Other: LIC-08-0069, Letter of Intent to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition, ML082710002, ML101040676, ML101050376, ML101270268, NLS2009099, SAMA Meteorological Anomaly Related to the Cooper Nuclear Station License Renewal Application | |
MONTHYEARLIC-08-0069, Letter of Intent to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition2008-06-0909 June 2008
[Table View]Letter of Intent to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition Project stage: Other ML0830302462008-09-24024 September 2008 Copper Nuclear Station, License Renewal Application, Appendix E, Environmental Report Project stage: Other ML0827100022008-11-20020 November 2008 Response to Letter of Intent to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light-Water Reactor Electric Generation Plants, 2001 Edition Project stage: Other ML0833300662008-12-19019 December 2008 Determination of Acceptability and Sufficiency for Docketing and Opportunity for a Hearing Regarding the Application from Nebraska Public Power District, for Renewal of the Operating License for the Cooper Nuclear Station Project stage: Other ML0901203602009-01-0909 January 2009 Safety Evaluation Report Project stage: Request ML0836404012009-01-21021 January 2009 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for License Renewal for the Cooper Nuclear Station Unit 1 (TAC No. MD9763 and MD 9737) LTR Project stage: Other ML0906500612009-02-0202 February 2009 Letter from Nebraska State Historical Society Regarding Cooper Nuclear Station License Renewal Project stage: Other ML0907506862009-02-25025 February 2009 Scoping and Process Public Meeting Sides of February 25, 2009 Project stage: Request ML0907200662009-02-25025 February 2009 Comment (1) of James Gerweck, on Behalf of the Richardson County, Nebraska, Emergency Management Agency, Supporting CNS License Renewal Project stage: Other ML0908400632009-02-25025 February 2009 Transcript of Cooper Nuclear Station License Renewal Public Meeting - Afternoon Session, Wednesday, February 25, 2009, Pages 1-33 Project stage: Meeting ML0908400622009-02-25025 February 2009 Transcript of Cooper Nuclear Station License Renewal Pubic Meeting - Evening Session, February 25, 2009, Pages 1-41 Project stage: Meeting ML0907200682009-02-27027 February 2009 Comment (3) of Ashtin Paris, on Behalf of the City of Rock Port, Supporting Nebraska Public Power District'S Cooper Nuclear Station License Renewal Project stage: Other ML0908607622009-03-0909 March 2009 Letter from the Nebraska Department of Natural Resources the Cooper Nuclear Station License Renewal Project stage: Other ML0907200672009-03-10010 March 2009 Comment (2) of Alan Richard, on Behalf of Pawnee City Development Corporation, Supporting Renewal of License for Cooper Nuclear Station Project stage: Request ML0902205842009-04-0303 April 2009 Proposed Review Schedule Regarding the Application from Nebraska Public Power District for Renewal of the Operating License for the Cooper Nuclear Station Project stage: Other ML0908302482009-04-0303 April 2009 Environmental Site Audit Regarding Cooper Nuclear Station Unit 1 License Renewal Application (TAC MD9763 and MD9737) Project stage: Other ML0909302562009-04-0909 April 2009 Audit Plan for Aging Management Program Site Audit Regarding Cooper Nuclear Station Unit 1, License Renewal Application (Tac No. MD9737) Project stage: Other ML0909103082009-04-14014 April 2009 Summary of Public Environmental Scoping Meeting Related to the Review of the Cooper Nuclear Station, Licensed Renewal Application Project stage: Meeting ML0910702692009-04-16016 April 2009 EPA Comment on the Cooper Nuclear Station License Renewal Application Project stage: Other ML0911700312009-04-28028 April 2009 Environmental Site Audit Regarding Cooper Nuclear Station Unit 1 License Renewal Application Project stage: Other ML0909704142009-04-30030 April 2009 Summary of Site Audit Related to the Review of the License Review Application for Cooper Nuclear Station, Unit 1 Project stage: Approval ML0911905972009-05-0101 May 2009 Request for Additional Information for the Review of the Cooper Nuclear Station License Renewal Application (TAC No. MD9763 and MD9737) Project stage: RAI NLS2009039, Response to Request for Additional Information for License Renewal Application - Balance-of-Plant Scoping and Screening2009-05-28028 May 2009 Response to Request for Additional Information for License Renewal Application - Balance-of-Plant