after installation, i.e., factory and site acceptance tests, startup tests;
" hardware and software configuration control during the design phase and after installation.
14
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS Based on the above considerations, simultaneous failure of more than one processor pair and multiple smart combinations of failure states such as high and low are not considered. This approach is supported by reference 7 and is consistent with the guidelines of reference 6 and with the nuclear industry position.
5.1 Feedwater I SG Level One control processor pair is provided for level control for each steam generator so that a single processor pair failure will not cause more than one SG level control system failure. The controls for SGs 1-4 are located in processors CP01, CP02, CP03, and CP04, respectively. Three water level signals per steam generator are provided via isolated Eagle 21 outputs to the respective processors for control of both the feedwater regulating valves and the feedwater bypass regulating valves. A median signal selector function in the DCS provides a median signal for control use similar to unit 1 except the unit I MSS is implemented with hardware and unit 2 with software.
Two feedwater flow signals and two steam flow signals per loop are also provided to the respective SG level control processors. The DCS calculates an average of the two inputs for each variable for input to the controller. If one channel of feedwater flow or one channel of steam flow fails, a voter signal will determine which of the two channels should be used for control. The voter signal is the average of the feedwater flows of the other steam generators. The voter is not used for control. On unit 1 a single channel each of feedwater flow and steam flow are manually selected for control so that operator intervention is required if the selected channel fails or is to be tested. The average steam flow signals are transmitted from each SG level control processor to CP05 to develop the speed control setpoint for the main feedwater pumps.
The steam generator level setpoints for both the main and bypass feedwater regulating valves are generated from the second highest value (high median select) of the four NIS power inputs. Using the higher median signal prevents a single input failure from causing a spurious SG level setpoint change. On unit 1, the programmed level setpoints for loops 1 and 4 are derived from a single NIS channel I module and the setpoints for loops 2 and 3 are similarly derived from NIS channel I1.A single input channel or module failure could cause a disturbance on two SG loops. The unit 1 bypass valves controllers also have a bias input from auctioneered high NIS. During low power operation with the bypass valves in auto, a single failure could result in all four bypass valves opening.
The unit 2 level demand signal (NIS power high median) is developed in CP06 (Rod Control). The signal is transmitted independently to each of the four SG level processors by a hardwired connection and also by a peer-to-peer network interface.
The programmed level setpoint for each SG is developed in each of the SG level control processors ýindependently of the others except for the common demand signal from CP06. See Figure 2.
Since all four SG level control processors are dependent on CP06 for the level demand, a failure of this processor could affect the level controls for all SGs. However, 15
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS the level setpoint algorithm in each of the level control processors limits the setpoint to the range of 38-60% (the no load and full load values). Each of the level control processors contains diagnostics which will detect failure of the level demand inputs and will then freeze the setpoint to the last good value and switch control to manual.
This will give operators time to respond before a significant transient is initiated.
At full power, a high failure of the NIS level demand signal from CP06 would not result in any change in SG levels because of the setpoint high limit (60%). At less than full power, the level program would open the feedwater regulating valves to increase SG levels to the high limit. This condition is less severe than the cases evaluated in the "Excessive Heat Removal Due to Feedwater System Malfunction" event described in FSAR section 15.2.10. The analysis considered four cases to be limiting:
- 1. Accidental opening of one feedwater control valve with the reactor at zero load.
- 2. Accidental opening of all feedwater control valves with the reactor at zero load.
- 3. Accidental opening of one feedwater control valve with the reactor at full power.
- 4. Accidental opening of all feedwater control valves with the reactor at full power.
The analysis concluded that the hot zero power feedwater malfunction is bounded by the hot full power feedwater malfunction. The event is terminated by the steam generator high-high level signal, which closes all feedwater control and isolation valves and trips the main feedwater pumps. The cases assuming all the valves fully open bound the conditions resulting from a high failure of CP06.
Similarly, in response to a low failure of the NIS level demand signal from CP06, the level control system would reduce flow by closing the feedwater valves to match SG levels to the demand value. The system response to this failure is constrained by the low limit on the setpoints (38%). This failure is bounded by the "Loss of Normal Feedwater" event described in FSAR Section 15.2.8.
A failure of one SG level control CP could result in both the main and bypass valves either opening or closing depending on the signals failing high or low. Both these cases are bounded by the analyses as described above.
TVA calculation EPMFBN072892 (reference 14) evaluates feedwater system failures at different power levels to determine the maximum feedwater flows for single and multiple loop failures. In each case the calculation assumes both the main and bypass valves in the failed loop to be wide open instead of in their normal zero or full power position, providing conservatively maximum flow results. The results of this calculation were used as input to the FSAR feedwater malfunction analysis discussed above. The FSAR cases analyzed bound those evaluated in the calculation.
5.2 Main Feedwater Pumps Speed Control The feedwater pump speed controls in CP05 utilize median signal selectors for three feedwater header pressure (feedwater pump discharge) inputs and three main steam header pressure inputs. Use of the MSS eliminates the potential for a transient initiated by a single transmitter failure as on unit 1. The feedwater pump programmed DP 16
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS setpoint is a function of the four-loop average of the loop steam flows with each loop flow being the average of two flow measurements from the respective SG control processor (CP01, CP02, CP03, CP04). The average loop flow for each SG is transmitted to CP05 via the network. The SG 1 and SG 2 flows are also hardwired to provide additional reliability. Failure of the steam flow inputs from two or more SGs, including complete loss of the networked inputs, will freeze the DP setpoint at the last good value. See Figure 3.
