MONTHYEARLIC-08-0069, Letter of Intent to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition2008-06-0909 June 2008 Letter of Intent to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition Project stage: Other ML0827100022008-11-20020 November 2008 Response to Letter of Intent to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light-Water Reactor Electric Generation Plants, 2001 Edition Project stage: Other NLS2009099, SAMA Meteorological Anomaly Related to the Cooper Nuclear Station License Renewal Application2009-12-0707 December 2009 SAMA Meteorological Anomaly Related to the Cooper Nuclear Station License Renewal Application Project stage: Other ML1010406762010-04-0303 April 2010 Comment (1) of Andrew Smith, Supporting Cooper Nuclear Station License Renewal Project stage: Other ML1013205452010-04-0707 April 2010 Transcript of Cooper, License Renewal Public Meeting, Afternoon Session, April 07, 2010, Pages 1-20 Project stage: Meeting ML1013206182010-04-0707 April 2010 Transcript of Cooper, License Renewal Public Meeting: Evening Session, April 07, 2010, Page 1-20 Project stage: Meeting ML1014401332010-04-0707 April 2010 Letter to Nuclear Regulatory Commission Relicensing Committee from Robert Engles, Mayor of City of Auburn, Nebraska Project stage: Request ML1010503762010-04-0707 April 2010 Preliminary Site-Specific Results of the License Renewal Environmental Review for Cooper Nuclear Station Project stage: Other ML1014401322010-04-27027 April 2010 Letter to NRC from Robert Stewart, Department of Interior, on the Cooper Nuclear Station Dseis Project stage: Request NLS2010042, Enclosure 1, Annual Radioactive Effluent Release Report January 1, 2009 Through December 31, 20092010-04-30030 April 2010 Enclosure 1, Annual Radioactive Effluent Release Report January 1, 2009 Through December 31, 2009 Project stage: Request ML1012702682010-05-0303 May 2010 Comment (2) of Ronald Hammerschmidt on Behalf of Us Environmental Protection Agency on Review of Generic Environmental Impact Statement for License Renewal of Cooper Nuclear Plants, Unit 1 Project stage: Other NLS2010048, Annual Radiological Environmental Report for 20092010-05-14014 May 2010 Annual Radiological Environmental Report for 2009 Project stage: Request ML1021003712010-07-31031 July 2010 NUREG-1437, Supp 41, Generic Environmental Impact Statement for the License Renewal of Nuclear Plants: Supplement 41 Regarding Cooper Nuclear Station, Final Report. Project stage: Acceptance Review ML1022902322010-08-30030 August 2010 Final Supplement 41 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Cooper Nuclear Station (TAC MD9763 and MD9737) Project stage: Acceptance Review 2010-04-30
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000285/20240032024-10-29029 October 2024 NRC Inspection Report 05000285/2024003 LIC-24-0012, Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information2024-10-0707 October 2024 Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information LIC-24-0011, Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-00952024-10-0202 October 2024 Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-0095 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24243A1042024-09-12012 September 2024 Proposed Revision to the OPPD FCS DQAP - Request for Additional Information (License No. DPR-40, Docket Nos. 50-285, 72-054, and 71-0256) ML24255A0962024-09-12012 September 2024 License Amendment Request to Revise the License Termination Plan - Request Supplemental Information (License No. DPR-40, Docket No. 50-285) IR 05000285/20240022024-08-21021 August 2024 NRC Inspection Report 05000285/2024002 ML24235A0822024-08-10010 August 2024 Response to Fort Calhoun Station, Unit No. 1 - Phase 1 Final Status Survey Report to Support Approved License Termination Plan - Request for Additional Information - Request for Additional Information (EPID L-2024-DFR-0002) July 8, 2024 ML24180A2082024-07-0808 July 2024 Phase 1 Final Status Survey Reports Request for Additional Information Letter ML24183A3222024-07-0808 July 2024 Proposed Revision to the Omaha Public Power District Fort Calhoun Station Decommissioning Quality Assurance Plan - Acceptance Review LIC-24-0007, License Amendment