Scoping and Screening Project stage: Response to RAI ML0912000172009-05-29029 May 2009 Issuance of Environmental Scoping Summary Report Associated with the Staff'S Review of the Application by the Nebraska Public Power District, for Renewal of the Operating License for Cooper Nuclear Station Unit 1 Project stage: Approval ML0917500882009-06-0101 June 2009 CNS Lr - NDEQ 2009 Ambient Network Plan Project stage: Request ML0918300552009-06-0808 June 2009 Reply from Fish and Wildlife Service on Transmission Line for Cooper Nuclear Station License Renewal Project stage: Other ML0915303162009-06-0808 June 2009 Request for Additional Information for the Review of the Cooper Nuclear Station License Renewal Application Project stage: RAI ML0917501182009-06-11011 June 2009 CNS Lr - Tornado Occurrences in Nemaha County, Ne 1950-2009 Project stage: Request ML0913803652009-06-15015 June 2009 Audit Report Regarding the Cooper Nuclear Station, Unit 1, License Renewal Application Project stage: Acceptance Review NLS2009040, Response to Request for Additional Information for License Renewal Application - Aging Management Programs2009-06-15015 June 2009 Response to Request for Additional Information for License Renewal Application - Aging Management Programs Project stage: Response to RAI NLS2009049, Response to Request for Additional Information for License Renewal Application - Section B and C2009-06-22022 June 2009 Response to Request for Additional Information for License Renewal Application - Section B and C Project stage: Response to RAI ML0916002892009-06-29029 June 2009 Request for Additional Information for Cooper Nuclear Station License Renewal Project stage: RAI ML0916002782009-06-29029 June 2009 Request for Additional Information for the Review of the Cooper Nuclear Station License Renewal Application Project stage: RAI NLS2009048, Response to Request for Additional Information for License Renewal Application Severe Accident Mitigation Alternatives2009-07-0101 July 2009 Response to Request for Additional Information for License Renewal Application Severe Accident Mitigation Alternatives Project stage: Response to RAI ML0917503682009-07-0101 July 2009 Summary of Regulatory Audit Related to the Review of the License Renewal Application for Cooper Nuclear Station Project stage: Approval ML0918802582009-07-0808 July 2009 Environment Project Manager Change for the License Renewal of Cooper Nuclear Station Project stage: Other ML0919005022009-07-14014 July 2009 Request for Additional Information for the Review of the Cooper Nuclear Station License Renewal Application Project stage: RAI ML0918804822009-07-14014 July 2009 Request for Additional Information for the Review of Cooper Nuclear Station License Renewal Application Project stage: RAI ML0918804782009-07-14014 July 2009 Request for Additional Information Project stage: RAI ML0918703042009-07-16016 July 2009 License Renewal Request for Additional Information Project stage: RAI ML0918702982009-07-16016 July 2009 Request for Additional Information for the Review of the Cooper Nuclear Station License Renewal Application Project stage: RAI ML0921600842009-07-20020 July 2009 Notice of Diane Curran'S Withdrawal of Appearance Project stage: Request NLS2009055, Response to Request for Additional Information for License Renewal Application2009-07-29029 July 2009 Response to Request for Additional Information for License Renewal Application Project stage: Response to RAI ML0920902762009-07-29029 July 2009 Request for Additional Information for the Review of the Cooper Nuclear Station License Renewal Application (TACs MD9763 and MD9737) Project stage: RAI NLS2009063, Response to Request for Additional Information for License Renewal Application2009-08-17017 August 2009 Response to Request for Additional Information for License Renewal Application Project stage: Response to RAI ML0919600402009-08-19019 August 2009 Summary of Regulatory Audit Related to the Review of the License Renewal Application for Cooper Nuclear Station Project stage: Approval ML0923106542009-08-28028 August 2009 Request for Additional Information for the Review of the Cooper Nuclear Station License Renewal Application Project stage: RAI ML0926500572009-09-28028 September 2009 Request for Additional Information for the Review of the Cooper Nuclear Station License Renewal Application Project stage: RAI ML0926809352009-10-0707 October 2009 Request for Additional Information for the Review of the Cooper Nuclear Station License Renewal Application Project stage: RAI ML0927300142009-10-15015 October 2009 Request for Additional Information for the Review of the Cooper Nuclear Station License Renewal Application Project stage: RAI 2009-04-09 |