Redundant DCS modules provide 4-20 mA speed demand outputs for each MFP. The signals are converted to 10-50 mA and auctioneered before being transmitted to each MFP speed changer. Both the DCS output modules and the external signal converters are current limited. A high failure of a pump speed demand output (such as from a processor pair failure) would result in increased feedwater flow.
The feedwater flow values used in the maximum feedwater flow calculation (reference
- 14) discussed in the previous section are conservatively large values which in the limiting case are beyond the guaranteed .pump operating range and may be at the run-out range as noted in the calculation. Thus, even if a MFP speed control processor failure caused both MFPs to go to the maximum speed allowed by the speed changers and approach runout, the results would -still be bounded by the maximum feedwater flow analysis of reference 14 and the FSAR feedwater malfunction analysis. In addition, the level control systems would continue to maintain the desired SG levels by adjusting the feedwater regulating valves.
Low failure of a pump speed demand output would result in decreased feedwater flow and subsequent drop in SG level. This condition is bounded by the Loss of Normal Feedwater event described in FSAR Section 15.2.8.
5.3 SG PORVs The SG PORVs provide capability for SG pressure control and for a controlled plant cooldown when the condenser steam dump system is not available. The controls for each of the SG PORVs are in separate processors, CP07, CP08, CP09, and CP10, so that only one PORV control system will be affected by a processor pair failure. Steam dump control is assigned to CP1 1. Each PORV control has three steam pressure inputs from the corresponding steam line, two of which are from isolated Eagle 21 outputs. The median of three steam pressure signals in each CP is input to the PORV controller. See Figure 4. The unit 1 PORV controls have only one pressure input.
The SG PORVs should be available to dump excess steam generated from a loss of load or turbine trip event (FSAR 15.2.7 and reference 3.A section 4.1.7) if the condenser is not available. Separation of the controls for the PORVs and the steam dumps maximizes the availability of steam relief for a single CP failure. In addition, a discrete high pressure output is provided from the steam pressure median signal in each CP to open the PORV when the rate of pressure increase is greater than the controller's capability to control. On unit 1 this interlock is performed by a single mechanical pressure switch.
17
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS Inadvertent opening of a SG relief valve is identified as an initiator in the analysis of the Accidental Depressurization of Main Steam event in FSAR section 15.2.13 and described in reference 3.A section 4.1.12. With the SG PORV controls in separate processors, no single CP failure will result in more than one PORV opening. Safety related controls independent of the DCS are available to close a PORV opened by a control system failure.
The safety analyses credit the main steam safety valves for pressure relief for events involving significant pressure increases where the PORVs may be unable to control the pressure increase, such as a load rejection with steamline isolation, or if a PORV fails to open. Safety-grade manual controls are available for control of the PORVs if needed.
6.4 Rod Control The reactor control system controls reactor power by maintaining reactor coolant average temperature to within + 3.5 0 F of the programmed temperature. The system is designed to automatically control the reactor in the range of 15-100 percent of rated power for the following design transients:
- 10 percent step change in load or a ramp increase or decrease of 5 percent/minute without reactor trip, steam dump, or pressurizer relief actuation.
0 50 percent step load decrease without reactor trip (10% control rods, 40% steam dump).
The reactor control signal consists of an error signal used to determine rod speed and position (direction) to maintain programmed Tavg. The two channels used to generate the total error signal are the deviation of the primary coolant average temperature (Tavg) from the programmed average temperature (Tref) and the mismatch between turbine load and nuclear power. The Tavg control signal is the auctioneered highest value of the four loop Tavg inputs from Eagle 21. The Tref signal is generated from the second highest of four turbine impulse pressure signals as determined by a higher median signal selector in the DCS. The Tref signal should be more reliable than unit I where it is derived from a single channel.
The error between Tref and Tavg constitutes the primary control signal for rod control.
The power mismatch signal improves system performance by enhancing response and reducing transient peaks. The control system maintains Tavg within prescribed limits during normal operation and anticipated operational transients and is capable of restoring coolant average temperature to the programmed value following a change in load.
Turbine load is also represented by the Tref signal. The nuclear power input to the power mismatch circuit is derived from the auctioneered highest of the four NIS power range signals. A second nuclear power signal, the higher median value (2nd highest),
is developed for input to the SG level control systems (section 5.1). A channel deviation alarm will be generated if any NIS input deviates significantly from the higher 18
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS median value and that input will not be used in the algorithm. The output will be frozen if two or more input signals are determined to be bad.
The Tavg, Tref and nuclear power signals derived in CP06 for use in the rod control system are also used for other control functions. The auctioneered Tavg signal is sent to CP1 I for steam dump control (section 5.5) and to CP1 3 for pressurizer level control (section 5.7). Tref is transmitted to CP1 I for steam dump control and to CP05 for the steam dump loss of load interlock. The higher median nuclear power signal is transmitted independently to each of the four SG level control systems in CP01, CP02, CP03 and CP04 as described in section 5.1. See Figure 5.
Since control is based on the highest of the loop average temperatures, control rod position is based upon the most limiting temperature measurement with respect to DNB margins. A spurious low average temperature signal from any loop Tavg channel will cause no control action. Depending on the magnitude, a spurious high average temperature signal could cause rod insertion (safe direction) or may be removed from the algorithm if it deviates excessively from the next highest signal. A channel deviation alarm will be generated by the DCS if any of the Tavg inputs deviates significantly from the auctioneered (highest) value. Operators can block any Tavg channel from control use with the Tavg defeat switch on the main control board or via an operator work station.