Request (LAR) to Revise License Termination Plan (LTP)2024-06-18018 June 2024 License Amendment Request (LAR) to Revise License Termination Plan (LTP) IR 05000285/20240012024-06-0505 June 2024 NRC Inspection Report 05000285/2024001 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities LIC-24-0008, Proposed Revision to the Omaha Public Power District (OPPD) Fort Calhoun Station (FCS) Decommissioning Quality Assurance Plan (Dqap), Unit No. 1 and ISFSI2024-05-16016 May 2024 Proposed Revision to the Omaha Public Power District (OPPD) Fort Calhoun Station (FCS) Decommissioning Quality Assurance Plan (Dqap), Unit No. 1 and ISFSI LIC-24-0003, Independent Spent Fuel Storage Installation - Radiological Effluent Release Report and Radiological Environmental Operating Report2024-04-25025 April 2024 Independent Spent Fuel Storage Installation - Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-24-0006, (Fcs), Unit 1, Independent Spent Fuel Storage Installation, Phase 1 Final Status Survey Report to Support Approved License Termination Plan2024-04-17017 April 2024 (Fcs), Unit 1, Independent Spent Fuel Storage Installation, Phase 1 Final Status Survey Report to Support Approved License Termination Plan ML24079A1702024-03-10010 March 2024 ISFSI, Unit 1 - 10 CFR 50.59 Report, Quality Assurance (QA) Program Changes, Technical Specification Basis Changes, 10 CFR 71.106 Quality Assurance Program Approval, Aging Management Review, Commitment Revisions and Revision of Updated Safe LIC-24-0005, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2024-03-0101 March 2024 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-24-0002, Independent Spent Fuel Storage Installation - Submittal of Annual Radioactive Effluent Release Report2024-02-27027 February 2024 Independent Spent Fuel Storage Installation - Submittal of Annual Radioactive Effluent Release Report ML24019A1672024-01-31031 January 2024 Issuance of Amendment to Renewed Facility License to Add License Condition to Include License Termination Plan Requirements IR 05000285/20230062023-12-21021 December 2023 NRC Inspection Report 05000285/2023006 LIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information IR 05000285/20230052023-11-0202 November 2023 NRC Inspection Room 05000285/2023005 ML23276A0042023-09-28028 September 2023 U.S. EPA Response Letter to NRC Letter on Consultation and Finality on Decommissioning and Decontamination of Contaminated Sites MOU - Fort Calhoun Station, Unit 1 – (License No. DPR-40, Docket No. 50-285) IR 05000285/20230042023-09-13013 September 2023 NRC Inspection Report 05000285/2023-004 LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 ML23234A2412023-08-18018 August 2023 Email - Letter to M Porath Re Ft Calhoun Unit 1 LTP EA Section 7 Informal Consultation Request ML23234A2392023-08-18018 August 2023 Letter to B Harisis Re Ft Calhoun Unit 1 LTP EA State of Nebraska Comment Request.Pdf IR 05000285/20230032023-07-10010 July 2023 – NRC Inspection Report 05000285/2023003 ML23082A2202023-06-26026 June 2023 Consultation on the Decommissioning of the Fort Calhoun Station Unit 1 Pressurized Water Reactor in Fort Calhoun, Nebraska ML23151A0032023-06-0505 June 2023 – Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 IR 05000285/20230022023-06-0505 June 2023 NRC Inspection Report 05000285/2023002 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000285/20230012023-02-24024 February 2023 NRC Inspection Report 05000285/2023001 LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report ML23020A0462023-01-19019 January 2023 Threatened and Endangered Species List: Nebraska Ecological Services Field Office IR 05000285/20220062023-01-0505 January 2023 NRC Inspection Report 05000285/2022-006 ML22357A0662022-12-30030 December 2022 Technical RAI Submittal Letter on License Amendment Request for Approval of License Termination Plan IR 05000285/20220052022-10-26026 October 2022 NRC Inspection Report 05000285/2022-005 ML22276A1052022-09-30030 September 2022 Conclusion of Consultation Under Section 106 NHPA for Ft. Calhoun Station LTP ML22258A2732022-09-29029 September 2022 Letter to John Swigart, SHPO; Re., Conclusion of Consultation Under Section 106 Hnpa Fort Calhoun Station Unit 1 