ML101440132 | |
Person / Time | |
---|---|
Site: | Cooper |
Issue date: | 04/27/2010 |
From: | Stewart R US Dept of Interior, Office of Environmental Policy and Compliance, US Dept of Interior, Office of the Secretary |
To: | Rulemaking, Directives, and Editing Branch |
References | |
ER 10/174, NUREG-1437, Suppl 41 | |
Download: ML101440132 (1) | |
Similar Documents at Cooper | |
---|---|
Category:Letter
MONTHYEARIR 05000298/20240032024-11-0505 November 2024
[Table view]Integrated Inspection Report 05000298/2024003 ML24250A2052024-10-0808 October 2024 Issuance of Amendment No. 278 Regarding Revision to Technical Specification Table 3.3.2.1-1 and Transfer of Minimum Critical Power Ratio Values to Core Operating Limit Report ML24227A0822024-09-0303 September 2024 Summary of Regulatory Audit in Support of License Amendment Request to Modify the High Pressure Coolant Injection Low Flow Value IR 05000298/20240052024-08-22022 August 2024 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2024005) IR 05000298/20240022024-07-25025 July 2024 Integrated Inspection Report 05000298/2024002 ML24183A1722024-07-17017 July 2024 Issuance of Amendment No. 277 to Adopt TSTF-374, Revision to TS 5.5.13 and Associated TS Bases for Diesel Fuel Oil ML24197A1462024-07-15015 July 2024 NRC Region IV Ltr to Cooper Nuclear Station Re FEMA Level 1 Finding ML24134A1782024-07-0303 July 2024 Issuance of Amendment No. 276 Revision to Technical Specification 3.8.3, Diesel Fuel Oil, Lube Oil and Starting Air, to Allow for Cleaning, Inspection and Any Needed Repairs During Refuel Outage 33 ML24197A0682024-06-24024 June 2024 FEMA Ltr to Missouri State Emergency Management Agency - Level 1 Finding, 24 June 2024 ML24192A0112024-06-13013 June 2024 2024-06-Post Exam Comments 05000298/LER-2023-002-01, Secondary Containment Differential Pressure Perturbation Exceeds Technical Specifications2024-06-0606 June 2024 Secondary Containment Differential Pressure Perturbation Exceeds Technical Specifications IR 05000298/20244012024-06-0404 June 2024 Security Baseline Inspection Report 05000298/2024401 ML24151A1082024-05-30030 May 2024 NRC Initial Operator Licensing Examination Approval 05000298/2024301 ML24137A0942024-05-17017 May 2024 Regulatory Audit Plan in Support of License Amendment Request to Modify Allowable Value Regarding Technical Specification for High Pressure Coolant Injection Pump Discharge Low Flow 05000298/LER-2024-005, High Pressure Coolant Injection Pressure Switch Installation Causes Condition That Could Have Prevented Fulfillment of a Safety Function and a Condition Prohibited B Technical2024-05-13013 May 2024 High Pressure Coolant Injection Pressure Switch Installation Causes Condition That Could Have Prevented Fulfillment of a Safety Function and a Condition Prohibited B Technical. 05000298/LER-2024-004, Main Turbine Stop Valve Position Switches Do Not Meet Channel Independence Criteria Results in Two Channels Being Declared Inoperable and a Condition Prohibited by Technical Specifications2024-05-0909 May 2024 Main Turbine Stop Valve Position Switches Do Not Meet Channel Independence Criteria Results in Two Channels Being Declared Inoperable and a Condition Prohibited by Technical Specifications IR 05000298/20240012024-05-0303 May 2024 Integrated Inspection Report 05000298/2024001 ML24129A0952024-04-25025 April 2024 Preparation and Scheduling of Operator Licensing Examinations IR 05000298/20240102024-04-24024 April 2024 Comprehensive Engineering Team Inspection Report 05000298/2024010 05000298/LER-2024-003, High Pressure Coolant Injection Steam Leak Causes Condition That Could Have Prevented Fulfillment of a Safety Function and a Condition Prohibited by Technical Specifications2024-04-22022 April 2024 High Pressure Coolant Injection Steam Leak Causes Condition That Could Have Prevented Fulfillment of a Safety Function and a Condition Prohibited by Technical Specifications ML24096A1202024-04-0505 April 2024 Issuance of Amendment No. 275 Revision to Technical Specification 3.3.1.1 (Emergency Circumstances) ML24093A2282024-04-0202 April 2024 Notice of Enforcement Discretion for Cooper Nuclear Station IR 05000298/20240902024-04-0101 April 2024 – Notice of Violation, NRC