Failure of the CP06 outputs could cause rod insertion or withdrawal similar to the analog system failures on unit 1. The control rod drive system (not part of the DCS) is designed such that no more than two banks can be withdrawn at any time. The FSAR section 15.2.2 analysis of an Uncontrolled Rod Cluster Control Assembly Bank Withdrawal at Power, which assumes the simultaneous withdrawal of two banks at maximum speed, remains bounding for unit 2 DCS failures. Rod withdrawal blocks originate from systems external to the DCS.
Rod control and the control systems with which it shares control signals (steam dump, pressurizer level and SG level) are segregated such that failure of CP06 will not disable more than one of these systems.
5.5 Steam Dump The condenser steam dump system assists in mitigating a load reduction to reduce the effects of the transient imposed on the RCS. As noted previously, the SG PORVs provide capability for SG pressure control and for a controlled plant cooldown when the condenser steam dump system is not available. Therefore, the steam dump controls are assigned to CP1 1, while the SG PORVs are in CP07, CP08, CP09, and CP10.
Redundant pressure inputs are provided for the steam pressure mode. The median of three steam header pressure channels in CP05 (MFP Speed control) is provided to CP1 1 by both hardwired and networked connections. One of these three pressure channels is also hardwired as an input to CP1 1 so that steam dump control in the steam pressure mode is not disabled by failure of CP05.
19
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS Turbine impulse pressure, which is representative of turbine load, is used to generate the programmed reference average coolant temperature (Tref) as described previously. The Tref input to steam dump control is the higher median of four turbine impulse pressure signals input to the rod control processor pair CP06. Tref is an input to the.load rejection controller and the load rejection bistables which trip on excessive deviation between Tavg and Tref. The Tavg input to steam dump is the auctioneered high Tavg signal, also developed in CP06.
The Tref and Tavg signals are transmitted from CP06 to CP1 1 by both hardwired and networked connections to improve signal reliability. Due to the upper and lower range limits applied to these signals within CPI 1, failure of the Tavg and Tref outputs from CP06 would be less severe than failure of the CP1 1 outputs and similar to failure of a single module in unit 1.
To prevent actuation of steam dump on small load perturbations, an independent load rejection circuit (C-7) is provided in the DCS. This circuit senses the rate of decrease in the turbine load as detected by the turbine impulse pressure. C-7 is an arming interlock which will unblock the dump valves when the rate of load rejection exceeds a preset value corresponding to a 10% step load decrease. Independence is accomplished by providing one of the turbine impulse pressure inputs to a second processor pair, CP05, to generate the C-7 permissive. If the turbine impulse pressure input to C-7 came from the same processor as Tref, a low failure of one processor could both arm the dump valves and actuate the trip outputs, opening all of the valves.
Providing a redundant input to C-7 in a different processor prevents a failure of CP1 1 from causing all of the steam dump valves to open when at full load, resulting in a rapid depressurization of the main steam system. See Figure 6.
The basis for this design is the consideration of steam dump failures in two analyzed events: Excessive Load Increase (FSAR section 15.2.11) and Accidental Depressurization of Main Steam (FSAR section 15.2.13). These analyses assume the inadvertent opening of a steam dump, relief or safety valve. Maintaining functional independence between the C-7 loss-of-load interlock and Tref as described above ensures that the analyses remain bounding. These events are further described in reference 3.A sections 4.1.10 and 4.1.12.
5.6 Pressurizer Pressure The pressurizer maintains reactor coolant system pressure during operation and can accommodate certain transients without reactor trip. The pressurizer controls are divided into two groups, identified as Pressurizer A (PRZA) and Pressurizer B (PRZB),
which utilize separate processor pairs, CP1 2 and CP1 3. Each processor receives inputs from two of the four pressurizer pressure channels via isolated outputs from Eagle 21. An average of the two inputs in each CP is transmitted via the network to the other CP pair and a median signal is developed in each processor. The median signal in PRZA (CP1 2) is input to a master controller whose output is used for control of the pressurizer spray valves and the variable and backup heaters. Figure 7 is a simplified sketch of the principal pressurizer control features.
20
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS The spray valves controllers are assigned to different CPs to provide functional diversity. The spray valve controller in PRZB (CPI13) receives its input from the master controller via both the network and a hardwired connection. The median signals from both CPs are used for redundant actuation of the pressurizer power-operated relief valves (PORVs).
The unit 1 configuration has the controllers for the spray valves and the variable heater driven from the master controller output so that failure of or loss of power to the master controller would result in loss of the automatic control of these functions. However the unit 1 spray valve control stations in the main control room (MCR) are independent of the master controller in the manual mode and are powered from a different power source. The unit 2 DCS hand-auto stations in the MCR, however, will not function if the CP fails. Placing one spray valve controller and associated hand-auto station in PRZB (CP13) maintains manual control capability for at least one spray valve if one of the pressurizer CPs fails. Both the variable and backup heaters can be operated independently of the DCS from the MCR. Diverse spray isolation valve controls are provided external to the DCS if needed.
The pressurizer PORVs limit system pressure during a large power mismatch to a value below the high pressure reactor trip setpoint for transients up to and including a 50% step load decrease with steam dump actuation. A coincident high pressure signal from two independent channels (one from each processor) is needed for the actuation of each PORV. The PORVs also limit undesirable opening of the pressurizer safety valves. Condenser steam dumps and atmospheric steam dumps are controlled by different processor pairs than the pressurizer PORVs.
A spurious high or low control signal resulting from failure of CP12 can cause both spray valves to open or close and heaters to turn on or off as described above. A spurious high signal can cause decreasing pressure by turning off the heaters and actuating spray. Failure of a single CP will not cause spurious opening of a PORV since coincident high pressure signals are required from both processors.