ML22265A0262022-09-26026 September 2022 U.S. Nuclear Regulatory Commissions Analysis of Omaha Public Power Districts Decommissioning Status Report (License No. DPR-40, Docket No. 50-285) IR 05000285/20220042022-09-14014 September 2022 NRC Inspection Report 05000285/2022004 ML22138A1252022-08-0303 August 2022 Letter to Mr. Timothy Rhodd, Chairperson, Iowa Tribe of Kansas and Nebraska, Re., Ft Calhoun LTP Section 106 ML22138A1222022-08-0303 August 2022 Letter to Mr. John Shotton, Chairman, Otoe-Missouria Tribe of Indians, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1302022-08-0303 August 2022 Letter to Justin Wood, Principal Chief, Sac and Fox Nation, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22214A0922022-08-0303 August 2022 Letter to Stacy Laravie, Thpo, Ponca Tribe of Nebraska, Re., Ft Calhoun LTP Section 106 2024-09-18
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 20, 2008 Mr. David J. Bannister Vice President and CNO Omaha Public Power District Fort Calhoun Station FC-2-4 Post Office Box 550 Fort Calhoun, NE 68023-0550 SUB~IECT: FORT CALHOUN STATION, UNIT NO.1 - RESPONSE TO LETTER OF INTENT TO ADOPT NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 (TAC NO. MD9736)
Dear Mr. Bannister:
By letter to the Nuclear Regulatory Commission (NRC) dated June 9, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML081620232), the Omaha Public Power District (OPPD), informed the NRC staff of its intent to adopt National Fire Protection Association (NFPA) Standard 805, "Performance-Based Standard for Fire Protection for Light-Water Reactor Electric Generation Plants," 2001 Edition, pursuant to Section 50.48(c) of Title 10 of the Code of Federal Regulations, at the Fort Calhoun Station, Unit 1 (FCS).
OPPD's letter stated that it intends to transition to the performance-based standard for fire protection at FCS, and that the period of transition was to commence on June 9, 2008. OPPD also requested an enforcement discretion period of 3 years in accordance with the NRC's Enforcement Policy.
On April 18, 2006, the NRC published in the Federal Register (71 FR 19905) a revision to its enforcement policy extending the NFPA 805 transition discretion period from 24 to 36 months.
Therefore, the requested 36-month discretion period for FCS is granted. As such, the NRC considers the discretion period for FCS to begin on June 9, 2008, and to expire on June 9, 2011.
In addition, in accordance with the Enforcement Policy, the discretion will continue past the 36-month period while the NRC staff is reviewing the license amendment request for transitioning to NFPA 805.
It should be noted that in order to receive enforcement discretion, a licensee must, in part:
(a) evaluate the risk significance of all noncompliances to assure that they do not constitute "Red" (or Severity Levell) findings under the NRC's reactor oversight program, (b) enter all noncompliances into a corrective action program, and (c) implement and maintain appropriate compensatory measures until the corrective actions are completed, or until the NRC staff issues the license amendment with its associated safety evaluation. Regulatory Issue Summary 2005-07, "Compensatory Measures to Satisfy the Fire Protection Program Requirements," provides additional guidance regarding appropriate compensatory measures.
D.J. Bannister -2 If you have any questions regarding this matter, please contact Alan Wang, Project Manager for FCS, at 301-415-1445.
Sincerely, J
.Q~~ -Jf Yj;+/-h~
eph G. Giitter, Director ivision of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285 cc: Distribution via Listserv
November 20, 2008 D. J. Bannister -2 If you have any questions regarding this matter, please contact Alan Wang, Project Manager for FCS, at 301-415-1445.
Sincerely, IRAI Joseph G. Giitter, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC Lpl4 Reading File RidsAcrsAcnw_MailCTR Resource RidsNrrDorl Resource RidsNrrDorlLpl4 Resource RidsNrrDra Resource RidsNrrDraAfpb Resource RidsNrrLAJBurkhardt Resource RidsNrrPMAWang Resource RidsRgn4MailCenter Resource RidsOeMailCenter Resource RidsOgcRp Resource PLain, NRR/DRAlAFPB MVaaler, NRR/DORL ADAMS Accession No. Ml082710002 NRR-106 OFFICE DORLlLPL4/BC NAME DATE