Inspection Report 05000298/2024090 05000298/LER-2024-001, Inoperable Turbine Stop Valve Limit Switch Causes Condition Prohibited by Technical Specifications2024-03-0404 March 2024 Inoperable Turbine Stop Valve Limit Switch Causes Condition Prohibited by Technical Specifications 05000298/LER-2024-002, Technical Specifications Prohibited Condition for Inoperable Service Water Booster Pump2024-03-0404 March 2024 Technical Specifications Prohibited Condition for Inoperable Service Water Booster Pump IR 05000298/20230062024-02-28028 February 2024 Annual Assessment Letter for Cooper Nuclear Station - Report 05000298/2023006 IR 05000298/20230042024-02-12012 February 2024 Integrated Inspection Report 05000298/2023004 ML24033A3092024-02-12012 February 2024 Summary of Regulatory Audit Regarding the Relief Request RC3-02 Regarding Drywell Head Bolting IR 05000298/20230122024-02-12012 February 2024 NRC Inspection Report 05000298/2023012 ML23334A2012024-01-0303 January 2024 Issuance of Amendment No. 274 Revision to Technical Specifications to Adopt TSTF-551, Revision 3, Revise Secondary Containment Surveillance Requirements 05000298/LER-2023-002, Secondary Containment Differential Pressure Perturbation Exceeds Technical Specifications2023-12-20020 December 2023 Secondary Containment Differential Pressure Perturbation Exceeds Technical Specifications ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23311A1122023-11-0909 November 2023 Project Manager Assignment IR 05000298/20230032023-11-0202 November 2023 Integrated Inspection Report 05000298/2023003 IR 05000298/20234012023-11-0101 November 2023 Cyber Security Report 05000298/2023401 Public ML23264A8052023-10-11011 October 2023 Issuance of Amendment No. 273 Revision to Technical Specifications to Adopt TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23233A1882023-09-0505 September 2023 Regulatory Audit Plan in Support of Relief Request RC3-02 Regarding Drywell Head Bolting IR 05000298/20243012023-09-0101 September 2023 Notification of NRC Initial Operator Licensing Examination 05000298/2024301 IR 05000298/20230052023-08-21021 August 2023 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2023005)- Mid Cycle Letter IR 05000298/20230022023-08-0808 August 2023 Integrated Inspection Report 05000298/2023002 IR 05000298/20234022023-08-0303 August 2023 NRC Security Inspection Report 05000298/2023402 ML23214A2742023-08-0303 August 2023 Nuclear Station - Notification of Inspection (NRC Inspection Report 05000298/2023004) and Request for Information IR 05000298/20234202023-08-0101 August 2023 Security Baseline Inspection Report 05000298/2023420 05000298/LER-2022-002-01, Manual Core Spray Injection to Restore Skimmer Surge Tank Level2023-06-29029 June 2023 Manual Core Spray Injection to Restore Skimmer Surge Tank Level ML23173A0862023-06-26026 June 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000298/2023401 IR 05000298/20230102023-05-17017 May 2023 Biennial Problem Identification and Resolution Inspection Report 05000298/2023010 05000298/LER-2022-004-01, 1 for Cooper Nuclear Station, Manual Reactor Scram and Group I Isolation Due to Main Turbine Bypass Valve Failing Open2023-05-11011 May 2023 1 for Cooper Nuclear Station, Manual Reactor Scram and Group I Isolation Due to Main Turbine Bypass Valve Failing Open 05000298/LER-2023-001, Valve Test Failures Result in Condition Prohibited by Technical Specifications2023-05-0808 May 2023 Valve Test Failures Result in Condition Prohibited by Technical Specifications IR 05000298/20234032023-05-0404 May 2023 Security Baseline Inspection Report 05000298/2023403 ML23129A2822023-04-20020 April 2023 Submittal of Revision 31 to Updated Safety Analysis Report 2024-09-03 |
Text
United States Department of the Interior OFFICE OF THE SECRETARY TAKE PRIDE*
Office of Environmental Policy and Compliance INAMERICA Denver Federal Center, Building 67, Room 118 Post Office Box 25007 (D-108)
Denver, Colorado 80225-0007 April 27, 2010 9043.1 ER 10/174 Chief, Rules and Directive Branch, Division of Administrative Services, Mail Stop T-6D59 U.S Nuclear Regulatory Commission Washington, D.C. 20555-0001
Dear Sir or Madam:
The Department of the Interior has reviewed the Draft Generic Environmental Impact Statement (EIS), NUREG-1437, Supplement 41, for License Renewal of Nuclear Plants; Cooper Nuclear Station, Unit 1, Nemaha County, Nebraska and has no comments on the document.
Sincerely, Robert F. Stewart Regional Environmental Officer