A spurious low signal can cause increasing pressure by turning on the heaters and turning off spray. The rate of pressure rise achievable with heaters is slow, and ample time and pressure alarms are provided to alert the operator of the need for appropriate action. In addition, operation of either PORV can maintain pressure below the high pressure trip setpoint for most transients. No credit is taken for the relief capability provided by the PORVs during a pressure surge.
Cold Overpressure Mitigation System (COMS)
Two independent sets of controls are provided for mitigation of RCS overpressure events (e.g., inadvertent ECCS actuation) during low temperature operation. Each of two processor pairs, CP12 and CP13, receives signals from redundant channels of wide range RCS pressure and temperature via isolated outputs from Eagle 21. Each processor provides an output to open one PORV if necessary to prevent pressure from exceeding allowable limits. The actuation logic is manually armed (unblocked) external to the DCS when plant operation is at a temperature below the arming setpoint.
21
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS Manual arming prevents a spurious PORV opening due to a processor failure whenever the RCS temperature is above the arming temperature. In lower modes COMS will open the PORVs. See Figure 8.
5.7 Pressurizer Level, Charging and Letdown Flow RCS inventory is maintained by controlling charging and letdown flows to keep the pressurizer at programmed level as a function of the average reactor coolant temperature (Tavg). A portion of the charging flow is provided to the reactor coolant pump (RCP) seals.
Consistent with the unit 1 design, the unit 2 design for pressurizer level control incorporates redundancy for letdown isolation and pressurizer heater protection. Two processor pairs, CP12 and CP13, receive inputs from three pressurizer level channels via isolated outputs from Eagle 21. Two channels are input to CP13; the third is input to CP12. The third channel is then networked to CP13, where a median signal is developed. The median signal in CP13, with the programmed level input from auctioneered high Tavg (from CP06), provides the setpoint to the charging flow controller in CP13. A low level output from either CP12 or CP13 will close the letdown isolation valves and shutoff the heaters. See Figure 9. The controllers for pressurizer pressure and pressurizer level (via charging flow) are in different CPs, providing additional diversity.
A spurious high or low control signal resulting from failure of CP13 can cause an increase or decrease in charging flow and a slow change in pressurizer level. The high pressurizer level and high pressurizer pressure reactor trips prevent liquid discharge through the safety valves in the event of a level control failure. With redundant outputs from two pressurizer level control CPs, a single CP failure will not prevent letdown isolation nor result in the heaters being uncovered.
The Tavg signal (level demand) from CP06 is transmitted independently to CP1 3 by a hardwired connection and also over the network. The pressurizer programmed level setpoint is calculated in CP13 and is limited to the range of 25-60% (the no load and full load values). Failure of the Tavg level demand signal from CP06 would be less severe than failure of the CP1 3 outputs and similar to Tavg failure on unit 1.
Charging Flow In the AUTO mode, the charging flow controller output is limited to a minimum flow of 55 gpm to the RCP seals and the regenerative heat exchanger. The limit does not apply in MANUAL mode. The redundant output field bus modules also have a fail-safe feature which will maintain the output at 55 gpm minimum flow on loss of communication with the processor. Thermal barrier cooling provides back up for cooling the RCP seals.
External to the DCS, the charging flow valve controls also include a high select pneumatic relay in series with the signal to the valve positioner to prevent the valve from closing completely due to a spurious control signal during an Appendix R fire 22
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS event. The relay ensures a minimum flow rate of 32 gpm is maintained to the RCP seals regardless of the status of the DCS.
Letdown When the normal letdown path is out of service the excess letdown path can be used to maintain RCS inventory and ensure that the allowable backpressure on the RCP pump No. 1 seals is not exceeded. Controls for the letdown and excess letdown paths are in separate processors. The excess letdown path instrumentation is in CP12 while the normal letdown instrumentation is controlled from CP13.
5.8 Volume Control Tank Level The two level channels governing the water inventory in the volume control tank are input into separate processor pairs, CP12 and CP13. The CP12 level signal is then networked and hardwired to CP13 where an average of the two level signals is developed for diversion valve control and auto makeup control. A redundant high level interlock is provided in CP1 2 for diverting letdown flow to the holdup tank. Independent indications and high and low level alarms are provided from each channel/CP so that operators are alerted to a CP failure and can take appropriate action.
Low-low level signals are provided from each CP for re-aligning charging flow suction to the Refueling Water Storage Tank. Since valve alignment to the RWST requires a low-low level signal from both channels, a high output failure from either CP will prevent the switchover to RWST. Operators are alerted by redundant low level alarms from each channel/CP with ample time for action to maintain water supply to the charging pumps.
Failure effects of VCT level controls are similar to unit 1 except that failure of one transmitter will not disable automatic makeup. See Figure 10.
5.9 BOP Turbine Runback For conditions where the turbine-generator steam consumption exceeds the amount of feedwater being delivered to the steam generators, a decrease in turbine load is required to prevent a reactor trip due to low-low steam generator water level. The turbine runback is discussed here not because of a need for segmentation but because of its significance in preventing a trip. The changes which have been implemented for unit 2 will increase reliability, eliminate single point failures, and provide improved protection against certain failures.
One such condition is the loss of a main feedwater pump, which will initiate runback of the turbine to below 85% and start the Standby Main Feedwater Pump. The unit can be operated at 85% load with one MFP and the SBMFP in operation.
The load reference for the BOP turbine runback is turbine impulse pressure. On unit 1 the turbine impulse pressure input to turbine runback is derived from a single 23
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS transmitter and associated bistables. The unit 2 turbine runback functions will be implemented in DCS with the higher median turbine impulse pressure signal providing the load reference and the switch functions implemented with outputs to relay logic similar to unit 1. Implementing the unit 2 runback in the DCS provides increased reliability and less susceptibility to single point failures.
Another condition requiring runback involves the No. 3 heater drain tank (HDT). With all drains from the No. 3 HDT being bypassed to the condenser, the condensate and feedwater systems can deliver only 85% guaranteed flow to the steam generators. A turbine-generator load runback to less than 85% power will be initiated when all of the following conditions exist concurrently: Unit load greater than 85% (as indicated by turbine impulse pressure), No. 3 HDT pump discharge low flow, and No. 3 HDT high level.
As noted above the turbine load reference is provided by the higher median of four turbine impulse pressure inputs to the DCS (CP06). The No. 3 HDT pump discharge flow is the median of three redundant flow measurements with redundant low flow switch outputs. The No. 3 HDT level signal is also the median of three redundant level measurements. The No. 3 HDT flow and level signals are processed in CP08.
Implementing these features in the DCS provides a significant reliability improvement.
Having the load reference signal in a different processor than the No. 3 HDT flow and level signals also provides a degree of protection against a false runback from a single CP failure.
6.0 Conclusions Review of the design and licensing basis for WBN unit 2 identified requirements for segmentation of control systems and functions important to safe plant operation and ensuring the safety analyses remain bounding. The WBN unit 2 DCS design incorporates the principal segmentation features described below.
Failure of a one control processor pair, with all outputs failing high, low or as is, will not cause:
- 2. The feedwater control valves in one loop to fail open concurrent with the main feedwater pump speed control to going to maximum speed.
- 3. All the condenser steam dump valves to fail open.
- 7. Both pressurizer spray valves to fail open or closed. Loss of charging flow to the Reactor Coolant Pump seals.
24
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS
- 8. Loss of both reactor coolant letdown paths.
- 9. Complete loss of pressurizer heater control and protection.
These requirements are satisfied by segmentation of the controls into multiple processor pairs as shown in Table 1.
Based on this evaluation, the design of the WBN unit 2 DCS does not introduce new control system failures which could adversely impact the safety analyses as described in the FSAR. Functional diversity and independence are provided for the critical control systems as required by the design basis and in a manner consistent with the unit 1 design. The segmentation implemented for unit 2 eliminates the possibility of a single processor pair failure from disabling multiple control systems or redundant features of these systems.
25
Calculation Identifier: DCSSEGMENT REV 0 Calculation
Title:
SEGMENTATION ANALYSIS FOR WBN UNIT 2 DCS APPENDIX A FUNCTIONAL LOGIC SKETCHES FIGURES 1-10 Al
NEWORK 4I- --- 7-- - - -- - - -
STM FLOW STM FLOW STM FLOW STM F CP01 CP02 CP03 CP(
SGI SG2 SG3 SG SG LVL SP SG LVL SP SG LVL SP S
+S L--------- I -------------------- II-- -----------------------
. , NETý 0) 0)
CP07 CP08 CP09 cP10 03 SG1 PORV SG2 PORV SG3 PORV SG4 PORV
>cI FIGURE 1 MZ SHARED SIGNALS
Calculation Identifier: DCSSEGMENT Appendix A I II III IV 2-F-3-35A 2-F-3-35B 2-F-1 -3A 2-F-1 -3B FW REG VALVE FW BYPASS MFP SPEED MFP SPEED SG1 REG VALVE CONTROL CONTROL SG 1 CP05 CP05 (Typical SG 2-4) (SG 1&2 ONLY)
FIGURE 2 SG LEVEL CONTROL A3
!F MFP2A MFP 2B STEAM DUMP SPEED SPEED CP11 CHANGER CHANGER 0
FIGURE 3 MAIN FEEDWATER PUMPS 0
>c~n 0 z X-Z
Calculation Identifier: DCSSEGMENT Appendix A MOM 2-P-1-2A 2-PT-1-6 SG 1 PORV SG 4 PORV FIGURE 4 SG PORVs A5
-v PIN
'> MIsmatch TAVG DO I A IAO.
jV I I, +IF SG LEVEL LFV TURBINE #3 HTR DRAIN STEAM DUMP PZR LEVEL CP01 SG 2 LEVEL V I RUNBACK TANK LEVEL CPi I CP13 CP02 SG 3 LEVEL VV CP03 SG 4 LEVEL CP04 FIGURE 5 0
ROD CONTROL C)C,'
TAVGITREF/NIS m DG)
Q. m
2-P-1-72 ROD CONTROL (CP06)
J, MODULATE STEAM OPEN 6 STEAM DUMP VALVES EACH STEAM DUMP DUMP VALVES LOSS OF LOAD CD INTERLOCK C-7 FIGURE 6 >cj (DG STEAM DUMP VALVES CONTROL X Z
Calculation Identifier: DCSSEGMENT Appendix A 2-P-68-340 2-P-68-323 2-P-68334 2-P-68-322 2PCV0680334 HI PRESS INTLK (2PS0680323F)
LOOP 1 SPRAY (2PC0680340B)
VARIABLE HEATER (2PC0680340E)
LO PRESS ALM BACKUP HTRS (2PS0680340G)
FIGURE 7 PRESSURIZER PRESSURE CONTROL A8
Calculation Identifier: DCSSEGMENT Appendix A I I I I III II II II II II LOW PRESS HI PRESS LOW PRESS HI PRESS ARMING INTERLOCK ARMING INTERLOCK PERMISSIVE 2-PCV-68-340A PERMISSIVE 2-PCV-68-334 2-PCV-68-340A 2-PCV-68-334 FIGURE 8 COLD OVERPRESSURE MITIGATION SYSTEM (PZR PORVS)
A9
Calculation Identifier: DCSSEGMENT Appendix A I 11-171Z-1ý125-e-10 I 2-L-68-320 2-L-68-339 2-L-68-335 HI LEVEL ALARM (2LS0680335D)
LO LEVEL HEATERS OFF HEATERS OFF DEV ALARM LETDOWN ISOL LETDOWN ISOL (2LS0680339F) LO LEVEL ALARM LO LEVEL ALARM (2LS0680339D) (2LS0680335E)
HI LEVEL DEV ALARM (2LS0680339E)
FIGURE 9 PRESSURIZER LEVEL CONTROL A10
Calculation Identifier: DCSSEGMENT Appendix A 2-LT-62-130A 2-LT-62-129A LOW-LOW LEVELVE INTLK RWST VALVE (2LS0620129A)
HIGH LEVEL INTLK DIVERSION VALVE (2LS0620129E)
DIVERSION VALVE CONTROL LOW-LOW LEVEL INTLK RWST VALVE (2LS0620130B)
FIGURE 10 VOLUME CONTROL TANK LEVEL CONTROL All
Calculation Identifier: DCSSEGMENT APPENDIX B SAFETY ANALYSIS REVIEW The design basis accidents analyzed in the FSAR and WB-DC-40-70, Accident Analysis Parameter Checklist (AAPC), are listed in the following table. The modeling of the control systems for each event is described in the Plant Parameter List tables (item 6 of section 4.x.x.3) of the AAPC. Each analysis has been reviewed to verify that no new control system failures are introduced which could adversely impact the safety analyses. Typically, the control systems are assumed to function only if their operation results in more severe accident results. This does not imply that any segmentation requirements should be applied as a result of these assumptions. The principal aim of this review is to identify configurations wherein failure of a control processor pair could result in plant conditions which are more limiting than those analyzed. Segmentation configurations required to address such conditions are identified as well as those configurations which would enhance the availability of control systems/functions for transient response.
FSAR AAPC TITLE .. EVENT ANALYSIS 15.2 4.1 Condition II- Faults of Moderate Frequency 15.2.1 4.1.1 Uncontrolled Rod Cluster Control Assembly Bank Withdrawal From Subcritical Pressurizer Pressure NA Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA.. Rod control malfunction is an initiator.
Steam Dump NA Conclusion Event is characterized by a power excursion and is terminated by high flux trips. No specific control systems segmentation implications.
15.2.2 4.1.2 Uncontrolled Rod Cluster Control Assembly Bank Withdrawal at Power Pressurizer Pressure PORVs and sprays are assumed to function.
Pressurizer Level Level control is not modeled; the high pressurizer water level reactor trip is not credited in the analysis for DNB or overpressure protection because the makeup and letdown functions of the CVCS inhibit the high pressurizer water level trip from being reached during a pressurizer fill event.
Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA. Rod control malfunction is an initiator.
Steam Dump NA Conclusion Rod control should be in different cp pair than pressurizer pressure (PORVs and spray valves),
pressurizer level, and CVCS. PORV controls should be in different cp pairs so that a cp pair failure B1
Calculation Identifier: DCSSEGMENT APPENDIX B SAFETY ANALYSIS REVIEW FSAR J AAPC TITLE EVENT ANALYSIS does not disable both; similar for spray valves.
15.2.3 4.1.3 Rod Cluster Control Assembly Misalignment Pressurizer Pressure PORVs and sprays are assumed to function before and after reactor trip.
Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA. Rod control is assumed to be operating in AUTO.
Steam Dump NA Conclusion Rod control should be in different cp pair than pressurizer pressure controls.
15 2.4 4.1.4 Uncontrolled Boron Dilution Pressurizer Pressure NA Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA, but two cases implicitly assumed: AUTO rod control and MANUAL rod control. In AUTO, event will cause power and temperature increase and rod control system will insert rods.
Steam Dump NA Conclusion Since failure of boric acid and primary makeup water controls in IA could initiate event, they should be in different cp than rod control. Mitigated by reactor trip or operator intervention. Event is bounded by other non-LOCA transients.
152.5 4.1.5 Partial Loss of Forced Reactor Coolant Flow Pressurizer Pressure NA Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA. Rod control is assumed to be operating in MANUAL.
Steam Dump NA Conclusion Control systems not modeled. Event terminated by reactor trip. No segmentation requirements.
15.2.6 4.1.6 Startup of an Inactive Reactor Not analyzed; N-1 RCP operation prohibited by Tech Specs.
Coolant Loop .. .. ... ...
SO B2
Calculation Identifier: DCSSEGMENT APPENDIX B SAFETY ANALYSIS REVIEW FSAR AAPC TITLE EVENT ANALYSIS 15.2.7 4.1.7 Loss of External Electrical Load and/or Turbine Trip Pressurizer Pressure Pressure control (PORVs and sprays) assumed in DNB analysis; no pressure control for over pressure analysis.
Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA. Rod control is assumed to be operating in MANUAL.
Steam Dump Not modeled, but desirable for steam dumps to be available to minimize pressure increase and remove decay heat.
Conclusion If condenser not available, atmospheric dump valves (SG PORVs) should be available. Rod control, pressurizer pressure and steam dump and SG PORVs should be in different cp pairs. Pzr PORV controls should be in different cp pairs; similar for spray valves and SG PORVs.
1562.8 4.1.8 Loss of Normal Feedwater Pressurizer Pressure Pressure control (PORVs; sprays and heaters) assumed to function before and after reactor trip.
Pressurizer Level NA. Low level heater cutout assumed.
Steam Generator Level NA Main Feedwater Pump Flow NA. MFP or reg valve controls malfunction could initiate.
Rod Control NA. Rod control is assumed to be operating in MANUAL.
Steam Dump NA Conclusion Rod control and pressurizer pressure controls should be in different cp pairs. Pzr PORV controls should be in different cp pairs; similar for spray valves. Heater shutoff controls should also be in different cp pairs. Manual control of heaters is available outside the DCS. FW reg valves should be in different cp pairs, one per loop with MFP control in another.
15.2.9 Loss Of Onsite and External Addressed in 15.2.7, 15.2.8 and 15.3.4.
(Offsite) Ac Power 15.2.10 4.1.9 Excessive Heat Removal Due to Feedwater System Malfunctions Pressurizer Pressure Pressure control (PORVs and sprays) assumed to function.
Pressurizer Level NA Steam Generator Level Feedwater flow control malfunction, both single loop and multiple loops, is initiating event.
Assumes feedwater control valves full open in one or all loops. TVA calc used as input assumed all 4 main reg valves wide open plus one bypass valve wide open. This analysis bounds the IA failure mode which is limited to a single CP failure which could cause both main and bypass valves in one loop to fail open while other valves continue to regulate.
B3
Calculation Identifier: DCSSEGMENT APPENDIX B SAFETY ANALYSIS REVIEW FSAR AAPC J TITLE EVENT ANALYSIS Main Feedwater Pump Flow NA Rod Control Both AUTO and MANUAL rod control assumed.
Steam Dump NA Conclusion Controls for feedwater reg valves should be in four different cp pairs, one per loop, with feedwater pump speed control in a fifth, to limit effects of a single cp pair failure. SG level control setpoint program for each loop should reside in different cp pair. MFP and reg valve controls, rod control and pressurizer pressure controls should be segregated. Pzr PORV controls should be in different cp pairs; similar for spray valves.
15.2.11 4.1.10 Excessive Load Increase Incident Pressurizer Pressure NA Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA. Both AUTO and MANUAL rod control assumed.
Steam Dump NA. Steam dump control malfunction could be initiator. Analysis assumes that a single controller malfunction does not cause steam dump because of an interlock which blocks the opening of the valves unless a large turbine load decrease or turbine trip has occurred (the C-7 permissive derived from turbine impulse pressure loop 1-72)
Conclusion The C-7 loss of load permissive should be segregated from the steam dump controls so that a
=single cp failure does not result in opening of all steam dump valves.
15.2.12 4.1.11 Accidental Depressurization of the Reactor Coolant System Pressurizer Pressure Not modeled, but event initiator is inadvertent opening of pzr relief (PORV) or safety valve, with safety valve being more limiting.
Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA. MANUAL rod control assumed.
Steam Dump NA.
Conclusion Pzr PORV controls should be segregated so that a single cp failure does not open both PORVs.
15.2.13 4.1,12 Accidental Depressurization of the Main Steam System (Steamline Break Core Response)
Pressurizer Pressure NA L Pressurizer Level NA B4
Calculation Identifier: DCSSEGMENT APPENDIX B SAFETY ANALYSIS REVIEW FSAR AAPC TITLE EVENT ANALYSIS Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA. MANUAL rod control assumed.
Steam Dump Not modeled, but inadvertent opening of a single steam dump valve is one initiator. Analysis does not evaluate opening of all steam dumps.
Conclusion The C-7 loss of load permissive should be segregated from the steam dump controls so that a single cp failure does not result in opening of all steam dump valves.
15.2.14 4.1.13 Inadvertent Operation of the Emergency Core Cooling System Pressurizer Pressure For the minimum DNBR case, pressurizer heaters are assumed not available; the opposite is assumed for the pressurizer filling case. Sprays are assumed operable for both cases. The limiting case for pressurizer filling assumed PORVs are isolated and not available for pressure relief. In lower modes, cold overpressure mitigation system (COMS) provides protection by opening PORVs.
Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA. MANUAL rod control assumed.
Steam Dump NA.
Conclusion COMS controls for each PORV should be segregate.d.
15.3 4.2 Condition III - Infrequent Faults 15.3.1 4.2.1 Small Break Loss of Coolant Accident Pressurizer Pressure NA Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA Steam Dump NA.
Conclusion No segmentation requirements.
15.3.4 4.2.2 Complete Loss of Forced (CLOF)
Reactor Coolant Flow Pressurizer Pressure NA Pressurizer Level NA B5
Calculation Identifier: DCSSEGMENT APPENDIX B SAFETY ANALYSIS REVIEW FSAR JAAPC TITLE EVENT ANALYSIS Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA. MANUAL rod control assumed.
Steam Dump NA; Conclusion No segmentation requirements.
15 3 6 4. 2.3 Single Rod Cluster Control Assembly Withdrawal at Full Power Pressurizer Pressure NA Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA. Rod control malfunction is an initiator.
Steam Dump NA.
Conclusion No segmentation requirements.
15.4 4.3 Condition IV - Limiting Faults 15.4.1 4.3.1 Large Break Loss of Coolant Accident Pressurizer Pressure NA Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA.
Steam Dump NA.
Conclusion No segmentation requirements.
15.4.2.1 4.3.2 Major Rupture of a Main Steam System Pipe (Steamline Break Core Response)
Pressurizer Pressure NA Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA. MANUAL rod control assumed.
Steam Dump NA.
86
Calculation Identifier: DCSSEGMENT APPENDIX B SAFETY ANALYSIS REVIEW FSAR AAPC TITLE EVENT ANALYSIS Conclusion No segmentation requirements.
15.4.2.2 4.3.3 Major Ruptureofa Main Feedwater Pipe Pressurizer Pressure Pressurizer PORVs are assumed to function.
Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA. MANUAL rod control assumed.
Steam Dump NA.
Conclusion No segmentation requirements.
15.4.3 4.3.4 Steam Generator Tube Rupture Pressurizer Pressure NA Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA.
Steam Dump NA.
Conclusion No segmentation requirements.
15.4.4 4.3.5 Single Reactor Coolant Pump Locked Rotor
-Pressurizer Pressure NA Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA Rod Control NA. MANUAL rod control assumed.
Steam Dump NA.
Conclusion No segmentation requirements.
15.4.6 4.3.6 Rupture of a Control Rod Drive Mechanism Housing (Rod Cluster Control Assembly Ejection)
Pressurizer Pressure NA Pressurizer Level NA Steam Generator Level NA Main Feedwater Pump Flow NA B7
Calculation Identifier: DCSSEGMENT APPENDIX B SAFETY ANALYSIS REVIEW FSAR AAPC TITLE EVENT ANALYSIS Rod Control NA.
Steam Dump NA.
Conclusion No segmentation requirements.
NA - Not modeled or not applicable to analysis.
B8
A4iacArne# I Its, Design Verification Report WBN Unit 2 Calculation No. DCSSEGMENT Design Verified (System, Structure, Component): Method(s)
-- Interdisciplinary Review System 098, non-safety related NSSS and BOP digital Off-Project Design Review control system X- Individual Critical Review Alternate Calculation Qualification Testing Document(s) Reviewed: DCSSEGMENT, Rev. 0, Segmentation Analysis for WBN Unit 2 DCS Summary of Review (attach additional sheets if needed):
A design verification has been performed by the design review method in accordance with 25402-3DP-GO4G-00027, Rev. 3.
Conclusions (attach additional sheets if needed)
Technical adequacy of this calculation was verified by determining that the methodology was adequate to ensure compliance with regulatory and design basis requirements, design inputs were appropriately addressed, and results and conclusions are valid.
Signature of Verifier Organization Position Report Prepared by J. T. Kepler WBN2 Engineering I & C Engineer Name J. T. Kepler Signature Date I/
Refer to the electronic documents in TVA Business Support Library (BSL) for current revision.
25402-3DP-GO4G-00027 EFFECTIVE DATE: 12-23-09 Page 1 of 3
Aifa~rCiMex1 f Design Verification Checklist (excerpted from ANSI N.45.2.11 [1974 Edition]
Name and Document Number (See Section 2.3.9.)
Design Verification Element Note: Any items checked "No" automatically imply the design is not Yes No NIA verified. Remarks
- X Is the person performing the design verification qualified to originate the document?
X Is the design verification being performed by someone other than the supervisor of the originator? Ifthe supervisor of the originator is performing design verification, mark the answer "N/A" and provide justification in the document (see section 2.3.7 for requirements).
X Do the collective results of the design input/output substantiate the concept and approach chosen to ensure the design activity provides an adequate, accurate, andworkable solution to the problem/question being resolved?
X Were the design inputs correctly selected and incorporated into design?
X Are assumptions necessary to perform the design activity adequately described and reasonable? Where necessary, are assumptions identified for subsequent re-verifications when the detailed design activities are completed?
X Are the appropriate quality and quality assurance requirements specified?
X Are the applicable codes, standards and regulatory requirements including issue and addenda properly identified, and their requirements for design met?
X Have applicable construction and operating experiences been considered?
X Have the design interface requirements been satisfied?
X Were appropriate design methods and computer programs used?
X Is the design output reasonable compared to design inputs?
X Are the specified parts, equipment, and processes suitable for the required application? Are all applicable construction specifications referenced on the drawing(s)?
X Are the specified materials compatible with each other and the design environmental conditions to which the material will be exposed?
X Have adequate maintenance features and requirements been specified?
X Are accessibility and other design provisions adequate for initial installation and for performing needed maintenance and repair? _
X Have adequate accessibility been provided to perform the in-service inspection expected to be required during the plant life?
X Has the design properly considered radiation exposure to the public and plant personnel (e.g., ALARA)?
X Are the acceptance criteria incorporated inthe design documents sufficient to allow verification that design requirements have been satisfactorily accomplished?
Refer to the electronic documents in TVA Business Support Library (BSL) for current revision, 25402-3DP-GO4G-00027 EFFECTIVE DATE: 12-23-09 Page 2 of 3
Design Verification Checklist (excerpted from ANSI N.45.2.11 [1974 Edition]
Name and Document Number (See Section 2.3.9.)
Design Verification Element Note: Any items checked 'No" automatically imply the design is not Yes No NIA verified. Remarks
- X Have adequate pre-operational and subsequent periodic test requirements been appropriately specified?
X Have adequate handling, storage, cleaning, and shipping requirements been specified?
X Are adequate identification requirements specified?
X Are requirements for record preparation review, acceptance, retention, etc., adequately specified?
X Has constructability been adequately considered?
- It is encouraged that the verifier provide a brief explanation of the considerations utilized in performing the design verification activity in the "Remarks" column Refer to the electronic documents in TVA Business Support Library (BSL) for current revision.
25402-3DP-GO4G-00027 EFFECTIVE DATE: 12-23-09 Page 3 of 3